HomeMy WebLinkAbout20200850 Ver 1_Percussive Activity_20200626Blasting will be most likely required to complete the proposed work during Summer 2020 - Fall
2021. Geotechnical investigations have been performed along the project corridor, but the
specific locations where blasting might be necessary are not yet known. Pre -drilling will be
performed once construction begins and the blasting plan will be developed as necessary. The
blasting plan will be provided upon request once completed.
There are no red HUCs within 0.25 mile from the study area.