Aerial of SR2 from plans. Trees in red rectangle on left side of stream (facing downstream) are mostly
on the terrace outside of the work area and will not be removed during construction. See photo below.
The single row of trees in the yellow rectangle are primarily on one side of the creek. See other photo
below.
SR2 facing upstream. Trees on terrace will not be impacted. The sycamore on the right bank will be
protected during construction.
SR2 facing upstream in the upper incised reach. The plan in this portion of the reach is to raise the
existing bed elevation and provide additional bedform diversity. The contractor should be able to work
from the left bank in this section to preserve mature vegetation on the right bank.
Trees that are stressed or dead will be harvested for use in the project.