Todd and Erin,
Wiesner, Paul
Thursday, June 18, 2020 8:27 AM
Tugwell, Todd J CIV USARMY CESAW (US); Davis, Erin B
Allen, Melonie; Bradley Breslow; Ryan Medric; Kim Browning
Meeting Minutes_601 East Credit Release Site Visit -June 1, 2020_DMS# 95756_SAW#
2013-00265 DWR# 20140547
601 East_95756_IRT Credit Release Memo -June 2020.pdf
Follow up
Completed
The meeting minutes from the June 1, 2020 IRT credit release site visit are attached.
Please let us know if you have any questions, comments or concerns.
Rya n,
Please include the final meeting minutes in the 2020 MY6 report for reference.
Thanks
Paul Wiesner
Western Regional Supervisor
North Carolina Department of Environmental Quality
Division of Mitigation Services
828-273-1673 Mobile
Pau l.wiesner(cancdenr.gov
Western DMS Field Office
5 Ravenscroft Drive
Suite 102
Asheville, N.C. 28801
{�YTy Mln/n!TiiwJ��
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
1
M E M O R A N D U M
3600 Glenwood Avenue, Suite 100
TO: Paul Wiesner - DMS
FROM: Ryan Medric - RES
DATE: 6/11/2020
fires
Raleigh, North Carolina 27612 919.209.1052 tel. 919.829.9913 fax
RE: 601 East MY5 (2019) IRT Credit Release Site Visit
Attendees:
IRT: Todd Tugwell (USACE), Mac Haupt (NCDWR), Erin Davis (NCDWR)
DMS: Paul Wiesner
RES: Brad Breslow, Ryan Medric
Site Visit Date: June 1, 2020
The IRT, DMS, and RES had a site visit at the 601 East Stream Restoration Site to discuss the Monitoring
Year 5 (2019) credit release. The main topics of discussion were the potential flow issues, beaver dams,
and encroachment. Details are bulleted below:
- Flow was observed throughout all project reaches, however, the IRT requested the flow gauge on
Reach 1 be moved further upstream towards the ephemeral reach. On 6/3/2020 RES moved the
flow gauge from XS2 up to XS 1.
- The IRT observed beaver dams on Reach 2 and 3 and encroachment along Reach 4. RES addressed
these items on 6/2/2020 (photos attached). The IRT noted that RES needs to be timelier when
addressing maintenance issues.
- The IRT also observed missing easement signage and small areas of easement
scalloping/encroachment. RES agreed to repair any easement scalloping/encroachment and agreed
to ensure all required easement marking and signage are updated and present by the end of MY6
(2020) monitoring.
- Reach 2 showed far less parrotfeather than previously observed. RES will continue
observing/treating the parrotfeather as necessary.
- General site vegetation was above average in height, especially along the channel. A few small bare
herbaceous areas were noted likely due to bench cutting during construction.
- At the end of the meeting, the IRT agreed to release 2019 project credit as proposed by DMS.
Beaver dam removal and livestaking
Easement marking and planting
�
Headcut repair with seeding and coir logs