HomeMy WebLinkAboutNC0003425_Exhibit 1 Email_20100310EXHIBIT 1
Zimmerman to Watts Email
re: Duke & Progress Energy Well Installation
March 10, 2010
From: Zimmerman, Jay <jay.zimmerman@ncdenr.gov>
Sent: Wednesday, March 10, 2010 9:16 AM
To: Watts, Debra <debra.watts@ncdenr.gov>
Cc: Bush, Ted <ted.bush@ncdenr.gov>; Smith, Eric <eric.g.smith@ncdenr.gov>
Subject: RE: Duke and Progress Energy - Well Installation Schedule
Debra,
The dates for Progress Energy don't seem aggressive enough considering some of the issues. The SWPS has some new
information suggesting heavy metals are leaching into the surface waters via groundwater at Roxboro plant at Hyco
Lake. They also have concerns that the ash pond at Cape Fear may be leaking. Danny Smith may bring this up during his
field visit with Chuck and Eric Smith. Have we or do we intend to negotiate a more aggressive schedule or do we agree
with what they propose? What role do the regions have (ours in this case)?
Thx
E-mail correspondence to and from this address may be subject to the North Carolina Public Records Law and may be disclosed to
third parties.
From: Watts, Debra
Sent: Tuesday, March 09, 2010 5:12 PM
To: Bush, Ted; Barnhardt, Art; Davidson, Landon; Knight, Sherri; May, David; Pitner, Andrew; Stehman, Charles;
Zimmerman, Jay
Cc: Smith, Eric; Wilcox, Betty; Watts, Debra
Subject: Duke and Progress Energy - Well Installation Schedule
Regional Supervisors:
APS had asked both Duke and Progress Energy to place wells at their compliance boundaries for their facilities with Ash
Ponds. Duke has submitted a fairly aggressive schedule (below in email from Allen Stowe). Progress Energy has
provided the chart below as to when they will have final proposed locations.
We are providing these dates to you to give you an idea when the utility companies may be contacting you. Please let
myself or Eric Smith know if you have questions. Debra
Progress Energy
Facilities
Date for Proposed
Locations
Target Sampling Date
Ashville
Finalized location with ARO
Weatherspoon
June 14, 2010
Fall 2010
Lee
July 19, 2010
Fall 2010
Mayo
September 13, 2010
Fall 2010
Roxboro
November 22, 2010
Spring 2011
Cape Fear
December 20, 2010
Spring 2011
From: Stowe, Allen [maiIto:Allen.Stowe@duke-energy.com]
Sent: Monday, March 08, 2010 2:04 PM
To: Watts, Debra
Cc: Sullivan, Ed M; Everett, George T; Nispel, Debbie
Subject: Duke Energy Ash Basin Monitoring - Well Installation Schedule
Debra,
I have listed our projected well installation schedule for the groundwater monitoring well systems around our ash basins.
As we discussed, we will need written confirmation from Aquifer Protection regarding well locations before initiating well
installation, which is reflected in the table below:
Order
Facility
Aquifer Protection
Approval Date
Well Installation Date
1
Riverbend Steam Station
April 1, 2010
August 31, 2010
2
Marshall Steam Station
Aril 1, 2010
August 31, 2010
3
Allen Steam Station
May 1, 2010
September 30, 2010
4
Cliffside Steam Station
May 1, 2010
September 30, 2010
5
Buck Steam Station
May 15, 2010
October 15, 2010
6
Belews Creek Steam
Station
June 1, 2010
October 31, 2010
7
Dan River Steam Station
June 1, 2010
October 31, 2010
If you need any additional information, please let me know. Thanks
Allen Stowe
EHS Water Management
Duke Energy Carolinas
AIIen.Stowe@duke-energy.com
704-382-4309 (Office)
704-516-5548 (Cell)