FW: Deep River Road Realignment Permit
Euliss, Amy
Sent: Monday, November 23, 2009 12:10 PM
To: Carrillo, Sonia
Please add to 2009-1106. Thanks.
From: Andrews, Richard [mailto:Richard.Andrews@stantec.com]
Sent: Monday, November 23, 2009 12:07 PM
To: Euliss, Amy
Subject: Deep River Road Realignment Permit
Amy,
Per our conversation and the permit conditions required by NCDWQ, the culvert extension at UT-2 of the Deep River
Road Realignement Project will be installed "in-the-dry". Due to the relatively small quantity of flow in UT-2, it can be
characterized as primarily transporting storm water from the existing road during precipitation events. To comply with
permit conditions, scheduling of the installation of the pipe will be done when zero flow is observed from the existing
culvert. If flow is occuring at the time of construction, a temporary barrier will be installed at the outfall of the upstream
catch-basin in order to stop flow during the construction and create dry conditions in the impacted stream channel. If dry
conditions cannot be achieved from a barrier alone, a pump-around system will be used without creating any temporary
impacts downstream.
Richard Andrews
Environmental Scientist
Stantec
801 Jones Franklin Road Suite 300
Raleigh NC 27606
Ph: (919) 865-7583
Fx: (919) 851-7024
Cell: (919) 280-3265
richard.andrews@stantec.com
stantec.com
The content of this email is the confidential property of Stantec and should not be copied, modified, retransmitted, or used for any
purpose except with Stantec's written authorization. If you are not the intended recipient, please delete all copies and notify us
immediately.
® Please consider the environment before printing this email.
https://mail.nc.gov/owa/?ae=Item&t=1 PM.Note&id=RgAAAADMSzLcd9 W2TJH14%2bmA°/`2I%... 2/8/2010