June 16, 2020
LETTER OF APPROVAL WITH MODIFICATIONS
Virginia Rand Bowman, Power of Attorney for W. Kenan Rand Jr.
1530 N. Gregson Street Suite 3F
Durham, NC 27701
RE: Project Name: Waterside Lane
Acres Approved: 2.63
Project ID: VANCE-2020-005
County: VANCE, City: Middleburg, Address: Daniel Boone Trail
River Basin: Roanoke, Stream Classification: Other
Submitted By: Nathan Hymiller, PLS
Date Received by LQS: May 11, 2020
Plan Type: New
Dear Ms. Bowman,
The subject erosion and sedimentation control plan has been approved by default. The Sedimentation
Pollution Control Act (hereinafter "Act") states that this plan must be filed a minimum of 30 days (15 days
for revised plans) prior to the activity and the approving authority must approve or disapprove the submitted
plan within 30 days (15 days for revised plans) of receipt of G.S. I I3A-54.1. The Act further states that if
the approving authority fails to approve or disapprove the submitted plan within the 30-day (15 days for
revised plans) period, the plan will be deemed approved. The Modifications Required for Approval are
listed on the attached page. The enclosed Certificate of Approval must be posted at the job site. This plan
approval shall expire three (3) years following the date of approval, if no land -disturbing activity has been
undertaken, as is required by Title 15A NCAC 4B .0129.
As of April 1, 2019, all new construction activities are required to complete and submit an electronic Notice
of Intent (eNOI) form requesting a Certificate of Coverage (COC) under the NCGO10000 Construction
General Permit. After the form is reviewed and found to be complete, you will receive a link with payment
instructions for the $100 annual permit fee. After the fee is received, you will receive the COC via
email. You MUST obtain the COC prior to commencement of any land disturbing activity. The eNOI
form maybe accessed at decnc.s?ov/NCG01. Please direct questions about the eNOI form to Annette Lucas
at Annette.Lucas ncdenr. ov or Paul Clark at Paul.Clark(&ncdenr.gov. If the owner/operator of this
project changes in the future, the new responsible party is required to apply for his/her own COC.
Title 15A NCAC 4B .0118(a) and the NCGO1 permit require that the following documentation be kept on
file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCGO1 permit and the COC, once it is received.
3. Records of inspections made during the previous 12 months.
No th C.aroltna D®partnient of Gnvlronmental QunG:t Divtsinn cN [nervy. Mineral and Land krsour,,ei;
Q. E Raleigh Rr,lional OI'Ftrcc 108 M&I Service. Centrr 380013am tt Drirr Raleigh, 4orlh CarnYna 27htly
Q�
a7a`w wv m :om�N � 919791_ L2())
Letter of Approval with Modifications
ATTN: Virginia Rand Bowman
June 16, 2020
Page 2of7
Also, this letter gives the notice required by G.S. 1 13A-61.1(a) of our right of periodic inspection to insure
compliance with the approved plan.
Title 15A NCAC 413.011 S(a) requires that a copy of the approved erosion control plan be on file at the job
site. Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection to
insure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance -oriented, requiring protection of
existing natural resources and adjoining properties. If, following the commencement of this project, it is
determined that the erosion and sedimentation control plan is inadequate to meet the requirements of the
Sedimentation Pollution Control Act of 1973 (North Carolina General Statute l 13A-51 through 66), this
office may require revisions to the plan and implementation of the revisions to ensure compliance with the
Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State water
quality laws, regulations, and rules. In addition, local city or county ordinances or rules may also apply to
this land -disturbing activity. This approval does not supersede any other permit or approval.
Please note that this approval is based in part on the accuracy of the information provided in the Financial
Responsibility Form, which you provided. You are requested to file an amended form if there is any change
in the information included on the form. This permit allows for a land -disturbance, as called for on the
application plan, not to exceed the approved acres_ Exceeding the acreage will be a violation of this permit
and would require a revised plan and additional application fee. In addition, it would be helpful if you notify
this office of the proposed starting date for this project. Please notify us if you plan to have a preconstruction
conference.
Your cooperation is appreciated.
Sincerely,
Assistant Regional Engineer
Land Quality Section
Enclosures: Certificate of Approval
NPDES NCGO1 Fact Sheet
cc: Nathan Hymiller, PLS (p1s30I QMaol.com) — Electronic Copy
Virginia Rand Bowman (gianyb@ngaterealtyxom) — Electronic Copy
Regional Office file
Letter of Approval with Modifications
ATTN: Virginia Rand Bowman
June 16, 2020
Page 3 of 7
MODIFICATIONS REQUIRED FOR APPROVAL
Project Name: Waterside Lane
Project ID: VANCE-2020-005
County: VANCE
1. Provide a legend with symbolslicons to identify all proposed erosion and sedimentation control
measures. Measures are to be to scale. Use the symbols to identify the proposed location of
the structures on the plan. (GS113A-57(3), 15A NCAC 04B .0105,15A NCAC 04B .0106(5))
• Identify and label temporary diversion ditches on the plan sheet.
• Include the baffles, skimmers, and spillways within the footprint of each basin.
2. Provide identifiers for the proposed ESC devices (basins, ditches, etc.) on plan sheets that
correspond with supporting calculations. (113A-57(3), 15A NCAC 04B .0105, 15A NCAC
04B A 106(5), and NCGO I Part 11 Section A (4)).
3. Include the elevations associated with the contours on the plan sheets. (GS113A-57(3), 15A
NCAC 04B .0105, 15A NCAC 04B A 106(5))
4. Provide the location of the site, to scale as near as possible, on a USGS quad map and on the
most recent paper -bound version of the Natural Resources Conservation Service (MRCS) soil
survey map. Delineate the project limits on these maps. (GS 113A-57.4(c), 15A NCAC
04B .0105, 15A NCAC 04B .0106(a)(1) and (a)(3))
5. Per the topo map provided it appears there is a stream within the limits of disturbance and a
pond adjacent to the limits of disturbance. Identify the streams and and wetlands on the plan
sheets. Include any additional measures needed to protect these areas. (GS 113A-54.1(a), 15A
NCAC 04B .0106)
6. If applicable, provide a copy of the USACE 404 permit and DWR 401 certification for the
office file. Submit documentation with maps showing location and extent of impacts to
streams and wetlands with any special conditions pertaining to erosion and sediment control
and restoration of affected areas. Identify the streams and wetlands on the plan sheets. Identify
the permitted impacts and impact areas on the erosion and sedimentation control plan sheets to
correspond with the USACE and DWR documents. Include any additional measures,
construction specifications, maintenance requirements and construction sequencing as required
by the 404/401 on the plan sheets. (GS 113A-54.1(c), 15A NCAC 04B .0106(1))
7. Provide a detailed/specific construction sequence that coordinates the timing of land -disturbing
activities with the installation and removal of all proposed erosion and sedimentation control
measures. Address the conversion of temporary structures that will be converted to permanent
Letter of Approval with Modifications
ATTN: Virginia Rand Bowman
June 16, 2020
Page 4of7
structures (i.e. temporary diversion ditches converting to permanent roadside ditches). (15A
NCAC 04B. 0106(5))
• Note that construction activities that have an E&SC Plan approved on or after April 1,
2019 are required to fill out and submit an electronic Notice of Intent (e-NOI) form.
All construction activities are required to follow the new NCGOI permit regardless of
when they were approved.
• The NCGO1 Ground Stahilization and Materials Handling Plan Sheet must be added
to the plans. A pdf and an AutoCAD version are located at deq.nc_gov/NCG01..
• The NCGOI Inspection, Recordkeeping, and Reporting Plan Sheet must be added to
the plans. A pdf and an AutoCAD version are located at dgq.nc.gov/NCGOl.
• Add the following statement to the construction sequence: "Erosion and Sediment
Control (E&SC) permit and a Certificate of Coverage (COC) must be obtained before
and land disturbing activities occur." The COC can be obtained by filling out the
electronic Notice of Intent (e-NOI) form at dcq.nc.gov/NCGO1. Please note, the c-
NOI form may only be filled out once the plans have been approved. A copy of the
E&SC permit, the COC, and a hard copy of the plan must be kept on site, preferably
in a permits box, and accessible during inspection.
• Add a requirement to the construction sequence to contact the DEMLR Raleigh
Regional Office at least 48 hours prior to commencing the land -disturbing
activity. The contact number is (919) 791-4200. (15A NCAC 04B .106(b))
• Provide a detailed site -specific construction sequence the removal of the basins. Basins
may not be removed until all upland areas are permanently stabilized. Detail the use of
silt bags in the construction sequence. (GS 113A-57(3), 1 SA NCAC 04B .0113)
• Add the following statement to the construction sequence: "The contractor shall
conduct self -inspections of the erosion and sedimentation control measures and
compete the following combined self -inspection form found on the DEMLR website
https://files.nc v-ov/ncdeq/ ncray%2OMincral°/a20and°/a2OLand°/`2OResources/Storm
wwater/NPDES%20General%2OPermits/DEMLR-CSW-Monitoring-Form-Rev-
August-8-2019.pdf . Twelve months of complete inspection forms shall be kept on -site
and available for inspection at all times. It is recommended a copy be kept in a permits
box." (GS 113A-54.1 (e), 15A NCAC 04B.0131, NCGO1 Part Ill Sections A and B)
• Add the following statement to the construction sequence, "When the project is
complete, the pennittee shall contact DEMLR to close out the F.c4tSC Plan." After
DEMLR informs the permittee of the project close out, via inspection report, the
penruttee shall visit deq.nc.gov/NCGOI to submit an electronic Notice of Termination
(e-NOT). A $100 annual general permit fee will be charged until the e-NOT has been
filled out.
• Add the following statement to the construction sequence: "Self -inspections for
erosion and sedimentation control measures are to be performed at least once every
seven calendar days and within 24 hours of every rain event of greater than 1 inch. Any
needed repairs shall be trade immediately to maintain measures as designed. All ESC
measures shall be maintained as specified in the construction details on this plan."
Letter of Approval with Modifications
ATTN: Virginia Rand Bowman
June 16, 2020
Page 5 of 7
Provide stockpiletstaging areas, concrete washouts, and dedicated areas for demolition,
construction, and other wastes. These areas are to be within the limits of disturbance and
should be located at least 50 feet away from storm drain inlets, temporary diversions, channels,
and surface water bodies. Identify the location of these areas and structures on the plan
sheets. Provide adequate measures around the stockpile areas. A revised Financial
Responsibility/Ownership Form and additional fee may be necessary, if the total disturbed
acreage exceeds the original submittal. (GS113A-57(3), 15A NCAC 04B .0105, 15A NCAC
04B .0106(5), GS 113A-57(4), NCGO 1 Section H.F)
9. Provide a structure/device for dewatering the temporary basins prior to removal. Silt bags are
typically used for this purpose. Provide a plan detail, construction specifications, and
maintenance requirements for this device. Include a symbol/icon on the legend for this structure.
Detail the use of this device in the construction sequence. Include the location of the sediment
filter bag on the plan sheets. (GS 113A-57(3), 15A NCAC 0413.0113)
10. Identify and label temporary diversion ditches on the plan sheet. Diversion ditches must have
a stable conveyance as they enter basins/traps. Show the stable conveyance on the plan sheet.
Provide a plan detail, construction specifications, and maintenance requirements for the stable
conveyance. (GS 113A-57(3), 15A NCAC 04B .0113)
11. Drainage areas exceeding one acre must have a properly designed surface dewatering device
(Basins 9 and 10 are to be designed as skimmer basins). It is recommended that areas that have
less than one acre of drainage area utilize sediment traps. Identify baffles and spillways on the
plan sheet. Provide a plan detail, construction specifications, and maintenance requirements for
the sediment traps. Provide calculations for sediment traps. See attached spreadsheet. (GS
11 3A-57(3),15A NCAC 0413.0113)
12. Check dams with weirs may be better suited for drainage areas with drainage areas less than
0.5 acres. These devices off sediment storage capacity but do not require baffles. If check
dams are being utilized, identify on the plan sheets. Provide a plan detail, construction
specifications, and maintenance requirements for the check dams with weir. Provide
calculations for the sediment storage area and include the dimensions of these areas on the plan
sheets. (GS 11 3A-57(3),15A NCAC 04B .0113)
13. If skimmer basins are being utilized, please identify baffles, skimmer orientation, and
emergency spillway on the plan sheet. Provide silt fence outlets adjacent to skimmer outlets.
(GS 11 3A-57(3),15A NCAC 04B .0113)
14. Identify silt fence outlets on the plan sheet. Provide an icon/symbol for the silt fence outlets.
(GS 11 3A-57(3),15A NCAC 04B .0113)
15. It appears basins 3 through 10 are located within fill material. Basins are to be installed before
clearing and grading and may not be removed until permanent stabilization has been
established. Please verify how basins will be installed in fill material.
Letter of Approval with Modifications
ATTN: Virginia Rand Bowman
June 16, 2020
Page 6of7
lb. Provide a plan detail, construction specifications, and specific maintenance requirements for
all proposed sediment and erosion control structures included on the plan (i.e. temporary
diversions, permanent roadside ditches, check dams with weir, sediment trap, skimmer, porous
baffles, pipe inlet protection). Recommend placing maintenance requirements with the
associated construction detail. (GS I I3A-57(3), 15A NCAC 04B .0113)
17. Provide a plan detail and construction specifications for the silt fence and silt fence outlet that
complies with the skirt trench requirements per the Erosion and Sediment Control Planning
and Design Manual. The skirt is to be trenched in, at a minimum, 8 inches vertically and 4
inches horizontally. (GS 113A-57(3), 15A NCAC 0413.0113)
18. Provide a plan detail and construction specifications for the construction entrance that complies
with the requirements per the Erosion and Sediment Control Planning and Design Manual. The
minimum width of the entrance is to be 12 feet. (GS 113A-57(3), 15A NCAC 04B .0113)
19. Construction specifications for the skimmer basin are to include the excavation, embankment
construction, spillway construction, and skimmer basin installation. Specify on the plan detail
that an impermeable liner is to be installed on the spillway. The emergency spillway is to be
installed in undisturbed ground (not over the skimmer pipe). Include a stone pad for the
skimmer to rest upon and a rope attached to the skimmer for maintenance in the plan
detail. Include the basin surface area dimensions, depth, side slopes, dam height, embankment
width, length of emergency spillway, skimmer size, skimmer orifice size, and dewatering time
on the plan sheets. (GS 113A-57(3), 15A NCAC 04B .0113)
20. Provide design calculations for cross sections and method of stabilization for the planned
channels and the temporary diversions. Include appropriate permissible velocity and/or shear
stress data. Provide a plan detail to include the swale dimensions (bottom width, side
slopes). (GS 113A-57(3), 15A NCAC 04B .0113)
21. Provide liners/matting to aid the stabilization of planned channels and temporary diversions
when the runoff velocity will exceed 2 ft/sec on bare earth during the 2-year rainfall event that
produces the peak runoff. The product(s) selected must have a permissible shear stress that
exceeds the shear stress of the design ntnoff event. If liners/matting is to he installed, provide
a plan detail, construction specifications, and maintenance requirements. Include the
installation of liners in the construction sequence. (GS 113A-57(3), 15A NCAC 04B .0113)
22. This plan approval is for streets, utilities and sediment and erosion control measures only. Land
disturbing activity on individual lots is not approved with this plan review. Before house
construction begins on the lots, a plan showing the individual lot measures will be
required. Provide a note to this effect on the plan sheet. (GS 113A-57(3), 15A NCAC 04B
.0105, 15A NCAC 04B .0106(5))
Letter of Approval with Modifications
ATTN: Virginia Rand Bowman
June 16, 2020
Page 7 of 7
23. Consideration should be given to avoiding Sericia Lespedeza as it is considered an invasive
species, per NC State University/AT&T University Cooperative Extension. The Extension
recommends the following alternative native species: Switchgrass (Panicum virgatum),
Splitbeard Bluestem (Andropogon ternarius), Partridge Pea (Chamaecrista fasciculata).
24. Consideration should be given to avoiding Tall Fescue as it is considered an invasive species,
per NC State University/AT&T University Cooperative Extension. The Extension
recommends the following alternative native species: Switchgrass (Panicum virgatum), Big
bluestem (Andropogon gerardii), Little bluestem (Schizachyrium scoparium), Indian grass
(Sorghastrum nutans), Beaked panicgrass (Panicum anceps), Purpletop (Tridens flavus),
Broomsedge (Andropogon virginicus), Deer tongue (Dicanthelium clandestinum), Canadian
wildrye (Elymus canadensis), Virginia wildrye (Elymus virginicus), Sensitive partridge pea
(Chamaecrista nictitans), and Partridge Pea (Chamaecrista fasciculata).
25. Provide two copies of the plan set (one full-size and one half-size), showing the
modifications required for approval prior to initiating land disturbing activity. To
facilitate DEMLR review, bubble, highlight, or otherwise identify the changes to your
resubmittal. Provide one copy of additional items (such as design calculations). Provide a
cover letter referencing the project name, project ID, and purpose for submittal. (G.S. 113A-
57(4))
Ref: G.S. 113A-54.1 through G.S. 113A-57
Sections 15A NCAC 04A.0101 through 15A NCAC 04E.0504
General Permit NCG 010000 NPDES for Construction Activities