DEPARTMENT OF PUBLIC UTILITIES
Post Office Box 2263
SMITHFIELD, NC 27577
(919) 989-5075
April 7, 2020
LETTER OF APPROVAL
Mr. James Gilbert
James M. Gilbert, Inc.
PO Box 236
Clayton, NC 27528
RE: Project Name: Langdon Farm Subdivision Phase 2
Project ID: JC# 20-018-P
Disturbed Acres Approved: 13 acres
Stream Classification: Sassarixa Creek (C, NSW)
Submitted By: Dalton Engineering
To Whom It May Concern:
Johnston County has reviewed the subject erosion and sedimentation control plan for the above
referenced site. We find the plan to be acceptable and hereby issue this Letter of Approval. The
attached Certificate of Approval must be posted at the job site. This plan sball expire three (3) years
following the date of approval, if no land disturbing activity has been undertaken, as is required by Title
15A NCAC 4B .0129.
As of April 1, 2019, all new construction activities are required to complete and submit an electronic
Notice of Intent (NOI) form requesting a Certificate of Coverage (COC) under the NCG010000
Construction Stormwater General Permit. This form MUST be submitted prior to the commencement
of any land disturbing activity on the above named project.'The NOI form may be accessed at
deq.nc.gov/NCGO 1. Please direct questions about the NOI form to Annette Lucas at
Annette.lucas@ncdenr.gov or Paul Clark at Paul.clark@ncdenr.gov. After you submit a complete and
correct NOT Form, a COC will be emailed to you within three business days. Initially, DEMLR will
not charge a fee for coverage under the NCGOI permit. However, on or after May 1, 2019, a $100 fee
will be charged annually. This fee is to be sent to the DEMLR Stormwater Central Office staff in
Raleigh.
Title 15A NCAC 4B .0118(a) and the NCG01 permit require that the following documentation be kept
on file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCGOI permit and the COC, once it is received.
3. Records of inspections made during the previous 30 days.
Letter of Approval
Langdon Farms Phase 2
Project No.: 20-018-P
April 7, 2020
Also, this letter gives the notice required by G.S. 113A-61. l(a) of our right of periodic inspection to
ensure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance -oriented, requiring protection of
existing natural resources and adjoining properties. If, following the commencement of this project, the
erosion and sedimentation control plan is inadequate to meet the requirements of the Sedimentation
Pollution Control Act of 1973 (North Carolina General Statute 113A-51 through 66), this office may
require revisions to the plan and implementation of the revisions to insure compliance with the Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State water
quality laws, regulations, and rules. In addition, local city or county ordinances or rules may also apply
to this land -disturbing activity. This approval does not supersede any other permit or approval.
Please note that this approval is based in part on the accuracy of the information provided in the
Financial Responsibility Form, which you provided. You are requested to file an amended form if there
is any change in the information included on the form. In addition, it would be helpful if you notify this
office of the proposed starting date for this project.
Please schedule a pre -construction meeting with this office before beginning construction
Your cooperation is appreciated.
Sincerely,
Beth McLaughlin
McLaughlin Consulting
Contractor for Johnston County Public Utilities