From: Goss, Stephanie
Sent: Wednesday, April 1, 2020 4:13 PM
To: Hopper, Christopher D CIV (USA); brownenvgrp@gmail.com
Subject: High Gate 3 Crossing / DWR Project # 20200285 / Johnston County
Wyatt,
On February 21, 2020, the Division of Water Resources (Division) received your application requesting a 401 Certification
and Buffer Authorization from the Division for your project. The Division has determined that your application is
incomplete and cannot be processed. The application is on -hold until the following information is received. Please
complete the following items in the application:
• Please provide the Division a copy of your response from the U.S. Army Corps of Engineers requesting additional
information. [15A NCAC 02H .0502(c)] [15A NCAC 02H .0502(c)
• The Corps of Engineers must also verify the Nationwide Permit that is to be used to authorize this project. [15A
NCAC 02H .0502(a)(7)]
Pursuant to Title 15A NCAC 02B .0233 (8), the applicant shall furnish all of the above requested information for the
proper consideration of the application. If all of the requested information is not received in writing within 30 calendar
days of receipt of this letter, the Division will be unable to approve the application and it will be returned.
Thanks in advance!
Stephanie Z. Goss
Environmental Specialist II
Division of Water Resources
Raleigh Regional Office
3800 Barrett Drive
Raleigh, NC 276og
919-791-4256
E-mail correspondence to and from this address may be subject to the
North Carolina Public Records Law and may be disclosed to third parties
From: Hopper, Christopher D CIV (USA) <Christopher.D.Hopper@usace.army.mil>
Sent: Tuesday, March 24, 2020 4:08 AM
To: brownenvgrp@gmail.com
Cc: Goss, Stephanie <stephanie.goss@ncdenr.gov>
Subject: [External] SAW-2020-00395 / High Gate 3 Crossing / 1294 Shotwell Road / Town of Clayton / Johnston County -
INCOMPLETE NOTIFICATION
External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
liort.spam@nc.gov
Hello Wyatt:
I hope this email finds you well. I'm writing to formalize our conversation last week. Per our discussion, the Pre -
construction Notification (PCN) for the proposed High Gate 3 project (SAW-2020-00395), dated February, 212019 is
incomplete. Please don't hesitate to call if there are any questions.
1) I'm unable to process the application without information about the site prior to development of the first two
phases. Portions of wetlands had been located in the past associated with proposed crossings, and a soil stream
is shown extending onto the property. Please work with the project owner to share any surveys and/or
approvals received for this site prior to development.
2) We also cannot permit a road crossing that isn't associated with, or needed to construct, the project.
Once we receive this information, we'll resume our review of this project. Please provide the requested information
within 30 days, or your application will be withdrawn. Feel free to contact me with any questions or concerns.
Christopher D. Hopper
Regulatory Specialist
U.S. Army Corps of Engineers
Regulatory Division
3331 Heritage Trade Drive, Suite 105
Wake Forest, NC 27587
(919) 554-4884, Ext. 35
We would appreciate your feedback on how we are performing our duties. Our automated Customer Service Survey is
located at: http://corpsmapu.usace.army.mil/cm apex/f?p=136:4:0 fcorpsmapu.usace.army.mill. Thank you for taking
the time to visit this site and complete the survey.