Loading...
HomeMy WebLinkAbout19950324 Ver 1_Complete File_19950327- 'D?m?g532y - _ ? 4 3 6 YS i (G95 STATE OF NORTH CAROLINA DEPARTMENT OF TRANSPORTATION JAMES B. HUNT. JP. R. SAMUEL HUNT III GOVERNOR P.O. BOX 25201, RALEIGH, N.C. 27611-5201 SECRETARY March 13, 1995 District Engineer \ US Army Corps of Engineers `•'i P. 0. Box 1890 Wilmington, North Carolina 28402-1890 Attention Regulatory Branch Dear Sir: Subject: Sampson County, Widening of SR 1311 (North Boulevard) in Clinton, Federal Aid No. STP-1311(2), State Project No. 8.2280701, TIP Project No. U-2514 and COE Action ID. No. 199300258. The North Carolina Department of Transportation proposes to improve a one mile section of SR 1311 from US 421 to SR 1838 in Clinton. The improvements consist of widening the existing two lane, twenty-four foot section to a five lane, sixty-four foot curb and gutter section except at the 701 interchange. At this interchange a fifty-nine foot curb and gutter section that retains-the existing bridge over US 701 is proposed. The project also includes the construction of a temporary detour at an unnamed tributary of Williams Old Mill Branch. Please find enclosed a copy of the project planning report for the above referenced project. The project is being processed by the Federal Highway Administration as a Categorical Exclusion in accordance with 23 CFR 771.115 (b). Therefore,-we-anticipate that this activity will be authorized under Nationwide Pei it .?33 CFR 330 Appendix A(b)(23). All conditions of this Nationwide Permit will be followed during the construction of the project. The enclosed CE indicates that the project will result in 0.76 acres of wetland impacts. These impacts would occur by crossing two unnamed tributaries of Williams Old Mill Branch. The document also states that temporary detours will be necessary at these two crossings resulting in wetland impacts. However, since the CE was completed in October 1994 additional measures have been taken to avoid and minimize wetland impacts. The final hydraulics analysis reduced the impacts associated with the two crossings and determined that only one detour would be necessary. This temporary detour will be D March 13, 1995 Page 2 required for the tributary located 1500 feet east NCDOT Highway Maintenance Facility (see CE aerial anticipated wetland impacts as currently proposed Site 1: Tributary 500 feet east of US 421 Site 2: Tributary 1500 feet east of US 421 Temporary Detour: located At site 2. Total of US 421 adjacent to the photograph). The are as follows: 0.01 acres 0.14 acres 0.09 acres 0.24 acres As a result, we anticipate that a 401 General Certification No. 2745 will apply to this project, and are providing one copy of the CE document to the North Carolina Department of Environment, Health and Natural Resources for this project. If you have any questions concerning this project, please do not hesitate to call Scott P. Gottfried at 919-733-3141. Sincerely, H. Franklin Vick, P.E., Manager Planning and Environmental Branch HFV/so Enclosures cc: Mr. Ernie Jahnke, COE Wilmington Field Office Mr. John Dorney, DEM Mr. Jimmy Lee, PE, Bridge Maintenance Unit Mr. Don Morton, PE, Highway Design Branch Mr. A. L. Hankins, PE, Hydraulics Mr. John Smith Jr., PE, Structure Design Mr. Tom Shearin, PE, Roadway Design Unit Mr. D. J. Bowers, Division 3 Engineer Ms. Ellen Lorscheider, Geotechnical Unit Mr. Kelly Barger, Program Development Clinton, Sampson County, SR 1311 (North Boulevard) From US 421 to SR 1838 (Beaman Street) Federal Aid Project No. STP-1311(2) State Project No. 8.2280101 TIP No. U-2514 CATEGORICAL EXCLUSION U. S. DEPARTMENT OF TRANSPORTATION FEDERAL HIGHWAY ADMINISTRATION AND N. C. DEPARTMENT OF TRANSPORTATION DIVISION OF HIGHWAYS APPROVED: A, a e H. Fran in Vic P. E., anager Planning and Environmental Branch, NCDOT ff 4 't 57 L 44 Date Nic L. Graf, P. E. wz Divis on Administrator, FHWA t° 4 2 Clinton, Sampson County, SR 1311 (North Boulevard) From US 421 to SR 1838 (Beaman Street) Federal Aid Project No. STP-1311(2) State Project No. 8.2280701 TIP No. U-2514 0 CATEGORICAL EXCLUSION r Documentation Prepared in Planning and Environmental Branch By: C amue Keith Jr. Project Planning Engineer Linwood tone Project Planning Unit Head ss ?r??EESSi?•f? `e- SEAL /0 9?= 6944 ic ar B. Davis, P. %?'i•.ENC?NEEQ?.•`,:?. Richard- Assistant Manager, Planning and Environmental Bf?Q '••........•• pJ I 4 Summary of Environmental Commitments This document calls for the following environmental commitment: A. Two service stations are located at the western end of the project with four petroleum storage tanks located on site. The recommended alternative (symmetric widening) will not require the removal of any of these storage tanks. If this recommendation is not followed, some of these tanks may need to be removed. ppp? I I 4 TABLE OF CONTENTS PAGE 1 I. DESCRIPTION OF THE PROPOSED ACTION ......................... 1 A. General Description ................................... 1 B. Summary of Proposed Improvements ...................... 1 1. Project Termini .................................. 1 2. Project Length ................................... 1 3. Cross Section.. ............................... 2 4. Right of Way Width ............................... 2 5. Access Control ................................... 2 6. Drainage Structures.. . ......................... 2 7. Design Speed and Speed Zones .............. 3 8. Intersection Treatment and Type of Control....... 3 9. Railroads ........................................ 3 10. Parking.. ................................. 3 11. Bicycle Provisions ............................... 3 12. Sidewalks ........................................ 3 13. Utilities ........................................ 4 14. Cost Estimate .................................... 4 II. NEED FOR THE PROPOSED PROJECT .............................. 4 A. Existing Roadway Inventory ............................ 4 J 1. Cross Section .................................... 4 2. Right of Way.. . ... .................... 4 3. Type of Roadside Development ..................... 4 4. Structures.. .................................. 4 5. Access Control ................................... 4 6. Speed Zones..... ... ....... . ... ......... 4 7. Intersecting Roads and Types of Control .......... 5 8. Railroads ........................................ 5 9. Sidewalks ........................................ 5 10. Utilities.. .................................... 5 11. Geodetic Markers ................................. 5 12. School Buses ..................................... 5 B. Functional Classification ............................. 5 C. Traffic Volumes and Capacity .......................... 6 1. Signalized Intersections ......................... 6 2. Unsignalized Intersections ....................... 8 E. Accident History ...................................... 8 TABLE OF CONTENTS (Continued) PAGE III. RECOMMENDED IMPROVEMENTS AND ALTERNATIVES CONSIDERED....... 9 A. Recommended Improvements.... ........................ 9 B. Other Alternatives Considered ......................... 9 IV. ENVIRONMENTAL IMPACTS ...................................... 10 A. Social Environment .................................... 10 1. Neighborhood Characteristics ..................... 10 2. Public Facilities ................................ 10 3. Cultural Resources ............................... 10 a. Architectural Resources ..................... 10 b. Archaeological Resources .................... 10 4. Relocation Impacts ............................... 11 B. Economic Environment .................................. 11 C. Land Use .............................................. it 1. Scope and Status of Planning ..................... 11 2. Existing Zoning .................................. 11 3. Existing Land Use ................................ 11 4. Future Land Use .................................. 12 5. Farmland ......................................... 12 D. Natural Environment ................................... 12 1. Ecological Resources ............................. 12 a. Terrestrial Communities ..................... 13 b. Aquatic Communities.. .... ... ...... 17 C. Anticipated Impacts: Biotic Communities ..... 19 2. Protected Species ................................ 22 a. Federally Protected Species ................. 22 b. Federal Candidate Species ................... 23 C. State Protected Species ..................... 24 3. Physical Resources ............................... 24 a. Geology, Topography, and Soils .............. 24 b. Water Resources ............................. 25 C. Floodplain Involvement ...................... 26 d. Wetlands .................................... 26 4 4. Air Quality and Traffic Noise .................... 26 TABLE OF CONTENTS (Continued) PAGE E. Contaminated Properties ............................... 33 F. Construction Impacts .................................. 34 G. Permits ............................................... 35 H. Mitigation ............................................ 36 V. COMMENTS AND COORDINATION .................................. 36 A. Comments Received... . ......................... 36 B. Citizens Informational Workshop ....................... 36 C. Public Hearing ........................................ 37 FIGURES Figure 1 - Vicinity Map Figure 2 - Aerial Mosaic - Symmetric Widening (Recommended) Figure 3a - Projected Traffic Volumes Figure 3b - Projected Traffic Volumes Figure 4a - Proposed Intersection Geometrics at US 421 Figure 4b - Proposed Intersection Geometrics at SR 1838 Figure 4c - Existing Intersection Geometrics at US 421 Figure 5a - Roadway Typical Section Figure 5b - Proposed Bridge (US 701) Typical Section Figure 6 - Clinton Thoroughfare Plan Figure 7 - Wetland Locations Figure 8 - 100-Year Flood Zones APPENDIX Appendix A - Agency Comments Appendix B - Air Quality and Traffic Noise Data r I 4 Clinton, Sampson County, SR 1311 (North Boulevard) From US 421 to SR 1838 (Beaman Street) Federal Aid Project No. STP-1311(2) State Project No. 8.2280701 TIP No. U-2514 1. DESCRIPTION OF THE PROPOSED ACTION A. General Description The North Carolina Department of Transportation (NCDOT), Division of Highways, proposes to improve a one-mile section of SR 1311 (North Boulevard) from US 421 to SR 1838 (Beaman Street) in Clinton, Sampson County (see Figures 1 & 2 for project location). The improvements consist of widening the existing two-lane, 24-foot section to a five-lane, 64-foot curb and gutter section except at the US 701 interchange. At the interchange, the proposed cross section is a five-lane, 59-foot curb and gutter section that retains the existing bridge over US 701. This section will consist of two travel lanes in each direction and a continuous center turn lane. The proposed widening is symmetrical about the centerline of SR 1311 and requires the acquisition of approximately 20 feet of right of way. Temporary construction easements are necessary in addition to required right of way. This project is included in the 1995-2001 Transportation Improvement Program (TIP) with the total cost estimated at $2,290,000. This estimate includes $240,000 for right of way, $1,850,000 for construction, and $200,000 for prior funding. The current estimated cost of this project is $1,921,900, which includes $1,500,000 for construction and $421,900 for right of way acquisition. The project is scheduled in the TIP for right of way acquisition in Federal Fiscal Year 1995 (FFY 1995) and construction in FFY 1996. No adverse environmental impacts are anticipated from the proposed improvements. The project has been coordinated with the appropriate state and regional review agencies, federal permit agencies, and local government officials. B. Summary of Proposed Improvements 1. Project Termini The project's western terminus is US 421 and its eastern terminus is SR 1838 (Beaman Street) (see Figures 1 & 2). 2. Project Length The length of the proposed improvements to SR 1311 total 1.0 mile. 2 3. Cross Section The proposed cross section provides a five-lane, 64-foot curb and gutter section with two 12-foot wide travel lanes in each direction and a 12-foot wide continuous center turn lane except at the US 701 interchange. The proposed cross section across the bridge at the US 701 interchange is a five-lane, 59-foot curb and gutter section containing two 11-foot travel lanes in each direction and an 11-foot continuous center turn lane. A center turn lane is necessary across the bridge in order to allow left turns onto the ramps at each end of the bridge. This cross section uses the existing 59-foot bridge at this interchange. The NCDOT Structure Design Unit analyzed the bridge and determined that widening the bridge an additional two feet on each side would overstress the exterior girders. Due to these overstresses, and the fact that there is no reasonable design or retrofit method that will correct the potential overstresses, bridge widening is not recommended as a part of this project. The widening will be symmetric about the centerline of existing SR 1311 (North Boulevard). 4. Right of Way Width A right of way width of 80 feet is needed to contain the proposed five lane curb and gutter section. In addition to this right of way, temporary construction easements will be necessary. 5. Access Control There is no control of access along the project, except in the area of the US 701 interchange. No additional control of access is proposed as a part of project U-2514. 6. Drainage Structures There are two large drainage structures along this project. The first structure, located approximately 1500 feet east of the west terminus, is a 60-inch corrugated metal pipe on an unnamed tributary to Old Mill Creek. A preliminary hydraulic analysis indicates that this structure is slightly undersized and should be replaced with a 10-foot by 8-foot reinforced concrete box culvert (RCBC) at the same location with approximately the existing roadway grade. Due to the high traffic volume on SR 1311 and the absence of a suitable detour, a temporary detour is recommended. The recommended drainage structure for this detour is a 48-inch diameter pipe. A minor channel change may be required in conjunction with this culvert replacement. The second major drainage structure involved is a 72-inch reinforced concrete pipe (RCP) approximately 1500 feet from the east project terminus. A preliminary hydraulic analysis indicates that it is also undersized; therefore it is recommended that the existing 72-inch pipe be removed and replaced with a 9-foot by 6-foot reinforced concrete box culvert (RCBC) at the same location and with approximately the existing roadway grade. This culvert replacement will also require a temporary detour. The recommended structure for the detour is a 36-inch pipe. 1 4 7. Design Speed and Speed Zones The proposed roadway section will have a design speed of 50 miles per hour (mph). The posted speed limit is 45 mph from US 421 to the US 701 interchange and 35 mph from the US 701 interchange to SR 1838 (Beaman Street). The posted speed limits of 45 mph and 35 mph will be retained. 8. Intersection Treatment and Type of Control All roadway intersections will be at-grade with the exception of the US 701 interchange. A sketch of the proposed intersection treatments are shown in Figures 4a and 4b. 9. Railroads This project does not affect a railroad or rail corridor. 10. Parking Parking is presently not permitted and will not be provided for or permitted along the project. 11. Bicycle Provisions This section of SR 1311 in Clinton is not included in the TIP for bicycle improvements nor is it a part of the Bicycling Highway Program. For these reasons, no special accommodations for bicycles are recommended as a part of this project. 12. Sidewalks Currently, there are no sidewalks along this section of SR 1311. The City of Clinton has asked that sidewalks be constructed along the north side of SR 1311 from the Northside Plaza shopping center to SR 1838 (see letter in Appendix). A sidewalk is justified along this portion of SR 1311 because of the pedestrian traffic generated by the shopping center and the residences in the neighborhood adjacent to SR 1311. The total construction cost for the sidewalk is $19,200. NCDOT will participate in 80 percent ($15,360) of the cost and the city of Clinton will be responsible for the remaining 20 percent ($3,840) as outlined in the NCDOT Pedestrian Policy Guidelines. An 8-foot berm will be constructed behind the curb along the remainder of the project to allow future sidewalk construction. 13. Utilities Overhead electric lines exist along the project. Telephone, cable television, gas, water, and sanitary sewer lines exist underground along the project. Utility conflicts are expected to be moderate. 4 A. 14. Cost Estimate The estimated cost for the recommended symmetric widening alternative is $1,921,900 which includes $1,500,000 for construction and $421,900 for right of way acquisition. II. NEED FOR THE PROPOSED PROJECT Existing Roadway Inventory 1. Cross Section The existing roadway consists of a two-lane, 24-foot, shoulder section. 2. Right of Way The existing right of way width is approximately 60 feet. 3. Type of Roadside Development Roadside development is mainly commercial, light commercial, and residential. 4. Structures Bridge number 52 over US 701 was built in 1972 as part of State Project Number 8.1273003. This bridge is 59 feet wide from rail to rail and has a sufficiency rating of 95.4 out of a possible 100. There are two large drainage structures within the project limits. The first, located approximately 1500 feet from the west terminus, is a 60-inch corrugated metal pipe on an unnamed tributary to Old Mill Branch. The second major drainage structure is a 72-inch reinforced concrete pipe (RCP) located approximately 1500 feet from the east project terminus (See Section I. B. 6. for recommended structure improvements). 5. Access Control Control of access exists along the project only in the area of the US 701 interchange. 6. Speed Zones The posted speed limit is 45 mph from the west project limit (US 421) to the US 701 interchange and 35 mph from the interchange to the east project limit (SR 1838). 5 7. Intersecting Roads The following eight roadways intersect SR 1311 (North Boulevard): 1. US 421 2. SR 1834 (Industrial Drive) 3. US 701 Bypass 4. Lakeview Drive 5. Jasper Street 6. Connie Court 7. Lloyd Street 8. SR 1838 (Beaman Street) All streets intersect SR 1311 at grade except US 701 which has an interchange. US 421 is a signalized intersection. All other intersections along the project are unsignalized and stop sign controlled. 8. Railroads No rail corridors are located in the project area. 9. Sidewalks No sidewalks exist along either side of SR 1311. 10. Utilities Overhead electric lines exist along the proposed project. Telephone, cable television, gas, water, and sanitary sewer lines exist underground along the project. Utility conflicts are expected to be moderate. 11. Geodetic Markers No geodetic survey markers are located within the project area. 12. School Buses Four school buses make two trips each per day for a total of eight bus trips per day along the project. The Clinton City Schools administrative staff and Board of Education reviewed the proposed improvements and support the project. B. Functional Classification and Thoroughfare Plan SR 1311 is designated a major thoroughfare on the mutually adopted Clinton Urban Area Thoroughfare Plan and is classified as a rural major collector. The route is not part of the Federal-Aid system. Figure 6 shows a portion of the current adopted thoroughfare plan. The proposed improvements are in conformance with the thoroughfare plan and will be a step towards its implementation. 6 C. Traffic and Capacity Analysis The current (1992) average daily traffic (ADT) volumes along SR 1311 range from 5400 vehicles per day (vpd) to 9600 vpd. Projected design year volumes (2016) range from 11400 vpd to 22,400 vpd. These estimates of the daily traffic include 1 percent truck-tractor semi-trailers and 2 percent dual tired vehicles. The traffic carrying capacity of a roadway is described by levels of service (LOS) which range from A to F. Level of service A, the highest level of service, is characterized by very low delay in which most vehicles do not stop at all. Typically, drivers are unrestricted and turns are made freely. In level of service B, traffic operation is stable but more vehicles stop and cause higher levels of delay. Level of service C is characterized by stable operation, with drivers occasionally waiting through more than one cycle length at a traffic signal. At level of service D, the influence of congestion becomes more noticeable. Delay for approaching vehicles may be substantial during short periods of the peak hour. Level of service E is considered to be the limit of acceptable delay and represents the theoretical capacity of the facility. Level of service F represents over saturated or jammed conditions which are considered unacceptable to most drivers. 1. Signalized Intersections The intersection of US 421 and SR 1311 is the only signalized intersection along the project. At this intersection, US 421 is 64 feet wide. Both the northbound and southbound intersection approaches consist of one exclusive left turn lane, one through lane, and one through/right turn lane. At the westbound approach to the intersection, SR 1311 has a pavement width of 64 feet and has an exclusive right turn lane, a through lane, and an exclusive left turn lane. At the eastbound approach to the intersection, SR 1311 has a pavement width of 36 feet and has an exclusive left turn lane and a through/right turn lane. This intersection is one of the controlling factors for the traffic carrying capacity of SR 1311. A capacity analysis was performed for the existing and projected traffic volumes at this intersection. The analysis was performed for the " do nothing" alternative and the proposed widening alternative to provide a basis of comparison between the alternatives. The results of the analysis are shown in Tables 2 and 3. 7 Table 2 LEVEL OF SERVICE FOR SIGNALIZED INTERSECTIONS No Build Alternative Existing Construction Year Design Year Traffic Traffic Traffic (1992) (1996) (2016) Avg. Delay LOS Avg. Delay LOS Avg. Delay LOS Capacity Intersection (sec/veh) (sec/veh) (sec/veh) (Year) US 421 6.6 B 15.9 C * F 2009 NOTE: *Denotes an average intersection delay greater than 60 seconds per vehicle Table 3 LEVEL OF SERVICE FOR SIGNALIZED INTERSECTIONS Proposed Widening Alternative Existing Construction Year Design Year Traffic Traffic Traffic (1992) (1996) (2016) Avg. Delay LOS Avg. Delay LOS Avg. Delay LOS Capacity Intersection (sec/veh) (sec/veh) (sec/veh) (Year) US 421 N/A N/A 11.6 B 34.1 D N/A r Based on the results of the capacity analysis, the existing signalized intersection of SR 1311 and US 421 (see Figure 4d) is currently operating at an acceptable level of service (level of service D or better). The existing intersection will reach a level of service E in the year 2009 and level of service F in the year 2010. With the proposed improvements, this intersection will operate at a level of Service D in the year 2016. 8 2. Unsignalized Intersections An analysis was performed for the unsignalized intersection of SR 1311 and SR 1838 to determine the effects of the proposed widening and predicted future traffic volumes. If this intersection remains unsignalized, left turn movements from SR 1311 onto SR 1838 will reach level of service F in the year 1998. As the projected traffic volumes develop, the Area Traffic Engineering Staff will reevaluate this intersection and determine if signalization is warranted. The intersection of US 701 Bypass and SR 1311 is a standard diamond interchange. A capacity analysis was also performed for this interchange to determine the impacts of the projected traffic increase at the interchange ramp terminals. The results of the capacity analysis indicate these intersections do not warrant signalization as a a part of this project. Additional analysis of these intersections will be needed as projected traffic volumes develop to determine if signalization is warranted. D. Accident History A total of 41 accidents were reported along the studied portion of SR 1311 between April 1, 1987 and February 29, 1992. The primary types of accidents were rear-end collisions (36.6%), accidents involving left turn movements (26.8%), and accidents involving angle or sideswipe collisions (24.4%). These three types of accidents combine to account for 87.84 of all accidents on SR 1311. Forty six percent of the accidents occurred at the intersection of SR 1311 and US 421. The total accident rate for the studied section of SR 1311 is 263.0 accidents per 100 million vehicle miles (acc/100 mvm) compared to the state average of 199.2 acc/100 mvm for similar routes. This accident rate is substantially higher than the statewide average for similar routes. The proposed widening improvements will reduce the potential for the types of accidents which presently occur along the project. The proposed project will improve the overall safety and convenience for motorists using SR 1311. 17 III. RECOMMENDED IMPROVEMENTS AND ALTERNATIVES TO THE PROPOSED PROJECT 1 r A. Recommended Improvements The recommended alternative consists of widening the existing facility to a five-lane curb and gutter section (see Figure 5a). The proposed cross section is a 64-foot curb and gutter section, except at the US 701 interchange where a 59-foot curb and gutter section is recommended across the existing bridge over US 701. The roadway will be striped to provide five, 12-foot lanes. In the interchange area, the roadway will be striped to provide five 11-foot lanes (see Figure 5b). Proposed widening will be symmetric about the centerline of the existing roadway. Existing right of way claimed along the project is 60 feet, and the proposed construction will require 80 feet of right of way. Temporary construction easements beyond the right of way limits will be necessary. Symmetric widening uses the existing right of way in the project area and will not require relocating residences, non-profit organizations, or businesses. B. Other Alternatives Considered Since the project calls for widening an existing segment of roadway, no other corridor alternatives were considered. However, other alignment alternatives were considered including: (1) asymmetric widening on the north side of SR 1311, and (2) asymmetric widening on the south side of SR 1311. The estimated cost for the asymmetric widening to the north side of SR 1311 is $2,211,700 which includes $1,569,200 for construction and $642,500 for right of way acquisition. The estimated cost for asymmetric widening to the south side of SR 1311 is $2,219,000 which includes $1,519,200 for construction and $699,800 for right of way acquisition. Both of the asymmetric widening alternatives are more expensive than the symmetric alternative ($1,921,900) because they require relocations resulting in a higher right of way cost. Asymmetric widening on the north side would result in five relocatees and asymmetric widening on the south side would result in three relocatees. The displacement of residences and businesses would also have an undesirable impact on the local community. The "do nothing" alternative was also considered, but rejected. The proposed cross section will provide a safer environment to accommodate the current and projected traffic volumes. IV. ENVIRONMENTAL IMPACTS A. Social Environment 1. Neighborhood Characteristics Sampson County is located in eastern North Carolina, and is bounded by Wayne, Duplin, Pender, Bladen, Cumberland, Harnett, and Johnston Counties. The county seat of Sampson County is Clinton. According to the 1992 Updated Census Estimates furnished by the North Carolina State Data Center, Sampson County has a population of 489428. The 1990 Census Report indicated that Clinton has a population of 8,204. The County's population density (persons per 10 square mile) for 1990 was 50.02. The immediate neighborhood of the project area is characterized by commercial, institutional, and residential development (the names of the businesses and the institutions along the project are shown in Figure 2). The proposed action is not expected to disrupt social cohesion, nor will it interfere with the operation of existing facilities and services. 2. Public Facilities Public facilities in the area consist of a Highway Patrol Station, NCDOT County Maintenance Yard and District Engineers Office, and the North Carolina Department of Corrections Sampson County Unit. None of these facilities will be adversely impacted by the proposed action. 3. Cultural Resources a. Architectural Resources This project is subject to compliance with Section 106 of the National Historic Preservation Act of 1966 and the Advisory Council on Historic Preservation's Regulations for Compliance with Section 106, codified at 36 CFR Part 800. The State Historic Preservation Office (SHPO), in a letter dated September 30, 1992 (see letter in the Appendix), recommended that an architectural historian from the Department of Transportation examine structures over 50 years old and report the findings to SHPO for concurrence. Two structures over 50 years of age exist in the area of potential effect. It was determined that the two structures are not eligible for inclusion in the National Register of Historic Places. In a letter dated September 27, 1993 (a copy of the letter is included in the Appendix), SHPO concurred with the findings of the NCDOT architectural historian. b. Archaeological Resources There are no known archaeological sites within the project area. It is unlikely that any archaeological resources which may be eligible for inclusion in the National Register of Historic Places will be affected by the proposed construction. The SHPO has reviewed the project scope and recommends no further archaeological investigation be conducted (see letter dated September 30, 1992 in Appendix). 4. Relocation Impacts The proposed project will result in no relocations of residents, non-profit organizations, or businesses. 11 B. Economic Environment The North Carolina Employment Security Commission indicated that during the month of February 1994, Sampson County had a total labor force of 22,980. Of this number, 21,250 persons were employed and 1730 (1.5 percent) were unemployed. The proposed improvement will enhance and improve the economic growth and development potential along SR 1311. Businesses along the proposed project route will be enhanced by increased visibility and accessibility. In addition, the proposed widening will eliminate some of the traffic impediments caused by traffic congestion, thereby saving energy and fuel costs. C. Land Use 1. Scone and Status of Plannin The proposed improvement is located in the planning and zoning jurisdiction of the City of Clinton. The City adopted its Land Development Plan in 1982. It also enforces a zoning ordinance and subdivision regulations. The City's Thoroughfare Plan was completed in 1980. 2. Existing Zoning For the most part, the zoning districts established along SR 1311 (North Boulevard) reflect the existing land uses, such as the residential district, which includes the Lakeview subdivision. Two Highway Commercial districts are located on the north side of SR 1311, one near US 421, the other midway between US 701 and SR 1838 (Beaman Street), which includes a shopping center. A Neighborhood Shopping district is located in the southeast quadrant of the US 421/SR 1838 intersection. A large Planned Industrial District comprises the northwest quadrant of the North Boulevard and US 701 interchange. A Light Industrial district is located at the interchange's northeast quadrant. 3. Existing Land Use Several institutional land uses are located between US 421 and the US 701 Bypass, including a NCDOT District Engineer's Office, NCDOT Maintenance Facility, and a North Carolina Department of Corrections Facility. In addition, an animal hospital, single family homes, and the Sampson Southeast Business Campus are located west of the US 701 Bypass. A North Carolina Highway Patrol office is located just east of the US 701 Bypass. Other land uses between US 701 Bypass and SR 1838 (Beaman Street) include the Northside Plaza shopping center, the Lakeview subdivision, a restaurant, and a Hospice Care facility. 12 D. 4. Future Land Use The 1982 Land Development Plan provides a set of goals and objectives develope to guide tie character and placement of new development within the Clinton planning area. No "future land use plan" is provided that specifies precisely which type of land use should occupy the various sections of the city. However, some locations are identified for commercial, residential, and industrial development. Low density residential development was designated for the area south of North Boulevard. Industrial development is planned for the US 701 and North Boulevard area, as well as on US 421 north of North Boulevard. No significant commercial development is anticipated along North Boulevard. The plan does not address specific transportation issues or needs. It does state the City's support for the implementation of the thoroughfare plan. 5. Farmland The Farmland Protection Policy Act requires all federal agencies or their representatives to consider the impact of land acquisition and construction projects on prime and important farmland soils. These soils are determined by the U.S. Soil Conservation Service, based on potential crop yield and the required expenditure of energy and economic resources. Land which has been converted to non-agricultural uses, either through development or the planning activities of the local government, is exempt from consideration under the Act. Virtually all of the land along North Boulevard supports non-agricultural uses, or has been designated for some other use through the zoning ordinance. Therefore, no further consideration of potential farmland impacts is required. Natural Environment 1. Ecological Resources The study area is defined by a corridor width of 150 feet. An ecological survey was conducted on September 23, 1992 and June 18, 1993 to identify vegetative communities and wildlife species contained in the project area. Vegetative communities and wildlife were inventoried and mapped during on-site surveys. Wetlands were identified using methods in the "Corps of Engineers Wetlands Delineation Manual" (1987). Preliminary resource information was gathered and reviewed prior to the site visit. The U.S. Geological Survey (USGS) quadrangle map (Clinton North), Soil Conservation Services (SCS) Soils Map of Sampson County, and National Wetland Inventory (NWI) maps were studied to identify potential wetland sites. "Classifications and Water Quality Standards Assigned to the Waters of the Cape Fear River Basin" (N. C. Department of Environment, Health, and Natural Resources) was consulted to determine best usage classifications for water resources. The Fish and Wildlife Service list of protected species and the North Carolina Natural Heritage Program (NCNHP) database of uncommon and protected species and unique habitats were researched to identify any protected species which may exist along the project. 1 13 1 Biotic Resources This section describes the ecosystems encountered and the relationships between floral and faunal components within Terrestrial and Aquatic ecosystems. Descriptions of the Terrestrial systems are subordinated into floral community classifications. Representative animal species which are likely to occur in these habitats are cited along with brief descriptions of their role within that community. Animals that were observed during the site visit are denoted by (*) in the text. a. Terrestrial Communities Five distinct vegetative community types occur along the alignment; however, there is some degree of overlap between communities, particularly with the faunal components. Numerous terrestrial animals are highly adaptive and populate a variety of habitats, therefore many of the species mentioned occur throughout the alignment. Specific community types may occur numerous times throughout the alignment, with slight variations from location to location. All community types have had some degree of human impact. Floodplaiin Forest This hardwood-dominated community type is associated with three small tributaries of Williams Old Mill Branch crossed by the alignment. Little of this habitat type remains due to development. Water oak ( uercus n), bee ch (Fagus randifolia), black willow a ix , and willow oak uercus ellos) form thick, mature, streamside canopies. F 00 p ain areas adjacent to the streams are composed mainly of red maple (Acer rubrum), tulip poplar (Liriodendron tuli ifera), sweet gum Li uiaambar styrac i f l ua) , black gum -Ny-ssa sylvatica), an water oak. T ei se areas are semi permanently to permanently flooded. Thick patches of cane (Arundinaria iggantea) and blackberry (Rubus sp.) are common. ru s and small trees such as American holly (Ilex opaca), ironwood (C?arpi_.n_us caroliniana), sweet bay (Manoia virainia?na), and blueberry Vaccinium elliottii), comprise the sub canopy. 0 Cinnamon fern (Osmunda cinnamomea) and Christmas fern (Polystic?hum acrostic o? es occur along the stream banks. Netted chain ern Woo war is areolata), lizards tail (Saururus cernuus), and arum Pe tan ra vii r iiinca) are some herbaceous species observed in t e periodic' ally inundated overflow areas. Cat brier (Smilax rotundifolia) and (S. larualfolia), grape (Vitis sp.), poison ivy Toxicodendrori radicans , an Virginia creeper (Parthenocissus quinque o is comprise a thick vine layer. The majority of this community type is classified as a "wetland" community. 14 This community, characterized by a mature canopy, provides a large amount of nesting habitat (between limbs, in cavities, etc.), cover, and food supply for a wide variety of animals. Birds are the primary group of animals which utilize the canopy component of the community. Summer (S), winter (W) and permanent (P) residents are cited, including: downy woodpecker (Picoides ubescens)*P, yellow-bellied sapsucker (S h ra icus varius , white-breasted nuthatch (Sitta carolinensis * , blue-gray gnatcatcher (Polio tila caeruTea) , to to titmouse (Parus bicolor)*P, an Caro ina Fic_cadee (Parus caoTinensis T. Insects are the primary dietary items of these species, owever many will also consume seeds and berries. The predatory barred owl (Strix varia)P inhabits wet bottomland hardwood forests, nest ni g in tree cavities and hunting from tree limbs. Rodents, frogs, insects and small birds are the primary prey items. Forest edges near clearings such as fields, cutovers, and roadways are preferred nesting sites for the red-shouldered hawk (Buteo lineatus)*P and summer tanager (Piranga rubra)*S. Other inhabitants which utilize the canopy component of this community include: the grey squirrel (Sciurus carolinensis)*, the nests of which are a familiar sig rt igh in t e canopy in most forested habitats of North Carolina; Virginia opossum (Didel his vviiryini?ana)*; green treefrog (H la cinerea); grey tree rog H. c rh soscelis and H. versicolor ; an?t?ie Carolina anole TAno is caro inensis), a common izard of forested habitats in tFie coastal pain. The anole, along with the treefrog, camouflages itself with the leaves and bark of the trees to avoid predation. The evening bat (N cticticeius humeralis) is a common spring-summer resident in this ha_bitat type, roosting in hollow trees or crevices under tree bark. The numerous shrubs of the sub-canopy provide a food source (berries) and offer shelter and nesting habitats to a large number of birds: yellow-rumped warbler (Dendroica coronata)W, solitary vireo (Vireo solitarius)S, gray cat it Dumete la carolinensis)S, and Nort ern cardinal (Cardinalis car ina is *P. Ground nesting birds found in this type of habitat include, American woodcock (Scolo ax minor)*, which prefers very wet areas, black-and-white waraxbler Mniotilta varia)P, and rufous sided towhee (Pi er thro hthalmus . Animas such as southern toad (Bufo terrestris *, mar a sa amander (Amb toma o acum), ground Min cince la lateralis), southeastersshrew Sorex lon irostris), and cotton mouse (Perom scus gossin?us), are common ere, living under the litter layer and in hollow logs. Because of their secretive nature, many of these species are rarely seen. The diet of these organisms includes beetles, ants and other insects, and herbaceous material. A population of Mabee's salamander (Ambystoma mabeei)* was found in this C 15 habitat, particularly in the overflow areas of the unnamed tributary of Mill Creek near the NC Department of Corrections Sampson County facility. Several southern dusky salamanders (Desmo nathus auriculatus)* were also observed near the streams at a three crossings. Other species which are associated with the forest floor are the golden mouse (Ochrotom ss nuttalli), which builds its nests several feet off t eh ground, in vines, or shrubs, and the eastern box turtle (Terrapene carolina), a common species feeding on plant materiTeal, fungi' inests, and small animals. Because of its sluggish pace, it is often killed trying to cross roadways between habitats. Fragmented Urban Forest Large tracts of this community type do not exist in the project area; however, numerous small patches occur scattered throughout the alignment, serving as narrow buffer zones between residential developments and the roadway. The canopy, dominated by loblolly pine (Pinus taeda), sweetgum, red maple, and water oak (uercus n1Fa), s relatively thin, consisting of trees with comparatively small trunk diameters for their height. Flowering dogwood (Cornus florida), black cherry (Prunus serotina), and American ho y are t e ominant mid-canopy components, along with shrubs that include wax myrtle (Myrica cerifera), white bay (Magnolia vir iniana), winged sumac (R ?F s co alina), and sassafras assa ras albidum). Herbaceous species observed include bracken fern (Pteridium a uilinium), goldenrod (Solids oo sp.), and white-topper aster Aster aternus). Longleaf pine (Pinus alustris) is a dominant canopy species in one very smaf7t-ract o this community type along the existing roadway, just east of the US 101 overpass. Many of the faunal species found in the Floodplain Forest, may occur here as well. However, the number of resident organisms and community diversity are expected to be low in the Fragmented Urban Forests, as foraging and nesting habitat is limited. Some animals are able to adapt to an urban existence, using the limited forested habitat for shelter and nesting, often finding food in residential and business areas, around feeders, garbage cans, and roadways (roadkills). These species are generally opportunistic feeders, able to consume whatever is available. Raccoons, grey squirrels, rodents, and some birds, including American robin (Turdus americanus)*P, Carolina wren (Thr othorus 1udovicianus) *?, an Wort ern mockingbird (Mimus po yg ottos * , are common species found here. 16 Fallow Field These are small plowed crop fields which had been left unneeded during the spring-summer (1992) growing season. Consequently various rank vegetation has populated these fields in varying densities. These species include dog fennel (Eu atorium ca illifolium), black-eyed Susan (Rudbeckia hirta), blackberry Ru us spp. , goldenrod, and sericea Lespedeza cuneata). Numerous rodents such as the eastern harvest mouse (Reithrodontom ss humulis) and Norway rat (Rattus norve icus), occupy ield habitats because of the cover- oo source (seeds, roots, insects). The eastern kingsnake (Lam ro eltis etulus), and eastern milk snake (L. trian ulum), ee on rodents, as do birds of prey such as the red-shoulder hawk, red-tailed hawk (Buteo jamaciacensis)P* and American kestrel (Falco s arveriusj . The eastern cottontail (S lvila us f on anus , an small birds, are also consumed by the hawks. These s are attracted to the open field habitat because they rely on sight to hunt. Hawks usually soar above the open fields to spot their prey, and the kestrel hunts from a perch (powerline, tree limb). Ground-nesting birds such as the rufous-sided towhee, mourning dove (Zenaida asiatica)*P, and bobwhite (Colinus vir inianus)P use tFe thi'covergrowth to nest and feed on weed sees an insects. The brown-headed cowbird (Molothrus ater)P is a common resident of the coastal plain, whic ee s i`n old fields on grains, seeds, and insects. This species does not construct nests, but it lays its eggs (usually one at a time) in nests of other birds such as the rufous-sided towhee and solitary vireo, and then removes one of the hosts' eggs. The host bird broods the foreign egg until the young bird leaves the nest shortly after hatching. Roadside Habitat The flat, broad, routinely maintained roadside shoulder is composed predominantly of coastal Bermuda grass, with closely cropped herbaceous plants such as chickweed (Stellaria media butter cup (Ranunculus sp.), dandelion (Taraxacumicina e , and wild onion A ium canadense) scattere t roughout. On the edges of the mowed area are other species which are common in disturbed areas or "waste places". These include pokeweed (Ph tolacca americana), Japanese honeysuckle (Lonicera japonica), nig ha de (Solanum sp.), broomstraw An ropogon '- sp. , and dog fennel. Many of the birds which occur in the other habitats mentioned will forage along roadsides on weed seeds, berries, and the many insects found in this habitat. Many animals, including snakes, turtles, raccoons, opossums, and rabbits are hit by automobiles. ?7 17 i These become food for scavenger species such as turkey vulture (Cathartes aura)*P and common crow (Corvus brachyrhync os * , domestic dogs, and cats. Because of the limited size, nature of a roadside environment, expected to reside along the road. musculus) will construct nests out along the roadway. The five-lined small lizard common throughout the cardboard, tires, and other debris diversity, and the precarious few vertebrate species are Occasionally, house mice (Mus of and under discarded tras-Fi skink (Eumeces fasciatus), a state, is men found under along roadside environments. Business/Residential Lawn A major portion of the communities impacted by this project are commercial and residential landscapes ranging from the sparsely vegetated (mostly asphalt) business parking lots, to well manicured decorative residential lawns. Turf grasses are the dominant plants growing here. These species include coastal Bermuda (C ny odon dactylon) and fescue (Festuca sp.). Growth is kept low y regu ar mowing, thus very ew of er plant species are found here. Herbaceous species such as red clover (Trifolium prate??nse), dandelion, and wild onion were observed scattered throughout. Flower beds containing ornamental species and varieties are present throughout these habitats as are various ornamental trees and shrubs used for landscaping purposes. These species include bradford pear (P rus calleryana 'Bradford'), crepe myrtle (La erstroemia indica , mimosa A izia 'ulibrissin), hollies I ex spp. , o ive bush SE-laeagnus un ens , hydrangea (H?rangea), gardenia (Gardenia p.), and-several azalea species R o o endron spp.). Several animals previously mentioned are able to survive with human development and use this habitat type as foraging and nesting areas. Many of these species are birds, which are frequent visitors to bird feeders. b. Aquatic Communities Two types of aquatic communities will be impacted by the proposed project. Descriptions of vegetation and vertebrate species residing in or in close association with the water bodies are provided. Many terrestrial animals are integral components of aquatic ecosystems and will be considered in this discussion. Small Coastal Plain Stream Because of the sluggish flow and high biological demand, dissolved oxygen levels are generally very low in these types of streams. Consequently, fish occurring in these waters are well adapted to low oxygen levels, and many, like the eastern mudminnow (Umbrea mea)*, are able to use atmospheric oxygen, by gulping ai- at t e surface. 18 Cursory surveys of the stream, using a fine mesh dip net, yielded very few species. Redfin pickeral (Esox americana)* and the "live-bearing" eastern mosquitofish (Gambia a inis * were captured during site visits along with numerous crayfish (Cambarus sp. or Procambarus sp.). The apparent low diversity may ??ue to overall- w water levels and relatively sparse floating and submerged vegetation, which attract food supply and offer shelter. During the June 18, 1993 site visit, hundreds of eastern mudminnows were observed in the floodplain pools. This unusual occurrence was probably a result of abnormally high waters during the spring, and these fish were able to populate pools not normally containing fish. It was evident during the site visit that these pools were beginning to dry up. Although these fish can survive for several days in muddy pools with almost no water, they become easy prey for opportunistic foragers such as raccoon, eastern ribbon snake (Thamnophis sauritus), eastern garter snake (T. sirtalis)*, Norway rat, a?tton mouse (Peromyscus gossypinus . Normally, these pools do not contain fish, and they are used as breeding pools by a variety of amphibians such as Mabee's salamander, spotted salamander (Amb stoma maculatum), brimleys chorus frog (Pseudacris brimleyi , an sout erg n cricket frog (Acris rg?yllus). Mating for most of these species usually takes p? in early spring, following rains. The larvae undergo developmental stages in these ponds before transforming into adults. Several southern leopard frogs (Rana s henoce hala)* were observed near the stream banks. These-Trogs often venture far from water to feed on a variety of insects and other invertebrates. These ventures from the safety of the stream leave them susceptible to predation, particularly from barred owls, which consume a large amount of frogs during summer months. Small Residential Development Lake This man made impoundment is fed by a small stream crossed by the alignment, eventually flowing out of the pond and into Mill Branch. Lakeview subdivision is developed around the approximately 2.4-hectare (6-acre) lake. These lakes are usually stocked with gamefish, including largemouth bass (Micro terus salmoides)*, bluegill (Le omis macrochirus), and black crappie Pomoxis ni romaculatus , shortly ter construction and are popular fishing spots. Emergent vegetation along the shallow banks includes smartweed (Pol onum sp.), green arum (Peltandra vir inica), and marsh pennywort H drocot le umbel lata . T is c umpsilky strand algae (S ro ra sp. an s en er pondweed (Potamogeton pusillus) occur near the banks and out into the open waters. A 19 large number of aquatic insects congregate around these mats and are fed upon by various sunfish (Le omis spp.) and young largemouth bass. Bowfin (Amia Galva), older largemouth bass and brown bullhead (catfish) Icta uTrus nebulosus) are the primary predators in small coastal plain lakes. The diet of these predators includes smaller fish, frogs, and large insects. The presence of these predators controls population sizes of the prey fish. An abundant fish observed here is the carp (C rinus carpio)*, which was introduced to the United States in 1832 from Europe because of its popularity as a food fish. Today few people will eat this abundant and widespread species, as it is considered a "trash" fish of inferior quality. This assumption is erroneous, for food quality of this species is highly dependent on water quality and diet. Duckweed (Lemna sp.) occur in dense floating mats near the lake edge. Sever ducks were observed during the site visit including mallard (Anal lat rh nchos)*, wood duck (Aix sponsa)*, and domestic kite ucc*. Frogs likely inhabiting this pond include pickeral frog (Rana alustris)*, green frog (R. clamitans melanota), and bu Mrog R. catesbeiana). The snapping turtle (Chel dra ser entina), a large aggressive turtle common in most fres water a itats of North Carolina, feeds on fish, invertebrates, small ducks, and plant material. This turtle often wanders from one water body to another and is most aggressive when encountered on land. Other turtles likely to occur in this pond are the yellow- bellied slider (Trachem s scri to scri ta)* and the spotted turtle (Clemmys utg tats . Burrows of the semiaquatic muskrat (Ondatra zibethicus)* were evident along the shore banks. They have fi storMc? aTTy been common occupants of river and lake bank habitats throughout the state. This mammal has been extensively trapped for fur, which resulted in diminished populations. Recent regulatory measures and development of commercial rearing operations have reduced trapping pressures, helping to restore populations in some areas. Birds such as the belted kingfisher (Me aceraceryle aallcyonn)*, green heron (Butorides striatus)* and the great blue heron (Ardea herodias * were o s- near the lake during site visits. The major portion of their diet consists of small fish and aquatic invertebrates. C. Anticipated Impacts: Biotic Communities Construction of this project will have various impacts on the biotic communities described. This section quantifies and qualifies impacts on these resources in terms of the area impacted (cleared/modified) and ecosystem effects. Temporary and permanent impacts are considered here. 20 Terrestrial Community Impacts Project construction will result in clearing and degradation of portions of the five plant community types described. The estimated acreage loss to these communities is listed in Table 1. It should be noted that estimated impacts were derived using a 150-foot corridor. Project construction will not require the use a 150-foot corridor; therefore, actual impacts will be considerably less. Table 1 ESTIMATED TERRESTRIAL COMMUNITY IMPACTS Community Acres Floodplain Forest 1- Fragmented Urban Forest 2.0 Fallow Field 1.9 Roadside 1.5 Residential/Business Lawn 8.7 15.4 The plant communities found along the project alignment serve as shelter, nesting and foraging habitat for numerous species of wildlife. Loss of habitat is likely to reduce the number of faunal organisms and concentrate them into a smaller area, causing some species to become more susceptible to disease, predation, and starvation. Individual mortalities are likely to occur to animals closely associated with the ground (snakes, small mammals, etc.) because of construction machinery used during clearing and grading activities. Displacement of faunal organisms will occur during construction activity. These animals may return to the area following construction, but the amount of forested habitat will be reduced. The five-lane roadway will further dissect the forested communities, causing habitat reduction. This will likely isolate populations on both sides of the roadway, because many animals will be unable to cross the widened road. The project, however, will not adversely affect these terrestrial communities as a whole. Aquatic Community Impacts The aquatic environment serves as a major food source for many terrestrial organisms such as raccoons, various species of snakes, birds, turtles, and amphibians. It also serves as a means of predator avoidance for amphibians (frogs and salamanders), reptiles (snakes and turtles), and mammals (muskrats, mink and beavers). i 21 The existing pipes at the stream crossings will be replaced by box culverts. There will be some habitat loss in terms of permanent fill as a result of construction. Although the lake will not be directly impacted by construction, impacts may still occur from fill and modified areas. The tributary feeding the lake is crossed by the alignment, and any sediment or pollutants reaching the stream are likely to reach the lake as well. The potential for erosion into the lake is also a strong possibility since the road is approximately 100 feet upslope from the pond. Other ensuing impacts to the aquatic communities can be attributed to construction related sedimentation and erosion. Although sedimentation and erosion may be temporary processes during the construction phase of this project, environmental impacts from these processes may be long-lived or irreversible. Potential impacts to aquatic systems from project construction include disturbance of benthic habitat and increase of sediment load. Benthic non-mobile organisms such as filter and deposit feeders and macro and micro alga are particularly sensitive to construction activities such as dredging, filling, pile driving operations, and slope stabilization. These construction activities physically disturb the attachment substrate, resulting in loss of sessile benthic organisms. Many of these aquatic organisms are slow to recover, or repopulate an area, because they require a stabilized substrate which may take a long time to develop. Therefore, changes in community composition are likely as a result of substrate disturbance. Light penetration, essential for photosynthetic species which are the primary producers in the food chain, will be reduced as a result of siltation. Clogging of feeding apparati of suspension feeders and burial of newly settled larvae of these organisms, are other effects of siltation. These species are often primary consumers in the food chain, and are a major step in the aquatic food web. Impacts to these organisms may directly effect organisms higher in the food chain, such as game fish, raccoons and mink. Mobile aquatic organisms are generally not directly as sensitive to siltation, however gills of fish, crustaceans, larval amphibians, and insect forms can become clogged and dysfunctional as a result of sedimentation. Additionally if measures are not taken to reduce the amount of probable increased concentrations of toxic compounds (gasoline, oil, etc.) in the stream, mortalities to numerous types of aquatic organisms are likely. 22 2. Since erosion and sedimentation are extremely detrimental to aquatic ecosystems, strict adherence to Best Management Practices (BMP's) for protection of surface waters will be observed to ensure the biological integrity of the water resources impacted by this project. Protected Species a. Federally Protected Species Plants and Animals with federal classifications of Endangered (E), Threatened (T), Proposed Endangered (PE), and Proposed Threatened (PT) are protected under provisions of Section 7 and Section 9 of the Endangered Species Act of 1973, as amended. As of July 09, 1993, the U.S. Fish and Wildlife Service (USFWS) lists the red-cockaded woodpecker (Picoides borealis) and the pondberry (Lindera melissifolia) for ampson County. The project area does not support suitable habitat for the red-cockaded woodpecker. However, suitable habitat for the pondberry exists in the stream floodplains. A brief description of these species characteristics and habitat requirements are provided below. Picoides borealis (red-cockaded woodpecker) taE Family: Picidae Listed: 10/13/70 The adult red cockaded woodpecker's (RCW) plumage is entirely black and white except for small red streaks on the sides of the nape in the male. The back is black and white with horizontal stripes, and the breast and underside are white with streaked flanks. There is a large white cheek patch surrounded by the black cap, nape, and throat. RCW's use open old growth stands of southern pines, particularly longleaf pine, for foraging and nesting habitat. A forested stand must contain at least 50 percent pine. These birds nest exclusively in trees that are over 60 years old and are contiguous with pine stands at least 30 years of age. The foraging range of the RCW reaches 500 acres, and this acreage must be contiguous with suitable nesting sites. These woodpeckers nest exclusively in living pine trees and usually in trees that are infected with the fungus that causes red-heart disease. Cavities are located in colonies from 12 to 100 feet above the ground and average 30 to 50 feet in height. They can be identified by a large incrustation of running sap that surrounds the tree, which is referred to as "candle-sticking". This is arguably used as a defense against possible predators. A clan of woodpeckers usually consists of one breeding pair and the offspring from previous years. The eggs -qq 23 are laid in April, May, and June and hatch 38 days later. Clutch size is from three to five eggs. All members of the clan share in raising the young. RCWs feed mainly on insects but may feed on seasonal wild fruits. Biological Conclusion: No Effect No large mature pine stands occur within one half mile of the project area. Construction of this project will have no effect on this species. Lindera melissifolia (pondberry) Status: -E - Family: Lauraceae Listed: July 31, 1986 Flowers: March - early April Pondberry is a deciduous, aromatic shrub with a distinct sassafras-like odor, approximately 2 meters tall and spreading through stolons. The very thin alternate leaves are between six and sixteen centimeters long and two to six centimeters wide, with rounded bases. It has small pale yellow flowers that appear in early spring before the leaves. The fruit which matures in August or September is a bright red drupe. This plant grows in lowland habitats with hydric soils, which are generally flooded at some time during the growing season. It is associated with the margins of sinks, ponds, and other like depressions. The soils present are sandy with a high peat content in the subsurface. These areas show signs of past fire maintenance and now have shrubby conditions. The plants generally grow in shady areas but may also be found in areas that receive full sunlight. Biological Conclusion: No Effect The flooded lowland areas associated with the streams crossed in the project area offer marginally suitable habitat for this species. This area is not prime habitat because there does not appear to have been a fire regime associated with this habitat. Plant by plant surveys were conducted in these areas, within the project right of way. No plants were observed. Construction of this project will not adversely impact this species. b. Federal Candidate Species There are a total of seven federal candidate (C2) species and one federal candidate (Cl) species listed for Sampson County (Table 2). Candidate 2 (C2) species are defined as taxa for which there is some evidence of vulnerability, but for which 24 there are not enough data to warrant a listing of Endangered, Threatened, Proposed Endangered, or Proposed Threatened at this time. Candidate 1 (Cl) species are defined as taxon for which USFWS has on file enough substantial information to list as Endangered or Threatened. Listing is "warranted but precluded by other pending proposals of higher priority." The USFWS is "directed to make prompt use of the emergency listing provisions if the well-being of any such species is at significant risk." The North Carolina status of these species are listed also. These species are mentioned here for information purposes, should they become protected in the future. Surveys for these species were not conducted during site visits, nor were any of these species observed. Table 2 FEDERAL CANDIDATE SPECIES SAMPSON COUNTY Scientific Name Common Name Habitat NC Status Aimophila aestivalis Rana areolata-cp to Din ro-coTea andersoni' Dionaea muscci ul?a Lit a aestiM is Mac rides caro iniana oro o us tereti o ius o i aqo verna Bachman's sparrow No Carolina crawfish frog No SC none No C Venus flytrap No C-SC Pondspice Yes C Carolina bogmint No C wireleaf dropseed No T spring-flowering No E goldenrod SC denotes Federal Candidate species NC Status: SC, C, T, and E denote Special Concern, Candidate, Threatened and Endangered respectively. Candidate species are not afforded state protection. C. State Protected Species Plants or animals with state designations of Endangered (E), Threatened (T), or Special Concern (SC) are given protection by the State Endangered Species Act and the N.C. Plant Protection and Conservation Act of 1979, administered and enforced by the North Carolina Wildlife Resources Commission and the North Carolina Department of Agriculture. A search of the NCNHP data base of rare plants and animals revealed no current or historical records of North Carolina rare and/or protected species occurring near the project area. 25 3. Physical Resources a. Geology, Topography, and Soils Sampson County is in the Coastal Plain Physiographic Province. The county is drained by the Cape Fear River Drainage System. The topography of the area is characterized as broad, gently undulating to nearly flat plains, but includes some side slopes along the dissected, shallow stream valleys. Elevation in the project area ranges from 125 feet above mean sea level (msl) to 150 feet above msl. The smooth plains have low local relief, with the exception of the moderately sloping stream banks. Sediments are marine and alluvial in nature from the early to late Pleistocene epoch (less than 2.8 million years old). The mineralogic soil classes vary from kaolinitic to a mixed mineralogy (more than 10 percent expanding 2:1 clay mineral). The soils of the area are generally moderate to well drained loams and sands (Norfolk Loamy Sand, Marvyn Loamy Sand, and Wagram Loamy Sand units). The frequently flooded Bibb and Johnston soils are frequently associated with creeks. Much of the soils along the alignment are classified as Norfolk Urban Land Complex, consisting of soils of the Norfolk Loamy Sand Unit and impervious materials (asphalt, concrete etc). b. Water Resources The proposed alignment crosses three unnamed tributaries of Williams Old Mill Branch, which flows into the Great Coharrie Creek. The Great Coharrie Creek flows into the Black River approximately 20 miles downstream of the project crossings. Unnamed tributaries are assigned the classification of their respective tributaries as designated by the North Carolina Department of Environment, Health and Natural Resources (DEHNR), Classifications and Water Quality Standards Assigned to The Waters of the Cape Fear River Basin, 1993. Williams Old Mill Branch is designated as Class C Sw. Class C designates waters suitable for aquatic life propagation and survival, fishing, wildlife, secondary recreation and agriculture. The supplemental classification Sw denotes Swamp Waters, which are waters that have low velocities and characteristics which are different from adjacent streams. No waters classified as High Quality Waters (HQW), Outstanding Resource Waters (ORW), nor Water Supplies (WS I or WS II) occur within 1.6 km (1 mile) of the project area. 26 Water Resource Impacts Potential impacts to the waters affected by the proposed project caused by construction-related sedimentation and turbidity include decreases of dissolved oxygen and changes in temperature. This is due to vegetation loss (covered with sediment) and reduction of water clarity. Alterations of water level, due to interruptions or restrictions to surface water flow are also likely, because the replacement structures will have a different surface area for the stream to flow through (i.e. extension of the culvert). The proposed culverts should allow for normal flows, however extreme flows may create some problems with obstruction from accumulated debris. An increase in the concentration of toxic compound (gasoline, oil, etc.) concentrations in the stream is also likely, coming from construction related machinery and road paving activities as well as increased roadway surface area. C. Floodplain Involvement Sampson County is a participant in the National Flood Insurance Regular Program. A copy of the Flood Insurance Rate Map, which shows the approximate limits of the 100-year floodplain in the vicinity of the two drainage crossings, is included in the Appendix. These crossings are in moderately developed areas, but the immediate floodplain at each crossing is undeveloped and wooded. There are no buildings with floor elevations below the 100-year flood level at either of the two crossings. The proposed widening will have no adverse impact on the existing floodplains. d. Wetlands Surface waters and their associated wetlands fall under the broad category of "Waters of the United States as defined in 33 CFR 328.3. The Army Corps of Engineers (COE) claims jurisdiction over the discharge of dredged or fill material into these waters as authorized by Section 404 of the Clean Water Act. Wetland communities were identified using the criteria specified in the 1987 "US Army Corps of Engineers Wetlands Delineation Manual". For an area to be considered a "wetland", the following three specifications must be met: 1) presence of hydric soils (low soil chroma values), 2) presence of hydrophytic vegetation, and 3) evidence of hydrology or hydrological indicators including saturated soils, stained, matted vegetation, high water marks on trees, buttressed tree bases, and surface roots. 1 27 Construction of the proposed project will fill surface waters from an unnamed stream and ditches. The project will impact approximately 0.76 acre of Palustrine forested deciduous wetlands at two sites. Wetland impacts along the project corridor are unavoidable because wetlands are located along the stream banks on both sides of the existing alignment. Strict adherence to Best Management Practices (BMP's) will be observed to ensure the biological integrity of the water resources impacted by this project (see sections IV. G and IV. H of this report for permit and mitigation requirements). 4. Air Quality and Traffic Noise Air pollution is produced in many different ways. Emissions from industrial and internal combustion engines are the most prevalent sources. Other sources of common outdoor air pollution are solid waste disposal, forest fires, and burning in general. The impact resulting from the construction of a new highway or the improvement of an existing highway can range from aggravating existing air pollution problems to improving the ambient air conditions. Motor vehicles are known to emit carbon monoxide (CO), nitrogen oxide (NO), hydrocarbons (HC), particulate matter, sulfur dioxide (S02), and lead (Pb) (listed in order of decreasing emission rate). The primary pollutant emitted from automobiles is carbon monoxide. Automobiles are considered to be the major source of CO in the project area. For these reasons, most of the analysis presented is concerned with determining expected carbon monoxide levels in the vicinity of the project. In order to determine the ambient CO concentration at a receptor near a highway, two concentration components must be used: local and background. The local component is due to CO emissions from cars operating on highways in the near vicinity (i.e., distances within 100 meters) of the receptor location. The background component is due to CO emissions from cars operating on streets further from the receptor location. In this study, the local component was determined using line source computer modeling, and the background component was determined by the North Carolina Department of Environment, Health and Natural Resources (NCDEHNR). These two concentration components were determined separately, then added together to determine the ambient CO concentration for comparison to the National Ambient Air Quality Standards (NAAQS). Automobiles are generally regarded as sources of hydrocarbons and nitrogen oxides. Hydrocarbons and nitrogen oxides emitted from cars are carried into the atmosphere where they react with sunlight to form ozone and nitrogen dioxide. Area-wide automotive emissions of HC and NO are expected to decrease in the future due to the continued installation and maintenance of pollution control devices on new cars, and thus help lower ambient ozone and nitrogen dioxide levels. 28 The photochemical reactions that form ozone and nitrogen dioxide require several hours to occur. For this reason, the peak levels of ozone generally occur 10 to 20 kilometers downwind of the source of hydrocarbon emissions. Urban areas as a whole are regarded as sources of hydrocarbons, not individual streets and highways. The emissions of all sources in an urban area mix together in the atmosphere, and in the presence of sunlight, the mixture reacts to form ozone, nitrogen dioxide, and other photochemical oxidants. The best example of this type of air pollution is the smog which forms in Los Angeles, California. Automobiles are not generally regarded as significant sources of particulate matter and sulfur dioxide. Nationwide, highway sources account for less than seven percent of particulate matter emissions and less than two percent of sulfur dioxide emissions. Particulate matter and sulfur dioxide emissions are predominantly the result of non-highway sources (e.g., industrial, commercial, and agricultural). Because emissions of particulate matter and sulfur dioxide from cars are very low, there is no reason to suspect that traffic on the project will cause air quality standards for particulate matter and sulfur dioxide to be exceeded. Automobiles emit lead as a result of burning gasoline containing tetraethyl lead which is added by refineries to increase the octane rating of the fuel. Newer cars with catalytic converters burn unleaded gasoline eliminating lead emissions. Also, the United States Environmental Protection Agency (EPA) has required the reduction in the lead content of leaded gasolines. The overall average lead content of gasoline in 1974 was 2 grams per gallon. By 1989, this composite average had dropped to 0.01 grams per gallon. In the future, lead emissions are expected to decrease as more cars use unleaded fuels and as the lead content of leaded gasoline is reduced. "The Clean Air Act Amendments of 1990 makes the sale, supply, or transport of leaded gasoline or lead additives unlawful after December 31, 1995." Because of these reasons, it is not expected that traffic on the proposed project will cause the NAAQS for lead to be exceeded. A microscale air quality analysis was performed to determine future CO concentrations resulting from the proposed highway improvements. "CAL3QHC - A Modeling Methodology For Predicting Pollutant Concentrations Near Roadway Intersections" was used to predict the CO concentration at the nearest sensitive receptor to the project. Inputs into the mathematical model to estimate hourly CO concentrations consist of a level roadway under normal conditions with predicted traffic volumes, vehicle emission factors, and "worst case" meteorological parameters. The traffic volumes are based on the annual average daily traffic projections. Carbon monoxide vehicle emission factors were calculated for the construction year 1996 and for the design 2016 using the EPA publication "Mobile Source Emission Factors" and the MOBILE 5A mobile source emissions computer model. 1 1 29 The background CO concentration for the project area was estimated to be 1.9 parts per million (ppm). Consultation with the Air Quality Section, Division of Environmental Management, North Carolina Department of Environment, Health, and Natural Resources indicated that an ambient CO concentration of 1.9 ppm is suitable for most suburban areas. The "worst case" air quality receptor resulting from the widening project was determined to be receptor number 14. The receptor is located 50 feet from the proposed centerline of the median. The "build" and "no build" one hour CO concentrations for years 1996 and 2016 for this receptor are as follows: One Hour CO Concentrations (PPM) "Build" "No Build" Receptor 1996 2016 1996 2016 R-14 2.5 2.7 2.4 2.7 Comparison of the predicted CO concentrations with the NAAQS (maximum permitted for 1-hour averaging period = 35 ppm; 8-hour averaging period = 9 ppm) indicates no violation of these standards. Since the results of the "worst case" 1-hour CO analysis is less than 9 ppm, it can be concluded that the 8-hour CO level does not exceed the standard. The results also show that the building of the project will not adversely effect air quality conditions in the area. Refer to Appendix B for input data. The project is located within the jurisdiction for air quality of the Fayetteville Regional Office of the NC Department of Environment, Health, and Natural Resources. The ambient air quality for Sampson County has been determined to be in compliance with the National Ambient Air Quality Standards. This project is not anticipated to create any adverse effect on the air quality of this attainment area. Traffic Noise This analysis was performed to determine the effect of the proposed widening of SR 1311 in Sampson County on noise levels in the immediate project area. This investigation includes an inventory of existing noise sensitive land uses and a field survey of ambient (existing) noise levels in the study area. It also includes a comparison of the predicted noise levels and the ambient noise levels to determine if traffic noise impacts can be expected resulting from the proposed project. Traffic noise impacts are determined from the current procedures for the abatement of highway traffic noise and construction noise, appearing as Part 772 of Title 23 of the Code of Federal Regulations. If traffic noise impacts are predicted, examination and evaluation of alternative noise abatement measures for reducing or eliminating the noise impacts must be considered. 30 Noise is defined as unwanted sound. It is emitted from many sources including airplanes, factories, railroads, power generation plants, and highway vehicles. Highway noise, or traffic noise, is usually a composite of noises from engine exhaust, drive train, and tire-roadway interaction. The magnitude of noise is usually described by its sound pressure. Since the range of sound pressure varies greatly, a logarithmic scale is used to relate sound pressures to some common reference level, usually the decibel (dB). Sound pressures described in decibels are called sound pressure levels and are often defined in terms of frequency weighted scales (A, B, C, or D). The weighted-A scale is used almost exclusively in vehicle noise measurements because it places most emphasis on the frequency range to which the human ear is most sensitive (1,000-6,000 Hertz). Sound levels measured using A-weighting are often expressed as dBA. Throughout this report, references will be made to dBA, which means an A-weighted decibel level. Several examples of noise pressure levels in dBA are listed in Table N1 of Appendix B. Review of Table N1 indicates that most individuals in urbanized areas are exposed to fairly high noise levels from many sources as they go about their daily activities. The degree of disturbance or annoyance of unwanted sound depends essentially on three things: 1) the amount and nature of the intruding noise, 2) the relationship between the background noise and the intruding noise, and 3) the type of activity occurring where the noise is heard. In considering the first of these three factors, it is important to note that individuals have different hearing sensitivity to noise. Loud noises bother some more than others and some individuals become aroused to anger if an unwanted noise persists. The time patterns of noise also enter into an individual's judgement of whether or not a noise is objectionable. For example, noises occurring during sleeping hours are usually considered to be much more objectionable than the same noises in the daytime. With regard to the second factor, individuals tend to judge the annoyance of an unwanted noise in terms of its relationship to noise from other sources (background noise). The blowing of a car horn at night when background noise levels are approximately 45 dBA would generally be much more objectionable than the blowing of a car horn in the afternoon when background noises might be 55 dBA. The third factor is related to the interference of noise with activities of individuals. In a 60 dBA environment, normal conversation would be possible while sleep might be difficult. Work activities requiring high levels of concentration may be interrupted by loud noises while activities requiring manual effort may not be interrupted to the same degree. L 31 Over a period of time, individuals tend to accept the noises which intrude into their lives, particularly if noises occur at predicted intervals and are expected. Attempts have been made to regulate many of these types of noises including airplane noise, factory noise, railroad noise, and highway traffic noise. In relation to highway traffic noise, methods of analysis and control have developed rapidly over the past few years. In order to determine that highway noise levels are or are not compatible with various land uses, the Federal Highway Administration (FHWA) has developed noise abatement criteria and procedures to be used in the planning and design of highways. These abatement criteria and procedures are set forth in the aforementioned Federal reference (Title 23 CFR, Part 772). A summary of the noise abatement criteria for various land uses is presented in Table N2. The Leq, or equivalent sound level, is the level of constant sound which in a given situation and time period has the same energy as does time varying sound. In other words, the fluctuating sound levels of traffic noise are represented in terms of a steady noise level with the same energy content. Ambient noise measurements were taken in the vicinity of the project to determine the existing background noise levels. The purpose of this noise level information is to quantify the existing acoustic environment and to provide a base for assessing the impact of noise level increases. The existing Leq noise level along SR 1311 as measured at 50 feet from the roadway ranged from 64.9 to 67.2 dBA. The ambient noise measurement sites and measured exterior Leq noise levels are presented in Figure N2 and Table N3, respectively. Existing roadway and traffic conditions along SR 1311 were incorporated in the most current traffic noise prediction model to compute existing Leq noise levels. These computed values were compared with existing Leq noise levels which were measured at three locations along the proposed project. The computed existing Leq noise levels were within 1.0 and 6.6 dBA of the measured noise levels for both measurement sites. Differences in dBA levels can be attributed to "bunching" of vehicles, low traffic volumes, and actual vehicle speeds versus the computer's "even-speed" vehicles and single vehicular speed. The prediction of highway traffic noise is a complicated procedure. In general, the traffic situation is composed of a large number of variables which describe different cars driving at different speeds through a continually changing highway configuration and surrounding terrain. Obviously, to assess the problem certain assumptions and simplifications must be made. The procedure used to predict future noise levels in this study is the Noise Barrier Cost Reduction Procedure, STAMINA 2.0 and OPTIMA (revised March, 1983). The BCR (Barrier Cost Reduction) procedure is based upon the FHWA Highway Traffic Noise Prediction Model (FHWA-RD-77-108). The BCR traffic noise prediction model uses the 32 number and type of vehicles on the planned roadway, their speeds, the physical characteristics of the road (curves, hills, depressed, elevated, etc.), receptor location and height, and, if applicable, barrier type, barrier ground elevation, and barrier top elevation. This noise analysis is based on preliminary roadway alignments. The proposed project is to widen the existing two-lane highway to a multi-lane facility (five-lane curb and gutter) from US 421 to SR 1838. Only those existing natural or man-made barriers which could be modeled were included. The roadway sections and proposed intersections were assumed to be flat and at-grade. Thus, this analysis represents "worst-case" topographic conditions. The noise predictions made in this report are highway-related noise predictions for the traffic conditions during the year being analyzed. Peak hour design and level of service (LOS) C volumes were compared, and the volumes resulting in the noisiest conditions were used with proposed posted speed limits. Thus, during all other time periods, the noise levels will be no greater than those indicated in this report. The STAMINA 2.0 computer model was used to determine the number of land uses (by type) which, during the peak hour in the design year 2016, would be exposed to noise levels approaching or exceeding the FHWA noise abatement criteria and those land uses predicted to expect a substantial noise increase. The basic approach was to select receptor locations such as 25, 50, 100, 200, 400, 800, and 1600 feet from the center of the near traffic lane (adaptable to both sides of the roadway). The location of these receptors were determined by the changes in projected traffic volumes along the proposed project. The result of this procedure was a grid of receptor points along the project. Using this grid, noise levels were calculated for each identified receptor. The Leq traffic noise exposures for each design alternative are listed in Table N4. Information included in these tables consists of listings of all receptors in close proximity to the project, their ambient and predicted noise levels, and the estimated noise level increase for each. The total number of impacted receptors, whether by approaching or exceeding the noise abatement criteria or by a substantial increase in exterior noise levels are given in Table N5. Under Title 23 CFR Part 772, ten residential receptors were impacted by highway traffic noise in the project area. Other information included in Table N5 is the maximum extent of the 72 and 67 dBA noise level contours. This information should assist local authorities in exercising land use control over the remaining undeveloped lands adjacent to the roadway in local jurisdiction and to prevent further development of incompatible activities and land uses. 33 Table N6 indicates the exterior noise level increases for the identified receptors in each roadway section. Noise level increases are predicted to range from +1 to +5 dBA. When real-life noises are heard, level changes of 2-3 dBA are barely perceptible. A 5 dBA change is more readily noticeable, and a 10 dBA change is judged by most people as a doubling or a halving of the loudness of the sound. Traffic noise impacts occur when the predicted traffic noise levels either: 1) approach or exceed the FHWA noise abatement criteria (with "approach" meaning within 1 dBA of the Table N2 value), or 2) substantially exceed the existing noise levels. The NCDOT definition of substantial increase is also shown in Table N2. Consideration for noise abatement measures must be given to receptors which fall in either category. There are ten impacted receptors in the project area. Alignment selection involves the horizontal or vertical orientation of the proposed improvements in such a way as to minimize impacts and costs. The selection of alternative alignments for noise abatement purposes must consider the balance between noise impacts and other engineering and environmental parameters. For noise abatement, horizontal alignment selection is primarily a matter of locating the roadway at a sufficient distance from noise sensitive areas. Changing the highway alignment is not a viable alternative for noise abatement. Traffic system management measures which limit vehicle type, speed, volume and time of operations are often effective noise abatement measures. For this project, traffic management measures are not considered appropriate for noise abatement due to their effect on the capacity and level of service on the proposed roadway. Physical measures to abate anticipated traffic noise levels can often be applied with a measurable degree of success using solid mass, attenuable measures to effectively diffract, absorb, and reflect highway traffic noise emissions. Solid mass, attenuable measures may include earthen berms or artificial abatement walls. For a noise barrier to provide sufficient noise reduction it must be high enough and long enough to shield the receptor from significant sections of the highway. Access openings in the barrier severely reduce the noise reduction provided by the barrier. It then becomes economically unreasonable to construct a barrier for a small noise reduction. Safety at access openings (driveways, crossing streets, etc.) due to restricted sight distance is also a concern. Furthermore, to provide a sufficient reduction, a barrier's length would normally be eight (8) times the distance from the barrier to the receptor. For example, a receptor located 50 feet from the barrier would normally require a barrier 400 feet long. An access opening of 40 feet (10 percent of the area) would limit its noise reduction to approximately 4 dBA (Fundamentals and Abatement of Highway Traffic Noise, USDOT, chapter 34 Businesses, churches, and other related establishments located along a particular highway normally require accessibility and high visibility. Solid mass, attenuable measures for traffic noise abatement would tend to disallow these two qualities and, thus, would not be acceptable abatement measures in this case. Based on the above factors, no physical abatement measures are feasible, and none are recommended for this project. The traffic noise impact for the "Do Nothing" alternative was also considered. Four residences would experience traffic noise impacts by approaching or exceeding the FHWA's Noise Abatement Criteria (NAC). No receptors will be impacted by substantial increases in exterior noise levels, since these increases ranged from +0 to +3 dBA. General construction noise impacts, such as temporary speech interference for passers-by and those individuals living near the project, can be expected particularly from paving operations and the earth moving equipment during grading operations. However, considering the relatively short-term nature of construction noise and the limitation of construction to daytime hours, these impacts are not expected to be substantial. The transmission loss characteristics of nearby natural elements and man-made structures are believed to be sufficient to moderate the effects of intrusive construction noise. No traffic noise abatement measures are proposed for this project. This evaluation completes the highway traffic noise requirements of Title 23 CFR 772, and unless a major project change develops, no additional reports are required for this project. E. Contaminated Properties A reconnaissance survey of the project corridor identified two active facilities which have the potential for underground storage tanks (USTs) or hazardous materials involvement. In a subsequent records search of the Division of Environmental Management (DEM) Groundwater Section, the following information was obtained. The Best Way Amoco Station is located at the intersection of SR 1311 and US 421 in the southeast quadrant of the intersection. A site investigation revealed three gasoline USTs and one kerosene UST. The four USTs are located are found 90 to 110 feet south of the centerline of SR 1311 and 150 to 170 east of the centerline of US 421. A BP Service Station is located directly across SR 1311 from the Best Way Amoco in the northeast quadrant of the intersection. All of the four petroleum tanks at this station are above ground storage tanks (AST's) and found 120 feet north of the centerline of SR 1311 and 220 feet east of the centerline of US 421. 35 A files search of the Division conducted to determine whether any potentially contaminated sites were these files and the DEM groundwater within the Sampson County area we corridor. of Solid Waste Management was also known regulated dumps or other within the corridor. After reviewing incident list, none of the known sites re identified within the project The Geotechnical Unit recommends that the right of way not exceed 70 feet north or south of the existing centerline of SR 1311 at the beginning of the project. This would allow NCDOT to avoid purchasing any USTs or associated pump islands. After approximately 300 feet from the beginning of the project widening could occur with no known involvement with potentially contaminated properties. Table 3 Potential Storage Tank Impacts Facility Location UST's Best Way Amoco Southeast quadrant of US 421 4 and SR 1311 AST's BP Service Station Northeast quadrant of US 421 4 SR 1311 F. Construction Impacts There are some environmental impacts normally associated with highway construction. These are generally of short term duration and measures will be taken to minimize these impacts. During construction of the proposed project, all materials resulting from clearing and grubbing, demolition, and other operations will be removed from the project, burned, or otherwise disposed of by the contractor. Any burning done will be in accordance with the applicable laws, ordinances, and regulations of the North Carolina State Implementation Plan (SIP) for Air Quality in compliance with 15 NCAC 2D.0520. Care will be taken to insure burning will be done at the greatest distance practicable from dwellings and not when atmospheric conditions are such as to create a hazard to the public. Burning will be done under constant surveillance. Measures will be taken to allay the dust generated by construction when the control of dust is necessary for protection and comfort of motorists or area residents. The general requirements concerning erosion and siltation are covered in Article 107-3 of Standard Specifications for Roads and Structures , which is entitled "Contro?of Erosion, Siltation, ana -Pollution". The N.C. Division of Highways has also developed an Erosion and Sedimentation 36 Control Program which has been approved by the N.C. Sedimentation Control Commission. This program consists of the rigorous requirements to minimize erosion and sedimentation contained in the Standard Specifications together with the policies of the Division of Highways regarding the control of accelerated erosion on work performed by State Forces. Waste and debris will be disposed of in areas outside of the right of way and provided by the contractor, unless otherwise required by the plans or special provisions or unless disposal within the right of way is permitted by the Engineer. Disposal of waste and debris in active public waste or disposal areas will not be permitted without prior approval by the Engineer. Such approval will not be permitted when, in the opinion of the Engineer, it will result in excessive siltation or pollution. Borrow pits and all ditches will be drained to alleviate breeding areas for mosquitoes. In addition, care will be taken not to block existing drainage ditches. The construction of the project is not expected to cause any serious disruptions in the services of any of the utilities serving the area. Prior to construction, a determination will be made regarding the need to relocate or adjust any existing utilities in the project area. A determination of whether the NCDOT or the utility owner will be responsible for this will be made at this time. In all cases, the contractor is required to notify the owner of the utility in advance as to when this work will occur. In addition, the contractor is responsible for any damages to water lines incurred during the construction process. This procedure will insure that water lines, as well as other utilities, are relocated with a minimum of disruption to the community. Traffic service in the immediate area may be subjected to brief disruption during construction of the project. Every effort will be made to insure the transportation needs of the public are met both during and after construction. General construction noise impacts such as temporary speech interference for passers-by and those individuals living or working near the project can be expected, particularly for paving operations and from earth moving equipment during grading operations. However, considering the relatively short term nature of construction noise, these impacts are not expected to be significant. The transmission loss characteristics of nearby structures will moderate the effects of intrusive construction noise. G. Permits Impacts to Waters of the United States fall under the jurisdiction of the U.S. Army Corps of Engineers (COE). A Nationwide permit 33 CFR 330.5 (A) 26 is likely to be applicable. This permit applies to wetlands that are adjacent to surface waters, are above headwaters (with annual flow less than 5 cubic feet per second (cfs)) and the impacts are less than one acre. A Pre-discharge Notification to the COE is required. 37 A North Carolina Division of Environmental Management (DEM) Section 401 (1665) Water Quality General Certification is also required, prior to issuance of the Nationwide permit. Final permit decisions lie with the Army Corps of Engineers. H. Mitigation Projects authorized under Nationwide Permits usually do not require compensatory mitigation according to the 1989 Memorandum of Agreement between the Environmental Protection Agency and the Department of the Army. V. COMMENTS AND COORDINATION A. Comments Received Comments on the proposed improvements to SR 1311 were requested from the following federal, state, and local agencies. An asterisk indicates that a written response was received. Responses are included in the appendix. *U.S. Army Corps of Engineers - Wilmington U.S. Environmental Protection Agency - Atlanta *U.S. Department of Transportation - FHWA *U.S. Fish and Wildlife Service - Raleigh *N.C. Department of Public Instruction *N.C. Department of Cultural Resources *N.C. Department of Environment, Health, and Natural Resources N.C. Department of Human Resources *N.C. State Clearinghouse *N.C. Wildlife Resources Commission Region M Planning Agency *City of Clinton Mayor of Clinton Sampson County Commissioners *Clinton City Schools B. Citizens Informational Workshop A Citizen's Informational Workshop was held on November 10, 1992 at the District 2 (Division 3) Highway Maintenance Facility to discuss the proposed improvements. The NCDOT Office of Public Affairs advertised the workshop in the major local media prior to its being held. Approximately 15 people (not including NCDOT representatives) attended the informational workshop. All of the people who attended the informational workshop live or work along the project. Although concern was expressed over the project's impacts to their properties, the project was strongly supported. Peak hour congestion and intersection safety were among the existing problems pointed out by workshop attendees. Both residents and business owners in the project area favored the symmetric widening alternative. 38 Representatives from the Sampson County Correctional Center indicated widening asymmetrically toward the Correctional Center could involve moving the existing fenceline and two guntowers. They also emphasized the importance of maintaining a safety barrier between the guntowers and the road. Representatives from Week's Animal Clinic, located directly across the road from the Correctional Center, also attended the workshop. They maintained asymmetric northside widening could extensively damage their parking lot. Relocating the parking lot to the opposite side of the clinic would adversely alter entry conditions for customers. Both parties agreed symmetric widening appeared to be a fairer alternative than asymmetric widening. C. Public Hearing A public hearing will be held following the circulation of this document. The public hearing will provide more detailed information to the public about the proposed improvements. The public will be invited to make additional comments or voice concerns regarding the proposed project. FIGURES r r I I r II I I m r aYes`s:. tI r a> jig l?j,l f?t y >? ,k A 'h, t.?i?t ?, ? ;f yes < ?a• a f > ot. XJ I q [ O ! ?aPA C7 Ju CD --j N CO p x - z tr Z mow,. ,' y ?. , y 0 Aft ci) (n ;U)?<t ` 1.S 83dSer m?3mm+ k o??? * }, a O V) Z m5az Z 2 z ?.'? ; NC) KA • ??t ;I, o mmm ,soy 10 31NNOJ b v l ?'' } e xz o 41L m - 1SQ ?. r 7N N 0 0) Ur ?c _ O Uy O d `?.o aco0 N N l? ca 'cr V D c O Eo cc¢ mm? L ? lQ N ? oED O'-'• v` N AWL t? T O T C C'J OC ? c ? aotm co m CO 0 1 - E CD O co xE ?0 co D 4 OR .d d R ?1 1 IR Lb Z _ 0 co bb r4 cr) ?Nd c/JZ V 4 %?C ? z? 89 cc lP 6l N? 99 t, ` l£ z T ' 1 ca l_l l 9 _ O T m s 8z ?r 1 T? NZ f&ww 5l 6 L .14 I 4 ? ? ez r-too N? -z Z ol 9 T O CD 1 T n 0 ? ^ Z ?I N - ?C ? o NIA C0 D ?CD a !M! cc /m 0 M rn A ? o N U 1- •- NI D c m : U) to to 4- p fn^ it p + p-? O O T - 0 B N1? ,0 d 0 O CD c O?- m Q m_ - CO LM 0 Cam Em or Z? y 7 T?wL T 0(0 c M q„I T v T r ? CV N?? N T O M U 4-- NFa? c -'? c O rky U m 42 CD M C Q co ? r 7 m U w Q 0 -? co w O .?. ???? r c WC-3 4-- We- -+ -.Icon 1 JU t 06 Z 14 -l LS .? 1 1 it KLJU z Zl bb t 1 6L Cl Nn t .uim 1 I t L9 I 4- ^T r _ N v m m ~ Go ?V?o c c m " to Av CD CC Co U U CD 48 o m CD m •+ w 4- co SIN C C U U r ca w T M M C cr- o CD Z Mhc) m 4 ` -? m Q CJN? ;AQ 4-- NN (o r Id pT? SLY Y Z bb l Lojkl) r Zl ££ 4 ?o 0 V FApN N m D m Y 9 M W U. North Boulevard (SR 1311) at US 421 Proposed Intersection Geometrics br- r N SR 1311 North Boulevard Figure 4a K- North Boulevard (SR 1311) at Beaman Street (SR 1838) Proposed Intersection Geometrics SR 1311 North Boulevard 00 c? 3 CD CD CD CO CO CIO CO Figure 4b y North Boulevard (SR 1311) at US 421 Existing Intersection Geometrics ; SR 1311 North Boulevard Figure 4c W i co LL Z O f- V W N W L7 O 2 Q m V W Z g iD a LO d CD LL 1- T T to CO) o? a W m r 0 N z Q m m w m > :) o V W W z m 0m m W N W oz o° I- M v W U) N V 1 421 N 1314 C y 111111 Clllllllll? III; iIIIIIIIIII11111111111111 v.?1111111? Vs a O V ?11111111111n?n???n1111 i O U-2514 c C a 174 9 a - C ? 14?? ^E S' \\<? I 1849 . RP, I :I e Q E E W-L i3 nrE gap;: 1k 18 o ~ d? GRG E ;b' _L%GC n `\4 PARK ..PT ?rE C-E J sl cAnv?Ew O _ 4,E p11??L??838 1839 =I ? EE« 5 t EMETFIR , a 'Cpr•r In' a '~v r^ s 1 II? , `' Q ' E 2 i v m TAR MEMOPIA? \ \ .a/ r y ao` fq HO SPiTA? 5. .. P?5,0 SAM: c 6? 5 3OgN #_ 4ON " n .rM ?'E C y, ?o~9a i S`•?' P AESc v`r ?a ?O? Cq ?C? 1 e?« ° iNST 6a- CHy s. D f• ? \ / O s ?y .BET \ O <? r VENT- - ?` 43 \ l 'p«DEps << WApDL, V ?1 3AW t I S t 9 ~fq ff. . C .. ':)GAP 5T \ N' 1344 \ 9f F;PST -' 'IAA AA i METH O /J\ f CAA ? y \ CH. OF GOO 11312 \ `°qfs, FIGURE 6 1313 ?\ '0•, Portion of Thoroughfare 134.1 421 Plan // qq CJC q' ? C A \ fq (q ?\ 1339 `\?i?? cL^NroN ??.\.. ^?°c ;. ..?., ?• •• ` SM 170 NORTH CAROLINA DEPARTMENT OF 1842 0 - _ TRANSPORTATION DIVISION OF HIGHWAYS PLANNING AND ENVIRONMENTAL ?,? ? ?- - ?? Cam="• I i Q? ?? BRANCH SR 1311 US 421 TO SR 1838 ??, /""? ? \' SAMPSON COUNTY U-2514 Browns 1827 "_ i ??? ??-. 1 Chapel; _ ? \ ?-- o ?\ ? • \\ ? ? ;? Wetland Locations FIGURE 7 A ,50" -r , u ) I ?? " 153 1 n vso 104 - ras • - - %"fending Strip rn7 \ _ I /' • \ r 1742 PROJECT - ISO - - 52 LIMIT , 1751. Radio Tower PROJECT LIMIT) =E +- i? ??• 1 E = ,`F 354 vl - ? A•e rP f __ dl ? ? • ' r? :Cem 3 TE 2-' _.-BITE ? ... ???`?: ? I. "'•?? ? "-moo 1y (t/"?..-. \?` V : ? n r ?- 1 1 ? \ Su r Q ? ?\ N U 11 A o I 1 403 % \a tel T p !d ?, " tta' I/ off- .. ' ?i'" . ..? Theater :?, Sew' •" '1 ?? , - CI. Royal Mi Br lo _- _ _ ? ` r 1 '} ?_ a ?,FrBher \ i ?? •??\? Tcw&r c. } N .W Q Q w X _ W Z Z O NO O N N WC ZX O iS ?ol Business `- o .° I 0 ..N Q W Z O N 9,8- ;PoT W 2 \ Ln \ .000' 1 L~ :::.. a ? M=ooh v b e ? ? ,:;:. ',?,?q 400 W zr` CO) ? z N O `= Q u a z ?F O N H V ? 7 Q J a CV) ?I O W m . O' w O _ E J '1638 X W Z O N I I I 'I L-9•ZL 3NOZ , I I I F G X V i m I 'C C "' I C of V . a o . . 'I I X w Z O N co Y. V LL. A DW -- Z X O N C X APPENDIX DEPARTMENT OF ADMINISTRATION SEP 116 WEST JONES STREET DCKNOWLEDGEMENT NORTH CAROLINA STATE CLEARINGHOUSE RALEIGH NORTH CAROLINA 27603-8003 D1OF RECEIPT MAILSO TO: FROM: `1C DEPT OF TRANSPORTATION MS. JEANETTE FURNEY L.J. ',LARD ADMINISTRATIVE ASSISTANT PLANNING E ENVIRON. BRANCH STATE CLEARINGHOUSE HIGHWAY BLDG./INTER-OFFICE OROJECT DESCRIPTION: SCOPING - PROPOSED IMPROVEMENTS TO SR 1311 (NORTH 3LVD.) FROM US 421 TO SR 1838 (BEAMAN STREET) IN CLINTON, SAMPSON COUNTY TIP rU-2514 TYPE - SCOPING THE "N.C. STATE CLEARINGHOUSE HAS RECEIVED THE ABOVE PROJECT FOR INTEA:;OVERNMENTAL REVIEW. THIS PROJECT HAS SEEN ASSIGNED STATE APPLICATION NUMBER 93E422001639 PLEASE USE THIS NUMBER WITH ALL INQUIRIES OR CORRESPONDENCE WITH THIS OFFICE. REVIEW OF THIS PROJECT SHOULD BE COMPLETED ON OR BEFORE 11/01/92. SHCULO YOU HAVE ANY QUESTIONS PLEASE CALL (919) 733-0499, NORTH CAROLINA STATE CLEARINGHOUSE =M208 DEPARTMENT OF ADMINISTRATION % 116 WEST JONES STREET ,. 11-02-92 r RALEIGH NORTH CAROLINA 27603-80 INTERGOVERNMENTAL REVIEW COMMENTS NpV 0 3 192 MAILED T0. FROM. Z p?VISIG'`? GF ` NC DEPT OF TRANSPORTATION MRS. H?GNWAYQ?. CHRYS BAGGETT L-J- WARD DIRECTOR PLANNING E ENVIRON- BRANCH N C STATE CLEARINGHOUSE HIGHWAY BLDG./INTER-OFFICE PROJECT DESCRIPTION: SCOPING - PROPOSED IMPROVEMENTS TO SR 1311 (NORTH BLVD-) FROM US 421 TO SR 1838 (BEAMAN STREET) IN CLINTONI SAMPSON COUNTY TIP #U-2514 SAI NO 93E42200163 PROGRAM TITLE - SCOPING THE ABOVE PROJECT HAS BEEN SUBMITTED TO THE NORTH CAROLINA INTERGOVERNMENTAL REVIEW PROCESS- AS A RESULT OF THE REVIEW THE FOLLOWING IS SUBMITTED: ( ) NO COMMENTS WERE RECEIVED ( X) COMMENTS ATTACHED SHOULD YOU HAVE ANY QUESTIONS9 PLEASE CALL THIS OFFICE (919) 733-0499- C-C- REGION M NT OF Ty?'ym fN 5 X a ?q'9CH 3 ?0s United States Department of the Interior FISH AND WILDLIFE SERME Raleigh Field Office Post Office Box 33726 Raleigh, North Carolina 27636-3726 December 1. 1992 Mr. L. J. Ward. Manager Planning and Environmental Branch ` Division of Highways N.C. Department of Transportation Post Office Box 25201 Raleigh. North Carolina 27611-5201 a Y SEC 0 2 1992 u, ?lvtis??'' r Subject: SR 1311 (North Boulevard). from US 421 to SR 1838 (Beaman Street). Clinton; Sampson County; Federal Aid Project No. STP-1311(2). State Project No. 8.2280701. TIP No. U-2514 Dear Mr. Ward: For your information, the U.S. Fish and Wildlife Service is providing an updated listing of Federally listed species for the subject project. The attached page identifies the Federally listed endangered (E) and/or threatened (T) and/or species proposed for listing as endangered (PE) or threatened (PT) which may occur in the area of influence of this action. If the proposed project will be removing pines greater than or equal to 30 years of age in pine or pine/hardwood habitat, surveys should be conducted for active red-cockaded woodpecker cavity trees in appropriate habitat within a 1/2 mile radius of project boundaries. If red-cockaded woodpeckers are observed within the project area or active cavity trees found. the project has the potential to adversely affect the red-cockaded woodpecker and you should contact this office for further information. There is no Federally-listed critical habitat in the project impact area for any of the above referenced species. Your concern for endangered species is appreciated, and we look forward to working with you on endangered species matters in the future. Sincerely yours. Debbie Mi ogno Endangered Species Coordinator Enclosure REVISED JANUARY 1, 1992 Sampson County - Red-cockaded woodpecker (Picoides borealis) - E American alligator (Alligator mississipviensis) - T S/A+ Pondberry (L de a melissifolia) -E There are species which, although not now listed or officially proposed for listing as endangered or threatened, are under status review by the Service. These "Candidate"(C1 and C2) species are not legally protected under the Act, and are not subject to any of its provisions, including Section 7, until they are formally proposed or listed as threatened or endangered. We are providing the below list of candidate species which may occur within the project area for the purpose of giving you advance notification. These species may be listed in the future, at which time they will be protected under the Act. In the meantime, we would appreciate anything you might do for them. Carolina crawfish frog (Rana areolata caoito) - C2 Spring-flowering goldenrod (Solidago verna) - C2 Wireleaf dropseed (Sporobolus teretifolius) - C2 Bachman's sparrow (Aimoohila aestivalis) - C2 American sandburrowing mayfly (Do ani americana) - C2 Cylindrocolea andersoni - Cl Pondspice ( tsea aestivalis) - C2 Carolina bogmint (Macbridea caroliniana) - C2* *Indicates no specimen in at least 20 years from this county. +Threatened/Similarity of Aoeearance . STATE North Carolina Department of Cultural Resources = James G. Martin, Governor Patric Dorsey, Secretary September 30, 1992 \ MEMORANDUM Division of Archives? and History William S. Price, Jr., Director TO: L. J. Ward, P.E., Manager Planning and Environmental Branch Division of Highways Department of Tnat ion FROM: David Brook lv?40f Deputy State toric Preservation cer SUBJECT: SR 1311 (North Boulevard) from US 421 to SR 1838 (Beaman Street), Clinton, Sampson County, U-2514, STP-1311(2), 8.2280701, CH 93-E-4220-0163 We have received information concerning the above project from the State Clearinghouse. We have conducted a survey of our survey site files which do not identify any structures of historical or architectural importance within the general area of the project. However, at an early scoping meeting for the project, we discovered that structures over fifty years of age may be located in the area of potential effect. We recommend that an architectural historian for the North Carolina Department of Transportation examine the area of potential effect and report the findings to us. Please submit photographs of any structures over fifty years of age, keyed to a map, along with a location description. Also include a brief statement about the structure's history and explain which National Register criteria it does or does not meet. Without this information we are unable to determine if the structure is eligible for listing in the National Register of Historic Places. There are no known archaeological sites within the proposed project area. Based on our present knowledge of the area, it is unlikely that any archaeological resources which may be eligible for inclusion in the National Register of Historic Places will be affected by the project construction. We, therefore, recommend that no archaeological investigation be conducted in connection with this project. The above comments are made pursuant to Section 106 of the National Historic Preservation Act of 1966 and the Advisory Council on Historic Preservation's Regulations for Compliance with Section 106, codified at 36 CFR Part 800. 109 EastJones Street • Raleigh, North Carolina 27601-2807 L. J. Ward September 30, 1992, Page 2 Thank you for your cooperation and consideration. If you have questions concerning the above comment, please contact Renee Gledhill-Earley, environmental review coordinator, at 919/733-4763. DB:slw cc: `State Clearinghouse B. Church µ .. t,. `C- r North Carolina Department of Cultural Resources James B. Hunt, Jr., Governor Betty Ray McCain, Secretary March 29, 1993 Nicholas L. Graf Division Administrator Federal Highway Administration Department of Transportation 310 New Bern Avenue Raleigh, N.C. 27601-1442 Re: SR 1311 from US 421 to SR 1838, Clinton, Sampson County, U-2514, 8.2280701, STP-1311121, ER 93- 8437 Dear Mr. Graf: GEI VF APR 0 2 1993 z U 222 DIVISION OF Q? G' HIGHWAYS ?,? "§4`i'/RONN?P Thank you for your letter of March 11, 1993, concerning the above project. We have reviewed the documentation provided to us regarding historic structures over fifty years of age and determined that additional information is needed to complete our review. As requested in our letter of September 30, 1992, to the North Carolina Department of Transportation (NCDOT), we need the photographs of the structures over fifty years of age within the area of potential effect keyed to a map showing the project area. A brief statement about each structure's history and an explanation concerning which National Register criteria they meet or why they are not eligible for listing should also be provided. without this information we are unable to determine whether the structures are eligible for listing in the National Register of Historic Places. For further guidance on the kinds of information helpful to us, the NCDOT staff architectural historian may want to review our guidelines for report preparation. As we have outlined in the past, we need information about the general character of the area as well as information on older properties which may or may not be eligible for listing in the register. The above comments are made pursuant to Section 106 of the National Historic Preservation Act of 1966 and the Advisory Council on Historic Preservation's Regulations for Compliance with Section 106, codified at 36 CFR Part 800. Thank you for your cooperation and consideration. If you have questions concerning the above comment, please contact Renee Gledhill-Earley, environmental review coordinator, at 919/733-4763. Sincerely, r t 'c " David Brook Deputy State Historic DB:slw/ cc: V L. J. Ward B. Church Preservation Officer 109 East Jones Street • Raleigh, North Carolina 27601-2807 Division of Archives and History William S. Price, Jr., Director QP North Carolina Department of Cultural Resources James B. Hunt, Jr., Governor Betty Ray McCain, Secretary September 27, 1993 Nicholas L. Graf Division Administrator Federal Highway Administration Department of Transportation 310 New Bern Avenue Raleigh, N.C. 27601-1442 RE: SR 1311 (North Boulevard) from US 421 to SR 1838 (Beamont Street), Clinton, Sampson County, U-2514, 8.2280701, STP-1311(2), ER 94-7365. Q`?C+ r ?[ Division of A0644.1 William S. Price, Thank you for your letter of August 31, 1993, concerning the above project. We have reviewed the phase I historic architectural resources report prepared by Kitty Houston for the North Carolina Department of Transporation concerning the project. Based upon the information in the report, we concur with the Federal Highway Administration's determination that the two structures over fifty years of age in the area of potential effect are not eligible for the National Register. We agree the two structures have little historical or architectural significance. The above comments are made pursuant to Section 106 of the National Historic Preservation Act of 1966 and the Advisory Council on Historic Preservation's Regulations for Compliance with Section 106, codified at 36 CFR Part 800. Thank you for your cooperation and consideration. If you have questions concerning the above comment, please contact Renee Gledhill-Earley, environmental review coordinator, at 919/733-4763. Sincerely, David Brook, Deputy State Historic Preservation Officer DB:slw cc: .,C.J. Ward B. Church !7 0. ?n 109 East Jones Street - Raleigh, North Carolina 27601-2807 ?P O S7 State of North Carolina Department of Environment, Health, and Natural Resources 512 North Salisbury Street • Raleigh, North Carolina 27611 James G. Martin, Governor William W. Cobey, Jr., Secretary MEMORANDUM TO: FROM: RE: DATE: Douglas G. Lewis Director Planning and Assessment ,r Chrys Baggett ?. . State Clearinghouse Melba McGee Project Review Coordinator 93-0163 - Scoping Proposed Improvements to SR 1311 (North Blvd.), Sampson County October 6, 1992 The Department of Environment, Health, and Natural Resources has reviewed the proposed scoping notice. The attached comments list and describe information that is necessary for our divisions to evaluate the potential environmental impacts of the project. More specific comments will be provided during the environmental review. Thank you for the opportunity to respond. The applicant is encouraged to notify our divisions if additional assistance is needed. MM: bb Attachments cc: David Foster P.O. Box 27687. Raleigh, North Carolina 227611-7687 Telephone 919-733.6376 An Equal OnnortUmrv Affirmative Action Fmnlover 9 North Carolina Wildlife Resources Commission 512 N. Salisbury Street, Raleigh, North Carolina 27604-1188, 919-733-3391 Charles R. Fullwood, Executive Director MEMORANDUM TO: Melba McGee, Planning and Assessment Dept.. Environment, Health, & Natural Resources FROM: Bennis St wart, Manager Habitat Conservation Program Date: -6ctober 5, 1992 SUBJECT: Request for information from the N. C. Department of Transportation (NCDOT) regarding fish and wildlife concerns for proposed improvements to SR 1311 (North Boulevard) from US 421 to SR 1838, Clinton, Sampson County, North Carolina, TIP No. U-2514,,DPA Project No. 93-0163. This correspondence responds to a request from Mr. L. J. Ward of the N. C. Department of Transportation (NCDOT) for our concerns regarding impacts on fish and wildlife resources resulting from the proposed roadway improvements. The N. C. Wildlife Resources Commission (NCWRC) has reviewed the proposed project, and a site inspection was conducted on September 25, 1992. Our comments are provided in accordance with provisions of the N. C. Environmental Policy Act (G.S. 113A-1 et seq., as amended; 1 NCAC 25), and the Fish and Wildlife Coordination Act (48 Stat. 401, as amended; 16 U.S.C. 661-667d). The proposed project involves widening of existing alignment in an area of extensive urban and residential development, and impacts to fish and wildlife habitat are expected to be minimal. While no specific concerns are anticipated, the following information is suggested for inclusion in the environmental document. Habitat types occurring on the construction site should be described and fish and wildlife species potentially impacted should be inventoried as in past NCDOT environmental documents. To the extent possible, borrow areas and construction easements should be included in the study area. Information on State- and Federally listed fish and wildlife species may be obtained by Memo Page 2 October 5, 1992 contacting Randy Wilson, Nongame and Endangered Species Program Manager, at (919) 733-7291. Cover type maps showing wetland and upland acreages impacted by the project will facilitate comprehensive assessment and review of project impacts. Wetland acreages should include all project-related areas that may undergo hydrologic change as a result of ditching, other drainage, or filling for project construction. The need for channelizing or relocating portions of streams crossed and the extent of such activities should also • be addressed. Mitigation for unavoidable loss of wetland and stream habitat should be discussed in the environmental document, and degradation of habitat quality as well as quantitative losses should be considered. If we can further assist your office, please call David Yow, Highway Project Coordinator, at (919) 528-9887. Thank you for the opportunity to provide input in the early planning stages for this project. cc Thomas Padgett, District 4 Wildlife Biologist Keith Ashley, District 4 Fisheries Biologist Randy Wilson, Nongame and Endangered Species Program Manager David Yow, Highway Project Coordinator DLS/DLY State of North Carolina Department of Environment, Health, and Natural Resources Reviewing Office: C C C C C C C C C C C C r L_ INTERGOVERNMENTAL REVIEW - PROJECT COMMENTS Project Number: I Due Date: After review of this project it has been determined that the EHNR permit(s) and/or approvals indicated may need to be obtained in order for this project to comply with North Carolina Law. Questions regarding these permits should be addressed to the Regional Office indicated on the reverse of the form. All applications, information and guidelines relative to these plans and permits are available from the same Regional Office. Normal Process I Time PERMITS SPECIAL APPLICATION PROCEDURES or REQUIREMENTS (statutory time limit) J Permit to construct & operate wastewater treatment ili f Application 90 days before begin construction or award of 30 days ac ties, sewer system extensions, & sewer construction contracts On-site inspection. Post-application systems not discharging into state surface waters. technical conference usual (90 days) NPDES • permit to discharge into surface water and/or Application 180 days before begin activity. On•sile inspection. 90.120 days J permit to operate and construct wastewater facilities Pre-application conference usual. Additionally, obtain permit to discharging into state surface waters. construct wastewater treatment facility-granted after NPDES. Reply (NIA) time, 30 days after receipt of plans or issue of NPDES permit-whichever is later. Water Use Permit Pre application technical conference usually necessary 30 days (NIA) Well Construction Permit Complete application must be received and permit issued 7 days prior to the installation of a well. (15 days) Dredge and Fill Permit Application copy must be served on each adjacent riparian property 55 days owner. On-site inspection. Pre-application conference usual. Filling may require Easement to Fill from N.C. Department of (90 days) Administration and Federal Dredge and Fill Permit. Permit to construct & operate Air Pollution Abatement J facilities and/or Emission Sources as per 15A NCAC 21H.06 N/A 60 days (90 days) Any open burning associated with subject proposal must be in compliance with 15A NCAC 2D.0520. Demolition or renovations of structures containing Or%T ,9 asbestos material must be in compliance with 15A 92 60 days NCAC 2D.0525 which requires notification and removal N/A prior to demolition. Contact Asbestos Control Group , 919.733.0820. (90 days) Complex Source Permit required under 15A NCAC 2D 0800 . . The Sedimentation Pollution Control Act of 1973 must be properly addressed for any land disturbing activity: An erosion & s entalio ' control plan will be required if one or more acres to be disturbed. Plan filed with proper Regional Office (Land Ouality.. `. at least 30 20 days days before be mnin activity. A fee of $30 for the first acre and $20.00 for each additional acre or art must accompany the Plan. (30 days) The Sedimentation Pollution Control Act of 1973 must be addressed with respect to the referrenced Local Ordinance: (30 days) On-site Inspection usual. Surety bond filed with EHNR. Bond amount Mining Permit varies with type mine and number of acres of affected land. Any area 30 days mined greater than one acre must be permited. The appropriate bond (60 days) must be received before the permit can be issued. North Carolina Burning permit On-site inspection by N.C. Division Forest Resources if permit 1 day exceeds 4 days (N/A) Special Ground Clearance Burning Permit - 22 On-site Inspection by N.D. Division Forest Resources required "if more 1 day counties in coastal N.C. with organic soils than five acres of ground clearing activities are involved. Inspections (NIA) should be requested at least ten days before actual burn is planned." Oil Refining Facilities N/A 90.120 days (N/A) II permit required, application 60 days before begin construction. Applicant must hire N.C. qualified engineer to: prepare plans. 30 aays Dam Safety Permit inspect construction, certify construction is according to EHNR approv• ed plans. May also require permit under mosquito control program. And (60 Bays) a 404 permit from Corps of Engineers. An inspection of site is neces- sary to verify Hazard Classification. A minimum fee of $200.00 must ac- company the application.-An additional processing fee based on a percentage or the total project cost will-be required upon completion ""`' Continued on reverse y J ?\. IIt =? j'?j el State of North Carolina Department of Environment, hdNatural Resources s, Division t_and Resources James G. Martin, Govemor PROJECT REVIEW COMMENTS Charles H. Gardner William W. Cobey, Jr., Secretary Director Project Number: County: Project Name: i Geodetic Survey I This project will impact geodetic survey markers. N.C. Geodetic Survey should be contacted prior to construction at P.O. Box 27687, Raleigh, N.C. 27611 (919) 733-3836. Intentional destruction of a geodetic monument is a violation of N.C. General Statute 102-4. This project will have no impact on geodetic survey markers. Other (comments attached) For more information contact the Geodetic Survey office a x(919) 7.?,3-36 n ? C. Reviewer? Date Erosion and Sedimentation Control -Z No comment This project will require approval of an erosion and sedimentation control plan prior to beginning any land-disturbing activity if more than one (1) acre will be disturbed. ? If an environmental document is required to satisfy Environmental Policy Act (SEPA) requirements, the document must be submitted as part of the erosion and sedimentation control plan. If any portion of the project is located within a High Quality Water Zone (HQW), as classified by the Division of Environmental Management, increased design standards for sediment and erosion control will apply. The erosion and sedimentation control plan required for this project should be prepared by the Department of Transportation under the erosion control program delegation to the Division of Highways from the North Carolina Sedimentation Control Commission. Other (comments attached) For more information contact the Land Quality section at (919) 733-4574. Reviewer Date P.O. Box 27687 • Raleigh, N.C. 27611-7687 • Telephone (919) 733-3833 An Equal Opportunity Affirmative Action Employer ?0j1? ? .yam' .... •.. J `\ ..'\ _ // ,; i or •,.?1 7 r r I.S Ip1 r .V .:::ITT ANp 1 1.3 1 - ???.:) 1 1p1 , p ,S . 's ' _ !?? f.3 1 Irll ?I 1 ?t? •1 It. 46' - ('y , S s Irlr V 17MC ` ?? .SU ? X11 • ?' N..O...e I,3 .9!1 . 1.? ?t 1rn r.J? it]! \\'!? I I .fl T or ` r.1 UNKEY ?s IIy ?`? . `\ 111. .1 _ IOI. it? LL 1 / :?7 l?\\y _-?' NuN \, f. I?Ir TURKEY `07: ?! 1.0 r-'ICI] ly I0 ITLo t /3 `?\_ $ 111 !. 1? S tii r 1 • ?' 1024 4 t ! f Ci 111 ,.1 f•3 17••1 _J?' - 110 [N Y E LLIO TT ---1 I?IILbly AEr I!1 1.1 1!1! 7 CHICKEN ? `? 11.1! Mn ?Ir•I 111A .9 `} ?J 1T11 /ROtINtON SNIP t(K J.EL 190.E p `.I!•1 <? d iR o B ?JN t Sol ( Lt 51 OMi T ` Jf rr3 1 7 VOLT Mu ZI 7.1 //9,11 , rv . o L 10 U& J. 7 ., xtA-84 ra ?° y 1.44! 1tL1 11.1 t I :e Lt1i 1)71 • ?t 1.111 POLLY LW . 17.9 1770 • • `•'? '(, rf ?] u - / 1711 loft 17 it ! nu ?' Y lfiZ 3 1 1! J )11 IAY/t0 1.0 ? .p !11 .9 ` COR ~ 1.1 1.111 f u • ?J 1110 •'Iv A rw3 t•Mon7 uAE J NYIN[ NGStY ! 1147 Ll14! 1L'. •.. 1 1 T JUNK 1731 ? 1 1) l Jul foN ITN4!\ OLNTON '[•IJJ/ 1.15E ] I !] \P TWIN '`? 1t11 r LL4 / 1213 12 SA-b R . L• ,03 waRl _L .] 171• E SA- 4 // ,• / V7 -• ?Rf E71 .• `' !'? [• t YOMV[ -7 ` R NINlp? YATTNII 11 190^I ROES,fv 11 p7?A ¦AT OR '.I 54 IjRA11N \ /? 0..d Nill• ,t •? "'! SA-1 NOLT ORO Yt / a ,111 rON NtCR ) 31 i / I 17 ?AINCLOT ].] U NON[ T.71.r I 1 \ / ?1' 11 rp L r•] . II 1 , CLINTON COUNTY LAUNDRY T TNOL yll Lt LE • I 1 }? 1 CLI ON Ny CLIFTON J llrp •,7 • _I.1 J-114 ET DICK 1 '17 ?c. .aG?( ,6Q d4 .y I A lPr CL LL. LANK ? 1 If tC I LO E1 111 CCC?___9?•`QgT ?f N 111 'Cbl j3 C!) / T ?(C ?E/R-f 0 U.S AO r CC ? I-EARS 't 114 9 GHk IM UEA ' t MN[ER ] 1 1!?i *? • CLIN ON 9•31 rRFt R v \\ I146 i13 111 ?j, PO?. 7.461 / 1 .g !rli .? i 1Ll // 10?[ N 5 O9 71 -219 tw1.11 SUN." C -d Vit .6 Ny I I r .1 } [ PwoR ?N Crowwdl 1.9 , ,3• f 1120 112- 4a TECH ?iyT RidO• v turef, 1119 LLAL 'r G.ay 1!11 r GRIFFIN 44•1., CLINIPMr AZ NN ti J TILL / Ya Lug ) rATE0. .Q 1 \I ?P m1 LL1 1 111E 1114 / SA 17 CL IM}ORr ILL. .il u) treArott 11AL ., 1 . !12) •? I?Iio NL 7 n JA!! 1 `1 1111) ? j1t! r11i4 ! 1LSTTAART CNAPSI. ? 1144 111 1.. 7 7 h LL1 13 d .• 11 •OMN?1'..1?r 1111 Lui ?' •? ? NARANN ) 1441 I 1 Iu 112 lL11 v 1141 .1 ?? A•-II 1115 'T7 1114• •? ,7 % ?` 114E _ ° .1 \R No NIr .? 1211 ].] lilt \nORt.O[ f ' 1111 1L `? ry 2!! JtAN Nr /tra IJ11_ c LLIX 7•I 1799 •0 121 A7iY" LL1 !lV 1111 L c 2 CONCORD `? '• Cred1 L L &A, 610a1d , 1445 !. \ P FlwwlN r 114 121[ 'Y u i ` r f 9f.n11n 1.14! f ?? Ch t ?? tl ° 1?2 ^ 11Q! ) JUL 1]411?L 1141 • ?.• d 121! Lul 111.1 Irp1 r'0 1111 1m !? - ?• Ira Cul ?s 111 -11 •• r J `1 ? 1.1 1711, uu 1, Lu1 LL1A 1L4L 1144 1911 1L C7wR 1 a ,Y v 1141Q? fL41- Y•11 0 12n L till 111 1141 7U .rW le 111 1. 1111 1.0 , 6 l ,o 1717 1707 Ilr? 1171 `? 1701 AAL no 0 \ 1111 R-Y _ 'li (,oA.nf D 221 ?? RN 111! Ldrif 'e E 21 1 / 13-0 r 't. \ '1141 [L? IL19 A4Dolri}! d r 0 221 1 c i2,. LAKE 000 1 _ I,Ir Irlr A 22 ISMt )] 2.1 L aAN S' Im. u1 !UI T Vy ??LNN N 717 SAN )41 1 qo1 n07 :1En11U1G a 2, )? )f ) 71 1 '? • K 356 SI?IOIN 156 •O•. )09 LITTLE ?DUCRANAII Ifl• ` / / - ;, 1.3! • 3rr•w f n 1111 l7 2 220 L 156 22 ?.,_,_ 911[N\CN 1r•p '1r loot 5' CARROLI M1WM1 ' 111, N?~O ?.r M NiOAwRiM MM120 171. 3 O Il ?rll 2? K 223 , N 156 PAIKERSIUIG` ' U IuARO 9 3Ct0R0 [ 15 N?• \.7 +1917 N L.6 •O• 1f 1! III ?/? \6 is 2Y.• 1 V 220 undo p Irl1?® 'R 17or ?'?l? J- -1, IL]r r0 , 1.13 111 Iwl , I.07 Irl Ally D(1c FKn9n r \' 1 4Nr e 1 State of North Carolina ' Department of Environment, Health, and Natural. Resources Division of Environmental Management 512 North Salisbury Street • Raleigh, North Carolina 27604 James G. Martin, Governor A. Preston Howard, Jr., P.E. William V41. Cobey, Jr., Secretary September 28, 1992 Acting Director MEMORANDUM To: Melba McGee Through: John Dorne c -Monica Swihart07 From: Eric Galamb Subject: Proposed Improvements to SR 1331 from US 421 to SR 1838 in Clinton Sampson County State Project DOT No. 8.2280701, TIP #U-2514 EHNR # 93-0163, DEM WQ # 6818 The Water Quality Section of the Division of Environmental Management requests that the following topics be discussed: A. Please identify the borrow locations. B. Two streams and one pond will be impacted by this project. The stream classifications are C-Sw. Efforts should be made to minimize the impacts to these water bodies through sedimentation and eutrophication. C. Identify the linear feet of stream channelization/relocations. D. Wetland Impacts i) Identify the federal manual used for identifying and delineating jurisdictional wetlands. ii) Have wetlands been avoided as much as possible? iii) Have wetland impacts been minimized? iv) Mitigation measures to compensate for habitat losses. v) Wetland impacts by plant communities affected. vi) Total impacts of wetlands. vii) List the 401 Water Quality General Certification numbers to cover the project. REGIONAL OFFICES Asheville Fayetteville Mooresville Raleigh Washington Wilmington Winston-Salem 704/251.6208 919/486.1541 704/663-1699 919/571-4700 919/946-6481 919/395-3900 919/896-7007 Pollution Prevention Pays P.O. Box 29535, Raleigh, North Carolina 27626-0535 -Telephone 919.733-7015 An Equal Opportunity Affirmative Action Employer Please be aware that written concurrence of 401 Water Quality Certification may be required for this project. DEPARTMENT OF THE ARMY WILMINGTON DISTRICT, CORPS OF ENGINEERS P.O. BOX 1890 i. . " ' G? WILMINGTON, NORTH CAROLINA 28402-1890 0 IN REPLY REFER TO October 30, 1992 Planning Division Mr. L. J. Ward, P.E., Manager Planning and Environmental Branch Division of Highways North Carolina Department of Transportation Post Office Box 25201 Raleigh, North Carolina 27611-5201 Dear Mr. Ward: G E O NOV 0 S 1992 s C' D?VISIC!V OF t? HIGHIWAY? IN, e' This is in response to your letter of August 31, 1992, requesting our comments on the initiation of a study of the project, "SR 1311 (North Boulevard), from US 421 to SR 1838 (Beaman Street), Clinton, Sampson County, Federal Aid Project No. STP-1311(2), State Project No. 8.2280701, TIP No. U-2514" (Regulatory Branch Action I.D. No. 199300258). From the U.S. Army Corps of Engineers (COE) perspective, our comments involve impacts to COE projects, flood plains, and other environmental aspects, primarily waters and wetlands. The proposed project would not involve any constructed COE navigation or flood control projects. The proposed project is sited in the city of Clinton and Sampson County, which participate in the Federal Flood Insurance Program. From a review of the July 1991 Sampson County Flood Insurance Rate Map, the proposed project appears to cross streams which have been mapped by approximate methods. All drainage structures should be designed so as not to produce more than a 1.0-foot flood surcharge above the 100-year flood level and addressed in future environmental impact statements. The hydraulic effect of the project should be coordinated with the city of Clinton and Sampson County for compliance with their flood plain ordinances. Executive Order 11988 should also be reviewed and complied with. Department of the Army permit authorization, pursuant to Section 404 of the Clean Water Act of 1977, as amended, will be required for the discharge of excavated or fill material, including construction debris, into waters of the United States or any adjacent and/or isolated wetlands. Please provide sufficient information for our evaluation of environmental impacts for all construction corridors which you are considering. Included should be wetland and soils mapping, indicating wetland and soils types, and data regarding endangered species, cultural resources, and fish and -2- wildlife habitat. Adverse environmental impacts should be avoided and then minimized. Mitigation must be provided to compensate for unavoidable impacts. Our comments will be provided in response to such information. Because of this early review and evaluation, we would expect a most , expeditious processing of your application for the specific activity requiring Federal authorization. Questions or comments related to the permit may be directed to Mr. Rudolf Schiener, Wilmington Field Office, Regulatory Branch, telephone (919) 251-4629. We appreciate the opportunity to comment on this project. If we can be of further assistance to you, please do not hesitate to contact us. S Lace Lawrencq W./Saunders Chief, P nning Division i Federal Emergency Management Agency Region IV 1371 Peachtree Street, NE, Suite 700 Atlanta, GA 30309 R4-NT September 16, 1992 Mr. L. J. Ward, P.E., Manager Planning and Environmental Branch N. C. Division of Highways P. 0. Box 25201 Raleigh, North Carolina 27611 RE: City of Clinton and Sampson County, North Carolina SR 1311, from US 421 to SR 1838 extension State Project 8.2280701, TIP No. U-2514 Dear Mr. Ward: a Q SEP 211992 S ?v IyVISION OF .Z HIGHWAYS RESEP?'? This is in response to your letter dated August 31, 1992, requesting information in evaluating potential environmental impacts for the above-referenced project as it pertains to the National Flood Insurance Program. The City of Clinton and Sampson County North Carolina are participating in the Regular Phase of the National Flood Insurance Program (NFIP). Any encroachments into the floodplains or regulatory floodways must be in compliance with the NFIP regulations. The agency in charge must ensure compliance with the floodplain management regulations enacted by the State of North Carolina. In this regard, it is imperative that the agency coordinate closely with the appropriate staff in the Floodplain Management Section of the Division of Emergency Management. If we can be of further assistance, please contact Ms. Bel Marquez at (404) 853-4436. Sincerely, Mary Anne Lyle, Chie Risk Assessment Secti , NTHD Mr. Eddie Keith, Project Engineer NC Department of Transportation Division of Highways 124 Division Street Wilmington, NC 28401 S,r,tQ1nber 29, 1994 OHIes 01 City M,,099f Dear Mr. Keith: This letter is to advise you that we have reviewed the need for sidewalks along North Boulevard. We request that the State include sidewalks along the north side of Vorth Boulevard from Beaman Street to the Highway Patrol Station. It is our understandings that the. City's cost will be $3,840. We are prepared to pay this amount and forward it to the State. It there are any further details that, need to be worked out, please advise. F q?99' CIrY OF CLINTON P.O. BOX 199 CLINTON, NOn'H CAROLINA 711378.0199 Sincerely, Tommy M. Combs City Manager .w STATE o 9 - -NORTH CAROLINA DEPARTMENT OF PUBLIC INSTRUCTION 116 West Edenton Street, Education Building Raleigh, NC 27603-1712 October 12, 1992 BOB ETHERIDGE State Superintendent VF16 ACS 1 5 1992 = MEMOR ANDUM ? z Q F 22 V1S10^10 ?Q N' AN S TO: L. J. Ward, P.E. r. mot, ?? Manager of Planning and Research '"` NC Division of Highways FROM: Charles H / Assistant uperintendent P Auxiliary ervices RE: SR 1311 (North Boulevard), from US 421 to SR 1838 (Beaman Street), Clinton, Sampson County, Federal Aid Project 1311(2), State Project No. 8.2280701, TIP No. U-2514 No. STP- Please find attached communication from Charles R. Gainey, Superintendent for Clinton City Schools, relative to subject project. mrl Attachment(s) an equal opportunity/affirmative action employer CLINTON CITY SCHOOLS P.O. BOX 646 CLINTON, NORTH CAROLINA 28328 (919) 592-3132 CHARLES R. GAINEY, SUPERINTENDENT GLENDA PHILLIPS, ASSISTANT SUPERINTENDENT RONALD MONTGOMERY, ASSISTANT SUPERINTENDENT CLYDE LOCKLEAR, JR., FINANCE OFFICER October 7, 1992 BOARD OF EDUCATION DWIGHT HORNE, CHAIRMAN VICTOR FRYAR, VICE-CHAIRMAN HAZEL COLWELL QUINCY EDGERTON PAMELA YOUNG WARREN JOE BELL Dr. Charles H. Weaver Assistant State Superintendent Auxiliary Services Department of Public Instruction 116 West Edenton Street Education Building Raleigh, NC 27603-1712 Dear Dr. Weaver: OCT 1 2692 The Clinton City Schools Administrative Staff and Board of Education have reviewed the improvement project TIP No. U-2514. We have no negative reaction to the proposal. We believe the improvement will have a positive impact on the area. Yo truly, Charles R. Gainey, Ed.D. Superintendent CRG:ca L1 T ITY SCHOOLS ... Providing A Future For Our Children .d Appendix B Air Quality and Traffic Noise FIGURE N1 - PROJECT LOCATION SR 1311 Sampson County US 421 to SR 1838 TIP n U-2514 State Project n 8.2280701 11BEGIN PROJECT ¦ r 11133' 11 .27 a 1G ?::•:? :. ...t:t :• • ? 1i?i ty;r. 1L • t7?? 7N M / Jy•. END PROJECT 0 'Oy Mu 1 Fo i s? o• ?1 O 1 TABLE N1 HEARING: SOUNDS BOMBARDING US DAILY 140 Shotgun blast, jet 100 ft away at takeoff PAIN Motor test chamber HUMAN EAR PAIN THRESHOLD 130 Firecrackers 120 Severe thunder, pneumatic jackhammer Hockey crowd Amplified rock music UNCOMFORTABLY LOUD 110 Textile loom 100 Subway train, elevated train, farm tractor Power lawn mower, newspaper press Heavy city traffic, noisy factory LOUD 90 D Diesel truck 40 mph 50 ft. away E 80 Crowded restaurant, garbage disposal C Average factory, vacuum cleaner I Passenger car 50 mph 50 ft. away MODERATELY LOUD B 70 E Quiet typewriter L 60 Singing birds, window air-conditioner S Quiet automobile Normal conversation, average office QUIET 50 Household refrigerator Quiet office VERY QUIET 40 Average home 30 Dripping faucet Whisper 5 fat away 20 Light rainfall, rustle of leaves AVERAGE PERSON'S THRESHOLD OF HEARING Whisper JUST AUDIBLE 10 0 THRESHOLD FOR ACUTE HEARING Sources: World Book, Rand McNally Atlas of the Human Body, Encyclopedia Americana, "Industrial Noise and Hearing Conversation" by J. H. Olishifski and E. R. Harford (Researched by N. Jane Hunt and published in the Chicago Tribune in an illustrated graphic by Tom Heinz.) TABLE N2 NOISE ABATEMENT CRITERIA Hourly A-Weighted Sound Level - decibels (dBA) Activity Category Leq(h) Description of Activity Category A 57 Lands on which serenity and quiet are of extraordinary significance and serve an important public (Exterior) need and where the preservation of those qualities is essential if the area is to continue to serve its intended purpose. B 67 Picnic areas, recreation areas, playgrounds, active sports areas, parks, residences, motels, (Exterior) hotels, schools, churches, libraries, and hospitals. C 72 Developed lands, properties, or activities not included in Categories A or B above. (Exterior) D -- Undeveloped lands E 52 Residences, motels, hotels, public meeting rooms, schools, churches, libraries, hospitals, and (Interior) auditoriums. Source: Title 23 Code of Federal Regulations (CFR) Part 772, U. S. Department of Transportation, Federal Highway Administration DEFINITION OF SUBSTANTIAL INCREASE Hourly A-Weighted Sound Level - decibels (dBA) • Existing Noise Level Increase in dBA from Existing Noise in Leq(h) Levels to Future Noise Levels < 50 > 15 > 50 > 10 Source: North Carolina Department of Transportation Noise Abatement Guidelines. FIGURE N2 - NOISE MEASURMENT SITES SR 1311 Sampson County US 421 to SR 1838 TIP Y U-2514 State Project n 8.2280701 a1 Noise Measurement Sites • 421,:? f • :' 1 N •'r'f:Vi' is iii: ? ? 7?• • r:i+r::.; :•r,. - :;::? 1 1111 •JA 's GI aus. BEGIN PROJECT 70t U ? O ` a 11 •?0 'all A3. b 10 . ` L1L 1 ?? t.;;;. ? gfa Q" "Ch PROJECT ?•:f .?v G ? iarr 701 t? f m 1!1 ?`f fr u6Z J!1! „o v O 1 TABLE N3 AMBIENT NOISE LEVELS (Le9) SR 1311, From US 421 to SR 1838, Sampson County TIP# U-2514 Project# 8.2280701 NOISE LEVEL SITE LOCATION DESCRIPTION (dBA) 1. SR 1311, .13 Mile West of US 701 Grassy 64 2. SR 1311, .08 Mile West of Jasper Street Grassy 67 Note: The ambient noise level sites were measured at 50 feet from the center of the nearest lane of traffic. TABLE N4 Leq TRAFFIC NOISE EXPOSURES SR 1311, From U8 421 to SR 1838, Sampson County TIP# U-2514 Project# 8.2280701 AMBIENT NEAREST RECEPTOR INFORMATION NEAREST ROADWAY NOISE PROPOSED ROADWAY ID N LAND USE CATEGORY NAME DISTANCE(ft) LEVEL NAME DISTANCE(ft) Beginning of Project to West of US 701 Bypass 1 Business C SR 1311 90 L 61 SR 1311 90 L 2 Business C " 110 R 60 " 110 R 3 Residence B 100 R 61 " 100 R 4 Residence B " 80 R 62 " 80 R 5 Business C " 90 R 61 •' 90 R 6 Business C " 95 R 61 " 95 R 7 Business C " 100 R 61 •' 100 R 8 Business C " 90 L 61 " 90 L 9 Residence B " 150 L 57 " 150 L 10 Residence B " 65 L 63 " 65 L 11 Residence B " 65 L 63 " 65 L 12 Residence B 65 L 63 " 65 L 13 Residence B " 62 L 64 " 62 L 14 Business C " 50 R 65 " 50 R 15 Business C " 50 R 65 " 50 R 16 Business C " 100 R 61 " 100 R 17 Business C " 250 L 52 •' 250 L From East of US 701 Bypass to West of Lloyd Street 18 Business C SR 1311 90 L 63 SR 1311 90 L 19 Business C " 390 L 50 " 390 L 20 Residence B " 125 R 61 " 125 R 21 Residence B " 115 R 62 " 115 R 22 Residence B " 110 R 62 " 110 R 23 Residence B " 65 R 66 " 65 R 24 Residence B " 60 R 66 " 60 R 25 Residence B " 70 R 65 " 70 R 26 Residence B " 60 L 64 " 80 L 27 Residence B " 80 L 64 " 60 L 28 Residence B " 90 L 63 " 90 L PREDICTED NOISE LEVELS -L- -Y- MAXIMUM NOISE LEVEL INCREASE - - 66 + 5 - - 64 + 4 - - 65 + 4 - - " 67 + 5 - - 66 + 5 - - 65 + 4 - - 65 + 4 - - 66 + 5 - - 61 + 4 - - " 68 + 5 - - * 68 + 5 - - * 68 + 5 - - * 68 + 4 - - 69 + 4 - - 69 + 4 - - 65 + 4 - - 56 + 4 - - 65 + 2 - - 51 + 1 - - 62 + 1 - - 63 + 1 - - 63 + 1 - - * 67 + 1 - - * 68 + 2 - - * 67 + 2 - - * 66 + 2 - - * 66 + 2 - - 65 + 2 1/1 A NOTE: Distances are from center of the existing or proposed roadways. -L--> Proposed roadway's noise level contribution. All noise levels are hourly A-weighted noise levels. -Y--> Noise level from other contributing roadways. Category E noise levels shown as exterior/interior (58/48). * -> Traffic noise impact (per 23 CFR Part 772). TABLE A3 CAL3QHC: LINE SOURCE DISPERSION MODEL - MARCH, 1990 VERSION JOB: U-2514: SR 1311 Sampson County DATE: 04/10/1994 TIME: 22:11:27.31 RUN: SR 1311 1996, NO BUILD 45 MPH k SITE G METEOROLOGICAL VARIABLES VS . .0 CM/S U - 1.0 M/S LINK DESCRIPTION VD - .0 CM/S 20 108. CM CLAS - 5 (E) ATIM 60. MINUTES MIXH - 400. M AMB - 1.9 PPM LINK COORDINATES (M) LENGTH BRO TYPE VPH EF H W V/C QUEUE X1 Y1 X2 Y2 (M) (DEC) (C/MI) (M) (M) (VF-4) 1. Far Lane Link 3.7 -804.7 3.7 804.7 1609. 360. AG 310. 17.2 .0 9.8 2. Near Lane Link .0 804.7 .0 -804.7 1609. 180. AC 310. 17.2 .0 9.8 RECEPTOR LOCATIONS COORDINATES (M) RECEPTOR X Y Z 1. R14, 50' RT. CL RES -13.4 .0 1.8 JOB: U-2514: SR 1311 Sampson County MODEL RESULTS REMARKS : In search of the angle corresponding to the maximum concentration, only the first angle, of the angles with same maximum concentrations, is indicated as maximum. WIND ANGLE RANGE: 0.- 20. WIND ANGLE (DEAR) MAX DEGR. CONCENTRATION (PPM) REC1 2.4 1 RUN: SR 1311 1996, NO BUILD 45 MPH TABLE A2 CAL3QHC: LINE SOURCE DISPERSION MODEL - MARCH, 1990 VERSION JOB: U-2514: OR 1311 Sampson County DATE: 04/10/1994 TIME: 22:10:43.10 R RUN: SR 1311 2016, BUILD 45 MPH SITE 6 METEOROLOGICAL VARIABLES VS . .0 CM/S VD .0 CM/S 20 . 108. CM U - 1.0 M/S CLAS - 5 (E) ATIM - 60. MINUTES MIXH 400. M AMB - 1.9 PPM LINK VARIABLES LINK DESCRIPTION LINK COORDINATES (M) LENGTH BRG TYPE VPH EF H W V/C QUEUE X1 YI X2 Y2 (M) (DEG) (G/MI) (M) (M) 'i\'1:"j 1. Far Lane Link 7.3 -804.7 7.3 804.7 1609. 360. AG 680. 10.4 .0 13.4 2. Near Lane Link .0 804.7 .0 -804.7 1609. 180. AG 680. 10.4 .0 13.4 RECEPTOR LOCATIONS COORDINATES (M) RECEPTOR X Y Z 1. R14, 50' RT. CL RES -7.9 .0 1.8 JOB: U-2514: SR 1311 Sampson County MODEL RESULTS RUN: OR 1311 2016, BUILD 45 MPH REMARKS : In search of the angle corresponding to the maximum concentration, only the first angle, of the angles with same maximum R concentrations, is indicated as maximum. WIND ANGLE RANGE: 0.- 20. WIND CONCENTRATION ANGLE (PPM) (DEGR) REC1 MAX 2.7 DOOR. 2 TABLE Al CAL3QHC: LINE SOURCE DISPERSION MODEL - MARCH, 1990 VERSION JOB: U-2514: SR 1311 Sampson County DATE: 04/10/1994 TIME: 22:10:22.50 RUN: SR 1311 1996, BUILD 45 MPH 3 SITE 6 METEOROLOGICAL VARIABLES VS - .0 CM/S U - 1.0 M/S LINK DESCRIPTION VD - .0 CM/S ZO - 108. CM CLAS - 5 (E) ATIM - 60. MINUTES MIXH - 400. M AMB - 1.9 PPM LINK COORDINATES (M) LENGTH BAG TYPE VPH EF H w V/C QUEUE X1 Y1 X2 Y2 (M) (DEG) (G/MI) (M) (M) 1. Far Lane Link 7.3 -804.7 7.3 804.7 1609. 360. AG 310. 17.2 .0 13.4 2. Near Lane Link .0 804.7 .0 -804.7 1609. 180. AG 310. 17.2 .0 13.4 RECEPTOR LOCATIONS COORDINATES (M) RECEPTOR X Y Z 1. R14, 50' RT. CL RES -7.9 .0 1.8 JOB: U-2514: SR 1311 Sampson County MODEL RESULTS REMARKS : In search of the angle corresponding to the maximum concentration, only the first angle, of the angles with same maximum concentrations, is indicated as maximum. WIND ANGLE RANGE: 0.- 20. WIND ANGLE (DEGR) MAX DEGR. CONCENTRATION (PPM) REC1 2.5 2 RUN: SR 1311 1996, BUILD 45 MPH A TABLE N5 FBWA NOISE ABATEMENT CRITERIA SUMMARY SR 1311, From US 421 to SR 1838, Sampson County TIPN U-2514 Project# 8.2280701 Maximum Predicted Contour Approximate Number of Impacted Laq Noise Levels Distances Receptors According to dBA (Maximum) Title 23 CFR Part 772 Description 50' 100' 200' 72 dBA 67 dBA A B C D E 1. SR 1311, East to US 701 67 63 58 <49' 80' 0 5 0 0 0 2. SR 1311, East to Lloyd Street 67 62 57 <49, 74' 0 5 0 0 0 3. SR 1311, East to SR 1838 63 59 54 <49' <49' 0 0 0 0 0 TOTALS 0 10 0 0 0 NOTES - 1. 501, 1001, and 200' distances are measured from center of nearest travel lane. 2. 72 dBA and 67 dBA contour distances are measured from center of proposed roadway. TABLE N6 TRAFFIC NOISE LEVEL INCREASE SUMMARY SR 1311, From US 421 to SR 1838, Sampson County TIPN U-2514 Project# 6.2280701 RECEPTOR EXTERIOR NOISE LEVEL INCREASES Substantial Impacts Due Noise Level to Both Section <.0 1-4 5-9 10-14 15-19 20-24 >- 25 Increases(1) Criteria(2) 1. SR 1311, East to US 701 0 10 7 0 0 0 0 0 0 2. SR 1311, East to Lloyd St. 0 it 0 0 0 0 0 0 0 3. SR 1311, East to SR 1838 0 0 0 0 0 0 0 0 0 TOTALS 0 21 7 0 0 0 0 0 0 (1) As defined in Table N2. (2) As defined by both criteria in Table N2. TABLE A4 CAL3QHC: LINE SOURCE DISPERSION MODEL - MARCH, 1990 VERSION JOB: U-2514: SR 1311 Sampson County DATE: 04/10/1994 TIME: 22:11:13.64 t RUN: SR 1311 2016, NO BUILD 45 MPH SITE i METEOROLOGICAL VARIABLES 1 VS = .0 CM/S VD .0 CM/S ZO - 108. CM U . 1.0 M/S CLAS - 5 (E) ATIM ' 60. MINUTES MIXH - 400. M AMB - 1.9 PPM LINK VARIABLES LINK DESCRIPTION LINK COORDINATES (M) LENGTH BRG TYPE VPH EF H W V/(' QUEUE X1 Y1 X2 Y2 (M) (DEG) (G/MI) (M) (M) (VEA) 1. Far Lane Link 2. Near Lane Link RECEPTOR LOCATIONS 3.7 -804.7 3.7 804.7 I 1609. 360. AG 680. 10.4 .0 9.8 .0 804.7 .0 -804.7 1609. 180. AG 680. 10.4 .0 9.8 COORDINATES (M) RECEPTOR X Y Z 1. R14, 50' RT. CL RES -13.4 .0 1.8 JOB: U-2514: SR 1311 Sampson County MODEL RESULTS REMARKS : In search of the angle corresponding to the maximum concentration, only the first angle, of the angles with same maximum concentrations, is indicated as maximum. t WIND ANGLE RANGE: 0.- 20. WIND CONCENTRATION ANGLE (PPM) (DEGR) REC1 MAX 2.7 DEGR. 6 RUN: SR 1311 2016, NO BUILD 45 MPH ? ..__.. .+ STAri a State of North Carolina Department of Environment, Health, and Natural Resources Division of Environmental Management 512 North Salisbury Street • Raleigh, North Carolina 27604 James G. Martin, Governor A. Preston Howard, Jr., P.E. William W. Cobey, Jr., Secretary September 28, 1992 Acting Director MEMORANDUM To: Melba McGee 1 t»U?I7 Through: John Dorneq?) Monica Swihart From: Eric Galamb f Subject: Proposed Improvements to SR 1331 from US 421 to SR 1838 in Clinton Sampson County State Project DOT No. 8.2280701, TIP #U-2514 EHNR # 93-0163, DEM WQ # 6818 The Water Quality Section of the Division of Environmental Management requests that the following topics be discussed: A. Please identify the borrow locations. B. Two streams and one pond will be impacted by this project. The stream classifications are C-Sw. Efforts should be made to minimize the impacts to these water bodies through sedimentation and eutrophication. C. Identify the linear feet of stream channelization/relocations. D. Wetland Impacts i) Identify the federal manual used for identifying and delineating jurisdictional wetlands. ii) Have wetlands been avoided as much as possible? iii) Have wetland impacts been minimized? iv) Mitigation measures to compensate for habitat losses. v) Wetland impacts by plant communities affected. vi) Total impacts of wetlands. vii) List the 401 Water Quality General Certification numbers to cover the project. REGIONAL OFFICES Asheville Fayetteville Mooresville Raleigh Washington Wilmington Winston-Salem 704/251-6208 919/486-1541 704/663-1699 919/571-4700 919/946-6481 9 19/395 -3900 919/896-7007 Pollution Prevention Puys P.O. Box 29535, Raleigh, North Carolina 27626-0535 Telephone 919-733-7015 An Equal Opporttmity Affirmative Action Employer Please be aware that written concurrence of 401 Water Quality Certification may be required for this project. ,_;::! : i i) LA. F 1 :I: F; F.R ' Eirvu'?! ('i :J, E::.1 'M F' ».. ?? I::: V, i I I:::i: .... .... .... .... .... .... .... .._ .... .... ._ ._..... .... .... .._ ............ ._. ,, SEP 9 ' G>r r'?LYF.:.?lC,'f f.I .1. NC1 (:1I:r,.1ICI j ow f Ci FIF%(.1._11:::(:; F, F11, F'i:1; f:::I? :C i`4 ,`.'1.1f`F°:I: (:: :I: F::N_f. NF'C) F<r'iFl I C1 i'•1. IN 1, 1,4 (:: Y .i.. r?? .I. I :: '•i F. i I i i F::1:? ........ (?1'I'LII_:I?; {,:F'F::(:':I:I?''r' rtt?I? ?,.LLF'?CLI f.;C1i•iF'i?:::i•?I,`.;'? vCIN1'1F::NI L.. C) (:1 1.. I{I::(:!L_!:I:IiF?:? 1 .1iJI:?F:: F;. f* IA I::, F'{:(:11r:I:; fd C1!° F: E:: 'I' L.1 f ; i'.! "I (:1 i • i f :: (... is ; ; `, i"1 C (:; f:" E: , 1- :I. `?? :I ,>' :I: (:1 i'•1 (:1 I:: F' .... ,':; i`.! r ? :I: i ? C; r'?? i ?! i:; ;' ; `' ;!;' i:: ,`. , :' i`4 F:: i'?1..i . ?srnr 6> ? y. ?•rr{. STATE OF NORTH CAROLINA DEPART MENT OF TRANSPORTATIO c P.O. BOX 25201 RALEIGH 27611-5201 V\? JAMES G. MARTIN ,isIVISION OF HIGHWAYS GOVERNOR THOMAS J. HARRELSON August 31, 1992 WILLIAM G. MARLEY, JR., P.E. SECRETARY STATE HIGHWAY ADMINISTRAI OR MEMORANDUM TO: Mrs. Chrys Baggett, Director State Clearinghouse Dept. of Administration FROM: #-Planning L. J. Ward, Jr., P. E., Manager and Environmental Branch SUBJECT: SR 1311 (North Boulevard), from US 421 to SR 1838 (Beaman Street), Clinton, Sampson County, Federal Aid Project No. STP-1311(2), State Project No. 8.2280701, TIP No. U-2514 The Planning and Environmental Branch of the Division of Highways has begun studying the proposed improvements to SR 1311 (North Boulevard). The project is included in the 1993-1999 North Carolina Transportation Improvement Program and is scheduled for right of way in fiscal year 1995 and construction in fiscal year 1996. The proposed project begins at US 421 and extends eastward along existing SR 1311 (North Boulevard) to SR 1838 (Beaman Street). The TIP calls for widening the existing 24-foot, two lane facility to a 64-foot, face to face curb and gutter section (five 12-foot lanes). The proposed right of way width is 80 feet, expanding at streams to include all structures. Also, four-to-one slopes are proposed along the residential area between US 701 Bypass and Beaman Street for aesthetic purposes. The project is shown on the attached vicinity map. We would appreciate any information you might have that would be helpful in evaluating potential environmental impacts of the project. If applicable, please identify any permits or approvals which may be required by your agency. Your comments will be used in the preparation of a document evaluating environmental impacts of the project. It is desirable that your agency respond by November 4, 1992 so that your comments can be used in the preparation of this document. If you have any questions concerning the project, please contact Mr. Brian F. Yamamoto, Project Planning Engineer, of this Branch at (919) 733-7842. LJW/plr Attachment Ar Equal Opporiunity/Affirmative Action Employer ?r IJ /rr wfo? /B.rrll a ?ro??A T 9 \ Lon,9 Spiveys Sut ontown , Corner 10 11 13 421 ° I y J Ci Piney Green , Keener J 403 S A M P 13S O TN s 7,1 7 II a Ir, ?I Salemburg 101°"+ , Autryville •? `-rCllnlo? * ` I- li \ 4 e , ?sx 12 f 12 I olio t 7 Turk toseboro? I \ 1 r U o1. r , 111 1D1 \ 7 0 I/ sbur ? ? In?/g(pld ? r Garland Delwa? 7 ' 471% -? Harrells T Tomahellk .n / Q Derr d? Iva, A, I `? lee BIBEGIN PROJECT 70 7 Jes] Tc iety i 70? less 701 °us r 7o3 IelS / f ._ r Null ;J o I e? END PROJECT Tr1 \ !°5] iBJe 1----7 T--T -I'_I ,- -1_;c--`=_-) r CLINTON 10 V / O NORTH CAROLINA DEPARTMENT OF TRANSPORTATION DIVIS10N OIL HIGHWAYS PLANNING AND P.NVIRONMENI'AI, BRANCH SR 1311 US 421 TO SR 1838 SAMPSON COUNTY U-2514 0 mile 0.5 Sul i3il Z tcL,4 b ( l V i?r Y I I/ f Z- I le A v1 ACT 1ao ? t 5 ,??-ar, 6 ?f -Wz r? Z- 7 7 ?c/ /ZC% C 5. N. C. DEPARTMENT OF TRANSPORTATION TRANSMITTAL SLIP DATE 8 f la?9L TO: REF. NO. OR ROOM, BLDG. FROM: REF. NO. OR ROOM, BLDG. Q?r,ar a- ey\ 0-}o ACTION ? NOTE AND FILE ? PER OUR CONVERSATION ? NOTE AND RETURN TO ME ? PER YOUR REQUEST ? RETURN WITH MORE DETAILS ? FOR YOUR APPROVAL ? NOTE AND SEE ME ABOUT THIS XFOR YOUR INFORMATION ? PLEASE ANSWER ? FOR YOUR COMMENTS ? PREPARE REPLY FOR MY SIGNATURE ? SIGNATURE ? TAKE APPROPRIATE ACTION ? INVESTIGATE AND REPORT COMMENTS: SGO?oInG /?/CC?l?r?e ?/r?(,IT?S • L 401, ,?. srnt£ n STATE OF NORTH CAROLINA DEPART MENT OF TRANSPORTATION P.O. BOX 25201 RALEIGH 27611-5201 JAMES G. MARTIN GOVERNOR THOMAS J.HARREL.SON August 10, 1992 SECRETARY WETLN%! ,NATiT W!. ` DIVISION OF HIGHWAYS WILLIAM G. MARLEY, JR., P.E. STATE HIGHWAY ADMINISTRATOR MEMORANDUM TO: Scoping Meeting Attendants FROM: Brian F. Yamamoto Project Planning Engineer SUBJECT: SR 1311 (North Boulevard) from US 421 to SR 1838 (Beaman Street), Clinton, Sampson County, Federal Aid Project No. STP-1311(2), State Project No. 8.2280701, TIP No. U-2514 A scoping meeting for the subject project was held on August 4, 1992. The following persons were in attendance: Tom Tarleton Area Locating Engineer Joe Blair Division 3 Office Eric Galamb DEM - Wetlands Wady Williams FHWA Abdul Rahmani Hydraulic Design Danny Rogers Program Development Phil Williamson Photogrammetry Don Sellers Right of Way Debbie Barbour Roadway Design W. S. Cox Roadway Design Ron Allen Roadway Design Ray Moore Structure Design Robin Stancil SHPO Linwood Stone Planning and Environmental Brian Yamamoto Planning and Environmental John Wright Planning and Environmental In addition to these participants at the scoping meeting, the following persons submitted written comments prior to the meeting: Mike Bruff Statewide Planning Paul Worley State Rail Division Curtis Yates Bicycle Coordinator H. F. Koch Geotechnical Unit Alan Jones Cost Estimating An Equal OODortunitvlAftirmative Action Emnlover a August 10, 1992 Page 2 The scoping meeting began with a brief project description and Brian Yamamoto then asked for comments and suggestions. The Statewide Planning Branch had suggested in earlier correspondence that the east project limit be extended to US 701 Business. Danny Rogers confirmed that the project will not be extended to US 701 Business. Mr. Rogers noted that SR 1838 (Beaman Street) is currently a four lane section between North Boulevard and US 701 Business and would provide adequate access between the two facilities. Debbie Barbour acknowledged redesigning the North Boulevard/Beaman Street intersection, allowing North Boulevard to be the through movement instead of Beaman Street, had also been suggested by the Statewide Planning Branch. Joe Blair replied that Beaman Street appears to have the heaviest traffic movement and the intersection should retain Beaman Street as the main movement. However, Mr. Blair does anticipate the need to signalize the intersection in the near future. The proposed five-lane section identified in the TIP was then discussed. Mr. Blair commented that a three-lane section should be considered in lieu of a five-lane section, based on current traffic. Linwood Stone noted that a five lane section would better accommodate traffic operations near the North Boulevard/US 701 interchange. Traffic merging on and off the interchange ramps would interfere less with through movements if a five-lane section is provided. Mr. Stone stated a capacity analysis based upon traffic projections from the Traffic Surveys Unit would help determine which typical section to recommend and whether a signal is needed at the North Boulevard/Beaman Street intersection. Mr. Stone asked Danny Rogers if there were any changes in the updated Transportation Improvement Program (TIP) for the subject project regarding project limits, cross-section, or cost. Mr. Rogers stated that he was not aware of any changes and later confirmed this in a telephone conversation with Mr. Yamamoto. Mr. Stone requested that a right of way abstract be obtained and the information be shared with Roadway Design. The North Boulevard crossing of US 701 Bypass was the next topic discussed. According to Ms. Barbour, preliminary studies of Bridge No. 52, which carries North Boulevard over US 701 Bypass, indicate it cannot be widened without replacing the entire structure. Since the bridge has a high sufficiency rating (95.4 out of 100.0) and should provide reliable service for 30 years or more, it is recommended that the typical section near the bridge be reduced to a 59-foot, face to face curb and gutter section (five, 11 foot lanes with two foot concrete curbs). Ray Moore agreed with the recommendation to retain the existing structure. Wady Williams indicated that he had no problem with the recommendation, since this decision on a non-national highway road rests with the state. The meeting discussion shifted briefly to hydraulic aspects of the project. Abdul Rahmani commented there are two stream crossings on the project. One of the culverts is an undersized corrugated metal pipe and will likely be replaced with a reinforced concrete box culvert (RCBC). The second stream crossing will probably require only a culvert extension. Mr. Rahmani will supply additional information as it is available. 11 August 10, 1992 Page 3 Eric Galamb requested that stream classifications be provided to his agency as soon as possible. Mr. Yamamoto met with Dave Foster, of DEHNR, on August 4, 1992 at 2:30 to review the subject project. According to MR. Foster, both streams are classified as "C-Swamp" (C-SW). Mr. Foster also noted the potential for a Nationwide Section 404 permit, accompanied by a Section 401 Water Quality Certification. From an environmental standpoint, Mr. Foster feels this project could be considered a Categorical Exclusion. Historic/archaeological aspects of the proposed project were addressed by Robin Stancil. According to Ms. Stancil, no archaeological sites are listed on the National Register of Historic Places and no further archaeological investigations are necessary. Ms. Stancil also commented that no historic structures are recorded within the project limits; however, she recommended an NCDOT historian photograph structures in the project area and relay findings to her for SHPO concurrence. The corridor for the proposed improvements was briefly discussed. Mr. Yamamoto stated that asymmetric widening should be considered along parts of the project to utilize state owned property and reduce right of way expense. Don Sellers recommended that the. fence at the North Carolina Department of Corrections needs to be a construction limit. He related that moving the fence could be very expensive. Mr. Blair and Ms. Barbour suggested that four-to-one slopes be used along the residential area between US 701 Bypass and Beaman Street. Ms. Barbour stated that these slopes will be included in right of way cost estimates. An 80 foot right of way width, expanding at streams to include any structures, will be used in cost estimates. The project schedule was the last topic discussed in the scoping meeting. Ms. Barbour suggested that if Planning would postpone the completion date of the EA a few months, surveys could be completed and more accurate cost estimates could be included in the EA. Mr. Stone, Mr. Yamamoto, and Ms. Barbour agreed to the following schedule change in order to receive the most accurate cost estimates: Current Schedule Revised Schedule Completion Dates Completion Dates EA May 1993 October 1993 FONSI January 1994 April 1994 The Planning and Environmental Branch will continue with planning studies and request input from Federal and State agencies. BFY/rfm Attachment I, REPLY TO ATTENTION OF DEPARTMENT OF THE ARMY WILMINGTON DISTRICT, CORPS OF ENGINEERS P.O. BOX 1890 WILMINGTON, NORTH CAROLINA 28402-1890 October 16, 1995 Regulatory Branch Action ID No. 199300258 and Nationwide Permit No. 23 NC Department of Transportation Division of Highways Post Office Box 25201 Raleigh, North Carolina 27611-5201 Dear Sir: 0 50" 1995 Reference your March 13, 1995, request for Department of the Army (DA) authorization to improve a one mile section of SR 1311 from US 421 to SR 1838, on Little Coharie Creek, in Clinton, Sampson County, North Carolina. For the purposes of the Corps of Engineers' Regulatory Program, Title 33, Code of Federal Regulations (CFR), Part 330.6, published in the Federal Register on November 22, 1991, lists nationwide permits. Authorization, pursuant to Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act, was provided by Nationwide Permit No. 23 for activities undertaken, assisted, authorized, regulated, funded or financed, in whole or in part, by another Federal agency or department where that agency or department has determined, pursuant to the CEQ Regulation for the Implementing the Procedural Provisions of the National Environmental Policy Act, that the activity, work or discharge is categorically excluded from environmental documentation because it is included within a category of actions which neither individually nor cumulatively have a significant effect on the human environment, and the Office of the Chief of Engineers has been furnished notice of the agency's or department's application for the categorical exclusion and concurs with that determination. Your work is authorized by this nationwide permit provided it is accomplished in strict accordance with the enclosed conditions and provided you receive, a Section 401 water quality certification from the North Carolina Division of Environmental Management (NCDEM) and, if your work is located in the coastal area, a consistency determination from the North Carolina Division of Coastal Management (NCDCM). You should contact Mr. John Dorney, telephone (919) 733-1786, regarding water certification, and Mr. Steve Benton, telephone (919) 733-2293, regarding consistency determination. You are reminded that the fill material used to build the temporary detour should be removed and the ground below it restored to original grade as soon as traffic is returned to the normal course of SR 1311. In addition, you are reminded that the inside bottom elevation of new concrete box culverts should be no higher than the natural stream bed elevation, in order to facilitate the normal movement of aquatic organisms. This nationwide permit does not relieve you of the responsibility to obtain other required State or local approval. Printed on IS Recycled Paper I This verification will be valid until the nationwide permit is modified, reissued, or revoked. All nationwide permits are scheduled to be modified, reissued, or revoked prior to January 21, 1997. It is incumbent upon you to remain informed of changes to the nationwide permits. We will issue a public notice announcing the changes when they occur. Furthermore, if you commence or are under contract to commence this activity before the date the nationwide permit is modified, or revoked you will have twelve months from the date of the modification or revocation to complete the activity under the present terms and conditions of this nationwide permit. Questions or comments may be addressed to Mr. Matt Flint, Wilmington Field Office, Regulatory Branch, telephone (910) 251-4466. Sincerely, G. Wayne Wright Chief, Regulatory Branch Enclosure Copies Furnished (without enclosure): Mr. Steve Benton North Carolina Department of Environment, Health and Natural Resources Post Office Box 27687 Raleigh, North Carolina 27611-7687 V Mr. John Dorney Division of Environmental Management North Carolina Department of Environment, Health and Natural Resources 4401 Reedy Creek Road Raleigh, North Carolina 27607 Ms. Stephanie Briggs Supervisor, Permits Section Planning and Environmental Branch North Carolina Department of Transportation Division of Highways Post Office Box 25201 Raleigh, North Carolina 27611-5201 L;