Loading...
HomeMy WebLinkAbout20191577 Ver 1_USACE More Info Requested_20200422Strickland, Bev From: Fuemmeler, Amanda J CIV (US) <Amanda.Jones@usace.army.mil> Sent: Wednesday, April 22, 2020 1:18 PM To: Clement Riddle Cc: Homewood, Sue; Moore, Andrew W Subject: [External] RE: Ranger - 2019-01867 Follow Up Flag: Flag for follow up Flag Status: Flagged External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to report.spam@nc.gov Thanks Clement. In response to #1 below, please submit a plan that addresses how any accidental frack out will be contained/cleaned up during the drilling. As an update, I just emailed the finalized MCA for signature to Renee with SHPO which they have 30 days to review/sign. I sent an email to Byron asking on the status of the BA/BO..never heard anything. And just curious on DWR's end if there were any comments received to their Public Notice/comment period and if those were going to be made available? Amanda 828-271-7980 ext. 4225 From: Clement Riddle <clement@cwenv.com> Sent: Thursday, March 26, 2020 5:06 PM To: Fuemmeler, Amanda J CIV (US) <Amanda.Jones@usace.army.mil> Cc: Sue Homewood (sue.homewood@ncdenr.gov) <sue.homewood@ncdenr.gov>; Moore, Andrew W <andrew.w.moore@ncdenr.gov> Subject: [Non-DoD Source] Ranger - 2019-01867 Amanda, Please see below and the attached for the requested additional information. Should you have any additional questions, please do not hesitate to contact me. Thank you, Clement From: Fuemmeler, Amanda J CIV (US) <Amanda.Jones@usace.army.mil> Sent: Monday, March 16, 2020 11:37 AM To: Clement Riddle <clement@cwenv.com>; Homewood, Sue <sue.homewood@ncdenr.gov> Cc: Jones, M Scott (Scott) CIV USARMY CESAW (USA) <Scott.Jones@usace.army.mil>; Lee Thomason 1 <Ithomason@biltmorefarms.com>; Hamstead, Byron <byron hamstead@fws.gov> Subject: RE: [Non-DoD Source] FW: Ranger update: USACE Action ID 2019-01867 - DWR Project NO.20191577 Clement, Thanks for the update and wanted to respond with some additional items based on my site visit, your response and previous meetings/discussions along with an update on some other coordination issues: 1. 1 concur with Sue's comment so please copy me as well: "Will you please provide a plan sheet that shows where the HDD drilling pads and drilling mud containment areas will be. The Division will likely request additional information regarding the construction details for the HDD activities but for now if we can just have an updated plan showing the location that will help". (ClearWater) Please see attached new Figure 5.1. 2. Regarding the 25-foot buffer/protective fencing on undisturbed wetlands/streams: Thanks for getting that going as it will be a condition of our permit. Can this be extended to the five archeological sites referenced in Renee's January 14, 2020 letter? (ClearWater) Yes, protective fencing around Cultural resource areas has already been installed at sites 82 and 85. Fencing will be added at the remaining three locations before work begins near those portions of the site. 3. Regarding the Substation and revised building pad boundaries, coordination with Renee/SHPO will need to happen to make sure nothing has changed with regards to effects to listed historic properties. I'm assuming not but please provide a separate email to me covering these changes in relation to surveyed archaeological sites and historic structures so I can coordinate accordingly with their office. The location for the HDD footprint needs to be included as well if it outside previous project boundaries. (ClearWater) A separate email was sent to you on March 17, 2020 regarding the status of additional review. The completed addendum was emailed to you on March 26, 2020. 4. The Draft River Safety Plan (provided in 01/06/20 email): Please verify if there are any missing outfitters. We discussed the company next to Carrier Park and another potential company off Riverside Drive in Woodfin that needs to be included. Please see the revised River Safety Plan. (ClearWater) We have added two additional outfitters to the River Safety Plan. We are not aware of anyone else at this time but are continuing to review and will update this as necessary. 5. Additional information on minimization at bridge location (i.e. three lane versus five lane bridge): Please quantify the difference in impacts for a 3 versus 5 lane bridge, clarification on what future uses may be supported by a five lane bridge, and if DOT is requiring the pedestrian/sidewalk portion. (ClearWater) The raised center median of the currently proposed bridge (wide enough for five lane) is located such that it aligns with the existing intersection of NC 191(Brevard Rd) and the Blue Ridge Parkway Access Road and does not require relocation of this intersection. Relocation of this intersection is not considered feasible for this project as doing so would have major constraints including National Park Service land, steep topography in the northwest quadrant and Bent Creek passing just south. Relocating this intersection would require realignment of the Blue Ridge Parkway Access Road which would also likely require extension or relocation of existing culverts over Bent Creek. If a narrower three -lane bridge were constructed initially, it is anticipated the raised median would be constructed in the same location as the current proposed median (in order to line up with the existing intersection as noted above). If an additional 12-foot lane was added in each direction for future bridge widening, it is expected that 12 feet would have to be added to each bridge face as opposed to adding 24 feet to one side due to the insufficient distance (approximately 150 feet) between NC 191 and the start of the bridge for traffic to shift 12 feet over. If the bridge was built in two phases, the total footprint of temporary causeway impacts for both phases combined (this includes both the 12 month and 3 month portions of the causeways) would exceed that of the current proposed five -lane bridge. This is primarily due to the temporary causeways being required to extend both up and downstream of the bridge footprint during the future expansion, whereas the causeways are only required to extend downstream of the current proposed bridge. (e.g. Current bridge temporary impacts allow for workpads to extend 25 feet downstream of the downstream bridge face as large cranes will sit on these pads to hang the steel girders. Impacts extend an additional 9 feet downstream to account for side slope down to river bottom. For the future expansion, cranes would not be able to reach over the original bridge to hang girders on the opposite sides, so workpads would be required to extend these same distances both up and downstream of each respective bridge face.) Estimated total temporary causeway impacts for a three -lane bridge and the future widening are 0.55 and 0.58 acres, respectively. This gives a total of 1.13 acres with 0.33 acres of this being overlap between the two phases leaving a total of 0.80 acres of temporary causeway footprint when not double counting the overlap. By comparison, total temporary causeway impacts for the current five -lane bridge are 0.67 acres If the bridge was built in two phases, total permanent stream impacts for both phases would be expected to roughly match the corresponding permanent impacts for the current proposed five -lane bridge. Estimated total permanent bank stabilization impacts for a three -lane bridge and the future widening are estimated at 88 LF (0.024 acres) and 26 LF (0.007 acres), respectively. This gives a total of 114 LF (0.031 acres) which matches the current five -lane bank stabilization impacts. A three -lane bridge would be expected to have four piers per bent with two bents giving a total of 0.004 acres. The expansion would likely add an additional pier to each end of each bent giving an additional 0.002 acres. This total nearly matches the estimated total permanent drilled pier stream impacts of 0.005 acres for the current five -lane bridge. The bridge and road will incorporate elements of multi -modal transportation and NCDOT Complete Streets design criteria to facilitate turning over maintenance of the bridge to NCDOT. If additional lanes are required in the future, the striping on the bridge could be changed to accommodate these lanes. The bridge is being proposed because as discussed above and in the PCN submittal there are financial and environmental benefits to undertaking construction of this bridge all at one time, even if additional lanes are not needed for years or decades. Update on Coordination/Status of Application: Section 106 NHP β€” see above request (#3) but have forwarded a draft copy of the MOA to our legal counsel for review/comment that proposes a data recovery plan to mitigate the adverse effects on the only eligible site (archeological site on west bank of River in bridge footprint). MOA will need to be finalized before can issue our permit. Section 7 ESAβ€” Currently waiting on finalized Biological Assessment and then Biological Opinion to be issued before can issue our permit. Section 401β€” Unfortunately the public hearing has been canceled but it appears written comments will be accepted until April 20t". Please note that we will likely not wait on the issuance of the 401 to issue the 404/10 permit as long as I have everything I need on my end. USFS-Bent Creek Experimental Station β€” we had a request from the archaeologist to review the application and survey/reports which I have forwarded but haven't received any comment back on yet. Let me know if you have any questions, thanks! Amanda 828-271-7980 ext. 4225 CLearWaLer 32 Clayton Street Asheville, NC 28801 Office: 828-698-9800 Mobile: 828-606-5168 clement(cDcwenv.com B1ockedWWW.CWENV.00M The information in this email is confidential and may be legally privileged. It is intended solely for the addressee(s). Disclosure to other parties is prohibited. If you are not the intended recipient, any disclosure, copying, distribution or any action taken or omitted to be taken in reliance on it, is prohibited and may be unlawful.