Wanucha, Dave
From:Hining, Kevin J
Sent:Friday, June 26, 2020 8:43 AM
To:Wanucha, Dave
Cc:Mitchell, Robert K
Subject:RE: \[External\] Linville River /Ruffin St bridge project_Div 11
Attachments:Avery 1 bridge photos.pdf
Hey Dave,
Yep, that’s the temporary causeway. Also, the site is unique in that 80-90% of the flow is on the 221 side of the project,
and the causeway is on the other side. The side with the causeway is a flat, shallow pool with very little flow, so while
we have a causeway going out to the middle bent, it should be diverting/blocking very little flow. The attachment above
has a photo on it that will hopefully help show this (bottom of the page).
Hope that gives you what you need, but give me a shout if not. The 401 # is 20200187.
Thanks and hope all is well!
Kevin
Kevin Hining
Division 11 Environmental Officer
North Carolina Department of Transportation
828-386-7202 cell
kjhining@ncdot.gov
801 Statesville Rd.
PO Box 250
North Wilkesboro, NC 28659
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
_____________________________________________________________
From: Wanucha, Dave <dave.wanucha@ncdenr.gov>
Sent: Friday, June 26, 2020 8:24 AM
To: Hining, Kevin J <kjhining@ncdot.gov>
Subject: Fwd: \[External\] Linville River /Ruffin St bridge project
1
Hi Kevin,
Just a heads up. I’m not familiar with the project, but what Kevin explained sounds correct. I’ll touch base with
you in a few hours and then respond to Mr Erno. Thanks.
Dave Wanucha
Division of Water Resources
401 & Buffer Transportation Permitting
NC Department of Environmental Quality
336-776-9703 office
336-403-5655 mobile
Dave.Wanucha@ncdenr.gov
NC DEQ Winston Salem Regional Office
450 West Hanes Mill Road, Suite 300
Winston Salem, NC 27105
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
Begin forwarded message:
From: "Mitchell, Robert K" <kevin.mitchell@ncdenr.gov>
Date: June 26, 2020 at 7:25:07 AM EDT
To: Harry Erno <thes99@gmail.com>
Cc: "Wanucha, Dave" <dave.wanucha@ncdenr.gov>
Subject: RE: \[External\] Linville River /Ruffin St bridge project
Morning Mr. Erno.
This project was permitted out of our Winston Salem Office. Dave Wanucha is the contact. I have
copied him on the email if he wants to add anything or if you have additional questions. I’m not familiar
with this particular design, but I can say that one of our requirements when doing work in a stream is
that the water be diverted around the work area in order to minimize impacts to downstream
resources. This is important in reducing turbidity and sedimentation especially if there are trout in the
stream. On larger bodies of water such as the Linville River we also permit temporary causeways into
the water to provide a platform to do the work. Not sure if this is the case on this project, but that
might be what you are seeing (Dave can confirm this). DOT runs hydraulic models to make sure there is
no flooding impact upstream or downstream. These temporary causeways are removed when the work
is complete and the stream is restored to its original contours. Hope this helps.
Kevin Mitchell
Environmental Specialist II
Division of Water Resources
401 & Buffer Transportation Permitting
NC Department of Environmental Quality
2
828-296-4650 Office
828-231-1580 Mobile
Email Kevin.mitchell@ncdenr.gov
NC DEQ Asheville Regional Office
2090 U.S. Hwy. 70
Swannanoa, N.C. 28778
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
Based on the current guidance to minimize the spread of COVID-19, the Department of Environmental
Quality has adjusted operations to protect the health and safety of the staff and public. Many
employees are working remotely or are on staggered shifts. To accommodate these staffing changes, all
DEQ office locations are limiting public access to appointments only. Please check with the appropriate
staff before visiting our offices, as we may be able to handle your requests by phone or email. We
appreciate your patience as we continue to serve the public during this challenging time.
From: Harry Erno \[mailto:thes99@gmail.com\]
Sent: Thursday, June 25, 2020 5:39 PM
To: Mitchell, Robert K <kevin.mitchell@ncdenr.gov>
Subject: \[External\] Linville River /Ruffin St bridge project
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an
attachment to report.spam@nc.gov
Hello Kevin, I received your contact information from Dan Boss. I contacted him because of my
concern about the way the construction company that is working on the Ruffin Street bridge
project in Linville is diverting the water in the river. It appears that they are narrowing the flow
of the river (which I am pretty sure is not allowed without the Army Corp of Engineers
permission). My concern with the narrowing of the water flow is that this neighborhood is prone
to flooding as it is and if they are in fact narrowing the flow, it will only exacerbate the problem.
I am hoping that the boulders, etc that they are filling the river with now is simply a platform for
them to work on while they build the bridge and that the Fill will be removed once the project is
complete. Do you know whether this is the case or not? I appreciate your response.