HomeMy WebLinkAboutNCC201546_ESC Approval Submitted_20200420ROY COOPER
Ga o rwr
MICHAEL S. REGAN
Scs resary
BRIAN WRENN
rkcting Drrcc rcr
Little River Investments, Inc.
ATTN: Renee P. Baker, President
PO Box 1128
Zebulon, NC 27S97
NORTH CARD INA
Environmental Quafity
April 2, 2020
LETTER OF APPROVAL
RE: Project Name: Harrison Village Phase 3C
Project ID: FRANK-2020-022
Approved Acres: 2.23
County: FRANKLIN, City: Harris Address: Harrison Street
River Basin: Neuse Stream Classification: Other
Submitted By: Sanderson Engineering, Inc.
Date Received by LQS: March 31, 2020
Plan Type: Revised
Dear Ms. Baker:
The subject erosion and sedimentation control plan has been approved. The enclosed Certificate of
Approval must be posted at the job site. This plan approval sliall expire three (3) years following the date
of approval, if no land -disturbing activity has been undertaken, as is required by Title 15A NCAC 413.0129.
As of April 1, 2019, all new construction activities are required to complete and submit an electronic Notice
of Intent (eNOI) form requesting a Certificate of Coverage (COC) under the NCG010000 Construction
General Permit. After (lie form is reviewed and found to be complete, you will receive a link with payment
instructions for the $100 annual permit fee. After the fee is received, you will receive the COC via
email. You MUST obtain the COC prior to commencement of any land disturbing activity. The eNOI
form may be accessed at deq.nc.g!2vJNCG01. Please direct questions about (lie eNOI form to Annette
Lucas at Annette.Lucas a ncderingov or Paul Clark at Paul.Clark a ncdenn *ov. If the owner!operator of
this project changes in the future, the new responsible party is required to apply for his/her own COC.
Title 15A NCAC 413 .0118(a) and the NCGO l permit require that the following documentation be kept on
file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCGO1 permit and the COC, once it is received.
3. Records of inspections made during the previous 12 months.
� xEro:-nen`al quality Nnrth Carolina Ccparra�Uivisinn raf Lricrgy. \Iinrra) and land lic5nurcc5
Raleiyhltojiono101tlr.r hiMhh.ESrftiicCcrucr - '1800 Barreif Uriw Ra;cIglt North C.iri)Gna2st,UN
c)III Tcyl.4200
Letter of Approval
Little River Investments, Inc.
April 2, 2020
Page 2 of 2
Also, this letter gives the notice required by G.S. I I3A-61.1(a) of our right of periodic inspection to insure
compliance with the approved plan.
Title 15A NCAC 4B .0118(a) requires that a copy of the approved erosion control plan be on file at the jab
site. Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection to
insure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance -oriented, requiring protection of
existing natural resources and adjoining properties. If, following the commencement of this project, it is
determined that the erosion and sedimentation control plan is inadequate to meet the requirements of the
Sedimentation Pollution Control Act of 1973 (North Carolina General Statute 113A-5I through 66), this
office may require revisions to the plan and implementation of the revisions to ensure compliance with the
Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State water
quality laws, regulations, and rules. In addition, local city or county ordinances or rules may also apply to
this land -disturbing activity. This approval does not supersede any other permit or approval.
Please note that this approval is based in part on the accuracy of the information provided in the Financial
Responsibility Form, which you provided. You are requested to file an amended form if there is any change
in the information included on the form. This permit allows for a land -disturbance, as called for on the
application plan, not to exceed the approved acres. Exceeding the acreage will be a violation of this permit
and would require a revised plan and additional application fee. In addition, it would be helpful if you notify
this office of the proposed starting date for this project. Please notify us if you plan to have a preconstruction
conference.
Your cooperation is appreciated.
Sincerely,
Sally Castle, El
Regional Engineering Associate
Land Quality Section
Enclosures: Certificate of Approval
NPDES NCGOI Fact Sheet
cc: Steven S. Sanderson, PE (sandersonsengineering@yahoo.com)—Electronic Copy
Regional Office File