HomeMy WebLinkAboutNC0000396_Other Correspondence_20191104(� DUKE
ENERGY.
PROGRESS
Certified Mail: 7016 2140 0001 0231 1531
October 7, 2019
File No. 12520A
Division of Water Resources
Attention: Sergei Chernikov
WQ Permitting Section - NPDES
1617 Mail Service Center
Raleigh, NC 27699-1617
Subject: Asheville Steam Electric Generating Plant
NPDES Permit NC0000396
Garry A. Whisnant
Plant General Manager
Asheville Steam Electric Plant
Duke Energy Progress
ASVL PLT 1200 CP&L Dr
Arden, NO 28704
o: 828-687-5211
t 828.687-5204
garry. whisnant@duke-onergy.com
NOV 0 4 2019
Water Quality
Asheville Reg onal Office
onal tlons
Outfall 001 Notification of Waste Water Treatment System
Dear Dr. Chernikov:
With reference to Part I A (1) of the subject permit, this letter provides notification to you that
construction of the new waste water treatment system is scheduled to be completed and ready for
operation by October 31, 2019. This new WWTS consists primarily of a clarifier with polymer
addition and filter system for solid removal and includes pH adjustment processes. It is being
installed to replace the current WWTS that consists of a rim ditch, settling pond, filter system and pH
adjustment process.
This new WWTS may begin operation in November 2019 if deemed warranted. The current plan is
the WWTS will begin full operation in the first quarter of 2020 when the rim ditch, settling pond,
filter system and pH adjustment process are decommissioned. The treated discharge from this new
treatment system will combine with the discharge from the new Combined Cycle and ultimately
discharge to the French Broad River by NPDES outfall 001.
Should you have questions please contact Robert Wylie at 704 382-4669 or Teresa Williams at 828-
687-5240.
Sincerely,
Garry Whisnant, Plant Manager
GM II - Regulated Stations
CC: Division of Water Resources Certified Mail: 7016 2140 0001 0231 1555
Attention: Tim Heim
Asheville Water Quality Regional Operations Section
2090 U.S. 70 Highway
Swannanoa, NC 28778-8211