From: Ross Godwin <rgodwin@trianglesitedesign.com>
Sent: Friday, July 31, 2020 1:04 PM
To: Zorio, Stephanie
Subject: Re: [External] RE: Starbucks - Strickland Bridge / Raeford Rd - Sewer permitting
Follow Up Flag: Follow up
Flag Status: Flagged
7External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
report.spam@nc.gov
Stephanie
I just spoke with the contractor and we are going to install the duplex pump and both will be the same size so
let's keep moving forward with the fast trace permit. I will send the flow tracking update from PWC as soon as
I get it.
Get Outlook for iOS
From: Zorio, Stephanie <stephanie.zorio@ncdenr.gov>
Sent: Friday, July 31, 2020 9:36:30 AM
To: Ross Godwin <rgodwin@trianglesitedesign.com>
Subject: RE: [External] RE: Starbucks - Strickland Bridge / Raeford Rd - Sewer permitting
Hi Ross,
Unfortunately, per 2T regulations simplex grinder systems cannot be permitted through the fast track process and must
be submitted to Raleigh for full technical review.
More information can be found here. Particularly under "Standard Sewer Extension Permitting":
https://deg.nc.gov/about/divisions/water-resources/water-resources-permits/wastewater-branch/collection-
systems/sewer-extension-permitting
Would you like us to mail your application fee check back to you or destroy it here?
Regards,
Stephanie
Dr. Stephanie D. Zorio
Environmental Specialist
Office: 910 433 3322
Cell: 919 368 6077
stephanie.zorio@ncdenr.gov
225 Green Street
Suite '714
Fayetteville, NC 28384
r: t — `2Vothing Compares_
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
1 am currently teleworking. If you need immediate assistance please contact a water resources staff member at our main
number, 910-433-3300.
From: Ross Godwin [mailto:rgodwin@trianglesitedesign.com]
Sent: Friday, July 31, 2020 9:11 AM
To: Zorio, Stephanie <stephanie.zorio@ncdenr.gov>
Subject: [External] RE: Starbucks - Strickland Bridge / Raeford Rd - Sewer permitting
CAUTIOrnal email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
nc. ov
Stephanie
Please see the attachment where I made the update for item #1. Also regarding item 2, we are using a single grinder
pump. I'm following up with PWC to get item #3. Unfortunately the person at PWC that I've been working with is out
this week which is not good because the contractor is looking to get rolling Monday morning.
Ross Godwin
Triangle Site Design, PLLC
From: Zorio, Stephanie <stephanie.zorio@ncdenr.gov>
Sent: Friday, July 31, 2020 8:51 AM
To: Ross Godwin<rgodwin@trianglesitedesign.com>; Matt Lowder<mlowder@trianglesitedesign.com>
Subject: Starbucks - Strickland Bridge / Raeford Rd - Sewer permitting
Good morning,
I just have a couple comments about your application before it can be processed.
1. #6 on page 6 of the application pdf: Please include a copy of the flow reduction approval letter if a flow
reduction has been approved under 2T guidelines. However, I feel this likely a simple typo.
2. Will the pump station be duplex?
3. The Flow -Tracking document needs to indicate pump stations that are located between the project and the
Rockfish wastewater treatment plant (part II).
Please provide an updated application. A digital copy can be sent directly to me and I'll be happy to append it.
Thank you,
Stephanie
Dr. Stephanie D. Zorio
Environmental Specialist
Office: 910 433 3322
Cell: 919 368 6077
stephanie.zorio@ncdenr.gov
225 Green Street
Suite 714
Fayetteville, NC 28384
— `Nothing Compares -,,,-
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
I am currently teleworking. If you need immediate assistance please contact a water resources staff member at our main
number, 910-433-3300.