Hello everyone,
Please see Dare County's request below to allow dredging work to continue through June until July
1, due to work delays they've encountered, as outlined in their request. Please let me know if you
need any additional info and/or if you have any questions or concerns.
Thanks,
Heather
Heather Coats
Beach & Inlet Management Project Coordinator
Division of Coastal Management
North Carolina Department of Environmental Quality
910 796 7302 office
heather.coats&ncdenr.gov
127 Cardinal Drive Extension
Wilmington, NC 28405
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
From: Brent Johnson [mailto:brent.johnson@darenc.com]
Sent: Tuesday, June 9, 2020 11:17 AM
To: Coats, Heather <heather.coats@ncdenr.gov>; Ken Willson
<kwillson@coastalprotectioneng.com>; Pelletier, Josh R CIV CESAW CESAD (USA)
<Josh.R.Pelletier@usace.army.mil>
Cc: Winslow, Lancelot D <Iwinslow@ncdot.gov>
Subject: [External] South Ferry Channel
External email. Do not click links or open attachments unless you verify. Send all suspicious email as an
Mc.gov
Hello Heather.
Dare County would like to request an extension for the South Ferry Channel dredging event
currently being executed by NC DOT's dredge MANTEO. We are requesting a permit
extension to 1 July 2020. The dredge Manteo has been on the project site since May 15, 2020
and has completed 650 feet of dredging removing an estimated 20000 cy. NC DOT has been
delayed due to multiple uncontrollable and unforeseen issues in the last 24 days to include,
Tropical Storms, Nor'Easters, heavy winds, maintenance and manning issues due to NC DOT's
mandatory furloughs which has shut down operations for a total of 11 days so far. The tides
and current have been so strong that it shuts down operations for 4-5 hours. The project has
about 1000 feet remaining and they are averaging about 80 feet a day if conditions are good
which should take an additional 12 days. The 1 July extension matches our current federal
extension and allows an additional 4 days to account for any future unforeseen and
unpredictable issues.
I have attached an overlay showing progress and remaining 1000 feet. Please let me know if
you need anything else and thank you for the help and support.
Brent
Brent Johnson, PMP
Dare County Project Manager
Dare County Grants and Waterways
MAJOR, U.S. Army (Ret)
Brent. j ohnson&darenc. com
252-475-5628 Office
252-473-6653 Fax
757-897-6625 Cell
P.O. Box 1000
Manteo, NC 27954
Email correspondence to and from this address is subject to the North Carolina Public Records
Law and may be disclosed to third parties.