HomeMy WebLinkAboutSW6200303_O&M EZ - Boykin_20200605Operation & Maintenance Agreement
Project Name:
Project Location:
Boykin PV1 Solar Electric Power Plant
Wade, Cumberland County, North Carolina
Cover Page
Maintenance records shall be kept on the following BMP(s). This maintenance record shall be kept in a log in a known set
location. Any deficient BMP elements noted in the inspection will be corrected, repaired, or replaced These
deficiencies can affect the integrity of structures, safety of the public, and the pollutant removal efficiency of the BMP(s).
The BMP(s) on this project include (check all that apply & cc
Bioretention Cell Quantity:
Dry Detention Basin
Grassed Swale
Green Roof
Infiltration Basin
Infiltration Trench
Level Spreader/VFS
Permeable Pavement
Proprietary System
Rainwater Harvesting
Sand Filter
Stormwater Wetland
Wet Detention Basin
Disconnected Impervious Area
User Defined BMP
Quantity:
Quantity:
Quantity:
Quantity:
Quantity:
Quantity:
Quantity:
Quantity:
Quantity:
Quantity:
Quantity:
Quantity:
Present:
Present:
0
0
0
0
0
0
0
0
0
0
0
0
0
ng O&M tables wil
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
De aciclecl auto
Entire Site
I acknowledge and agree by my signature below that I am responsible for the performance of the maintenance procedures listed
for each BMP above, and attached O&M tables. I agree to notify NCDENR of any problems with the system or prior to any
changes to the system or responsible party.
* Responsible Party:
Title & Organization:
Street address:
City, state, zip:
Phone number(s):
Email:
Signature:
County of
personally appeared before me this
Fresh Air Energy XXXVIII, LLC
101 Second Street Ste. 1250
San Francisco, CA 94105
415-626-1802
ErikS@ecoplexus.com
, a Notary Public for the State of
, do hearby certify that
day of
acknowledge the due execution of the Operations and Maintenance Agreement .
Witness my hand and official seal,
Date:
and
STO,RZ
Version 1.4
My commission expires
6/5/2020
Page 1 of 3
STORM-EZ 6/5/2020
Version 1.4 O&M Manual Page 2 of 3
User Defined BMP Maintenance Requirements
Section 1
Important operation and maintenance procedures:
The entire vegetated area within the Solar Power Plant will be carefully managed to reduce the sediment load
leaving the site.
After the first-time fertilization to establish the permanent ground cover on the vegetated areas of the Solar
Power Plant, Minimize use of Herbicides and Fertilizers per NCDEQ Stormwater Design Manual E-6
Avoid Compaction of Subsoil per NCDEQ Stormwater Design Manual E-6 Recommendation 1
Avoid Concentration of Stormwater per NCDEQ Stormwater Design Manual E-6 Recommendation 3
The system will be visually inspected by the owner/operator at leastquarterly. Records of operation and maintenance will be kept
in a known set location and will be available upon request.
Section 2
Inspection activities shall be performed as follows. Any problems that are found shall be repaired immediately.
BMP element:
Potential problem:
How to remediate the problem:
Entire Vegetated Area
Areas of bare soil/ Gullies
Regrade necessary to remove the gully, replant disturbed area.
Entire Vegetated Area
Vegetation
Maintain vegetation at a heaight of approximately 12 inches.
Receiving Water Body
Erosion or signs of damage
Contact the NC Division of Water Quality 401 Oversight Unit.
STORM-EZ 6/5/2020