HomeMy WebLinkAboutNCC200801_ESC Approval Submitted_20200417Iredell County Planning & Development Erosion Control Section 349 North Center Street P.O. Box 788 Statesville, NC 28687 Date: December 17, 2019 LETTER OF APPROVAL WITH MODIFICATIONS Chris Younger South Iredell Community Development Corp. 500 S. Main St., Ste 449 Mooresville, NC 28115 RE: Project Name: Mooresville Business Park East Acres Approved with Modifications: 6.17 Project ID: MVLLE-2020-043 Project Location: PIN 4678383635.000 Submitted By: Stewart, Inc. Date Received: December 9, 2019 Plan Type: New Dear Mr. Younger: This office has reviewed the subject erosion and sedimentation control plan. We find the plan to be acceptable with modifications and herby issue this Letter of Approval with Modifications. Modifications must be received in this office no later than two weeks prior to the project start date. Failure to submit modified plans can result in a violation and fine under the Iredell County Land Development Code. The Modifications required for Approval are listed on the attached page. The Certificate of Approval issued by Iredell County must be posted at the job site. This plan approval shall expire three (3) years following the date of this approval as is required by Title 15A NCAC 413.0129 and Section 9.6.6 of the Iredell County Land Development Code. Title 15A NCAC 4B 0118(a) and Section 9.6.9 of the Iredell County Land Development Code requires that a copy of the approved erosion control plan be on file at the job site. Any amendments and/or revisions to the approved plan must be reviewed and approved prior to implementation in order for the site to remain in compliance. Failure to submit plans for approval may result in administrative actions and/or penalties as indicated in the Iredell County Land Development Code. Also, this letter gives notice as required by G.S. 113A-61.1(a) and Section 14.2.2 of the Iredell County Land Development Code, of our right of periodic inspection to insure compliance with the approved plan. Iredell County's Sedimentation Pollution Control Program is performance -oriented, requiring protection of existing natural resources and adjoining properties. If, following the commencement of this project, it is determined that the erosion and sedimentation control plan is Letter of Approval with Modifications Mooresville Business Park East December 17, 2019 Page 2 of 3 inadequate to meet the requirements of the Iredell County Land Development Code and the Sedimentation Pollution Control Act of 1973, (North Carolina General Statute 113A-51 through 66), this office may require revisions to the plan and implementation of the revisions to insure compliance with the Act and Code. Acceptance and approval of this plan is conditioned upon your compliance with Federal, State, and County water quality laws, regulations, and rules. This approval does not supersede any other permit or approval. As of May 1, 2019, all new construction activities are required to complete and submit an electronic Notice of Intent (NOI) form requesting a Certificate of Coverage (COC) under the NCGO10000 Construction Stormwater General Permit. This form MUST be submitted prior to the commencement of any land disturbing activity on the above named project. The NOI form may be accessed at deq.nc.gov/NCGOI I. Please direct questions about the NOI form to Annette Lucas at Annette.lucas@ncdenr.gov or Paul Clark at Paul.clark@ncdenr.gov. After you submit a complete and correct NOI Forn, a COC will be emailed to you within three business days. Initially, DEMLR will not charge a fee for coverage under the NCGOI permit. However, on or after May 1, 2019, a $100 fee will be charged annually. This fee is to be sent to the DEMLR Stormwater Central Office staff in Raleigh. Please note that this approval is based in part on the accuracy of the information provided in the Financial Responsibility Form, which you provided. You are requested to file an amended form if there is any change in the information included on the form. In addition, it is required that this office to be notified of the proposed starting date for this project. Please notify us when you plan to have a preconstruction conference. Your cooperation is appreciated. Sincerely, Randall Moore, CESSWI, CFM Erosion Control Inspector II Enclosures: Modifications Fact Sheet on the New NCGOI Permit Permit Letter of Approval with Modifications Mooresville Business Park East December 17, 2019 Page 3 of 3 MODIFICATIONS REQUIRED FOR APPROVAL Project Name: Mooresville Business Park East Project ID: MVLLE-2020-043 County: Iredell Reviewed by: Randall Moore Required changes are designated as "RC" under legal authority from NC General Statutes Chapter 113A Article 4 and the Iredell County Land Development Code. Suggested changes are designated as "SC" for improvement of the plan. 1. Prefer straw wattles for check dams. Provide detail. —RC 2. Silt fence should be across all downslope sides of disturbance and below basins. —RC 3. Basin #4 needs diversion to direct runoff into it. —RC 4. Basin #1 needs diversions to direct runoff into it. —RC 5. Basin #3 needs diversions to direct runoff into it. —RC 6. Use slope drains for diversions entering basins. —SC 7. Area between Basin 3 and Basins 1 & 2 should still be protected with silt fence and silt fence stone outlet until pipe is installed. —RC 8. Show sediment stockpiles on plan. At least 50 feet from any diversion or basin, with silt fence wrapped around downslope side of stockpile. —RC 9. Iredell County requires self -inspection for erosion control within 24 hours of any 1 inch and greater rainfall event. —RC 10. Silt fence to be 10 feet off toe of slopes. —RC 11. Slopes greater than 10 feet in height need more protection than silt fence. Use double row of silt fence with wire backing and silt fence stone outlets staggered. —RC 12. Basin 1 skimmer and orifice should be designed to dewater the required volume of 1,062 cubic feet in as close to 3 days' time as possible. —RC 13. Basin 2 skimmer and orifice should be designed to dewater the required volume of 1,710 cubic feet in as close to 3 days' time as possible. —RC 14. Basin 2 skimmer and orifice is listed as different sizes in the calculations book and on the basin detail sheet in plans. Fix this. —RC 15. Basin 3 skimmer and orifice should be designed to dewater the required volume of 1,728 cubic feet in as close to 3 days' time as possible. —RC 16. Basin 3 skimmer and orifice is listed as different sizes in the calculations book and on the basin detail sheet in plans. Fix this. —RC 17. Basin 4 skimmer and orifice should be designed to dewater the required volume of 2,196 cubic feet in as close to 3 days' time as possible. —RC Fact Sheet on the New NCGO1 Vla- ��cA� -� April 2019 0-•,, TM=D•E��� p The NC Construction General Permit (also known as "NCGO1") was renewed on April 1, 2019. The updated permit does not significantly change the measures that are required to be implemented on construction sites. However, there are some organizational and technical updates to the permit as described below. Most notably, there is a new process in which construction sites will obtain official coverage under an NCGO1 permit through an electronic process. DEMLR worked with a broad team of stakeholders to make all of these updates. If you have questions, contact Annette Lucas at Annette.lucas@ncdenr.gov or (919) 707-3639. Organizational Updates The new permit: o Repeats state requirements for E&SC Plans and organizes them with federal construction activity requirements; o Is clearly organized by topic; and a Has less text and more tables. Technical Updates The new permit: o Requires that the E&SC Plan meet SWPPP requirements (p. 2); © Provides a list of items that must be included in the SWPPP, such as the construction sequence, plans, calculations, etc. (p. 2-4);' m Has updated language on bypasses and upsets that is tailored to construction activities (p. 10); o Puts all timeframes for inspections, record -keeping and reporting in "calendar days" for clarity and consistency (p. 11-14);' m Changes the inspection frequency (during business hours) to at least once per 7 calendar days and after every storm > 1.0 inch (previously 0.5 inch);' and o Excludes weekends, state and federal holidays from normal business hours unless construction activities take place (p. 23). ' This list is based on website guidance by the DEMLR Sediment Program. ' The number of calendar days was selected to be as equivalent as possible with the previous permit. 3 The intent is to provide predictability to the inspection schedule. Acronyms to Know COC: Certificate of Coverage, proof of coverage under an NCGO1 permit DEMLR: NC Division of Energy, Mineral, and Land Resources E&SC: Erosion & Sedimentation Control e-NOI: Notice of Intent, application form for the NCGO1 permit e-NOT: Notice of Termination, form for closing out the NCGO1 permit SWPPP: Stormwater Pollution Prevention Plan, required by the NCGO1 The NCG01 Process The new NCGO1 applies to permits approved on or after April 1, 2019. Permittees will no longer receive a copy of the NCG01 permit in the mail with their E&SC Plan approvals and be considered as covered under the permit. Federal rules require that DEMLR receive an NO[ on each construction project and issue each construction project its own COC. Under the new NCGO1 process, construction sites will continue to receive approval for E&SC Plans from either DEMLP, or the delegated local E&SC program just like before. After receiving E&SC Plan approval, permittees will officially obtain coverage under the NCG01 by completing an e-NOI (available at deq.nc.gov/NCG01). The e-NOI will only take about 20 minutes to fill out and submit on-line. Initially, there will be no charge associated with applying for an NCGO1 permit but on or around June 1, 2019, DEMLR will begin charging a $100 annual general permit fee as required per §143-215.3D. DEMLR is working on creating a single application form that will allow an applicant to simultaneously apply for an E&SC permit and an NCGO1 COC. That effort is part of a larger Permit Transformation project at DEMLR. IREDELL COUNTY POBox 788 IREDELL 3490Orth Center St. Statesville, NC 28677 Permit Type: EROSION CONTROL - PLAN REVIEW APPLICATION NUMBER 303248 Issue Date: Parcel Number Street Address Jurisdiction Owner Information Applicant Information Contractor Information Name: SOUTH IREDELL Name: SOUTH IREDELL Name: SOUTH IREDELL COMMUNITY DEV CORP COMMUNITY COMMUNITY DEVELOPMENT CORP DEVELOPMENT CORP Address: Address: 500 S Main St., Ste. 449 Address: 500 S Main St., Ste. 449 Mooresville, NC 28115 Mooresville, NC 28115 Phone: Phone: (704)880-1085 Phone: (704)880-1085 Project Description Mooresville Business Park East E{}Plan Permit Details Fees PLAN REVIEW Amount: $1,225.00 I hereby certify that all information in this application is correct and all work will comply with the state code and all other applicable state and local laws, ordinances and regulations. The respective department will banotified ofany changes in the approved plans, a change of contractor, and/or specifications for the projectparmidadherein. This application becomes opermit only when validated and approved. Date: 12/17/2019 Signature of This permit shall expire three (3)years following the date mfapproval /fnm activity has been IREDELL COUNTY -NC Cash Register Receipt Iredell County Date Paid: Monday, December 09, 2019 Paid By: SOUTH IREDELL COMMUNITY DEV CORP Cashier: CCS Pay Method: CHECK 1022 Receipt Number R3562 Printed: Monday, December 9, 2019 11:16 AM 1 of 1 SUPERIOP,