HomeMy WebLinkAboutNC0025348_Other_20200317Regional Pretreatment Annual Report (PAR) Review
Is the PAR on time? Does it have two copies?
Did they send any other submissions with it?
Included?
ADEQUATE?
POTW noted Corrections?
Narrative
® YES
❑
NO
❑ NA
® YES
❑
NO
❑ NA
PPS Form
® YES
❑
NO
® YES
❑
NO
SNCR
® YES
❑
NO
® YES
❑
NO
IDSF
® YES
❑
NO
® YES
❑
NO
Allocation Table
® YES
❑
NO
® YES
❑
NO
Compliance Schedules
❑ YES
❑
NO
® NA
❑ YES
❑
NO
® NA
Public Notice
❑ YES
❑
NO
® NA
❑ YES
❑
NO
® NA
Program Information
® YES
❑
NO
® YES
❑
NO
❑ YES ® NO
Historical SNC
❑ YES
❑
NO
® NA
❑ YES
❑
NO
® NA
❑ YES ❑ NO ® NA
Regional Office: Washington
POTW: New Bern
NPDES Permit No. NCO025348
Report Period:1/1/2019 to 12/31/2019
® Full ❑ Modified
For modified programs evaluate shaded
items only. A Narrative is required for a
modified program only if there are SIUs
in SNC.
If No, check recommendation below;
1. Have at least 90% of SIU permits been issued within 180
❑ Yes ❑ No ® Not req'd
❑ NOD
❑ NOV
❑ QNCR
❑ NCP
❑ Civil Penalty
days of expiration? See Allocation Table).
Assessment
2. Were at least 80% of SIUs inspected? (See PPS Form)
® Yes ❑ No ❑ Not req'd
❑ NOD
❑ NOV
❑ QNCR
❑ NCP
❑ Civil Penalty
Assessment
3. Has effective enforcement been taken against industries in
❑ Yes ❑ No ® NA
❑ NOD
❑ NOV
❑ QNCR
❑ NCP
❑ Civil Penalty
SNC, including those causing pass -through or interference? (See
Assessment
Narrative and SNCR Form
4. Does public notice cover all SIUs in SNC?
❑ Yes ❑ No ® NA
❑ NOD
❑ NOV
❑ QNCR
❑ NCP
❑ Civil Penalty
Assessment
vote: txceptions snouia ue emiainea in the comment section below:
Narrative states a NOV was sent to Chatsworth Products for failure to calibrate flow
meter in 2018. I talked with Bruce and he confirmed that the NOV was sent in 2020 for
failure to calibrate flow meter in 2019 not 2018.
Reviewed By:��,�� Date: 3/17/2020
Regional Pretreatment Annual Report Review
New Bern 2019 PAR16