LETTER OF APPROVAL WITH MODIFICATIONS
Par 5 Development Group, LLC
Joseph Bland, EVP
2075 Juniper Lake Road
West End, NC 27376
RE: Project Name: Hope Mills S. Mains St. Dollar General
Acres Approved: 2.5
Project ID: CUMBE-2020-144
County: Cumberland City: Hope Mills
Address: Main Street
River Basin: Cape Fear
Stream Classification. Other
Submitted by: Scott Brown
Date Received by LQS: April 27, 2020
Plan Type: Commercial
Dear Mr. Bland:
This office has reviewed the subject erosion and sedimentation control plan. We find the plan to be
acceptable and hereby issue this Letter of Approval. The enclosed Certificate of Approval must be
posted at the job site. This plan shall expire three (3) years following the date of approval, if no land
disturbing activity has been undertaken, as is required by Title 15A NCAC 413.0129.
As of April 1, 2019, all new construction activities are required to complete and submit an electronic Notice
of Intent CNOI) form requesting a Certificate of Coverage (COC) under the NCGO10000 Construction
Stormwater General Permit. This form MUST be submitted and COC issued prior to the commencement of
any land disturbing activity on the above -named project. The NOI form may be accessed at
deq.nc.goyZNCG01. the NOI form to Annette Lucas at Annette.lucasC-ncdenr.gov or Paul Clark at
Paul.clark ncdenr. ov. After you submit a complete and correct NOI Form, a COC will be emailed to you
within three business days. Initially, DEMLR will not charge a fee for coverage under the NCG01 permit.
However, a $100 fee will soon be charged annually. This fee is to be sent to the DEMLR Stormwater Central
Office staff in Raleigh.
DENorth Carolina Department of Environmental Quality I Division of Energy. Mineral and Land Resources
Fayetteville Regional Office 1226 Green Street, Suite 7141 Fayetteville, North carolina 28301
NCRrA eAROLI
oq-e.n w e,. ft /� 910.433.3300
Title 15A NCAC 413 .0118(a) and the NCGO1 permit require that the following documentation be Dept on file
at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCGO1 permit and the COC, once it is received.
3. Records of inspections made during the previous 12 months.
Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection to ensure
compliance with the approved plan, including the use of equipment and technology owned and operated by
the Department, (e.g., survey equipment, vehicles, unmanned aerial vehicles, etc.). Unless this office hears
otherwise .from you, this correspondence serves as your authorization for DEMLR to utilize equipment
and/or technology on your property for inspection purposes.
Title 15A NCAC 413 .0118(a) requires that a copy of the approved erosion control plan be on file at the job
site. Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection to
insure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance -oriented, requiring protection of
existing natural resources and adjoining properties. If, following the commencement of this project, it is
determined that the erosion and sedimentation control plan is inadequate to meet the requirements of the
Sedimentation Pollution Control Act of 1973 (North Carolina General Statute 113A-51 through 66), this office
may require revisions to the plan and implementation of the revisions to ensure compliance with the Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State water
quality laws, regulations, and rules. In addition, local city or county.ordinances or rules may also apply to this
land -disturbing activity. This approval does not supersede any other permit or approval.
Please note that this approval is based in part on the accuracy of the information provided in the Financial
Responsibility Form, which you provided. You are requested to file an amended form if there is any change
in the information included on the form. This permit allows for a land -disturbance, as called for on the
application plan, not to exceed the approved acres. Exceeding the acreage will be a violation of this permit
and would require a revised plan and additional application fee. In addition, it would be helpful if you notify
this office of the proposed starting date for this project. Please notify us if you plan to have a preconstruction
conference.
Your cooperation is appreciated.
Sincerely,
Chris Baker
Assistant Regional Engineer
DEMLR - Fayetteville Regional Office
Enclosures: Certificate of Approval
cc: Scott Brown, P. E., 4D Site Solutions, Inc. — electronic copy
Michael Naylor, Cumberland County Inspections Office -- electronic copy
Fayetteville Regional Office
CHECKLIST OF REQUIRED MODIFICATIONS
In order for this office to complete its review of the referenced project in accordance with
GS 1.13A-50 to 66 of the Sedimentation Pollution Control Act of 1973 and associated
administrative rules Title 15A, North Carolina Administrative Code (NCAC), Chapter 4,
please provide the additional or revised information in accordance with the following
comments:
1. Include a construction drawing, specifications and maintenance requirements for the
energy dissipater.
Ref: G.S. 113A-54.1 through G.S. 113A-57
Sections 15A NCAC 04A.0101 through 15A NCAC 04E.0504
General Permit NCG 010000 NPDES for Construction Activities