HomeMy WebLinkAboutNC0001422_Appdx N - Remedial Alternative Cost Estimate Details_20200814Corrective Action Plan Update August 2020 L.V. Sutton Energy Complex SynTerra APPENDIX N REMEDIAL ALTERNATIVE COST ESTIMATE DETAILS Table 1: Summary of Capital and Annual Costs Source Area 1 - Remedial Alternative 2 Source Area 2 - Remedial Alternative 2 L.V. Sutton Energy Complex Wilmington, NC Capital Costs TASK # TASK UNIT QUANTITY RATE COST 1.0 Design/Engineering/Site Preparation Pre -Design Field Planning and Modeling LUMP SUM 1 $75,000 $75,000 Design Document/Work Plan LUMP SUM 1 $140,000 $146,000 Institutional Controls LUMP SUM 1 $20,000 $201000 $235,000 2.0 Monitoring Well Installation Monitoring Well Installation EACH 0 $0 $0 $0 3.0 Project Management Project Management (10% Capital Cost) LUMP SUM 1 $24,000 $24,000 $24,000 Total Capital Cost $259,000 Operations, Maintenance & Monitoring Costs TASK # TASK UNIT QUANTITY RATE COST 1.0 10perations and Maintenance Operations and Maintenance (Continued Groundwater Extraction at the Eastern Property Line) YEAR 5 $0 $0 $0 2.0 Effectiveness Monitoring Groundwater Sampling Event* YEAR 5 $0 $0 $0::::l 3.0 Reportin Annual Reporting EACH 5 $0 $0 Five -Year EMP Review Report EACH 1 1 $180,000 $180,600 $180,000 4.0 Project Management Project Management 10% Operations, Maintenance & Monitoring Cost LUMP SUM 1 $18,000 $18,000 $18,000 Total Operations, Maintenance, and Monitoring Cost $198,000 Present Worth Ana/vsis Year(s) I Cost Type Total Cost Discount Factor Present Value 0 ICapital Costs $259,000 1.000 $259,000 1-5 Operations, Maintenance & Monitoring $0 4.076 $0 5 1 Five -Year EMP Review Report $198,000 0.784 $155,138 Total Life Cycle Cost $415,000 Notes: 1. *Costs for sampling the existing monitoring wells are not included, as existing well monitoring is budgeted in Duke Energy's Asset Retirement Obligation program 2. Life cycle represents net present value of expenditures with capital costs incurred in Year 0 and annual costs incurred thereafter. Discount Rate of 5% assumed. 3. Costs presented herein represent a best estimate at this time. Actual costs may change based on a variety of factors during implementation. Page 1 of 1