HomeMy WebLinkAboutEmail RE Additional Guidance - 24583 Morman, Alaina
From: Garcia, Lauren V
Sent: Wednesday, April 22, 2020 4:02 PM
To: kiddconstruction864@gmail.com
Cc: Morman, Alaina
Subject: RE: [External] RE: eNOl Review - Peartree West Phase II
Attachments: Letter of Approval.pdf
Greetings,
Unfortunately,we are not able to issue a COC for a construction project that is already complete.
As of April 1, 2019, all new construction activities are required to complete and submit an electronic Notice of Intent
form requesting a Certificate of Coverage under the NCG010000 Construction Stormwater General Permit.This form
must be submitted and a COC issued prior to the commencement of any land disturbing activity onsite.This notice
was provided to the attention of Harold J. Kidd, Managing Member in the E&SC Approval Letter, dated November 15,
2019.
In compliance with the provisions of North Carolina General Statute 143-215.1, other lawful standards and regulations
promogulated and adopted by the NC Environmental Management Commission and the Federal Water Pollution Control
Act, and the North Carolina Sedimentation Pollution Control Act(SPCA) of 1973, all owners or operators of stormwater
point source discharges associated with construction activities including, clearing,grading, or excavation activities
resulting in the disturbance of land greater than or equal to one acre, or that are part of a common plan of development
of that size that are also subject to the NC SPCA, are required to obtain a Certificate of Coverage under the NCG01 to
discharge stormwater to surface waters.
Failure to receive coverage under this permit may result in assessment of state or federal civil or criminal penalties for
each day of each violation.
For future projects, please be sure to obtain coverage under the NCG01 permit BEFORE any land disturbing activity
occurs onsite.
For more information, here is a link to our Construction Stormwater Webpage:
https://deg.nc.gov/about/divisions/energy-mineral-land-resources/energy-mineral-land-permits/stormwater-
permits/construction-sw.
Here is link to the NCG01 electronic application, also available on this webpage:
https://edocs.deg.nc.gov/Forms/NCGOI-N01.
To view the NCG01 Permit:
https://files.nc.gov/ncdeg/Energy/20Mineral%20and%20Land%20Resources/Stormwater/NCG010000 Final Permit 20
19 04 01.pdf.
Let me know if you have any questions,
Lauren
From: kiddconstruction864@gmail.com <kiddconstruction864@gmail.com>
Sent:Tuesday,April 21, 2020 4:36 PM
To: Garcia, Lauren V<lauren.garcia@ncdenr.gov>
1
Cc: Morman,Alaina <alaina.morman@ncdenr.gov>
Subject: [External] RE: eNOI Review- Peartree West Phase II
External email. Do not click links or open attachments unless you verify.Send all suspicious email as an attachment to
report.spam@nc.gov
Hello,
Lots 24, 49 and 122 are sold and being lived in. The other lots are 100% complete but have not closet yet. When
Melissa went out to do an inspection, she knew that the lots were complete but said we were required to get coverage
due to when the original properties were disturbed.
Thankyou!
5�"i
Shari M.Groover
REALTOR@, Builder's Representative
Remax Choice
f
f
0 [facebook.coml [twitter.coml [insta ram.coml O [youtube.coml G [realtor.coml [zillow.coml
[linkedin.coml
Kidd Construction Company Inc.
AA All American Airborne Self Storage, LLC
Cross Creek Pawn and Jewelry, LLC
6885 Cliffdale Road
Fayetteville, NC 28314
910-864-9727
910-868-6796 Fax
www.teamgrooverhomes.com [sharigroover.coml
From: Garcia, Lauren V<lauren.garcia@ncdenr.gov>
Sent:Tuesday,April 21, 2020 2:04 PM
To: kiddconstruction864@gmail.com
Cc: Morman,Alaina <alaina.morman@ncdenr.gov>
Subject: eNOI Review- Peartree West Phase II
Greetings Harold,
I am reviewing the electronic application for Peartree West Phase II, NOI No. 24583, and needed to ask some
clarifying questions. Is the land disturbing activity for lots 24, 29, 48, 49, 50, 51, 52, and 122 complete? I saw
the note that home construction has been completed and some sold. If this is the case, it is possible you are
not required to obtain coverage a this time. Can you please elaborate on the status of this project?
2
Thanks,
Lauren
3