HomeMy WebLinkAbout20200347 Ver 1_RE_ B-5825 over Yadkin R stormwater question_20200330Wanucha, Dave
From: Barrett, William A
Sent: Wednesday, March 25, 2020 4:27 PM
To: Wanucha, Dave
Cc: Beckwith, Loretta A CIV USARMY CESAW (USA); Turchy, Michael A
Subject: RE: B-5825 over Yadkin R stormwater question
Dave,
Below is the response to your question that I received from the Hydraulic Engineer for the project:
"All proposed vertical deck drains (through the deck) on the proposed bridge will be at least 10 feet away from the top
of banks. As per NCDOT's 2016 Drainage Guidelines, there are no proposed deck drains located directly over the river.
Since the height of the deck drains over the floodplain is approximately 25 feet, the natural air movement will disperse
the water enough for it to be considered diffused flow when it reaches the ground surface below."
Thanks,
Bill
From: Barrett, William A
Sent: Wednesday, March 25, 2020 12:59 PM
To: Wanucha, Dave <dave.wanucha@ncdenr.gov>
Cc: Beckwith, Loretta A CIV USARMY CESAW (USA) <Loretta.A.Beckwith@usace.army.mil>; Turchy, Michael A
<matu rchy@ ncdot.gov>
Subject: RE: B-5825 over Yadkin R stormwater question
Hey Dave,
I'm working on getting some additional information to provide.
Thanks
Bill
From: Wanucha, Dave <dave: anL.acha( _n_cd_�nr,ggvv>
Sent: Wednesday, March 25, 2020 9:55 AM
To: Barrett, William A < a_ arrett.(�_ncdaat.egov_>
Cc: Beckwith, Loretta A CIV USARMY CESAW (USA) <Loretta.A.Beck Beckwith I> _
Subject: B-5825 over Yadkin R stormwater question
Hey Bill,
How will DOT treat stormwater from the new bridge? I cannot determine from the plans and the Stormwater
Management Plan (SWP) only states that it will be minimized. Please provide more detail. Thanks.
Division of Water Resources
4U18'Buffer Transportation Permitting
NCDepartment ofEnvirionmenta|Quality
336'776'9703office
336'403'5655mobi|e
NC DE{lWinston Salem Regional Office
45UWest Hanes Mill Road, Suite 3UU
Winston Salem, NCZ71U6