HomeMy WebLinkAbout710096_Plan of Action_20200521PLAN OF ACTION(Poa) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
Facility Number: 71-96 County: Pender
Facility Name: Stoneybrook
Certified Operator Name: Derek Brown
Operator Number: 19632
1. Current liquid level(s) in inches as measured from the current liquid level in the lagoon to the
lowest point on the top of the dam for lagoons without spillways; and from the current liquid level
in the lagoon to the bottom of the spillway for lagoons with spillways.
Lagoon 1 Lagoon 2 Lagoon 3 Lagoon 4 Lagoon 5
Lagoon Name/ID: 6179
Spillway(Y or N): N
Level(inches): 19
2. Check all applicable items
Liquid level is within the designed structural freeboard elevations of one or more structures.
Five and 30 day Plans of Action are attached. Hydraulic and agronomic balances are
within acceptable ranges.
X Liquid level is within the 25 year 24 hour storm elevations for one or more structures. A
30 day Plan of Action is attached. Agronomic balance is within acceptable range.
Waste is to be pumped and hauled to off site locations. Bolume and PAN content of waste
to be pumped and hauled is reflected in section III tables. Included within this plan is a list
of the proposed sites with related facility numbers, number of acres and receiving crop
information. Contact and secure approval from the DWQ prior to transfer of waste to a site
not covered in the facility's CAWMP.
Operation will be partially or fully depopulated.
*Attach a complete schedule with corresponding animal units and dates fro depopulation
*if animals are to be moved to another permitted facility, provide facility number, lagoon
freeboard levels and herd population for the receiving facility
3. Earliest possible date to begin land application of waste: as conditions permit
I hereby certify that I have reviewed the information listed above and included within the
attached Plan of Action, and to the best of my knowledge and ability, the information is
accurate and correct.
Mu phy Brown LLC
N,Jility wn ger (print
rg
Facility Owner/Manager (signature)
Phone: 910-293-3434
Date: 5121 /2020
II. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARD AND/OR 25 YR.124
HR, STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY
1. Structure ID: Stoneybrook line m = 1972.8 lb PAN
2. Structure ID: line m = lb PAN
3. Structure ID: line m = lb PAN
4. Structure ID: line m = lb PAN
5. Structure ID: line m = lb PAN
6. Structure ID: line m = lb PAN
n.lines 1+2+3+4+5+6= 1972.8lbPAN
III. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAY DRAW DOWN
PERIOD. DO
NOT LIST FIELDS
TO WHICH PAN
CANNOT BE APPLIED DURING
THIS 30
DAY PLKIM).
o. tract #
Stoneybrook
p. field #
L2
q. crop
Corn
r. acres
21.86
s. remaining IRR-
2 PAN balance
(lb/acre)
133.20
It. TOTAL PAN
BALANCE FOR
FIELD (tbs.)
column r x s
2911.8
u. application window'
Febl5-June
Stoneybrook
L3
Corn
13.51
120.00
1621.2
Feb15-June
'State current crop ending application date or next crop application oeglnning gate Tor avallaDle
receiving crops during 30 day draw down period.
v. Total PAN available for all fields (sum of column t) = 4533.0 lb. PAN
IV. FACILITY'S PoA OVERALL PAN BALANCE
w. Total PAN to be land applied (line n from section II) = 1972.8 Ib. PAN
PoA (30 Day) 2/21/00
x. Crop's remaining PAN balance (line v from section ill) = 4533.0 lb. PAN
y. Overall PAN balance (w - x) _ -2560 lb. PAN
Line y must show as a deficit. If line y does not show as a deficit, list course of action here including pump and
haul, depopulation, herd reduction, etc. For pump & haul and herd reduction options, recalculate new PAN based
on new information. If new fields are to be included as an option for lowering lagoon level, add these fields to the
PAN balance table and recalculate the overall PAN balance. If animal waste is to be hauled to another permitted
facility, provide information regarding the herd population and lagoon freeboard levels at the receiving facility.
Irrigation onto existing spray fields will continue as weather and field conditions permit. Additional land is availab
for pumping if needed.
PoA (30 Day) 2121100
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/identifier (ID): I Stone brook
2. Current liquid volume in 25 yr.124 hr. storm storage & structural freeboard
a. current liquid level according to marker 19.0
b. designed 25 yr.124 hr. storm & structural freeboard 19.8
c. line b - line a (inches in red zone) = 0.8
d. top of dike surface area according to design
(area at below structural freeboard elevation) 386750
e. line c112 x line d x 7.48 gallons/W 192859
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design 180
g. volume of waste produced according to structural design 422966
h. current herd # 4000 certified herd # 4000
actual waste produced = current herd # x line g
certified herd #
i. volume of wash water according to structural design
! excess rainfall over evaporation according to design
k. (lines h + i + j) x 7.48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
I. current waste analysis dated 1 5/18/2020
m. ((lines e + k)11000) x line I =
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
422966
01
225604
808551
1.97
1972.8
PoA (30 Day) 2/21100