September 19, 2018
Wire -Bond
Attn: Eddie Brown, Plant Manager
400 Rountree Road
Charlotte, NC 28224
2145 Suttle Avenue
Charlotte, NC 28208-5237
Subject: Industrial Facility Inspection
Wire -Bond — 400 Rountree Road, Charlotte
Dear Mr. Brown:
On August 24, 2018, Ron Eubanks of Charlotte -Mecklenburg Storm Water
Services (CMSWS) conducted an inspection of the above referenced facility as a
requirement of the City of Charlotte's NPDES Permit, NCS000240, Part II Section H.
Inspection authority is granted by Charlotte City Code Chapter 18, Article III, Section
18-82. At the time of inspection, the facility was observed to be in compliance with the
City of Charlotte Storm Water Pollution Control Ordinance. There were some storm
water pollution concerns noted and the following recommendations are provided:
1) Charlotte Storm Water Pollution Control Ordinance Review
• Stormwater System — Stormwater runoff drains by sheet flow and discharges from
the property via eight (8) outfalls. Inlet and outlet protection (i.e., Filtrexx filters
and straw bales) were observed at several stormwater catch basins and outfalls on
the property. Facility staff indicated that lot sweeping activities are conducted
twice a week to remove sediment accumulation. It is recommended that Wire -
Bond continue using inlet/outlet protection and lot sweeping activities to address
stormwater pollution on the property.
Erosion Issues — There was minor erosion observed near the fence line on the
western property boundary. It is recommended that the eroded area on the
property be stabilized with ground cover and/or rip rap to control stormwater
erosion.
Structural Stormwater BMPs — Filtrexx filter best management practices (BMPs)
are being used at each of the outfalls on the property to address elevated metals in
stormwater runoff from the property. It is recommended that the Filtrexx filters
be routinely inspected and replaced as needed.
Waste Storage/Disposal Areas — There are two (2) municipal waste dumpsters and
five (5) scrap metal containers located on the property. The municipal waste
dumpsters were covered and appeared to be in good condition; however, some of
the scrap metal containers were uncovered. It is recommended that the scrap
metal containers be covered to prevent stormwater accumulation and reduce
metals in stormwater runoff.
•
ObTo report pollution or drainage problems, call: 311
http://stormwater.charmeck.org
CHARLOTTE. .o
Eddie Brown, Plant Manager
September 19, 2018
Page 2
The inspection was also conducted as part of a cooperative working agreement between
Mecklenburg County and the North Carolina Department of Environmental Quality
(NCDEQ) — Division of Energy, Mineral and Land Resources (DEMLR). NCDEQ —
DEMLR has been copied on this report and made aware of the following observations
regarding the facility's NPDES stormwater permit:
2) Stormwater Pollution Prevention Plan (SPPP)
A Stormwater Pollution Prevention Plan (SPPP) has been developed and recorded for
Wire -Bond.
3) Qualitative Monitoring
Qualitative monitoring has been conducted and recorded for Wire -Bond.
4) Analytical Monitoring
Analytical monitoring has been conducted and recorded monthly for Wire -Bond per the
tiered response requirement of their NPDES Stormwater Permit.
5) Permit and Outfalls
Filtrexx filters and straw bales were observed at each of the outfalls on the property. It is
recommended that the filters and straw bales be inspected and replaced as needed.
Items under Sections 2 — 5 of this cover letter are specifically related to
requirements in your State -issued NPDES Stormwater Certificate of Coverage
NCG030629, and as such, you may receive a separate letter from NCDEQ asking you to
follow-up and address those particular items.
Thank you for your assistance and cooperation with the site inspection. The
attached report provides details about inspection observations and should be self-
explanatory. Please contact me at (980) 721-4191, if you have any questions or need
additional information concerning the report. For questions specifically regarding your
NPDES stormwater permit, please contact James Moore with NCDEQ — DEMLR at
(704) 663-1699.
Sincerely,
C�
P. Ronald Eubanks
Senior Environmental Specialist
Charlotte -Mecklenburg Storm Water Services
cc: Kristen O'Reilly, Charlotte -Mecklenburg Storm Water Services
James Moore, NCDEQ — DEMLR
Chadoffe-uKklert m 2 14 5 S u t t l e Avenue
STORMCharlotte, NC 28208
ER Facility Inspection
—� Services
Facility Name: Wire -Bond Inspection # : 39236
Contact: Eddie Brown, Plant Manager Permit #: NCG030629
Inspector: Ron Eubanks Receiving Stream: Kings Branch
Inspection Date: 08/24/2018 Entry Time: 8:30 am Exit Time: 10:15 am SIC #: 3496
Facility Description: Wire -Bond is located on approximately 7.45 acres of property at 400 Rountree Road in Charlotte.
The facility manufactures metal wire concrete wall reinforcement products. Zinc plating and hot dipped galvanizing
activities are conducted at the site.
File Review/History: Charlotte -Mecklenburg Storm Water Services (CMSWS) has conducted previous inspections at
Wire -Bond on February 29, 2012, August 24, 2015, August 17, 2017, and March 2, 2018. The report from the February
29, 2012 inspection was issued as a Notice of Violation under the City of Charlotte Storm Water Pollution Control
Ordinance.
Inspection Summary: The Wire -Bond facility was observed to be in compliance with the City of Charlotte Storm Water
Pollution Control Ordinance during the recent inspection. Please refer to the report for comments and recommendations
from the inspection.
jors
Site Inspection Deficiency Comments
Stormwater system (catch basins,
Recommendation
Stormwater runoff drains by sheet flow and discharges from
inlets, outfalls, etc.)
the property via eight (8) outfalls. Inlet and outlet protection
(i.e., Filtrexx Filters) were observed at several stormwater
catch basins and outfalls on the property. Facility staff
indicated that lot sweeping activities are conducted twice a
week to remove sediment accumulation. It is recommended
that Wire -Bond continue using inlet/outlet protection and lot
sweeping activities to address stormwater pollution on the
property.
Erosion issues
Recommendation
There was minor erosion observed near the fence line on the
western property boundary. It is recommended that the
eroded area on the property be stabilized with ground cover
and/or rip rap to control stormwater erosion.
Structural stormwater BMPs
Recommendation
Filtrexx filter stormwater best management practices are
being used at each of the outfalls on the property to address
elevated metals in stormwater runoff from the property. It is
recommended that the Filtrexx filter BMPs
be rountinely inspected and replaced as needed.
Illicit discharges/connections
No
There were no illicit discharges or connections observed on
the property during the inspection. Facility staff indicated
that the wash water from pressure washing activities on the
property is collected and properly disposed by a waste
disposal contractor.
Aboveground storage tank(s) - list
No
There is a 275-gallon used oil aboveground storage tank
tank sizes & contents
(AST) located in a covered area within secondary
containment.
•
Ob To report pollution or drainage problems call: 311
CHARLOTTE_ http://stormwater.charmeck.org
9/19/2018 1:52:04PM
0
Page 1 of 3
Site Inspection Deficiency Comments
Underground storage tank(s) - fill port
N/A
area; list tank sizes & contents
Outdoor material storage area(s)
No
Raw materials and finished product are stored outdoors on
the property. There are several 55-gallon drums of zinc and
vermiculite waste stored outdoors underneath a structural
canopy. The canopy was recently installed on the property
to provide additional outdoor storage.
Outdoor processing area(s)
N/A
Loading/unloading area(s)
No
There were no significant stormwater pollution issues
observed in the loading/unloading areas on the property.
Vehicle/equipment area(s) - fueling,
N/A
No fleet vehicle fueling or washing activities are conducted on
washing, storage, etc.
site.
Oil/water separator and/or
No
Wire -Bond pretreats process water from the plating lines
pretreatment
before discharging into the Charlotte Water sanitary sewer
system (Permit #3017). There is also an oil/water separator
located on the property. The oil/water separator should
continue to be routinely checked and cleaned to ensure it
functions properly.
Waste storage/disposal area -
Recommendation
There are two (2) municipal waste dumpsters and five (5)
dumpsters, scrap metal bins, etc.
scrap metal containers located on the property. The
municipal waste dumpsters were covered and appeared to be
in good condition; however, some of the scrap metal
containers were uncovered. It is recommended that the
scrap metal containers be covered to prevent stormwater
accumulation and reduce metals in stormwater runoff.
Food service area(s)
N/A
Indoor material storage area(s)
No
No stormwater pollution issues were observed in the indoor
material storage areas.
Indoor processing area(s)
No
No stormwater pollution issues were observed in the indoor
processing areas.
Floor drains
No
The pavement adjacent to the loading area was recently
sloped away from the manufacturing building to address
stormwater accumulation in the building. The floor drains
inside the manufacturing building are connected to an
oil/water separator which discharges into the sanitary sewer
system.
Spill response equipment
No
There are spill response kits located at the site which are
used to clean up spills and leaks on the property.
Stormwater Pollution Plan Observed Comments
Does the facility have a stormwater
pollution prevention plan?
Yes
Wire -Bond has prepared and implemented a Stormwater
Pollution Prevention Plan (SPPP) for the property.
General location (USGS) map
Yes
Narrative description of practices
Yes
Detailed site map
Yes
The site map has recently been updated to include the new
building location on the property.
List of significant spills (past 3 years)
Yes
No significant spills have occurred on the property during the
past 3 years.
Non-stormwater discharge evaluation
of outfall(s)
Yes
The recent non-stormwater discharge evaluation of the
outfalls was conducted and documented in the SPPP on
August 15, 2018.
Feasibility study
Yes
•
ObTo report pollution or drainage problems call: 311
CHARLMM http://stormwater.charmeck.org
9/19/2018 1:52:04PM
Page 2 of 3
Stormwater Pollution Plan Observed Comments
All necessary secondary
Yes
containment provided
Collected water evaluated and
N/A
The secondary containment area is covered.
documented prior to release
BMP Summary
Yes
Spill prevention and response plan
Yes
Preventative maintenance and good
Yes
housekeeping plan
Facility provides and documents
Yes
Wire -Bond conducts semi-annual employee training. The
employee training
recent employee training events were conducted in October
2017 and March 2018.
List of responsible parties
Yes
Reviewed and updated annually
Yes
The SPPP was reviewed and updated on August 15, 2018.
Stormwater facility inspection
Yes
Stormwater facility inspections are conducted monthly at the
program conducted semi-annually
site. The recent inspection was conducted on August 15,
2018.
Qualitative/Analytical Monitoring Observed Comments
Qualitative monitoring conducted
Yes
Qualitative monitoring is conducted monthly at the site. The
semi-annually
recent qualitative monitoring events were conducted on March
6, 2018; April 23, 2018; May 16, 2018; and July 24, 2018.
No storm events were sampled in June 2018; a no flow DMR
was submitted to NCDEQ for June 2018.
Analytical monitoring conducted
Yes
Analytical monitoring is conducted monthly at the site per
semi-annually
Tier 3 requirement of the Permit. The recent qualitative
monitoring events were conducted on March 6, 2018; April
23, 2018; May 16, 2018; and July 24, 2018. No storm events
were sampled in June 2018; a no flow DMR was submitted to
NCDEQ for June 2018. The zinc concentrations exceeded
the benchmark limit for the Permit.
Analytical monitoring from vehicle
N/A
maintenance
Permit and Outfalls Observed Comments
Copy of permit and certificate of
Yes
Wire -Bond has Certificate of Coverage No. NCG030629.
coverage onsite
All outfalls observed
Recommendation
Filtrexx filters and straw bales were observed at each of the
outfalls on the property. It is recommended that the filters
and straw bales be inspected and replaced as needed.
Number of Outfalls Observed
8
Representative outfall status
N/A
documented by NCDWQ
Annual no -exposure self
N/A
re -certification documented
•
ObTo report pollution or drainage problems call: 311
CttARL(YFTE_ http://stormwater.charmeck.org
9/19/2018 1:52:04PM