HomeMy WebLinkAbout20170926 Ver 1_401 Application_20170727July 28, 2017 WK Dickson Attn: Ward Marotti 616 Colonnade Dr Charlotte, NC 28205 Subject: REQUEST FOR ADDITIONAL INFORMATION Elkin Raw Water System Improvements Dear Mr. Marotti: ROY COOPER MICHAEL S. REGAN \.' l /1'1I S. JAY ZIMMERMAN 1)1"',,„ DWR # 17-0926 Surry County On July 27, 2017, the Division of Water Resources (Division) received your application requesting a 401 Water Quality Certification from the Division for the subject project. The Division has determined that your application is incomplete and cannot be processed. The application is on -hold until all of the following information is received: Need More Fee A review of the Pre -Construction Notification (PCN) Form indicates this application is for _490_ linear feet of stream impacts. Pursuant to 143-215.3D (e), a $570 permitting fee is required to process this application. Check # 009945 was applied; however, the remaining balance to remit is $330. Please remit a check to DEQ-DWR, 1617 Mail Service Center, Raleigh, NC 27699-1617. 2. Need Agent Authorization Form Page 10 of 10 of the Pre -Construction Notification (PCN) Form carries the signature of John Holcomb. Pursuant to 15A NCAC 02H .0502(f) in order for Mr. Holcomb to sign, the application package requires an agent authorization form from the applicant. An example can be found online: http://www.saw. usace.army.miI/Portals/59/docs/regulatory/regdocs/Permits/SAM PLE AGENT AUTHORIZATION FORM.pdf. Please submit four (4) copies of this documentation. Pursuant to Title 15A NCAC 02H .0502(e) the applicant shall furnish all of the above requested information for the proper consideration of the application. If all of the State of North Carolina I Environmental Quality I Water Resources 1617 Mail Service Center I Raleigh, North Carolina 27699-1617 919 807 6300 Page 2 of 2 requested information is not received in writing at the address below within 30 calendar days of receipt of this letter, the Division will be unable to process the application and it will be returned. The return of this project will necessitate reapplication to the Division for approval, including a complete application package and the appropriate fee. Please be aware that you have no authorization under Section 401 of the Clean Water Act for this activity and any work done within waters of the state may be a violation of North Carolina General Statutes and Administrative Code. Please contact Sheri Montalvo at 919-807-6303 or Sheri. montalvo(a�ncdenr.gov if you have any questions or concerns. Sincerely, Karen Higgins, Supervisor 401 & Buffer Permitting Unit cc: Town of Elkin, John Holcomb, 226 N. Bridge St., Elkin, NC 28621 USACE Raleigh Regulatory Field Office DWR WSRO 401 files DWR 401 & Buffer Permitting Unit Filename: 170926EIkin RawWater(surry)_HOLD �wI< LETTER OF TRANSMITTAL WDICKSON community infrastructure consultants 401 41' Street, SW, Suite 201 TO: NC DWR Hickory, North Carolina 28602 828.327.6911 tel. / 0 170926 401 & Buffer Permitting Unit 512 North Salisbury Street Raleigh, NC 27604 ATTENTION: Karen Higgins DATE: July 26, 2017 RE: NC DWR 401 Permit Package Elkin Raw Water System Improvements NC DWI CWSRF #WIF-1905 WKD Project #20160049.00.HI We are sending via: ® Overnight UPS ❑ Regular Mail ❑ Pick-up The following items: ❑ Correspondence ❑ Plans ❑ Specifications ❑ Hand Delivered ❑ Other as listed below: COPIES DATE NO. DESCRIPTION 2 7/26/17 1 Two (2) Sets of Full Size Color Drawings 2 7/26/17 2 Two (2) Sets of 11 x 17 Color Drawings 4 7/26/17 3 Four (4) Copies of PCN 401 Package with Support Documentation 1 7/26/17 4 Check for $240.00 to Payable to NC DEQ THESE ARE TRANSMTITED as checked below: ❑ For Approval ❑ As Requested ❑ Approved as Submitted ® For Your Use ❑ For Review and Comment ❑ Approved as Noted REMARKS: 11��—� � t I►VIE�n ❑ Forward to Subcontractor COPY TO: Robert Fuller, Town of Elkin SIGNED: Ward Marotti, Senior Scientist/PM \N AT F� O Nii� Y Office Use Only: Corps action ID no. DWQ project no. Form Version 1.4 January 2009 Page 1 of 10 PCN Form — Version 1.4 January 2009 Pre -Construction Notification (PCN) Form A. Applicant Information 1. Processing 1a. Type(s) of approval sought from the Corps:X❑ Section 404 Permit ❑ Section 10 Permit 1b. Specify Nationwide Permit (NWP) number: 12 or General Permit (GP) number: 1c. Has the NWP or GP number been verified by the Corps? ❑ Yes ❑X No 1 d. Type(s) of approval sought from the DWQ (check all that apply): ❑X 401 Water Quality Certification — Regular ❑ Non -404 Jurisdictional General Permit ❑ 401 Water Quality Certification — Express ❑ Riparian Buffer Authorization 1 e. Is this notification solely for the record because written approval is not required? For the record only for DWQ 401 Certification: ❑ Yes ❑X No For the record only for Corps Permit: ❑ Yes ❑X No 1f. Is payment into a mitigation bank or in -lieu fee program proposed for mitigation of impacts? If so, attach the acceptance letter from mitigation bank or in -lieu fee program. N Yes ❑X No 1 g. Is the project located in any of NC's twenty coastal counties. If yes, answer 1h below. ❑ Yes ❑X No 1 h. Is the project located within a NC DCM Area of Environmental Concern (AEC)? ❑ Yes NX No 2. Project Information 2a. Name of project: Elkin Raw Water System Improvements 2b. County: Surry 2c. Nearest municipality / town: Elkin 2d. Subdivision name: 2e. NCDOT only, T.I.P. or state project no: 3. Owner Information 3a. Name(s) on Recorded Deed: Worth Winebarger 3b. Deed Book and Page No. Book 804 Page 993 3c. Responsible Party (for LLC if applicable): 3d. Street address: 15821 Elkin Highway 268 3e. City, state, zip: Elkin, NC 28621 3f. Telephone no..- o.:3g. 3g. Fax no.: 3h. Email address: Page 1 of 10 PCN Form — Version 1.4 January 2009 4. Applicant Information (if different from owner) 4a. Applicant is: ❑ Agent ❑X Other, specify: Town of Elkin 4b. Name: John Holcomb, Town Manager 4c. Business name (if applicable): Town of Elkin 4d. Street address: 226 N. Bridge Street 4e. City, state, zip: Elkin, NC 28621 4f. Telephone no.: 336-835-9800 4g. Fax no.: 4h. Email address: jholcomb@elkinnc.org S. Agent/Consultant Information (if applicable) 5a. Name: Ward Marotti 5b. Business name (if applicable): WK Dickson 5c. Street address: 616 Colonnade Dr. 5d. City, state, zip: Charlotte, NC 28205 5e. Telephone no.: 919-368-8043 5f. Fax no.: 5g. Email address: wmarotti@wkdickson.com Page 2 of 10 B. Project Information and Prior Project History 1. Property Identification 1a. Property identification no. (tax PIN or parcel ID): 008040993 1 b. Site coordinates (in decimal degrees): ILatitude: 36.260412 Longitude: -80.868305 1 c. Property size: 13.78 acres 2. Surface Waters 2a. Name of nearest body of water to proposed project: Elkin Creek 2b. Water Quality Classification of nearest receiving water: C 2c. River basin: Yadkin Pee -Dee 3. Project Description 3a. Describe the existing conditions on the site and the general land use in the vicinity of the project at the time of this application: See attached. 3b. List the total estimated acreage of all existing wetlands on the property: 0.07 3c. List the total estimated linear feet of all existing streams (intermittent and perennial) on the property: 800 3d. Explain the purpose of the proposed project: See attached. 3e. Describe the overall project in detail, including the type of equipment to be used: See attached. 4. Jurisdictional Determinations 4a. Have jurisdictional wetland or stream determinations by the Corps or State been requested or obtained for this property / roject includin all rior hases in the ast? ❑ Yes ❑X No ❑ Unknown Comments: William Elliot (USAGE) visited the site on 5 October 4b. If the Corps made the jurisdictional determination, what type of determination was made? ❑ Preliminary ❑ Final 4c. If yes, who delineated the jurisdictional areas? Name (if known): Ward Marotti Agency/Consultant Company: WK Dickson Other: 4d. If yes, list the dates of the Corps jurisdictional determinations or State determinations and attach documentation. 5. Project History 5a. Have permits or certifications been requested or obtained for this project (including all prior phases) in the past? ❑ Yes ❑X No ❑ Unknown 5b. If yes, explain in detail according to "help file" instructions. 6. Future Project Plans 6a. Is this a phased project? ❑ Yes ❑X No 6b. If yes, explain. Page 3 of 10 PCN Form — Version 1.4 January 2009 C. Proposed Impacts Inventory 1. Impacts Summary 1 a. Which sections were completed below for your project (check all that apply): ❑X Wetlands Q Streams — tributaries ❑ Buffers ❑ Open Waters ❑ Pond Construction 2. Wetland Impacts If there are wetland impacts proposed on the site, then complete this question for each wetland area impacted. 2a. 2b. 2c. 2d. 2e. 2f. Wetland impact Type of impact Type of wetland Forested Type of jurisdiction Area of number Corps (404,10) or impact Permanent (P) or DWQ (401, other) (acres) Temporary T W1 T Excavation Bottomland Hardwood Forest No Corps 0.07 W2 - Choose one Choose one Yes/No - W3 - Choose one Choose one Yes/No - W4 - Choose one Choose one Yes/No - W5 - Choose one Choose one Yes/No - W6 - Choose one Choose one Yes/No 2g. Total Wetland Impacts: 0.07 2h. Comments: Temporary disturbance of an existing, maintained herbaceous wetland to install water line. Impact location is shown on drawing C2.2 and C3.2. 3. Stream Impacts If there are perennial or intermittent stream impacts (including temporary impacts) proposed on the site, then complete this question for all stream sites impacted. 3a. 3b. 3c. 3d. 3e. 3f. 3g. Stream impact Type of impact Stream name Perennial (PER) or Type of Average Impact number intermittent (INT)? jurisdiction stream length Permanent (P) or width (linear Temporary (T) (feet) feet) S1 T Excavation Elkin Creek PER Corps 30 50 S2 T No Impact Elkin Creek PER Corps 30 0 S3 T Excavation Elkin Creek PER Corps 30 40 S4 P Stabilization Elkin Creek PER Corps 30 330 S5 P Relocation UT Elkin Creek PER Corps 5 70 S6 - Choose one - - 3h. Total stream and tributary impacts aso 3i. Comments: Temporary impacts will result from installation of a raw water line. Permanent impacts will result from stabilization of Elkin Creek in the vicinity of (over) an existing raw water line and the realignment of an unstable, actively eroding unnamed tributary. Impact locations are shown on drawings C2.1, C2.3, C2.4, C3.1 Page 4 of 10 PCN Form — Version 1.4 January 2009 4. Open Water Impacts If there are proposed impacts to lakes, ponds, estuaries, tributaries, sounds, the Atlantic Ocean, or any other open water of the U.S. then indivi ually list all open water impacts below. 4a. Open water impact number Permanent (P) or Temporary T 4b. Name of waterbody (if applicable) 4c. Type of impact 4d. Waterbody type 4e. Area of impact (acres) 01 - Choose one Choose O2 - Choose one Choose 03 - Choose one Choose 04 - Choose one Choose 4f. Total open water impacts 4g. Comments: 5. Pond or Lake Construction If pond or lake construction proposed, the complete the chart below. 5a. Pond ID number 5b. Proposed use or purpose of pond 5c. Wetland Impacts (acres) 5d. Stream Impacts (feet) 5e. Upland (acres) Flooded Filled Excavated Flooded Filled Excavated P1 Choose one P2 Choose one 5f. Total: 5g. Comments: 5h. Is a dam high hazard permit required? ❑ Yes ❑ No If yes, permit ID no: 5i. Expected pond surface area (acres): 5j. Size of pond watershed (acres): 5k. Method of construction: 6. Buffer Impacts (for DWQ) If project will impact a protected riparian buffer, then complete the chart below. If yes, then individually list all buffer impacts below. If any impacts require mitigation. then vou MUST fill out Section D of this form. 6a. Project is in which protected basin? ❑ Neuse ❑ Tar -Pamlico ❑ Catawba ❑ Randleman ❑ Other: 6b. Buffer Impact number — Permanent (P) or Temporary T 6c. Reason for impact 6d. Stream name 6e. Buffer mitigation required? 6f. Zone 1 impact (square feet) 6g. Zone 2 impact (square feet B1 - Yes/No B2 - Yes/No B3 - Yes/No B4 - Yes/No B5 - Yes/No B6 - Yes/No 6h. Total Buffer Impacts: 6i. Comments: Page 5 of 10 D. Impact Justification and Mitigation 1. Avoidance and Minimization 1a. Specifically describe measures taken to avoid or minimize the proposed impacts in designing project. Instead of installing an additional raw water line to convey raw water flows from the reservoir to the treatment plant, the existing, exposed raw water line will be protected by stabilizing Elkin Creek using natural channel design techniques. This will minimize impacts, while simultaneously enhancing and stabilizing an actively eroding reach that contributes significant sediment loads into the system. Following the project's erosion and sedimentation control plan will minimize temporary water quality impacts to the maximum extent practicable. 1 b. Specifically describe measures taken to avoid or minimize the proposed impacts through construction techniques. Impacts will be minimized by following an approved erosion and sedimentation control plan, which was submitted to NCDEQ on 12 July 2017. Additional impacts to Waters of the US were avoided by using the existing line, rather than replacing it. 2. Compensatory Mitigation for Impacts to Waters of the U.S. or Waters of the State 2a. Does the project require Compensatory Mitigation for impacts to Waters of the U.S. or Waters of the State? ❑ Yes ❑X No 2b. If yes, mitigation is required by (check all that apply): ❑ DWQ ❑ Corps 2c. If yes, which mitigation option will be used for this project? ❑ Mitigation bank ❑Payment to in -lieu fee program ❑ Permittee Responsible Mitigation 3. Complete if Using a Mitigation Bank 3a. Name of Mitigation Bank: 3b. Credits Purchased (attach receipt and letter) Type: Choose one Type: Choose one Type: Choose one Quantity: Quantity: Quantity: 3c. Comments: 4. Complete if Making a Payment to In -lieu Fee Program 4a. Approval letter from in -lieu fee program is attached. ❑ Yes 4b. Stream mitigation requested: linear feet 4c. If using stream mitigation, stream temperature: Choose one 4d. Buffer mitigation requested (DWQ only): square feet 4e. Riparian wetland mitigation requested: acres 4f. Non -riparian wetland mitigation requested: acres 4g. Coastal (tidal) wetland mitigation requested: acres 4h. Comments: 5. Complete if Using a Permittee Responsible Mitigation Plan 5a. If using a permittee responsible mitigation plan, provide a description of the proposed mitigation plan. Page 6 of 10 PCN Form — Version 1.4 January 2009 6. Buffer Mitigation (State Regulated Riparian Buffer Rules) — required by DWQ 6a. Will the project result in an impact within a protected riparian buffer that requires buffer mitigation? E] Yes ❑X No 6b. If yes, then identify the square feet of impact to each zone of the riparian buffer that requires mitigation. Calculate the amount of mitigation required. Zone 6c. Reason for impact 6d. Total impact (square feet) Multiplier 6e. Required mitigation (square feet) Zone 1 3 (2 for Catawba) Zone 2 1.5 6f. Total buffer mitigation required: 6g. If buffer mitigation is required, discuss what type of mitigation is proposed (e.g., payment to private mitigation bank, permittee responsible riparian buffer restoration, payment into an approved in -lieu fee fund). 6h. Comments: Page 7 of 10 E. Stormwater Management and Diffuse Flow Plan (required by DWQ) 1. Diffuse Flow Plan 1a. Does the project include or is it adjacent to protected riparian buffers identified ❑ Yes ❑X No within one of the NC Riparian Buffer Protection Rules? 1 b. If yes, then is a diffuse flow plan included? If no, explain why. ❑ Yes ❑ No 2. Stormwater Management Plan 2a. What is the overall percent imperviousness of this project? 0 2b. Does this project require a Stormwater Management Plan? ❑ Yes ❑X No 2c. If this project DOES NOT require a Stormwater Management Plan, explain why: No new impervious area will be added. 2d. If this project DOES require a Stormwater Management Plan, then provide a brief, narrative description of the plan: 2e. Who will be responsible for the review of the Stormwater Management Plan? 3. Certified Local Government Stormwater Review 3a. In which localgovernment's jurisdiction is thisproject? Town of Elkin ❑ Phase 11 ❑ NSW 3b. Which of the following locally -implemented stormwater management programs ❑ USMP apply (check all that apply): ❑ Water Supply Watershed ❑ Other: 3c. Has the approved Stormwater Management Plan with proof of approval been ❑ Yes ❑X No attached? 4. DWQ Stormwater Program Review ❑Coastal counties ❑HQW 4a. Which of the following state -implemented stormwater management programs apply ❑ORW (check all that apply): ❑Session Law 2006-246 []Other: 4b. Has the approved Stormwater Management Plan with proof of approval been ❑ Yes ❑ No attached? 5. DWQ 401 Unit Stormwater Review 5a. Does the Stormwater Management Plan meet the appropriate requirements? ❑ Yes ❑ No 5b. Have all of the 401 Unit submittal requirements been met? ❑ Yes ❑ No Page 8 of 10 PCN Form — Version 1.4 January 2009 F. Supplementary Information 1. Environmental Documentation (DWQ Requirement) 1 a. Does the project involve an expenditure of public (federal/state/local) funds or the Yes ❑ No use of public (federal/state) land? 1 b. If you answered "yes" to the above, does the project require preparation of an environmental document pursuant to the requirements of the National or State ❑X Yes ❑ No (North Carolina) Environmental Policy Act (NEPA/SEPA)? 1 c. If you answered "yes" to the above, has the document review been finalized by the State Clearing House? (If so, attach a copy of the NEPA or SEPA final approval letter.) Q Yes ❑ No Comments: FONSI attached. 2. Violations (DWQ Requirement) 2a. Is the site in violation of DWQ Wetland Rules (15A NCAC 2H .0500), Isolated Wetland Rules (15A NCAC 2H .1300), DWQ Surface Water or Wetland Standards, ❑ Yes Q No or Riparian Buffer Rules (15A NCAC 2B .0200)? 2b. Is this an after -the -fact permit application? El Yes ❑X No 2c. If you answered "yes" to one or both of the above questions, provide an explanation of the violation(s): 3. Cumulative Impacts (DWQ Requirement) 3a. Will this project (based on past and reasonably anticipated future impacts) result in ❑Yes Q No additional development, which could impact nearby downstream water quality? 3b. If you answered "yes" to the above, submit a qualitative or quantitative cumulative impact analysis in accordance with the most recent DWQ policy. If you answered "no," provide a short narrative description. The project will not increase the water treatment plant's capacity and will, therefore, not support or result in additional development. As a result, no cumulative impacts to water quality are anticipated. 4. Sewage Disposal (DWQ Requirement) 4a. Clearly detail the ultimate treatment methods and disposition (non -discharge or discharge) of wastewater generated from the proposed project, or available capacity of the subject facility. The project will not generate additional wastewater flow volumes. Page 9 of 10 PCN Form — Version 1.4 January 2009 S. Endangered Species and Designated Critical Habitat (Corps Requirement) 5a. Will this project occur in or near an area with federally protected species or ❑ Yes ❑X No habitat? 5b. Have you checked with the USFWS concerning Endangered Species Act X❑Yes ❑ No impacts? 5c. If yes, indicate the USFWS Field Office you have contacted. Asheville 5d. What data sources did you use to determine whether your site would impact Endangered Species or Designated Critical Habitat? NHP element occurrences and USFWS scoping. 6. Essential Fish Habitat (Corps Requirement) 6a. WII this project occur in or near an area designated as essential fish habitat? ❑ Yes ❑X No 6b. What data sources did you use to determine whether your site would impact Essential Fish Habitat? Existing GIS data. 7. Historic or Prehistoric Cultural Resources (Corps Requirement) 7a. Will this project occur in or near an area that the state, federal or tribal governments have designated as having historic or cultural preservation ❑ Yes ❑X No status (e.g., National Historic Trust designation or properties significant in North Carolina history and archaeology)? 7b. What data sources did you use to determine whether your site would impact historic or archeological resources? SHPO scoping. S. Flood Zone Designation (Corps Requirement) 8a. Will this project occur in a FEMA -designated 100 -year floodplain? © Yes ❑ No 8b. If yes, explain how project meets FEMA requirements: See attached. The project is concurrently seeking confirmation of a No Rise to existing flood elevations. 8c. What source(s) did you use to make the floodplain determination? Project -specific modeling See attached Jam! (tel. H�co.�e 4�t f Applicant/Agent's Printed Name ppiicant/Agent's Signature Date (Agent's signature is valid only if an authorization letter from the applicant isprovided.) Page 10 of 10 A- P V K WDICKSON community infrastructure consultants Pre -Construction Notification (PCN) Form: Town of Elkin Raw Water Intake and Storage Improvements B3a. Describe the existing conditions on the site and the general land use in the vicinity of the project at the time of this application: The proposed water line and bank stabilization areas are located within and adjacent to an abandoned railroad bed, portions of which have been converted into a pedestrian and bicycle path that parallels Elkin Creek. The wetland area to be impacted is under and immediately adjacent to an NCDOT-maintained bridge and is dominated by herbaceous vegetation and regularly maintained. Stream crossings and stabilization areas are dominated by successional and mature bottomland hardwood forest. B3d. Explain the purpose of the proposed project: The project is needed to address deficiencies within the current raw water supply pumps at Big Elkin Creek, raw water supply piping from the reservoir to the water treatment plant and emergency raw water supply from the Yadkin River. Additionally, the project is to replace the inoperable sluice gates within the reservoir intake structure to permit multilevel withdrawal from the reservoir. A "no -action" alternative will leave the current raw water piping subject to continued erosion and undermining of the stream bank, potentially resulting in the failure of the raw water supply piping. A failure of the raw water supply line would have catastrophic consequences to the Town's ability to provide safe and reliable water to its citizens and would impact the public health and welfare. B3e. Describe the overall project in detail, including the type of equipment to be used: The project's Engineering Report/ Environmental Information Document (ER/EID) included an alternatives analysis, including the "No Action" alternative described above. The selected alternative (Alternative 4) proposes the continued use of the existing 24" cast iron raw water line with approximately 7001f of stream bank restoration/stabilization in the areas of exposed pipe, including the installation of three J -hooks within the stream to direct flows away from the stream bank, the construction of a new 12" emergency raw water line to the reservoir, replacement of the Big Elkin Creek raw water pumps, controls and valves, and replacement of the existing sluice gates in the outlet structure that are no longer operable. Elkin Raw Water Line and Bank Stabilization Improvements 25 July 2017 Page 2 The project will use normal construction equipment, including track hoes, bobcats and dump trucks. F8b.If yes, explain how project meets FEMA requirements: The project has been designed to result in no changes to flood elevations. Initial modeling results were provided to the North Carolina Department of Public Safety Division of Emergency Management National Flood Insurance Program (NCNFIP) on 8 June 2017. NCNFIP comments were received on 10 July 2017 (attached). Design was modified, per these comments. Models were revised to reflect these design changes and were re- submitted to NCNFIP on 26 July 2017. F8c. What source(s) did you use to make the floodplain determination? Project -specific modeling and NCNFIP review (see attached). WD ICKSON 7 • ♦ sr ✓ ffi ,"'. ;�r �* I ti �• S Hugh Chatham �+! .. •'t e.fl ; x I • : . _ �� Memorial ,rfi • i r I �Y Hospital ' I ` .+♦ •a. x Pleasant.'' t - i Y - - ;West " ' Hill >�•��.•. 00 f � ' k t �' 1 �.•• . rt �J I �j $t. - Hollywood _ • . Cemetary • Park e.;tib i - • p,r •- -71 _ ..,•+' • if I 01 • ,7 t ♦. l - — - s-.. 4� sT. � - r-" 1 , I � I t,74'L... p � •�t.l+ �- .` --.` � �� _ (- .� . '�.f yy Elkin • r , Y_ j / / IR -� . � I • �, , Surry Yadkin Rrver . ✓ ; .' " OPP' i �• _ • :. . r t I Yadkin i •" M I? 7i4 ' ++"+^ ar.,•.:— sem. �,ti�'"._ I / / ___ • ,•� �- �S' :� T; -�} "r , , -'• `� •'r mon - aYksd'"�, 6harl'ott N rih Id_ _ �♦rl ' Earotma � t(anta - Columbia • �� } 1 I1 III 111 ■ Existing Water Treatment Plant J Hook community infrastructure consultants Existing Raw Water Intake Boulder Toe molls 0 250 500 1, Existing Raw Water 000 � Emergency Raw Water Alignment i inch = 500 feet In Feet _J FaD FcC2 FrC E FaD FcC2 V FrC t community infrastructure consultants / FeC2 FeD2 ��-- FeD2 FaD FcC2 qFcB2CsA €� 0 FeC2 tx �,.., 1 FeD2 FcC2 FaD FeC2 WoD WfC2 FeD2 FcC2I L---\" r' ' t-" DeF ,, ;, Ud .,91 Ur RdE FuC2 FeD2 FuC2 FsE DrB Hwy- FsE FeD2 i FeC2 FeD2 FeC2 U j FeC2 FuC2 FeD2 i r FeC2 FeD2 FuC2 FeC2 FeD2 it FeD2 c` S 0 0 FeD2 \ (eD Legend N Figure 5.2: Soils and Prime Farmland Existing Raw Water Intake) Hook �E l J ® s Elkin, NC Existing Water Treatment Plant Farmland of Statewide Importance Boulder Toe ® Prime Farmland Emergency Raw Water Alignment Existing Raw Water Fsi_�FeD2 FeC2 0 500 1,000 2,000 Feet 1 inch = 500 feet WETLAND DETERMINATION DATA FORM — Eastern Mountains and Piedmont Region Project/Site: Elkin Water Line City/County: Surly Sampling Date: 5 Oct 2017 Applicant/Owner: Ek6n State: NC Sampling Point:_ Investigator(s): N.42rotti Section, Township, Range: Landform (hillslope, terrace, etc.): floodplain Local relief (concave, convex, none): concave Slope Subregion (LRR or MLRA): Lat: 36 9S0419 Long: -80.868305 Datum: Soil Map Unit Name: NWI classification: Are climatic / hydrologic conditions on the site typical for this time of year? Yes X No (If no, explain in Remarks.) Are Vegetation Soil or Hydrology significantly disturbed? Are "Normal Circumstances" present? Yes X No Are Vegetation Soil or Hydrology naturally problematic? (If needed, explain any answers in Remarks.) SUMMARY OF FINDINGS — Attach site map showing sampling point locations, transects, important features, etc. Hydrophytic Vegetation Present? Yes -x— No Is the Sampled Area Hydric Soil Present? Yes No within a Wetland? Yes No x Wetland Hydrology Present? Yes No__X_ HYDROLOGY Wetland Hydrology Indicators: Secondary Indicators (minimum of two required) Primary Indicators (minimum of one is required; check all that apply) _ Surface Soil Cracks (136) Surface Water (A1) _ True Aquatic Plants (1314) _ Sparsely Vegetated Concave Surface (138) _ High Water Table (A2) _ Hydrogen Sulfide Odor (Cl) _ Drainage Patterns (B10) Saturation (A3) _ Oxidized Rhizospheres on Living Roots (C3) _ Moss Trim Lines (B16) _ Water Marks (131) _ Presence of Reduced Iron (C4) _ Dry -Season Water Table (C2) _ Sediment Deposits (132) _ Recent Iron Reduction in Tilled Soils (C6) _ Crayfish Burrows (C8) _ Drift Deposits (133) _ Thin Muck Surface (C7) _ Saturation Visible on Aerial Imagery (C9) Algal Mat or Crust (134) _ Other (Explain in Remarks) _ Stunted or Stressed Plants (D1) _ Iron Deposits (65) _ Geomorphic Position (D2) Inundation Visible on Aerial Imagery (B7) _ Shallow Aquitard (D3) _ Water -Stained Leaves (139) _ Microtopographic Relief (D4) Aquatic Fauna (1313) _ FAC -Neutral Test (D5) Field Observations: Surface Water Present? Yes No x Depth (inches): Water Table Present? Yes No X Depth (inches): Saturation Present? Yes No X Depth (inches): Wetland Hydrology Present? Yes Nom_ includes capillary fringe) Describe Recorded Data (stream gauge, monitoring well, aerial photos, previous inspections), if available: Remarks: US Army Corps of Engineers Eastern Mountains and Piedmont – Version 2.0 VEGETATION (Four Strata) - Use scientific names of plants. Tree Stratum (Plot size 1. 5. 6. 7. 50% of total cover: Sapling/Shrub Stratum (Plot size: ) 1. 2. 3. 4. 5. 6. 7. 8. 9. 50% of total cover: Sampling Point: Absolute Dominant Indicator Dominance Test worksheet: % Cover Species? Status Number of Dominant Species That Are OBL, FACW, or FAC: 3 (A) = Total Cover 20% of total cover: = Total Cover 20% of total cover: Herb Stratum (Plot size: ) 1. hinrim P-ffimim, y FAG 2. 3 ersecarla lapathifolia ?n FACV Total Number of Dominant Species Across All Strata: 3 (B) Percent of Dominant Species That Are OBL, FACW, or FAC: 1 nn (A/B) Prevalence Index worksheet: Total % Cover of: Multiply by: OBL species x 1 = FACW species x 2 = FAC species x 3 = FACU species x 4 = UPL species x 5 = Column Totals: (A) (B) Prevalence Index = B/A = Hydrophytic Vegetation Indicators: 1 - Rapid Test for Hydrophytic Vegetation _y, 2 - Dominance Test is >50% _ 3 - Prevalence Index is s3.0' 4 - Morphological Adaptations' (Provide supporting data in Remarks or on a separate sheet) Problematic Hydrophytic Vegetation' (Explain) 'Indicators of hydric soil and wetland hydrology must be present, unless disturbed or problematic. 4. OBL Definitions of Four Vegetation Strata: 5. Carex lurida 15 6 Tree - Woody plants, excluding vines, 3 in. (7.6 cm) or more in diameter at breast height (DBH), regardless of 7. height. 9. 10. 11. Woody Vine Stratum (Plot size 1. 2. 3. 4. 5. = Total Cover 50% of total cover: 20% of total cover: = Total Cover 50% of total cover: 20% of total cover: (Include photo numbers here or on a separate sheet.) Sapling/Shrub - Woody plants, excluding vines, less than 3 in. DBH and greater than or equal to 3.28 ft (1 m) tall. Herb -All herbaceous (non -woody) plants, regardless of size, and woody plants less than 3.28 ft tall. Woody vine - All woody vines greater than 3.28 ft in Hydrophytic Vegetation Present? Yes No US Army Corps of Engineers Eastern Mountains and Piedmont - Version 2.0 SOIL Sampling Point: Profile Description: (Describe to the depth needed to document the indicator or confirm the absence of indicators.) Depth Matrix Redox Features (inches) Color (moist) % Color (moist) % Type Loc Texture Remarks 0-16 7.5YR2.4/4 1 nn RI 'Type: C=Concentration, D= Hydric Soil Indicators: Histosol (Al) Histic Epipedon (A2) Black Histic (A3) Hydrogen Sulfide (A4) Stratified Layers (A5) _ 2 cm Muck (A10) (LRR N) Depleted Below Dark Surface (A11) Thick Dark Surface (Al2) Sandy Mucky Mineral (S1) (LRR N, MLRA 147, 148) Sandy Gleyed Matrix (S4) Sandy Redox (S5) _ Stripped Matrix (S6) Type: Depth (inches): _ Dark Surface (S7) Polyvalue Below Surface (S8) (MLRA 147, 148) Thin Dark Surface (S9) (MLRA 147, 148) Loamy Gleyed Matrix (F2) Depleted Matrix (F3) Redox Dark Surface (F6) _ Depleted Dark Surface (F7) _ Redox Depressions (F8) _ Iron -Manganese Masses (F12) (LRR N, MLRA 136) _ Umbric Surface (F13) (MLRA 136, 122) Piedmont Floodplain Soils (F19) (MLRA 148) Red Parent Material (F21) (MLRA 127, 147) Indicators for Problematic Hydric Soils": 2 cm Muck (A10) (MLRA 147) _ Coast Prairie Redox (A16) (MLRA 147, 148) _ Piedmont Floodplain Soils (F19) (MLRA 136, 147) _ Very Shallow Dark Surface (TF12) Other (Explain in Remarks) 3Indicators of hydrophytic vegetation and wetland hydrology must be present, unless disturbed or problematic. Hydric Soil Present? Yes No X US Army Corps of Engineers Eastern Mountains and Piedmont — Version 2.0 WETLAND DETERMINATION DATA FORM — Eastern Mountains and Piedmont Region • Project/Site: Elkin Water Line City/County: Surry Sampling Date: 5 Oct 2017 Applicant/Owner: T.........r ten ii. State: NC Sampling Point:1A/�� Investigator(s): rntte Section, Township, Range: Landform (hillslope, terrace, etc.): ffanrinlain Local relief (concave, convex, none): r nnrrava Slope Subregion (LRR or MLRA): Lat: 36 960419 Long: -80.868305 Datum: Soil Map Unit Name: NWI classification: Are climatic / hydrologic conditions on the site typical for this time of year? Yes _X No (If no, explain in Remarks.) Are Vegetation Soil or Hydrology significantly disturbed? Are "Normal Circumstances" present? Yes X No Are Vegetation Soil or Hydrology naturally problematic? (If needed, explain any answers in Remarks.) SUMMARY OF FINDINGS — Attach site map showing sampling point locations, transects, important features, etc. Hydrophytic Vegetation Present? Yes —x No Is the Sampled Area Hydric Soil Present? Yes )f No within a Wetland? Yes X No Wetland Hydrology Present? Yes . No HYDROLOGY Wetland Hydrology Indicators: Secondary Indicators (minimum of two required) Primary Indicators (minimum of one is required: check all that apply) _ Surface Soil Cracks (136) _ Surface Water (Al) _ True Aquatic Plants (614) _ Sparsely Vegetated Concave Surface (138) High Water Table (A2) _ Hydrogen Sulfide Odor (Cl) _ Drainage Patterns (1310) _ Saturation (A3) —)4 Oxidized Rhizospheres on Living Roots (C3) _ Moss Trim Lines (B16) _ Water Marks (61) Presence of Reduced Iron (C4) _ Dry -Season Water Table (C2) _ Sediment Deposits (62) _ Recent Iron Reduction in Tilled Soils (C6) _ Crayfish Burrows (C8) _ Drift Deposits (133) _ Thin Muck Surface (C7) _ Saturation Visible on Aerial Imagery (C9) Algal Mat or Crust (64) _ Other (Explain in Remarks) _ Stunted or Stressed Plants (131) Iron Deposits (135) — Geomorphic Position (D2) _ Inundation Visible on Aerial Imagery (137) _ Shallow Aquitard (D3) Water -Stained Leaves (89) _ Microtopographic Relief (D4) Aquatic Fauna (613) _ FAC -Neutral Test (135) Field Observations: Surface Water Present? Yes No Depth (inches): Water Table Present? Yes _ No Depth (inches): 4 Saturation Present? Yes X No Depth (inches): Wetland Hydrology Present? Yes X No includes capillary fringe) Describe Recorded Data (stream gauge, monitoring well, aerial photos, previous inspections), if available: Remarks: US Army Corps of Engineers Eastern Mountains and Piedmont — Version 2.0 VEGETATION (Four Strata) — Use scientific names of plants. Sampling Point: Tree Stratum (Plot size: ) 1. 2. 3• 4. 5. 6. Absolute Dominant Indicator % Cover Species? Status Dominance Test worksheet: Number of Dominant Species That Are OBL, FACW, or FAC: (A) Total Number of Dominant Species Across All Strata: 3 (B) Percent of Dominant Species That Are OBL, FACW, or FAC: 1 nn (A/B) Prevalence Index worksheet: 7 = Total Cover Total % Cover of: Multiply by: 50% of total cover: 20% of total cover: OBL species x 1 = Sapling/Shrub Stratum (Plot size: ) FACW species x 2 = 1 FAC species x 3 = 2 FACU species x 4 = 3 UPL species x 5 = 4 Column Totals: (A) (B) 5. Prevalence Index = B/A = 6. Hydrophytic Vegetation Indicators: 7. _ 1 - Rapid Test for Hydrophytic Vegetation 8. _X 2 -Dominance Test is >50% 9. _ 3 - Prevalence Index is s3.0' = Total Cover 4 - Morphological Adaptations' (Provide supporting 50% of total cover: 20% of total cover: data in Remarks or on a separate sheet) Herb Stratum (Plot size: ) _ Problematic Hydrophytic Vegetation (Explain) 1. h inm is P-ffusms y 3. Persenaria lapaihifnlia 20 y FAG 4. 7. 8. 9. 10. 11. = Total Cover 50% of total cover: 20% of total cover: Woody Vine Stratum (Plot size: ) 1. 2. 5. = Total Cover 50% of total cover: 20% of total cover: numbers here or on a separate sheet.) 'Indicators of hydric soil and wetland hydrology must be present, unless disturbed or problematic. Tree – Woody plants, excluding vines, 3 in. (7.6 cm) or more in diameter at breast height (DBH), regardless of height. Sapling/Shrub – Woody plants, excluding vines, less than 3 in. DBH and greater than or equal to 3.28 ft (1 m) tall. Herb –All herbaceous (non -woody) plants, regardless of size, and woody plants less than 3.28 ft tall. Woody vine – All woody vines greater than 3.28 ft in Hydrophytic Vegetation Present? Yes --X— No US Army Corps of Engineers Eastern Mountains and Piedmont – Version 2.0 SOIL Sampling Point: Profile Description: (Describe to the depth needed to document the indicator or confirm the absence of indicators.) Depth Matrix Redox Features (inches) Color (moist) % 0-6 2.5YR2.5/1 Color (moist) % Tvoe Loc Texture Remarks 100 6-18 10YR3/2 go 7.5YR3/4 20 D M SL 'Type: C=Concentration, D=Depletion, RM=Reduced Matrix, MS=Masked Sand Grains. 2Location: PL=Pore Lining, M=Matrix. Hydric Soil Indicators: Indicators for Problematic Hydric Soils': _ Histosol (Al) _ Dark Surface (S7) _ 2 cm Muck (A10) (MLRA 147) Histic Epipedon (A2) _ Polyvalue Below Surface (S8) (MLRA 147, 148) _ Coast Prairie Redox (A16) Black Histic (A3) _ Thin Dark Surface (S9) (MLRA 147, 148) (MLRA 147, 148) _ Hydrogen Sulfide (A4) _ Loamy Gleyed Matrix (F2) _ Piedmont Floodplain Soils (F19) _ Stratified Layers (A5) Depleted Matrix (F3) (MLRA 136, 147) 2 cm Muck (A10) (LRR N) _ Redox Dark Surface (F6) _ Very Shallow Dark Surface (TF12) Depleted Below Dark Surface (A11) _ Depleted Dark Surface (F7) _ Other (Explain in Remarks) Thick Dark Surface (Al2) _ Redox Depressions (F8) Sandy Mucky Mineral (S1) (LRR N, _ Iron -Manganese Masses (F12) (LRR N, MLRA 147, 148) MLRA 136) Sandy Gleyed Matrix (S4) _ Umbric Surface (F13) (MLRA 136, 122) 3Indicators of hydrophytic vegetation and Sandy Redox (S5) _ Piedmont Floodplain Soils (F19) (MLRA 148) wetland hydrology must be present, Stripped Matrix (S6) _ Red Parent Material (F21) (MLRA 127, 147) unless disturbed or problematic. Restrictive Layer (if observed): Type: Depth (inches): Remarks: Hydric Soil Present? Yes X No US Army Corps of Engineers Eastern Mountains and Piedmont — Version 2.0 NC DWQ Stream Identification Form Version 4.11 Date: 5 October 2016 Project/Site: Elkin Water Line: LIT Elkin Ck. Latitude: 36.260412 Evaluator: Ward Marotti County: Surry Longitude: -80.868305 Total Points: Stream Determination (circle one) Other Stream is at least intermittent 47.75 Ephemeral Intermittent erennia e.g. Quad Name: if >_ 19 or perennial if >_ 30* 2 3 A. Geomorphology (Subtotal = 26___) Absent Weak Moderate Strong 1a Continuity of channel bed and bank 0 1 2 1.5 2. Sinuosity of channel along thalweg 0 1 2 3 3. In -channel structure: ex. riffle -pool, step -pool, ripple -pool sequence 0 1 O2 3 4. Particle size of stream substrate 0 1 2 3 5. Active/relict floodplain 0 1 2 3 6. Depositional bars or benches 0 1 2 3 7. Recent alluvial deposits 0 1 2 3 8. Headcuts 0 1 1 2 3 9. Grade control 0 0.5 1 Notes: 10. Natural valley 0 11. Second or greater order channel No = 0 Yes 3 Sketch: a artificial ditches are not rated; see discussions in manual B. Hvdroloqv (Subtotal = 12 ) 12. Presence of Baseflow 0 1 2 03 13. Iron oxidizing bacteria 0 1 2 3 14. Leaf litter 1.5 1 0.5 0 15. Sediment on plants or debris 0 0.5 1 16. Organic debris lines or piles 0 0.5 1KLY 17. Soil -based evidence of high water table? 0 No = 0 Yes 3 C. Biology (Subtotal = 9.75 ) 18. Fibrous roots in streambed 3 2 1 0 19. Rooted upland plants in streambed 3 2 1 0 20. Macrobenthos (note diversity and abundance) 0 1 2 3 21. Aquatic Mollusks 0 1 2 3 22. Fish 0 0.5 1 1.5 23. Crayfish 0 1 1.5 24. Amphibians 0 0.5 1 1.5 25. Algae 0 1 1 1.5 26. Wetland plants in streambed FACW = O. U5 OBL = 1.5 Other = 0 *perennial streams may also be identified using other methods. See p. 35 of manual. Notes: Sketch: NC DWQ Stream Identification Form Version 4.11 Date: 5 October 2016 Project/Site: Elkin Water Line: Elkin Ck Latitude: 36.260412 Evaluator: Ward Marotti County: Surry Longitude: -80.868305 Total Points: Stream Determination (circle one) Other Stream is at /east intermittent 54.25 Ephemeral Intermittent erennia e.g. Quad Name: if> 19 or perennial if 2: 30' 2 3 A. Geomorphology (Subtotal =_26 ) Absent Weak Moderate Strong 1a Continuity of channel bed and bank 0 1 2 0 2. Sinuosity of channel along thalweg 0 1 2 3 3. In -channel structure: ex. riffle -pool, step -pool, ripple -pool sequence 0 1 2 30 4. Particle size of stream substrate 0 1 2 3 5. Active/relict floodplain 0 1 2 3 6. Depositional bars or benches 0 1 2 3 7. Recent alluvial deposits 0 1 2 3 8. Headcuts 0 1 2 3 9. Grade control 0 0.5 1 Notes: 10. Natural valley 0 0.5 1 11. Second or greater order channel No = 0 Yes 3 a artificial ditches are not rated; see discussions in manual B. Hvdroloqv (Subtotal = 11.5 ) 12. Presence of Baseflow 0 1 2 03 13. Iron oxidizing bacteria 0 1 2 3 14. Leaf litter 0 1 0.5 0 15. Sediment on plants or debris 0 0.5 1 16. Organic debris lines or piles 0 1 0.5 1 17. Soil -based evidence of high water table? 0 No = 0 Yes =U3 C. Biology (Subtotal = ) 18. Fibrous roots in streambed 3 2 1 0 19. Rooted upland plants in streambed 3 2 1 0 20. Macrobenthos (note diversity and abundance) 0 1 2 3 21. Aquatic Mollusks 0 1 2 3 22. Fish 0 0.5 1 23. Crayfish 0 0.5 1 24. Amphibians 0 0.5 Cl)1.5 25. Algae 0 0.5 1 1.5 26. Wetland plants in streambed FACW = O. U5 OBL = 1.5 Other = 0 'perennial streams may also be identified using other methods. See p. 35 of manual. Notes: Sketch: 06;'North Carolina Department of Public Safety Emergency Management Roy Cooper, Governor Erik A. Hooks, Secretary July 3, 2017 George H. Crater Planning Director P. O. Box 857 Elkin, NC 28621 Michael A. Sprayberry, Director RECEIVED 07/10/2017 W.K. Dickson & Co., Inc. Subject: No -Rise Certification for Elkin Raw Water System Improvements, Town of Elkin, Sunt' County, North Carolina Dear Mr. Crater: The North Carolina Department of Public Safety Division of Emergency Management Risk Management National Flood Insurance Program (NCNFIP) staff has reviewed the hydraulic model and report for the Elkin Raw Water System improvements along Elkin Creek in the Town of Elkin, Surry County. The certification is dated June 8, 2017. It was received in this office on June 14, 2017. As I understand from the documents provided, the applicant is proposing to perform stream stabilization work in Elkin Creek to protect existing and proposed raw water infrastructure in the Town. of Elkin. The NCNFIP cannot concur with the No -Rise Certification based on the information in the report provided. In accordance with the FEMA Region IV "Procedures for No -impact Certification For Proposed Development in Regulatory Floodways", the NCNFIP review] identified the following issues that will need to be resolved prior to concurrence: 1. The modeling shows grading at cross-section 9596, but the plans do not show grading that far downstream. Also, since 9596 is the upstream bounding cross-section for C C Camp Road, changing this cross-section will change the internal cross-section for the bridge model. The plans do not indicate any proposed work under the C C Camp Road bridge. 2. If the No -Rise is contingent on the cross-section modification at 9596, including internal to the bridge, then work through the cross-section needs to be included on the topographic work map and plans. If not, the model should be adjusted. MAILING ADDRESS: 4218 Mail Service Center Raleigh NC 27699-4218 www.ncem_org r An Equal Gpportuntly Employer GTM OFFICE LOCATION: 4105 Reedy Creek Road Raleigh, NC 27607 Telephone: (919) 825-2341 Far (919) 825-0408 George Crater Page 2 of 2 July 3, 2017 If you have any questions or concerns with the items herein, please contact me at (.919) 825- 2300, by email at dan.brubaker@ncdps.g_ov or at the address shown on the footer of this document. Sincerely, John D. Brubaker, P.E., CFM NFIP Coordinator Risk Management cc: Milton Carpenter, Central Area Planner WK Dickson & Co., Inc. .,,Attn: Ebony Hagans, P.E. 720 Corporate Center Drive Raleigh. NC 27607 File FINDING OF NO SIGNIFICANT IMPACT AND ENVIRONMENTAL ASSESSMENT TOWN OF ELHIN RAW WATER SYSTEM EMPROVEMENrS RESPONSIBLE AGENCY: NORTH CAROLINA DEPARTMENT OF ENVIRONMENTAL QUALITY CONTACT: SETH ROBERTSON, P.E., CHIEF STATE REVOLVING FUND SECTION DIVISION OF WATER INFRASTRUCTURE 1633 MAIL. SERVICE CENTER RALEIGH, NORTH CAROLINA 27699-1633 (919) 707-9175 May 1, 2017 (This page.intendonally left blank) 0 I FINDING OF NO SIGNIFICANT IMPACT Article I, Chapter 113A of the North Carolina General Statutes requires an action to be subject to the requirements of the North Carolina Environmenlai Policy Act (NCEPA) if it involves the expenditure of public funds and if a potential impact is anticipated to the environment. The project has been evaluated for compliance with the NCEPA and is determined to be a major agency action, which will affect the environment. Project AppHcant: Project Description: Project Number. Project Cost: Drinking water State Revolving Loin F%md: Lord Faods: Town of Elkin, North Carolina The project will include the following improvements to the Town's drinking water infiastiucture: (1) restoration of approximately 700 linear feet (11) of stream bank; (2) 3,9001.f. of new IT' water main to extend the existing emergency raw water line to the Town's existing reservoir, (3) improvements to the existing reservoir outlet structure; and (4) replacement of existing submersible raw water pumps with three new vertical habine pumps, electrical controls, valves, and pump intake sediment scour system. WIF 1905 $1,724,152 $1,690,345 $33,807 The review process indicated that significant adverse environmental impacts should not occur if mitigative measures are implemented, and an environmental impact statement will not be requ ked The decision was based on information in the Engineering Report and reviews by governmental agencies. The attached Environmental Assessment supports this action and outlines mitigative measures that must be followed This Finding of No Significant Impact (FONSI) completes the environmental review record, which is available for inspection at the State Clearinghouse. No administrative action will be taken on the proposed project for at least 30 days after notification that the FONSI has been published in the North Carolina Environmental Bulletin. Sincerely, Seth Robertson, P.E., Chief State Revolving Fund Section Division of water Infrastructure ,, v; ENVIRONMENTAL ASSESSMENT A. Proposed Facilities and Actions The proposed project will make improvements to the Town of Elkin's raw water supply line between the Town's reservoir and water treatment plant (WT?), the emergency raw water line from the Yadkin River to the WTP, and the reservoir water intake pumps and outlet strictures. Approximately 7.00 linear feet (11) of stream bank will be restored and stabilized along Elkin Creek in endangered areas of the existing 24" raw water line. The existing emergency raw water line, which currently runs from the Yadkin River directly to the WTP, will be extended with 3,9001.f. of 12" line to connect to the existing influent supply line going into the reservoir to allow for pre -settling of the raw water prior to treatment. The existing submersible raw water intake pumps will be replaced with three new vertical turbine pumps, electrical controls, valves, and pump intake sediment scour system. At the outlet structure in the reservoir, sluice gates will be replaced to facilitate optional water withdrawal from the reservoir at different levels. F n�ding status: The estimated total cost for the project is $1,724,152. The Town is applying for a Clean Water State Revolving Fund (CWSRF) loan of $1,690,345. The loan fee of $33,807 will be covered by local funds. B. Exli tEnvi onment Tow 'ra by and Soils. Sury County is located in the Piedmont Physiographical Province. Elevations in the project area range from approximately 970 feet to 1,000 feet above mean sea level. The project area is located within the valley created by Elkin Creek and is in the Metagraywacke, Amphibolite, and Kyanite Schist geologic unit composed primarily of metasedimentary rock and amphibolite. Soils in the project area include the occasionally flooded Colvard and Suches complex with zero to three percent sloes, very rocky Devotion-Rhodhiss-Bannertown complex with forty to ninety-five percent slopes, moderately eroded Fairview Sandy Clay Loam with fifteen to twenty- five percent slopes, and stony Woolwine-Fairview-Westfield complex with fifteen to twenty-five percent slopes. Surface Water. The project area is located in the Upper Yadkin River Sub -Basin (HUC 03040101). Elkin Creek into and including the Elkin Reservoir is designated as WS -II, HQW, and CA, and it is designated Class C below the reservoir. Water Suvoly. The Town provides drinking water drawn from Elkin Creek immediately above and within the project area. C. Ex sdue Wastewater FacMes The Town's water system has 2,064 service connections, approximately 75% of which are residential meters. The Town also supplies wholesale water to Sung County and the Town of Ronda The Town's WTP has a permitted capacity of 3.0 MGD. The water system also includes a raw water intake pumping station on Elkin Creek; a 63 million gallon reservoir with influent and intake stiuchm; approximately 4,000 11 of 24" raw water supply piping for conveyance of raw water from the reservoir to the WTP; an emergency 12" raw water line from the Yadkin River to the WTP for standby service during drought conditions; a finished water distribution system with a 1 million gallon clearwell storage and elevated tank storage in each of the three pressure zones providing a total of 2.9 million gallons of storage; and approximately 55 miles of water mains ranging from 1" to 8" of asbestos cement, PVC, and cast iron for distribution of finished drinking water. Original portions of the water system serving the downtown area were installed in the 1920s. The raw water pumping station, reservoir, raw water supply line, and WTP were constructed in the mid-1960s with the emergency line added in 2004. The pumps at the raw water intake pump station were replaced in the mid-1980s. D. Need for Proposed Facilities and Accton Erosion of the stream bank has resulted in exposure and undermining of sections of the raw water supply line along Elkin Creek, which puts the line at risk of compromise. The existing pumps at the raw water intake pump station have operational, maintenance, and performance issues, and the valves and piping are showing signs of severe corrosion. The reservoir outlet shucture sluice gates for changing the intake water level are inoperable. The emergency raw water line from the Yadkin River frequently has turbidity levels that exceed the treatment capabilities of the plant without pre -settling. The project will address these problems to ensure the Town's ability to continue to provide safe water. E. Alternatives Analysis No -Action Alternative: The No -Action Alternative would leave the raw water subject to continued undermining, potentially resulting in failure of the line, with catastrophic consequences to the Town's ability to provide safe water to the community. Alternative 1— Complete Replacement and Relocation of 4.000 l.f. of the Raw Water Line: This alternative would replace approximately 4,0001.f. of the existing 24" cast iron raw water supply line with ductile iron pipe and relocating the line away from the areas subject to erosion and undermining. Ibis alternative would also include a 3,90011 extension of the emergency raw water line from the Yadkin River to the reservoir to allow for pre -settling, replacement of raw water intake pumps, controls, and valves, and replacement of the reservoir outlet sluice gates. This alternative was rejected because of the environmental impact that would result from right of way clearing and six stream crossings to relocate the raw water line and because of the high capital and present worth costs. 2 Alternative 2 — Replacement and Relocation of 1,7001.f. of the Raw Water Line: This alternative is similar to Alternative 1 but would replace and relocate a shorter segment of the water line (1,7001.f.) that is most at -risk of failure. lace Alternative 1, this alternative would also include the extension of the emergency raw water line, new intake pumps, and replacement of the reservoir outlet sluice gates. The proposed alignment of this alternative presented topography constraints to permit gravity flow, construction constraints associated with the Highway 286 bridge, and environmental impacts associated with clearing and three stream crossings to relocate the raw water line. This alternative was rejected because of these constraints, environmental impacts, and higher capital and present worth costs. Alternative 3 — New 4.000 U. Raw Water Line and Conversion of Existing Line: This alternative would construct a new 4,000 Lf. ductile iron raw water line and convert the existing cast iron raw water line into an emergency raw water line by reversing the flow direction and connections to the existing emergency raw water line from the Yadkin River. This alternative would include stream bank restoration, new intake pumps, and replacement of reservoir outlet sluice gates. This altemative has similar environmental impacts as the Preferred Alternative including four stream crossings and clearing for the new line; however, this alternative was rejected due to higher capital and present worth costs. Alternative 4 — Continued use of &jgfing Raw Water Line: This alternative will include restoration of approximately 7001.E of stream bank in areas of exposed pipe and installation of J -hook boulder in the stream to divert water and stabilize the stream bank in areas at risk of erosion to allow continued use of the existing raw water line. Lilce Alternatives 1 and 2, this alternative will also include the. extension of the emergency raw water line, new intake pumps, and replacement of the reservoir outlet sluice gates. This altemative is preferred because of the favorable environmental impacts achieved by stabilizing the sheam bank to avoid the construction impacts associated with relocating the line and lower capital and present worth costs. F. Environmental Conseauenaes and NMijmdve Measures TopogWI and Soils: Some temporary changes in topography are expected from construction activities to stabilize the stream bank, the emergency raw water line extension, replacement of existing sluice gates, and installation of the new raw water pumps. These construction areas will be returned to pre -construction elevation and slope upon completion of construction. Minor permanent changes to topography are anticipated from installation of a j -hook to redirect flows away from the existing raw water line. Permanent impaM to the 100 -year floodplain or floodway are not expected. A no -rise study will be conducted and if the results indicate that the initial design will impact the Elkin Creek floodway, design modifications will be implemented to offset impacts to obtain a No -Rise Certification. Applicable floodplain development permits will be obtained from the Town of Elkin. 3 Land Use: No permanent direct impacts to land use are anticipated. Temporary impacts to. Town greenways will occur during construction, but the construction site will be restored to existing conditions and use for greenways and trails following construction. Wetlands: Construction of the emergency raw water line will include two wetlands dossing with less than 0.10 acre of temporary impacts. Disturbed areas will be returned to original slope and contour and will be replanted with native vegetation. Construction will be in accordance with a NCDENR approved and county -approved erosion and sedimentation control plan and other provisions of the Sedimentation Pollution Control Act of 1973 to minimize impacts from erosion and sedimentation. The U.S. Army Corps of Engineers was consulted and did not object to the project (August 11, 2016). 1mMortant Farmlands: There will be no net loss of important farmlands. Silt fences will be used during construction, tion, and following consmiction, soil will be backfilled and returned to preconstruction slope and contour. Land that will be disturbed is not currently in agricultural use. Public Lands and Scenic. Recreational. and State Natural Areas: There will be no negative permanent impacts to public lands or scenic, recreational, or state natural areas. The project will improve long term water quality and aquatic habitat in Elkin Creek, which will benefit area 1adm• Cultural Resources: Ina memorandum dated August 29, 2016, (No. ER 16-1400, the North Carolina State Historic Preservation Office (SIPO) stated that no historic resources are likely to be affected by the project. Air QMdftr. Temporary impacts to ait quality including increased dust and vehicle exhaust emissions may occur during construction activities. Proper vehicle maintenance and emission control devices will reduce these impacts. No pert impacts are expected. Noise Levels: There will be a temporary increase in noise related to construction equipment during weekday working hours. Weekend and after-hours construction work is not anticipated. There will be no permanent impacts to noise levels once construction is complete. Water Resources: There is the potential for temporary impacts due to erosion and sedimentation during construction, including four stream crossings. Two crossings will be open M one will be jack and bore, and one will be installed in existing fill over an existing culvert. Stream bank stabilization will utilize natural channel design methods to restore the banks to their pre -erosion condition and J -hooks to divert flow away from sensitive areas of the streambank. To minimize construction impacts; all construction will be in accordance with a NCDENR approved and county -approved erosion and sedimentation control plan and other provisions of the Sedimentation Pollution Control Act of 1973. Long term impacts will be positive with the restoration and stabilization of the stream banks resulting in improved water quality and aquatic habitat in Elkin Creek. Forest Resources: Impacts to forest resources are not expected to be significant. Much of the alignment will use maintained greenways and easements. Where clearing is required, permanently maintained corridor widths will be limited to approximately 15 feet, and areas that do not require maintenance will be allowed to return to their natural conditions following construction. Shellfish or Fish and Their Habitats: Net impacts to shellfish, fish, and their habitats are expected to be positive. Construction impacts will be minimized through adherence to a NCDENR-approved and county -approved erosion and sedimentation control plan and other provisions of the Sedimentation Pollution Control Act of 1973. Restoration and stabilization of the stream bank will improve water quality and aquatic habitat in Elkin Creek. Wildlife and Natural Vel: Impacts to wildlife and natural vegetation will be temporary due to construction activities. Much of the construction will take place within or adjacent to existing maintained rights of way and trails with very limited, temporary impacts to habitats. Introduction of Toxic Substances: Introduction of toxic substances from construction activities is possible from vehicle fluids. Such impacts will be minimized by proper vehicle maintenance and proper collection of and disposal of fluids. The U.S. Fish and Wildlife Service reviewed the proposed project and concluded that the requiremeafs of Section 7(aX2) of the Endangered Species Act have been fulfilled (September 15, 2015, Log No. 4246-382). The North Carolina Wildlife Resources Commission, Natural Heritage Program, and DWR Winston-Salem Regional Office, and U.S. Army Corps of Engineers concur with the proposed project. The North Carolina Department of Cultural and Natural Resources is not aware of any properties of architectural, historical, or archaeological significance that would be affected by the project. G. Public Parddnadon, Sources Consulted A public meeting was held on February 13, 2017 including a presentation about the meeting. There were no objections to the project. The current user charge for a typical customer is $73.75 per month for 5,000 gallons for sewer and water combined The proposed project is expected to cause an increase of $10.06 ger month for a total of $83.81. Sources consulted about this project for information or concurrence included 1) Town of Elkin 2) North Carolina Department of Environmental Quality -Wildlife Resources Commission -Natural Heritage Program -DEQ Winston-Salem Regional Office -Division of Air Quality -Division of Water Resources -Division of Forest Resources -Division of Environmental Assistance and Customer Service -Division of Waste Management 5 n � i 3) North Carolina Department of Cultural and Natural Resources 4) North Carolina State Clearinghouse 5) North Carolina Department of Public Safety 6) U.S. Fish and Wildlife Service 7) U.S. Army Corps of Engineers 6 Elkin Creek Raw Water Intake Legend Water -Treatment Plant Water Booster Pump Station Water7ank aMlerintake Proposed Emergency Raw Water Line Fact: Existing Raw Water Lines — — Existing water Lines -•---- Stream/River — Roads Boundary Raw Water Intake Reservoir Proposed Stream Bank Restoration Proposed 3,900 LF 12" Emergency Raw Water Line Extension Raw Water Line I'mprove,m�e�ni is Figure HA AIternati''ve 4 Elkin, N July, 2014 1LO> t WCalCI'SO1-.1; %.r Y:nn:.".: Existing 12" Emergency Raw Water Line �eM la�]- a M sw 7�0 v ELKIN RAW WATER SYSTEM LEGEND PROPERTY BOUNDARY —R/W— RIGHT—OF—WAY Sheat Number —SeACK— SETBACK — - -PE— PERMANENT EASEMENT — PE — TcE TEMP. CONSTRUCTION EASEMENT —TCE— G4 LIMITS OF DISTURBANCE —L00- --srr— PERMANENT DRAINAGE EASEMENT —PDE - 100— INDEX CONTOUR —1- - — — — INTERVAL CONTOUR 96 c — — STORM DRAINAGE PIPE RESERVOIR INTAKE STRUCTURE PLAN 6 SECTIONS 0m STORM DRAINAGE STRUCTURE CIS Q STORM DRAINAGE MANHOLE E1.1 — - HYDROLOGIC FEATURE - -WBD— WETLANDS BOUNDARY EIA X— FENCE —X — — — - — — — BOTTOM OF BANK —BB— ---Te--- TOP OF BANK —TB- - DITCH LINE PLAN AND PROFILE - STA 30+00 TO STA. 36+87 — — — - — — — OVERHEAD WIRE —OW— I! POWER POLE f j� LIGHT POLE x F GUY WIRE C3.2 .irrrwwrwr. SHRUB LINE DETAILS -� TREE LINE — — — - — — — WATER LINE —W— % GATE VALVE N AIR RELEASE VALVE �- FIRE HYDRANT -"rT PERMANENT DIVERSION DITCH �-- TEMPORARY DIVERSION DITCH TEMPORARY SILT SILT FENCE j' TREE O SHRUB 0 SOIL BORE e1 OO ear x SPOT ELEVATION ELEV X CHECK DAM INLET PROTECTION RIP—RAP TEMPORARY SEEDING rs PERMANENT SEEDING PS TEMPORARY STREAM CROSSING IMPROVEMENTS FOR THE TOWN OF ELKIN NORTH CAROLINA JUNE 2017 DWI DWSRF # WIF-1905 LOCATION MAP NOT TO SCALE Note: Labels indicating permit locations were added after plans were sealed. JUL 2 7 2017 10 NOTICE TO CONTRACTOR 1) THE CONTRACTOR SHALL FIELD VERIFY THE ONSITE T.B.M. W( EXISTING ELEVATIONS. THE CONTRACTOR SHALL IMMEDIATELY CONTACT W.K. DICKSON 8 CO., INC. @ 828-327-6911 IF ANY DISCREPANCIES ARE FOUND IN ELEVATIONS SHOWN. SURVEY INFORMATION DATED NOVEMBER AND DECEMBER 2016 PROVIDED BY FOOTHILLS FORESTRY AND SURVEYING. 1106 NORTH BRIDGE STREET ELKIN, NORTH CAROLINA 285210 TELEPHONE (336) 835-5882. 2) PRIOR TO CONSTRUCTION, DIGGING, OR EXCAVATION THE CONTRACTOR IS RESPONSIBLE FOR LOCATING ALL UNDERGROUND UTILITIES (PUBLIC OR PRIVATE) THAT MAY EXIST AND CROSS THROUGH THE AREA(S) OF CONSTRUCTION, WHETHER INDICATED ON THE PLANS OR NOT. CALL "811"A MINIMUM OF 72 HOURS PRIOR TO DIGGING OR EXCAVATING. REPAIRS TO ANY UTILITY DAMAGED RESULTING FROM CONSTRUCTION ACTIVITIES SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR. � 811 VKnow what's below. Call before you dig DD CKSON uni+ inlresVudure —0- 4014TH nsWtents4014TH STREET SW HICKORY, NORTH CAROLINA 28602 0)82832711 0)82&327-9164 WWW.WKDICKSON.COM NC LICENSE NO.F-0374 aaH umWn� �. �o •' ``c �y �Iy3�l% PNOFESSION&rEAL IIIIIIII� 13 U IMO rn t— Z LU 2 W CC Z IL J �O CC W U D I } F— Q p Z 1 W I Q Z J I W Q z Y I w W z ¢ F3 a o PROD. MGR.: CRF I DESIGN BY: CRF DRAWN BY: CH/RJL PROD. DATE: I JUNE 2017 DRAWING NUMBER: G1 OF 29 i i WKD PROJ. NO.: 20160049.02.HI Sheet List Table Sheat Number Sheet Title GENERAL G1 COVER G2 GENERAL ACCESS LOCATION PLAN G3 GENERAL EROSION CONTROL DETAILS G4 GENERAL EROSION CONTROL DETAILS DIVISION 1 -RAW WATER INTAKE AND RESERVOIR INTAKE IMPROVEMENTS C1.1 RESERVOIR SITE PLAN C1.2 DEMOLITION PLAN C1.3 PROPOSED RESERVOIR PUMP STATION PLAN AND SECTION 01.4 RESERVOIR PUMP STATION PLAN AND SECTION - ELEV 931.0' Cls RESERVOIR PUMP STATION PLAN - ELEV 925.D CIA RESERVOIR INTAKE STRUCTURE PLAN 6 SECTIONS C1.7 RESERVOIR PUMP STATION FLUSHING SYSTEM CIS RESERVOIR PUMP STATION FLUSHING SYSTEM DETAILS DIVISION 1 -RAW WATER INTAKE AND RESERVOIR INTAKE IMPROVEMENTS: ELECTRICAL E1.1 ELECTRICAL SYMBOLS AND DETAILS 151.2 PUMP STATION ELECTRICAL PLAN AND DIAGRAMS E1.3 ELECTRICAL DETAILS EIA ELECTRICAL PLANS AND ELEVATIONS-DEMOURION ElZ EQUIPMENT ELEVATIONS AND DETAILS DIVISION 2 -EMERGENCY RAW WATER UNE EXTENSION C2.1 PLAN AND PROFILE- STA. 0+00 TO STA. 10+•00 C2.2 PLAN AND PROFILE - STA 10'00 TO STA 20~00 C2.3 C2A PLAN AND PROFILE - STA 30+00 TO STA. 36+87 C2.5 RAW WATER UNE DETAILS C2.6 RAW WATER LINE DETAILS C2.7 RAW WATER LINE DETAILS C2.8 STREAM CROSSING DETAILS DIVISION 3 -EX. RAW WL PROTECTION WITH STREAM BANK STABILVATON C3.1 CREEK RESTORATION - PLAN AND PROFILE C3.2 TRIBUTARY RELOCATION -NEW CHANNEL 03,3 DETAILS C3.4 DETAILS NOTICE TO CONTRACTOR 1) THE CONTRACTOR SHALL FIELD VERIFY THE ONSITE T.B.M. W( EXISTING ELEVATIONS. THE CONTRACTOR SHALL IMMEDIATELY CONTACT W.K. DICKSON 8 CO., INC. @ 828-327-6911 IF ANY DISCREPANCIES ARE FOUND IN ELEVATIONS SHOWN. SURVEY INFORMATION DATED NOVEMBER AND DECEMBER 2016 PROVIDED BY FOOTHILLS FORESTRY AND SURVEYING. 1106 NORTH BRIDGE STREET ELKIN, NORTH CAROLINA 285210 TELEPHONE (336) 835-5882. 2) PRIOR TO CONSTRUCTION, DIGGING, OR EXCAVATION THE CONTRACTOR IS RESPONSIBLE FOR LOCATING ALL UNDERGROUND UTILITIES (PUBLIC OR PRIVATE) THAT MAY EXIST AND CROSS THROUGH THE AREA(S) OF CONSTRUCTION, WHETHER INDICATED ON THE PLANS OR NOT. CALL "811"A MINIMUM OF 72 HOURS PRIOR TO DIGGING OR EXCAVATING. REPAIRS TO ANY UTILITY DAMAGED RESULTING FROM CONSTRUCTION ACTIVITIES SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR. � 811 VKnow what's below. Call before you dig DD CKSON uni+ inlresVudure —0- 4014TH nsWtents4014TH STREET SW HICKORY, NORTH CAROLINA 28602 0)82832711 0)82&327-9164 WWW.WKDICKSON.COM NC LICENSE NO.F-0374 aaH umWn� �. �o •' ``c �y �Iy3�l% PNOFESSION&rEAL IIIIIIII� 13 U IMO rn t— Z LU 2 W CC Z IL J �O CC W U D I } F— Q p Z 1 W I Q Z J I W Q z Y I w W z ¢ F3 a o PROD. MGR.: CRF I DESIGN BY: CRF DRAWN BY: CH/RJL PROD. DATE: I JUNE 2017 DRAWING NUMBER: G1 OF 29 i i WKD PROJ. NO.: 20160049.02.HI 0 0 P STATION OECgTURgV� ROJECT ACCESS POINT #2 (GREENWAY ACCESS EASEMENT p�Eas�,TN/C FROM OLD MILL LN) - PROJECT ACCESS ' POINT #1 1 6PSPN�N\��0� o� (DIRT ROAD TO z pL 2 RESERVOIR FROM m �' ' GG ' LYLES'ST COLLINS RD) OLD MILL LN �. ... ......... `L r� RAW WATER LINE it m /- PARTRIDGE W. ROBIN ST w COX AVE. a TEMP. CONSTRUCTIONNC p;I LOOP T E..HIG NO AVE. �. ;I @ WATERTREATMENT PLANT,1 �paA wrP SEE DETAIL DWG. C2.8 SO� ST �CF ***NOTICE*** BRIDGE CLEARANCE r- % Pao . . 26s wi Z �� < oma ELKIN RESERV IR IN Looe i'�~� RESERVOIR IMPROVEMENTS �S _37 o� ELKIN RECREATION CENTER, REAM BANK . .@ °�. o SEE DETAIL DWG. C2.8 STABILIZATION • PROJECT ACCESS m �. v \�\�y� °A���o 4*04- TEMP. CONSTRUCTION ENTRANCE j°GREENWAY ACCESS FROM OLD POINT#3 (FROM I oR �o a 4* @ GENERAL ACCESS LOCATION PLAN SCALE: 1" = 500' NOT TO SCALE 500 0 500 loon e SCALE: 1"=500 u WDICKSON inhashucture consultants 401 4TH STREET SW HICKORY, NORTH CAROLINA 28802 (t)828327-6911 (9828327-9164 WWW.WKDICKSON.COM NO LICENSE NO.F-0374 °1PN n unHq"`N,. PROFESSIONA SE L Illlllllm cc 0 Q O � a Wir j o w x H Z w 2 � Z a d J Z 20 O Q W U p U) CC 0 U crc wZ a Qz CC J Z �w LU cr z z J ~ �i w z cc o PROJ. MGR.: CRF DESIGN BY: CRF DRAWN BY: CHIRJL PROJ. DATE: JUNE 2017 DRAWING NUMBER: G2 OF 29 WKD PROJ. NO.: 20160049.00.H1 SEE DETAIL DWG. C2.8 6PSPN�N\��0� o z pL \� � °I°LoLVLN, �Esl o = OLD MILL LN MERGENCY 03 LU `L r� RAW WATER LINE it m /- PARTRIDGE LN ° z TEMP. CONSTRUCTIONNC @ WATERTREATMENT PLANT,1 �1 wrP SEE DETAIL DWG. C2.8 as o; Y� ***NOTICE*** BRIDGE CLEARANCE 26s wi 11'-0" MAXIMUM < oma TEMP. ONSTRU O EN RAN i'�~� y _37 o� ELKIN RECREATION CENTER, . . .@ °�. o SEE DETAIL DWG. C2.8 r� PROJECT ACCESS m �. ELKIN y RECREATION POINT#3 (FROM - CENTER J LK SP RST ELKIN RECREATION i 5� _ CENTER PARKING MEMORIAL i . . . OT TO GREENWAY) PARK ��. f ... . . . GENERAL ACCESS LOCATION PLAN SCALE: 1" = 500' NOT TO SCALE 500 0 500 loon e SCALE: 1"=500 u WDICKSON inhashucture consultants 401 4TH STREET SW HICKORY, NORTH CAROLINA 28802 (t)828327-6911 (9828327-9164 WWW.WKDICKSON.COM NO LICENSE NO.F-0374 °1PN n unHq"`N,. PROFESSIONA SE L Illlllllm cc 0 Q O � a Wir j o w x H Z w 2 � Z a d J Z 20 O Q W U p U) CC 0 U crc wZ a Qz CC J Z �w LU cr z z J ~ �i w z cc o PROJ. MGR.: CRF DESIGN BY: CRF DRAWN BY: CHIRJL PROJ. DATE: JUNE 2017 DRAWING NUMBER: G2 OF 29 WKD PROJ. NO.: 20160049.00.H1 STEEL POST FABRIC /-FILTER IIIER. WIDTH �T CLASS A STONE 1 FT HEIGHT, i FT. BEYOND EDGES STEEL POST GRADE (MAX.) 8 FT. MAX. SPACING WITH WIRE SUPPORT FENCE FiL= 9' MAX (RE STORAGE 19 GAUGE HARDWARE CLOTH W/ 1/4' MESH OPENING HEIGHT QJGE HARDWARE CLOTI 4' MESH OPENING RUN OFF NOTES: EROSION CONTROL MATTING MUST - � CONTROL MEET OR EXCEED THE FOLLOWING REQUIREMENTS: 1 PCT AND REPAIR FENCE R H STORM EVENT AND REMOVE .INS E AFTER EACH WASHED STONE ON UPSTREAM FACE 2OEM, _ 8, SEDIMENT WHEN DEPOSITS REACH 3D% OF FENCE HEIGHT. 2. REMOVED SEDIMENT SHALL BE DEPOSITED TO AN AREA THAT WILL NOT I�I�yy1I z 1I ' I I CONTRIBUTE SEDIMENT OFFSITE AND CAN BE PERMANENTLY STABILIZED. 3. SILT FENCE SHALL BE PLACED ON SLOPE CONTOURS TO MAXIMIZE PONDING y 1 -1 �L, EFFICIENCY. L ROCK SECTION DETAIL TRENCH WITH GRAVEL SILT FENCE - WIRE & STONE REINFORCED OUTLET NOT TO SCALE WIRE FABRIC FILTER FABRIC ;TART NEW ROLLNC m MOT, OVERW �II' FIGURE 2 FIGURE 1 INTERMITTENT CHECK • ANCHORINTITIAL BEGINING OF ROLL upsTREA�­�ST— AT TRENCH STAKE AT EMBANWENT � VINTERVALS Eil I" "�V� � GROXISTING UND 3 N LINE D AREA GE 4'� ANCHOR FABRIC ASSHOWN F`0� BOTTOM SECTION STRANTOP AND GA., TY0 VARIABLE AS DIRECTED BY THE ENGINEANCHOR B' MAXI ' A A OA, TVP. STAY WIRES, ANCHOR WIRE FABRIC TO 12'SPACING STEEL POST WITH MIN, 4 MIN. 14 GA FENCING STAPLES PER POST CATCH BASIN 19 GAUGE HARDWARE CLOTH PLAN W/1/4'MESH OPENING. rn N SECURELY STEEL POST 4' MAX SPACING BETWEEN POSTS. ANCHOR _ _ FABRIC TO z N0.5 WASHED w WIRE WITH f / FILTER STONE Z 2 lo�WIRE TIES FL--O-W� Fes- LOW MAX WIRE FILTER FABRIC TO BE �.y� 4 F FABRIC MESH POLYPROPYLENE NYLON, TIT g OPENING SIZE POLYESTER OR POLY- N w LI = 36 SQ. IN. ETHYLENE YARN OF LJ 34' ANCHOR FABRIC MESH MANUFACTURER TO BE IN 16' OF NO, 5 APPROVED BY ENGINEER WASHED STONE CI C\/ATIlIAI NOTES: 1. THE CONTRACTOR SHALL MAINTAIN ALL SILT FENCING BY REMOVING AND DISPOSING OF SILT ACCUMULATIONS AS DIRECTED BY THE ENGINEER. FILTER FABRIC SHALL BE REPLACED WHEN IT HAS DETERIORATED TO SUCH EXTENT THAT IT REDUCES THE EFFECTIVENESS OF THE SILT FENCE. 2. FILTER FABRIC SHALL HAVE A MINIMUM TENSILE STRENGTH (0 20% MAX. ELONGATION) OF 3018sILIN. IN.. WIRE FABRIC REQUIRED. 3. IF EXTRA STRENGTH FABRIC IS UTILIZED (MIN. TENSILE STRENGTH = 50 IDs/LJN. IN. @ MAX. 20% ELONGATION), WIRE FABRIC IS OPTIONAL, MAXIMUM POST SPACING = 6 FEET. 4. POSTS SHALL BE 1.33 blLF STEEL UNLESS OTHERWISE APPROVED BY ENGINEER. TEMPORARY SILT FENCE NOT TO SCALE SECTION A -A NOTES: i. SEDIMENT SHALL BE REMOVED AND TRAP RESTORED TO ITS ORIGINAL DIMENSIONS WHEN THE SEDIMENT HAS ACCUMULATED TO IM THE DESIGN DEPTH OF THE TRAP. REMOVED SEDIMENT SHALL BE DEPOSITED IN A SUITABLE AREA AND IN SUCH A MANNER THAT IT WILL NOT ERODE. 2. THE STRUCTURE SHALL BE INSPECTED AFTER EACH RAIN AND REPAIRS MADE AS NEEDED. 3. CONSTRUCTION OPERATIONS SHALL BE CARRIED OUT IN SUCH A MANNER THAT EROSION AND WATER POLLUTION SHALL BE MINIMIZED. 4. THE SEDIMENT TRAP SHALL BE REMOVED AND THE AREA STABILIZED WHEN THE REMAINING DRAINAGE AREA HAS BEEN PROPERLY STABILIZED. TEMPORARY CATCH BASIN SEDIMENT TRAP NOT TO SCALE ADO! INSTALLATION NOTES SITE PREPARATION GRADE AND COMPACT AREA. REMOVE ALL ROCKS, CLODS, VEGETATION, AND OBSTRUCTIONS SO THAT MATTING WILL HAVE DIRECT CONTACT WITH THE SOIL PREPARE SEEDBED BY LOOSENING 3 TO 4 INCHES OF TOPSOIL ABOVE FINAL GRADE TEST SOILS FOR ANY NUTRIENT DEFICIENCIES AND SUBMIT SOIL TEST RESULTS TO THE CITY. APPLY ANY TREATMENT SUCH AS UME OR FERTILIZERS TO THE SOIL IF NEEDED. DO NOT MULCH AREAS WHERE MAT IS TO BE INSTALLED. SEEDING APPLY SEED TO SOIL BEFORE PLACING MATTING. WHEN USING PERMANENT LINER, APPLY ADDITIONAL SEED AFTER INSTALLATION AND FILL MAT WITH SOIL INSTALLATION OVERLAP ADJACENT MATS 3' AND ANCHOR EVERY 18' ACROSS THE OVERLAP. THE HIGHER ELEVATION MAT SHOULD BE PLACED OVER THE LOWER ELEVATION MAT_ EDGES SHOULD BE SHINGLED AWAY FROM THE FLOW OF WATER. LAY MAT LOOSE TO ALLOW CONTACT WITH SOIL. DO NOT STRETCH TIGHT. ANCHOR MAT USING BIODEGRADABLE STAKES OR PINS. EXCAVATE INITIAL ANCHOR TRENCH 1rW ACROSS THE EMBANKMENT AT THE LOWER END OF THE PROJECT AS SHOWN ON SHEET 5. SEE FIGURE 1 FOR INITIAL ANCHOR TRENCH. PLACE 6' x 6' CHECK SLOTS AT 30' INTERVALS ALONG THE EMBANKMENT AND WEIR. SEE FIGURE 2. CUT 4' x 4' TRENCH ALONG TOP OF BANK FOR MAT TERMINATION. EXTEND MAT TOTE EDGE OF THE ASPHALT OR 2 TO 3 FEET ABOVE THE CREST IF POSSIBLE. BEGINNING AT THE CENTER OF THE EMBANKMENT AT THE DOWNSTREAM END OF THE AREA TO BE LINED, PLACE THE END OF THE ROLL IN ANCHOR TRENCH AND SECURE WITH BIODEGRADABLE STAKES OR PINS. SEE FIGURE 1. PLACE ADJACENT ROLLS IN THE ANCHOR TRENCH WITH A MINIMUM OF W OVERLAP. SECURE WITH BIODEGRADABLE STAKES OR PINES. BACKFILL ANCHOR TRENCH, AND COMPACT SOIL UNROLL MAT OVER COMPACTED ANCHOR TRENCH, STOP AT NEXT CHECK SLOT OR TERMINAL ANCHOR UNROLL ADJACENT ROLLS IN SAME MANNER, WITH A MINIMUM OF 3' OF OVERLAP. STAPLE AT 18' INTERVALS ALONG OVERLAP. FOLD AND SECURE MAT ROLLS TIGHTLY INTO CHECK SLOTS. LAY MAT N CHECK SLOT, FOLD BACK AGAINST ITSELF, ANCHOR THROUGH BOTH LAYERS, BACKFILL AND COMPACT SOIL. CONTINUE ROLLING MAP UPSTREAM. SEE FIGURE 2. BEGIN NEW ROLLS IN CHECK SLOT, AND OVERLAP ENDS MpBMUM OF 1'. SEE FIGURE 4 FOR TERMINATION AT UPSTREAM END. MAINTENANCE INSPECT ROLLED EROSION CONTROL PRODUCTS AT LEAST WEEKLY AND AFTER EACH SIGNIFICANT (12 INCH OR GREATER) RAIN FALL EVENT REPAIR IMMEDIATELY) GOOD CONTACT WITH THE GROUND MUST BE MAINTAINED. AND EROSION MUST NOT OCCUR BENEATH THE RECP. ANY AREAS OF THE RECP THAT ARE DAMAGED OR NOT IN CLOSE CONTACT WITH THE GROUND SHALL BE REPAIRED AND STAPLED. IF EROSION OCCURS DUE TO POORLY CONTROLLED DRAINAGE, THE PROBLEM SHALL BE FIXED AND THE ERODED AREA PROTECTED. MONITOR AND REPAIR THE RECP AS NECESSARY UNTIL GROUND COVER IS ESTABLISHED. CARRYCIASSBSTONE V 2' NCD.O.T. CLASS EROSION CONTROL MATTING MUST - � CONTROL MEET OR EXCEED THE FOLLOWING REQUIREMENTS: FIGURE WASHED STONE ON UPSTREAM FACE 2OEM, TOP OF BANK 100%COCONUT FIBER (COIR) TWINE WOVEN INTO A HIGH STRENGTH MATRIX. 8 _ THICKNESS -0.351N, MINIMUM. TERMINATION TENSILE STRENGTH - 1740 LBIFf MINIMUM SHEAR STRESS -4.5LBSSOFT FIGURE4 FLOW VELOCITY- OBSERVED 12 FT/SEC WEIGHT-2302ISY TERMINAL ANCHOR TRENCH SIZE-9.84FT X 185 FT (180 SY) 'C -FACTOR -0.002 OPEN AREA (MEASURED) -46% SLOPES -UP TO A MAXIMUM OF 1:1 EROSION CONTROL MATTING INSTALLATION NOT TO SCALE "�V� � GROXISTING UND 3 N LINE D AREA GE 4'� ANCHOR FABRIC ASSHOWN F`0� BOTTOM SECTION STRANTOP AND GA., TY0 VARIABLE AS DIRECTED BY THE ENGINEANCHOR B' MAXI ' A A OA, TVP. STAY WIRES, ANCHOR WIRE FABRIC TO 12'SPACING STEEL POST WITH MIN, 4 MIN. 14 GA FENCING STAPLES PER POST CATCH BASIN 19 GAUGE HARDWARE CLOTH PLAN W/1/4'MESH OPENING. rn N SECURELY STEEL POST 4' MAX SPACING BETWEEN POSTS. ANCHOR _ _ FABRIC TO z N0.5 WASHED w WIRE WITH f / FILTER STONE Z 2 lo�WIRE TIES FL--O-W� Fes- LOW MAX WIRE FILTER FABRIC TO BE �.y� 4 F FABRIC MESH POLYPROPYLENE NYLON, TIT g OPENING SIZE POLYESTER OR POLY- N w LI = 36 SQ. IN. ETHYLENE YARN OF LJ 34' ANCHOR FABRIC MESH MANUFACTURER TO BE IN 16' OF NO, 5 APPROVED BY ENGINEER WASHED STONE CI C\/ATIlIAI NOTES: 1. THE CONTRACTOR SHALL MAINTAIN ALL SILT FENCING BY REMOVING AND DISPOSING OF SILT ACCUMULATIONS AS DIRECTED BY THE ENGINEER. FILTER FABRIC SHALL BE REPLACED WHEN IT HAS DETERIORATED TO SUCH EXTENT THAT IT REDUCES THE EFFECTIVENESS OF THE SILT FENCE. 2. FILTER FABRIC SHALL HAVE A MINIMUM TENSILE STRENGTH (0 20% MAX. ELONGATION) OF 3018sILIN. IN.. WIRE FABRIC REQUIRED. 3. IF EXTRA STRENGTH FABRIC IS UTILIZED (MIN. TENSILE STRENGTH = 50 IDs/LJN. IN. @ MAX. 20% ELONGATION), WIRE FABRIC IS OPTIONAL, MAXIMUM POST SPACING = 6 FEET. 4. POSTS SHALL BE 1.33 blLF STEEL UNLESS OTHERWISE APPROVED BY ENGINEER. TEMPORARY SILT FENCE NOT TO SCALE SECTION A -A NOTES: i. SEDIMENT SHALL BE REMOVED AND TRAP RESTORED TO ITS ORIGINAL DIMENSIONS WHEN THE SEDIMENT HAS ACCUMULATED TO IM THE DESIGN DEPTH OF THE TRAP. REMOVED SEDIMENT SHALL BE DEPOSITED IN A SUITABLE AREA AND IN SUCH A MANNER THAT IT WILL NOT ERODE. 2. THE STRUCTURE SHALL BE INSPECTED AFTER EACH RAIN AND REPAIRS MADE AS NEEDED. 3. CONSTRUCTION OPERATIONS SHALL BE CARRIED OUT IN SUCH A MANNER THAT EROSION AND WATER POLLUTION SHALL BE MINIMIZED. 4. THE SEDIMENT TRAP SHALL BE REMOVED AND THE AREA STABILIZED WHEN THE REMAINING DRAINAGE AREA HAS BEEN PROPERLY STABILIZED. TEMPORARY CATCH BASIN SEDIMENT TRAP NOT TO SCALE ADO! INSTALLATION NOTES SITE PREPARATION GRADE AND COMPACT AREA. REMOVE ALL ROCKS, CLODS, VEGETATION, AND OBSTRUCTIONS SO THAT MATTING WILL HAVE DIRECT CONTACT WITH THE SOIL PREPARE SEEDBED BY LOOSENING 3 TO 4 INCHES OF TOPSOIL ABOVE FINAL GRADE TEST SOILS FOR ANY NUTRIENT DEFICIENCIES AND SUBMIT SOIL TEST RESULTS TO THE CITY. APPLY ANY TREATMENT SUCH AS UME OR FERTILIZERS TO THE SOIL IF NEEDED. DO NOT MULCH AREAS WHERE MAT IS TO BE INSTALLED. SEEDING APPLY SEED TO SOIL BEFORE PLACING MATTING. WHEN USING PERMANENT LINER, APPLY ADDITIONAL SEED AFTER INSTALLATION AND FILL MAT WITH SOIL INSTALLATION OVERLAP ADJACENT MATS 3' AND ANCHOR EVERY 18' ACROSS THE OVERLAP. THE HIGHER ELEVATION MAT SHOULD BE PLACED OVER THE LOWER ELEVATION MAT_ EDGES SHOULD BE SHINGLED AWAY FROM THE FLOW OF WATER. LAY MAT LOOSE TO ALLOW CONTACT WITH SOIL. DO NOT STRETCH TIGHT. ANCHOR MAT USING BIODEGRADABLE STAKES OR PINS. EXCAVATE INITIAL ANCHOR TRENCH 1rW ACROSS THE EMBANKMENT AT THE LOWER END OF THE PROJECT AS SHOWN ON SHEET 5. SEE FIGURE 1 FOR INITIAL ANCHOR TRENCH. PLACE 6' x 6' CHECK SLOTS AT 30' INTERVALS ALONG THE EMBANKMENT AND WEIR. SEE FIGURE 2. CUT 4' x 4' TRENCH ALONG TOP OF BANK FOR MAT TERMINATION. EXTEND MAT TOTE EDGE OF THE ASPHALT OR 2 TO 3 FEET ABOVE THE CREST IF POSSIBLE. BEGINNING AT THE CENTER OF THE EMBANKMENT AT THE DOWNSTREAM END OF THE AREA TO BE LINED, PLACE THE END OF THE ROLL IN ANCHOR TRENCH AND SECURE WITH BIODEGRADABLE STAKES OR PINS. SEE FIGURE 1. PLACE ADJACENT ROLLS IN THE ANCHOR TRENCH WITH A MINIMUM OF W OVERLAP. SECURE WITH BIODEGRADABLE STAKES OR PINES. BACKFILL ANCHOR TRENCH, AND COMPACT SOIL UNROLL MAT OVER COMPACTED ANCHOR TRENCH, STOP AT NEXT CHECK SLOT OR TERMINAL ANCHOR UNROLL ADJACENT ROLLS IN SAME MANNER, WITH A MINIMUM OF 3' OF OVERLAP. STAPLE AT 18' INTERVALS ALONG OVERLAP. FOLD AND SECURE MAT ROLLS TIGHTLY INTO CHECK SLOTS. LAY MAT N CHECK SLOT, FOLD BACK AGAINST ITSELF, ANCHOR THROUGH BOTH LAYERS, BACKFILL AND COMPACT SOIL. CONTINUE ROLLING MAP UPSTREAM. SEE FIGURE 2. BEGIN NEW ROLLS IN CHECK SLOT, AND OVERLAP ENDS MpBMUM OF 1'. SEE FIGURE 4 FOR TERMINATION AT UPSTREAM END. MAINTENANCE INSPECT ROLLED EROSION CONTROL PRODUCTS AT LEAST WEEKLY AND AFTER EACH SIGNIFICANT (12 INCH OR GREATER) RAIN FALL EVENT REPAIR IMMEDIATELY) GOOD CONTACT WITH THE GROUND MUST BE MAINTAINED. AND EROSION MUST NOT OCCUR BENEATH THE RECP. ANY AREAS OF THE RECP THAT ARE DAMAGED OR NOT IN CLOSE CONTACT WITH THE GROUND SHALL BE REPAIRED AND STAPLED. IF EROSION OCCURS DUE TO POORLY CONTROLLED DRAINAGE, THE PROBLEM SHALL BE FIXED AND THE ERODED AREA PROTECTED. MONITOR AND REPAIR THE RECP AS NECESSARY UNTIL GROUND COVER IS ESTABLISHED. CARRYCIASSBSTONE V 2' NCD.O.T. CLASS UP SIDES OF SPILLWAY MN MN. � CONTROL N.C.D.O,T, NO. 57 WASHED STONE ON UPSTREAM FACE 2OEM, VANES WH OF �1 mK) FLOW ` 1' VARIES WITH FILTER FABRIC MIN. DEPTH OF DRCH SECTION B -B ti? 2' MN. N.C.D.O.T. CLASS 8 EROSION CONTROL STONE 2 17 9 FILTER FABRIC Y MN. SECTION A -A STONE CHECK DAM MAINTENANCE FOR ALL CHECK DAMS: INSPECT CHECK DAMS AND CHANNELS FOR DAMAGE AFTER EACH RUNOFF EVENT. ANTICIPATE SUBMERGENCE AND DEPOSITION ABOVE THE CHECK DAM AND EROSION FROM HIGH FLOWS AROUND THE EDGES OF THE DAM, CORRECT ALL DAMAGE IMMEDIATELY. IF SIGNIFICANT EROSION OCCURS BETWEEN DAMS, INSTALL A PROTECTIVE RIP -RAP LINER IN THAT PORTION OF THE CHANNEL. REMOVE SEDIMENT ACCUMULATED BEHIND THE DAMS AS NEEDED TO PREVENT DAMAGE TO CHANNEL VEGETATION, ALLOW THE CHANNEL TO DRAIN THROUGH THE FIBER CHECK DAM, AND PREVENT LARGE FLOWS FROM CARRYING SEDIMENT OVER THE DAM. CHECK DAM SHALL BE CLEANED OUT WHEN 5D% OF STORAGE CAPACITY HAS BEEN FILLED IN WITH SEDIMENT. DWK DICKSON unit inhaslructure consullents 401 4TH STREET SW SUITE 201 HICKORY, NORTH CAROLINA 25602 (1)62&327$911 (QB28-327-9164 WWW,WKDICKSON.COM NC LICENSE NDT-0374 PNrR„qC Eeturys ' i'CART�� °rr PROFESSIONALSEAL O O U � DC N O O W W 6 Illlllllg H z Lu W J frz Q_ J 2i 0 O WU 0 W = U U) OC O m O O Lu z w J Q LLJ W cc (9 aj Z z Y W z O n o PROJ. MGR.: CRF DESIGN BY: CRF DRAWN BY: CH/RJL PROJ. DATE: JUNE 2017 DRAWING NUMBER: G3 OF 29 WKD PROJ. NO.: 20160049.00.HI EROSION CONTROL SEQUENCE OF CONSTRUCTION NOTES 1. SCHEDULE A PRECONSTRUCTION CONFERENCE ON-SITE WITH THE EROSION CONTROL INSPECTOR FROM THE WINSTON-SALEM REGIONAL OFFICE OF THE NORTH CAROLINA DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES (NCDENR, 336-776-9600), AND THE ENGINEER'S REPRESENTATIVE. 2. BEFORE INITIATION OF CONSTRUCTION, INSTALL PERIMETER EROSION CONTROL MEASURES SHOWN ON THE PLANS INCLUDING SILT FENCE AND STONE OUTLETS AT CREEK CROSSINGS ALONG WITH ANY REQUESTED BY THE NCDENR INSPECTOR RESULTING FROM THE PRECONSTRUCTION MEETING. CLEARING AREAS ONLY AS NEEDED TO INSTALL THE DEVICES. OWNER SHALL PERFORM SELF INSPECTION AFTER PERIMETER CONTROLS (SILT FENCE, CONSTRUCTION ENTRANCES, ETC.) ARE INSTALLED. 3. INSTALL WATER MAIN. EROSION CONTROL DETAILS ARE SHOWN ON THE DRAWINGS AND STRUCTURE LOCATIONS ARE DEFINED IN THE PLAN VIEWS. 4. REMOVEIREINSTALL SILT FENCE AND STONE OUTLETS DAILY AS REQUIRED TO FACILITATE CONSTRUCTION AT CREEK CROSSINGS INSTALLED BY DIRECT BURY. 5. MAINTENANCE OF EROSION CONTROL DEVICES IS THE CONTRACTOR'S RESPONSIBILITY. AFTER EACH RAIN STORM THE DEVICES SHALL BE INSPECTED FOR DAMAGE AND REPAIRS MADE AS NEEDED. ANY SILT ACCUMULATION SHALL BE REMOVED IMMEDIATEDLY AND DISPOSED OF PROPERLY. 6. RESEED AND MULCH DISTURBED AREAS AS GRADING IS COMPLETED ALONG ALL CONSTRUCTION. ALL DISTURBED AREAS MUST BE VEGETATED OR OTHERWISE STABILIZED WITHIN THE NUMBER OF DAYS NOTED IN THE GROUND COVER SCHEDULE AFTER BEING DISTURBED. THE CONTRACTOR SHALL UTILIZE THE SEEDING AND MULCHING SCHEDULES NOTED ON THE DRAWINGS. NO MORE THAN 1,000 LF OF ROAD SHOULDER SHALL BE DISTURBED PRIOR TO CLEANING/SEEDING. A. ALL LOCATIONS DISTURBED DURING CONSTRUCTION WILL BE RESTORED ACCORDING TO THE PERMANENT SEEDING SCHEDULE AS SHOWN ON THE PLANS. B. IF THE WATER AND/OR SEWER LINE IS LOCATED WITHIN AN EXISTING DITCH LINE, AND THE CHANNEL VELOCITY EXCEEDS 2 FTJSEC.. TEMPORARY CHANNEL LINERS (JUTE NET, STRAW WITH NET, FIBERGLASS ROVING, GEOTEXTILE FABRIC, ETC.) SHALL BE USED AS SHOWN ON THE PLANS AND AS DIRECTED BY THE ENGINEER. THESE DITCH LINES WILL BE RESTORED ACCORDING TO THE PERMANENT SEEDING SCHEDULE AS SHOWN ON THE PLANS. 7. AFTER COMPLETE STABILIZATION OF DISTURBED AREAS AND AS DIRECTED BY THE ENGINEER, REMOVE EROSION CONTROL DEVICES FROM THE SITE. EROSION CONTROL DEVICE MAINTENANCE NOTES: 1. THE CONTRACTOR IS RESPONSIBLE FOR THE MAINTENANCE AND REPAIR OF THE EROSION CONTROL DEVICES UNTIL CONSTRUCTION IS COMPLETE. 2. ALL EROSION AND SEDIMENT CONTROL DEVICES SHALL BE CHECKED FOR STABILITY AND OPERATION FOLLOWING EVERY RUNOFF PRODUCING RAINFALL BUT IN NO CASE LESS THAN ONCE PER WEEK 3. ANY NEEDED REPAIRS WILL BE MADE IMMEDIATELY TO MAINTAIN ALL PRACTICES AS DESIGNED. 4. SEDIMENT IS TO BE BE REMOVED FROM THE SEDIMENT TRAPS, BASINS AND INLET PROTECTION DEVICES WHEN STORAGE CAPACITY HAS BEEN APPROXIMATELY 60% FILLED. 5. GRAVEL IS TO BE CLEANED AND/OR REPLACED WHEN THE SEDIMENT POOL NO LONGER DRAINS PROPERLY. B. SEDIMENT IS TO BE REMOVED FROM BEHIND SILT FENCE WHEN IT BECOMES APPROXIMATELY 0.50' DEEP AT THE FEND. THE SILT FENCE IS TO BE REPAIRED AS NECESSARY TO MAINTAIN A BARRIER. 7. PERMANENT GROUND COVER MUST BE ESTABLISHED WITHIN THE PROPOSED DITCHES AND CHANNELS. B. ALL DISTURBED AREAS ARE TO BE FERTILIZED, SEEDED AND MULCHED AS NEEDED IN ACCORDANCE WITH THE SPECIFICATIONS. 9. ADDITIONAL MECHANICAL MEASURES WILL BE REQUIRED IF VEGETATIVE COVER CANNOT BE ESTABLISHED AS PROPOSED. 10. CONTRACTOR SHALL MAINTAIN A RAIN GAUGE ON SITE AND PROVIDE WEEKLY/POST RAINFALL INSPECTION REPORTS TO THE OWNER IN ACCORDANCE WITH NCDLR REQUIREMENTS. WATER LINE DATA TABLE TOTAL PROJECT/DISTURBED AREA 3.76 ACRES A TEMPORARY SEEDING SCHEDULE — LATE WINTER /EARLY SPRING Seeding Mixture Species Rate (Ib/—S) Japanese Millet 20 Winter Wheat / Rye 40 Seeding dotes Mountains - Above 2500 ft: Feb. 15 -May 15 Below 2500 ft: Feb. 1 -Noy 1 Piedmont - Jan. 1 -May 1 Coastal Plain - Dec.1-Apr. 15 Soil amendments Follow recommendations of soil tests or apply 2,000 Ib/acre ground agricultural limestone and 750 Ib/acre 10-10-10 fertilizer. Mulch Apply 4,000 Ib/ocre straw. Anchor straw by tacking with asphalt, netting or o mulch anchoring tool. A disk with blades set nearly straight can be used as a mulch anchoring tool. Maintenance Refertilize If growth is not fully adequate. Reseed, refertilize and mulch Im- mediately following erosion or other damage. TEMPORARY SEEDING SCHEDULE — SUMMER Seeding mixture Species Rate (Ib/acre) Browntop millet 40 Seeding dates Mountains - May 15 -Aug. 15 Piedmont - May 1 -Aug. 15 Coastal Plain - Apr. 15 -Aug. 15 Soil amendments Follow recommendations of soil tests or apply 2,000 m/ocre ground agricultural limestone and 750 Ib/acre 10-10-10 fertilizer. Mulch Apply 4,000 Ib/acre straw. Anchor straw by tacking with asphalt, netting or a mulch anchoring tool. A disk with blades set nearly straight can be used as an onchoOng tool. Maintenance Refertilize if growth is not fully adequate. Reseed, fertilize and mulch immediately following erosion or other damage. TEMPORARY SEEDING SCHEDULE — FALL Seeding mixture Species Rate (Ib/ocre) Japanese Millet 20 Winter Wheat / Rye 40 Seeding dates Mountains - Aug. 15 -Dec. 15 Coastal Plain and Piedmont - Aug. 15 -Dec. 30 Soil amendments Follow soil tests or apply 2,000 Ib/acre ground agricultural li ne- stone and 1,000 Ib/acre 10-10-10 fertilizer. Mulch Apply 4,000 Ib/acre straw. Anchor straw by tacking with asphalt, netting or a mulch anchoring tool. A disk with blades set nearly straight can be used as a mulch anchoring tool. Maintenance Repair and refertilize eorried areas immediately. Topdress with 50 lb /acre of nitrogen in arch. If it is necessary to extend temporary cover beyond June 15, overseed with 50 Ib/acre Kobe (Piedmont and Coastal Plain) or Korean (Mountains) lespedeza in late February or early March. PERMANENT SEEDING SCHEDULE -MIXTURE k1M Seeding Mixture Grass Rate (Ib/acre) Broomsedge (Andropogon virginicus) 5 Eastern Gomma grass (Tripsocum dactyloides) 4 Little Bluestem (Schizacharium scoporium) 4 Switch grass (panicum virgatum) 5 Herb Black Eyed Susan (Rudbeckia hirta) 0.5 Butterfly Weed (Asclepias tuberose) 2 Purple Coneflower (Echinaceo purpurea) 2 Clasping Coneflower (Rudbeckia amplexicaulis) 1 Blonketflower (Gaillordia aristata) 2 Blazing Star (Liotris spicato) 2 Giant Sunflower (Helianthus giganteus) 2 Annual Sunflower (Helianthus annuus 1 Tickseed Sunflower (Bidens bipinr 2 Bee Balm (Monardo fistulosa) 1 Seeding note After Aug. 1, use unscorified seed for sericea lespedeza. Nurse plants Between May 1 and Aug. 15 add 10 ib/acre German millet or 15 Ib/ocre Sudangrass. Prior to May 1 or after Aug. 15, add 40 Ib/acre rye (grain). It may be beneficial to plant the grosses in late summer and overseed the lespedezos in March. Seeding dates Best Possible Below 2500 ft: Aug. 15 -Sept. 1 July 25 -Sept. 15 Mar. 1 -Apr. 1 Mar. 1 -May 10 Above 2500 ft: July 25 -Aug. 15 July 15 -Aug. 30 Mor. 20 -Apr. 20 Mar. 5 -May 15 Complete seeding earlier in the fall, and start later in spring on north and east facing slopes. Soil amendments Apply lime and fertilizer according to soil tests, or apply 4,000 Ib/acre ground agricultural limestone and 1,000 Ib/acre 5-10-10 fertilizer. Mulch Apply 4,000-5,000 Ib/ave grain straw or equivalent cover of another suitable mulching material. Anchor mulch by locking with asphalt, roving or netting. Netting is the preferred anchoring method on steep slopes. Maintenance Mow no more than once a year. Refertflize in the second year unless growth is fully adequate. Reseed, fertilize and mulch damaged areas Immediately. 1. GROUND COVER- WHEREVER LAND DISTURBING ACTIVITY IS UNDERTAKEN ON A TRACT COMPRISING MORE THAN ONE (1) ACRE, A GROUND COVER SUFFICIENT TO RESTRAIN EROSION MUST BE PLANTED OR PROVIDED PER THE GROUND COVER SCHEDULE SHOWN ON THIS SHEET. 2. GRADED SLOPES AND FILLS - PER THE GROUND COVER SCHEDULE SHOWN HERE, OR AT THE COMPLETION OF ANY PHASE OF GRADING, WHICHEVER PERIOD IS SHORTER, SLOPES SHALL BE PLANTED OR OTHERWISE PROVIDED WITH GROUND COVER, DEVICES, OR STRUCTURES SUFFICIENT TO RESTRAIN EROSION. SIDE BRANCH REMOV OAT COIR 1LId{I7PAL-�I Imo'— MATTI GROUND COVER SCHEDULE SITE AREA DESCRIPTION STABILIZATION TIME FRAME STABILIZATION TIME FRAME EXCEPTIONS PERIMETER DIKES. SWALES, DITCHES AND SLOPES 7 DAYS NONE HIGH QUALITY WATER (HOW( ZONES 7 DAYS NONE IF SLOPES ARE 10' OR LESS IN LENGTH AND ARE SLOPES STEEPER THAN 3:1 7 DAYS NOT STEEPER THAN 2:1, 14 DAYS ARE ALLOWED SLOPES 3:1 OR FLATTER 14 DAYS 7 DAYS FOR SLOPES GREATER THAN 50 FEET IN LENGTH ALL OTHER AREAS WITH __I NON (EXCEPT FOR PERIMETERS SLOPES FLATTER THAN 4:1 14 DAYS AND HWO ZONES SIDE BRANCH REMOV OAT COIR 1LId{I7PAL-�I Imo'— MATTI FLATTOP END ON O 1.5' LATERAL BUD MIN IS. 45 DEGREE TAPERED BUTT END SECTION VIEW LIVE STOUT STAKES SHALL BE SPACED 2 FEET APART. 1. PER THE GROUND COVER SCHEDULE SHOWN HERE, OR AT THE COMPLETION OF ANY PHASE OF GRADING, WHICHEVER PERIOD IS SHORTER, DISTURBED AREAS SHALL BE PLANTED OR OTHERWISE PROVIDED WITH GROUND COVER, DEVICES, OR STRUCTURES SUFFICIENT TO RESTRAIN EROSION. DETAIL LNE STAKES SHOULD BE 23 FEET LONG. ADDITIONALLY. THE STAKES FIBER SHOULD HAVE A DIAMETER OF 0.75 TO 21NCHES LIVE STAKE NOT TO SCALE PLANT LIST LIVE STAKE SPECIES SCIENTIFIC NAME COMMONNAME PERCENT swix.o .. Silky Weow SD% Comus Bmomum Silky Dogwood 25% Viburnum dkniBlum Arrowwood 15% Sambucus Cenadenis Eld.A ,,y 10% ALL PLANTING AREAS COIR FIBER FABRIC MAT NOT BE CUT WITH PLANTING IMPLEMENTS. THE SMALLEST OPENING NECESSARY TO ACCOMMODATE EACH PLANT SMALL BE CUT INTO THE FABRIC USING A SHARP KNIFE OR SHEARS. ER PLANT SPACING PLANTS SHALL BE INSTALLED IN STAGGERED ROWS. PLANT SPACING SHALL BE APPROXIMATELY TWO FEET (20) BETWEEN PLANTS IN THE SAME ROW. ROWS SHALL BE STAGGERED SUCH THAT ROWS ARE APPROXIMATELY TWO FEET (210 APART. CONTRACTOR REWIRED TO USE COMBINATION OF A.I. PLANT SPECIES. LIVEBTAK X-----XT E 2'--� I I BOULDER TOE OR TOE OF BANK WD CKSON unil� inlrasuudurB wnwllAne 401 4TH STREET SW SUITE 201 HICKORY, NORTH CAROLINA 286M (1)828.327-6911 (9028-327-8164 WWW.WKDICKSON.COM NC LICENSE NO.F-0374 3TypN W uH4 . PROFESSKRIALSEAL 0 0 O W U Q N Z Ln Illlllllg W ? J Q Q Z o 20 Cr 2 Q Z 1692 U 0 Cj)U 0 Tn Uj Z 0 Y W UJ W Z Q W Q Z Z Y q W W Q3 6 2 a. O PROJ. MGR.: CRF DESIGN BY: F DRAWN BY: C L PROD. DATE: JUNE 2017 DRAWING NUMBER: G4 OF 29 MD PROJ. NO.: 20160049.00.H1 EXISTING 20" INFI:JLNi CONCRETE PIPE COLLARS BID ALT. #2 CONTRACTOR PROVIDED 8'' DISCHARGE PIPING ----TOP GFGRau ° _ - - - - -_ riw—__- - - \ 940 - PRECAST MANHOLE VALVE VAULT _- _- / _----_ SEE DETAIL DWG. CIA:',\ _-_ 1Q\\' \\25' BID ALT #2 TEMPORARY LOCATION OF EXIS,nNG POWER TRANSFORMER Rf SF ..v(11N BID ALT. #1 BACKWASH INTAKE & PUMP ASSEMBLY SEE DWG. C1.7 l �X EXISTING RESERVOIR INTAKE STURCTURE IMPROVEMENTS SEE DWG. CIA 25 0 25 50 SCALE: 1" = 25' --_�.X�-X .21_ .- _X._-= —=_—.K �_ - -_ - _ ------------- ------------------------- - - -------------- --- -- --- - ------------ -- — — — — — — — — — — - --sus-------------- - _ - - ---_ ----_ ----$ _--- _ - 0 END PUMP STATION AND INTAKE STRUCTURE - - - - - - Z GGNTRACT (DIVISION 1} - ....MNG 7R" G2ANER NAW �� _- — _- _- T WAT[A UWF _ Bag— BEGIN DIVISION 2 -12' EMERGENCY RAW WATER LINE _ -_ — — — — 935 _ — _ _ _ EXTENSION. SEE DWG. C2.1 FOR CONTINUATION. _� -- - - -- ---__ - _ - — — — — - — — - ----- - EMERGENCY RAW WATER LINE - _ _ -! -" _ _ 930 — - .— — — EXTENS—ION SEE DWIG. C2.1 OWNER PROVIDED �— T' VALVE VAULT // �� �_� PORTABLE BYPASS PUMP - l� ,I DRAIN TO r, a 12 cniC vA.vE WYE I�'I Ir' t C _" _ __ _ -DAYLIGHT _ .� _ _ - _ _ ✓.. - ,l ,� \� / r i , ,/, \l -- - _ 1 __ _ NOTE: I �\ //>, ->a' --='_ _ _ _ _ _ / ACCESS TO THIS AREA i ��<..,; I_ �- - �- _ _ _ — _ _ _ �_ Iz DRAIN _`�t�(�? FROM GREENWAY 15!9"_\ / JI ri/1� j - - 1.' Ex15TING O'JRiEO 1 \ BO ALT.112' _\ _` \ \ s:'m o_m -_ - % / \ III II' l i 111 /rte CONTRACTOR PROVIDED 5' - \ SUCTION PIPING I\ \ �_ ____---_.-___.___- _ ����� \ ON TOP OF GROUNDPUIMP NSTATION TAT oERvola 'f-pq' l l �l l 11 l l yf l r (�I 1 1 W1 SCREEN � I \ \ L y �. � �- - _ _ � Vi. YY� � �� � �\ / / / it I I: 11,1- 1 I1 1 l RAW WATER INTAKE PUMP I / r _ , \� \\\'N- / I I -fit yl I / STATION IMPROVEMENTS - _ - - - -. - ._ - - - - - - - - \ �5EEDWG. CI.2TOC1.5 I 11„!„17711 l;'IIIII1111 II - - - - IN\\ \ it 11 IIII�I I -__-� CULVERT INV. ELE'r \ \\ \IIII EMERGENCY RAW WATER LINE EXTENSION 1 45, \\\\ \\\�\\\\\\\\\\\\ SEE DWG. C2.1\\\\\\�\\\\\\1\I 920 \\\O\\\ \ \\ \0 \\ ` \ I // Q_-_---_-- --- - - -- --- �Z _--------- - = = ` - \ 1111\ 1 ✓ \ \\\\\�\;\\\\\1\\\\\1\ \\\\ _ �-Z7 930 \1\\\\\\\\\\\\\\ \\ — —_—\\Av\\ \\\\\ \Nq \\\\\\\\ \U \\�y\\11�\Q\\\ 1,111,11`,\ DD�ICKSON 401 4TH STREET SW HICK0".RRI CAROUNA 25= (I)82BCi27-B871 X79184 W W W.WKDICKSON.COM NC LICENSE NO.F4W4 pypN!!Nz!'W g _ r G�r�9 V80ifSSIONAL SEAL o cc O 05 z U cc o IIII I� U Illlllilg !r cl uj cl) H Z w c 0 Q Z 20 J WUZ Z�= 0 CID Lo 2 O cl)> 0 wcr) WZ� w a QY x D �w cc Uu w 0 o LL PROJ. MGR.: CHF DESIGN BY: CRF Z DRAWN BY: I CH/RUL PROJ. DATE: JUNE 2017 DRAWING NUMBER: o C1.1 OF 29 QWKD PROJ. NO.: Z 20160049.00.HI LL TBM "GPS CONTROL POINT -1' 60d NAIL ! N: 919592.3340 E: 1449174.9625 L 936.OB ST0. O+OOt�! BEGIN CONSTRUCTION -DIVISION2' / REMOVE BLIND FLANGE AND INSTALL fl( PROPOSED RJ 22-112' MJ VERT. BENDS �� ii BEGIN RESTRAINED JOINT PIPE I 91 NOTES: _ 1. PROPOSED EASEMENT LIMITS ARE I/�%i4.��� GOVERNED BY THE PROPOSED I2° STA. 0+49* /,�// / /! i./j'�` Z �� �_ ' _=�_ EMERGENCY RAW WATER LINE AT ' PROPOSED RJ MJ 45• BEND. j/� __ DEFLECTIONS AND BENDS WHERE rN:919565.43 / ti- �` \� `\ ���c COORDINATES ARE PROVIDED UNLESS E:1449183.16�\ OTHERWISE NOTED. &� /�� / / `� ,'� �=\�""'YR FLOOD PLAIN PIN 4941.6&99-J023 2 LIMITS OF DISTURBANCE(LOD) FOLLOW /- // / STA. 0+76t �/ �� 1 \ \ E1L 24° RAW iNATER UNE _ \� �(APPROX. LOCATION) Town of Elk,, \ ? / R81460 PG 142 THE PERMANENT EASEMENT (PE) T,r' /// / !PROPOSED RJ MJ 45° 'BEND//// /j�• / i ' i �QAPPROR LO,CATION,j, . _ = _ `fy - \\•� = BOUNDARY OR THE TEMPORARY �� '.:919538.10 PROPOSED TEMPORARY SRT �_ _ CONSTRUCTION EASEMENT TCE) /// / // �E1449187.75 i0 / - / /j °' z �� PROPOSED STONE OUTLET, TYP. C FENCE. TYP. ��_a�` // //// / STA 3+521 SEE DETAIL DWG. G3 �\ \\. BOUNDARY UNLESS OTHERWISE SEE _ DETAIL DWG` G3 �/ /PROPOSED RJ MJ 45' BEND ` �� ���'- '-� \\�\\\_�=��"`� SPECIFIED OR /�.919303.17 2G \ �/ R ///SEEDE EaM9205.42 _�>e1''.j�\�\\ � STA. 9*BEGINRESTRAINEDJOINT/�\\T.,\ ST0.8+553,/D STREAM CROSSING W1, \ \ P \ h END RESTRAINED JO.;�Gi,/ !IL DWG. C2.8 c IN r/ „b Fh PLACE FLOWABLE FILL IN TRENCH (STA. 0+19 TO / STA. 0+79) TOPIPE tyOf�9/'�e( SPRINGLINE, SEE WATER i y r LINE TRENCH IN DAM /; IMMG 433 ,/ I DETAIL C1.8 /s //�,fv,� RAW WATER PUMP D PL(DIVISION 1) PLA ' / SAPPRO%. LOCATION) (l W� \\ \�\\ STA. 8+43t- Cream Impact S 1 \ \\\ ✓� �7 \ \ 1 I � 1 _ ms PROPOSED RJ 1125' MJ BEND 14 "s - STA. ` STA 8+31Y'BEG\. RESTRAINED JOINT 7Ce� Stream Impact In i2a ///PROPOSED RJ 22.5• MJ BEND N:919428.05 �� / STA. 4+002 \ \ \ `END RESTRAINED JOINT PIPE \ \ PROPOSED 3* SINGLE BOGY COMBINATION AIR VALVE • SEE DETAIL DWG. C2.7 f \\\\���� \ \\ \ See Consan-anon E. -a-1 ` \\ \ STA. 6+173 \ waeo4RTer10 Tom ofElkin RB 1158 PG 982 BEGIN RESTRAINED JOINT PIPE \ \ , ( I \ 11 PIN 4941.6699.7041 W -f STA. 6+40*\ w mono Ranee VW.b-Jer PROPOSED RJ 22.5' MJ BEND R6 BW PG 993 N:919027.52 STA 1+82* E:1449121.09 PROPOSED RJ MJ 45' BEND ` _ - N:919452.03 - - E:144912BAl - -T71 ', SEE PROPOSED STREAM yi-�V�)"o.TiS•���{,.a:7's:..''T?L�1.�=��`"D '- CROSSING /WD RESTORATION _- (DIVISION 3) , p � SED STREAM - p p ......................IERTICALIEPARITIOI• 1 1 1 1 PROPOSED TEMP. STREAM CROSSING R9 804 PG 993 I a IC p pm .■ F p O< r W rJ m m m Wa�� Z m W/ 1-WHDPE SMOOTH LINED PIPE SEE DETAIL DWG. f00 >w �� Anil N� �i� ma v4a w m�LJ3vJ 'm v4a Id-rc wa PROP. 8' BACKWASH LINE (DMSKNI I) I I I I PLACE FLOWABLE FILL IN TRENCH (STA. 0+19 TO STA. 0+79) TO PIPE SPRINGLINE, SEE WATER LINE TRENCH IN DAM DETAIL C1.8 BTA. 1+032 PROP. RJ 45' MJ VERT. BEND 910 -0-50 0+00 0+50 1+00 PROPOSED STREAM CROSSING #1 SEE DETAIL DWG. C2.8 STA 1+ PROP. RJ. MJ VERT.BEND I 1+50 2+00 2+50 4+00 5+50 LOCATION AND GRAPHIC SCALE 40. 0 HORIZONTAL 4' 0 4- 8' VERTICAL �M t - &-i .-,- ' OPOSED 2' SINGLE BODY iMBINATION AIR VALVE E DETAIL DWG. C2.7 7+fist / /1 PROPOSED RJ 22.5° MJ BEND � SED STREAM - d ,rR, iyaiOSSINGANDRESTORATION, 1 SEE DETAIL DWG. C2.8 1'1N 494 h66-89-7641 ......................IERTICALIEPARITIOI• V b h acd Reoea a WmobaT,, PROPOSED TEMP. STREAM CROSSING R9 804 PG 993 I W/ I -W HDPE SMOOTH LINED PIPE � SEE DETAIL DWG. C2.8 .■ 1 VSTA. 9+87* I PROPOSED RJ 22.5° MJ BEND .918724.73 I E:1449265.05 PW 4941-0}86-7475 \ F1od E,,g- Pod R8 576 PG 461 1 STA 9+424 DEFLECT PIPE N:918757.80 I E:1449233.53 I L I 6+50 7+50 8+00 8+50 9+50 1 925 �D CKSON Communil inheshuaure consWlenb 401 4TH STREET SW SUITE 201 HICKORY. NORTH CAROUNA28602 (0828-327-6911 (0828-327-9164 W W W.WKDICKSON.COM NC LICENSE NO.F-0374 PROFESSIONALSEAL Ir0 w is yl O 3 U) F - Z Lu o + Lu o Z 7n 0-71 20 Q CM + Lu U Z o O >U 5:_ cc W OrL a? 3:w a CrCr Z o z J W z a p PROD. MGR.: CRF DESIGN BY: CH DRAWN BY: ICH PROJ. DATE: I JUNE 2017 DRAWING NUMBER: C2.1 OF 29 WKD PROJ. NO.: 20160049.00.H1 ......................IERTICALIEPARITIOI• � ...-. 1 .■ W/ 1-WHDPE SMOOTH LINED PIPE SEE DETAIL DWG. „REMEMBER ..■■■■ MENNEN.... .....M.1, ...... ...N...... Y MENNEN.N ...... ...O......NOMMEMENds \ .■■.NI■.■ '...■■■1 MEMENNOMME 6+50 7+50 8+00 8+50 9+50 1 925 �D CKSON Communil inheshuaure consWlenb 401 4TH STREET SW SUITE 201 HICKORY. NORTH CAROUNA28602 (0828-327-6911 (0828-327-9164 W W W.WKDICKSON.COM NC LICENSE NO.F-0374 PROFESSIONALSEAL Ir0 w is yl O 3 U) F - Z Lu o + Lu o Z 7n 0-71 20 Q CM + Lu U Z o O >U 5:_ cc W OrL a? 3:w a CrCr Z o z J W z a p PROD. MGR.: CRF DESIGN BY: CH DRAWN BY: ICH PROJ. DATE: I JUNE 2017 DRAWING NUMBER: C2.1 OF 29 WKD PROJ. NO.: 20160049.00.H1 _ \ « ER 100 YR TL66D PLAMT-_ _ _ = _ - - -' - _ RR SPIKE IN . \�.� - 3[APPROX. LOCATION) _=- _ -- -- -_ -_ _-_ \+ .N -= _ _ _ _ 12" BIRCH �- _—' N: 918510.6420 -"'`' E: 1449848.3650 Z: 926.24' zt\ oo >\ -FIELDVERIFY .4,- LOCATION OF EXISTI _ - - - -STA. 10+101 = - - - - - . - —s _RAW WATER LINE " — _ — = PIN 4vs1-oap11-5972 _ - END RESTRAINED JOINT PIPE -r= _ �_ �� - ,,, „ R6 1521 PG ass \� GRAPHIC SCALE 40' 0 40• W. HORIZONTAL 4' 0 VERTICAL NOTE: \ PROPOSED EASEMENT LIMITS ARE GOVERNED BY THE PROPOSED 12" EMERGENCY RAW WATER LINE AT DEFLECTIONS AND BENDS HERE RDINATE _ - ---- _ _° z 12 sas4 \ STA. 15+822 STA 16+492 ---- -- OTTH R CSE NOTED. S ARE PROVIDED UNLESS "g / \ r �. •n, -b. — J_ MAINTAIN IO' MIN. DEFLECT PIPE _. -- DEFLECT PIPE 7ER --_— — __ _ EX 2a" RAW WA LINE s - _�-_-, -73--_ HORIZONTAL SEPERATION =�-__ __ - -_, _ � TIN - � -- � N918374.63 (APPR074_LO_�_ ON� ,=r = _ _ _ \ 7 - - FROM CONCRETE BRIDGE PIERSE:1449755.92 E:144982.85 R \. 4 _ ` �---__--"��� J � _ �- / ' WETLAND IMPACT: p • Qj¢jn �j1�Qg \ �_ _ STA 18+322 - °�i- END RESTRAINED JOINT PIPE --PROPOSED STA. 18+092 \T+ kPROPOSED RJ 22.5' W BEND r N91828850 MA94TAIN 10' MIN. - �,1.9aa1 / HORIZONTAL SEPERATION FROM CONCRETE BRIDGE PIERS ( / STA. 10+882 ( DEFLECT PIPE ! / N:918692.54 E:1449356.59 _. STA 10+002 RAW WATER LINE LOCATION NC268BYPASS MARKER- VALVE BOX WI TRACER 'CC CAMP ROAD• WIRE, SEE DETAIL DWG. C2.6 a rr / ` \ E:1449942.34 PROPOSED TEMPORARY SILT FENCE. TYP. =- 1 �" T SEE DETAIL DWG. ### ���VYYY'YYY 'VYY �_ \STA. ncooT comrw ed Acus Y�-1,(..DEFLECTPIPE A"....,. s.,mo os ner �'Y`1!-\, N:918406.78 sarc regen We 1161aoz EX. 100 YR FLOOD PLAIN -Ls6+9o.00 45.AW P�mrsl-`�E:1449787.21 (APPROX. LOCATION) EX. 24" RAW WATER DUNE y �'✓ -�� \� \\\ / \ CROSS OVER EX. 24" RAW WATER LINE (APPROX. LOCATION) 1 SEE PROFILE. (FIELD VERIFY DEPTH AND \\ LOCATION OF EXISTING RAW WATER UNE) STA 17+862 BEGIN RESTRAINED JOINT PIPE \ Wetland Impact W1 /\~� \i _\`� PIN 4941-08-98-3167 STA 18*292 % James w Panus DEFLECT PIPE RB 1216 PG 594 N:918248.37 - E:1449950.77 \ STA - \\ RAW WATE LWE LOCATION - MARKER -V W/TRACER WIRE. SEE DETAILDWG. Z°3B\dp / 4 t R C/L FUN16 / Trnatnissbn Lina � J SY4ron 11J67.0 0 15 10 15 !0 5 0 VVI( CKSON viYffi1NgwC cUnSWWnLS 401 4TH STREET SW SUITE 201 HICKORY, NORTH CAROLINA 28602 (1)82532711 M828-327-9164 WWW+VWDICKSON.COM NC LICENSE NO.F-0374 y bg."r PROFESSIONAL SEN. Ir o U :_ 2 U z Ix I I I I I I I Z U W + > N Q CC Z TTI O_ J O 2O F- 0 Q CV t wU Z O_ U) Lu Z Q Z 0 CC J D. 2� W Z Q Q Z w g � a z J r W z Og a o PROD. MGR.: CRF DESIGN BY: CH DRAWN BY: CH PROD. DATE: JUNE 2017 DRAWING NUMBER: C2.2 OF 29 WKD PROD. NO.: 20160049.00.HI PIN 4941-12-974299 James W Patin at al R8865 PG 293 RB 1489 PG 978 IPA k wish West O49a a,Creep I— JOE 907.4019) STA. 23+221 BEGIN 12.0 HDPE (APPROX. LOCATION OF TIE-IN) i - HDPE TO DI COUPLING PROPOSED 75'x150' TEMPORARY WORK AREA — — FOR HDD SETUP EX 100 YR FLOOD PLAIN (APPROX LOCATION) PIN 4951.0407-2480 Town of Sam OB 109 PG 303 (1928-Slx FadllyTd) PIN 4951.09-07-5357 / emacs a Sloop I—(meals LLC STA 28+671 RB 1554 PG 149 / R, [BEGIN RESTRAINED JOINT PIPE 24 PIN 4951.09-07.5114 HDPE Re.y Johnson Joyce PROPOSED STRFJiM CRUJJINl9 S[. _..___ _ -�. �_ _, . _........ _.. _..._ RB 1015 PG 932 13+ eaU:lac ni enl (APPR01f. LOCATION) _ _—n/w- \ \ SEE PROFILE. (FlELD VERIFY DEPTH AND ( NO IMPACT) ` LOCATION OF EXISTING RAW WATER LINE) 1 1 - -Fri+--'-'---�wf" STA. 23+021 Y PIN 495109.072480 STA. 29+13t PROPOSED 2' SINGLE BODY ?qA \ Teva d E" END RESTRAINED JOINT PIPE,/ - COMBINATION AIR VALVE \ GB 109 PG 303 '. SEE DETAIL DWG. C2.7 \ (1928 -Shoe F.o(ory Trawl 1 N 20' Axes B U61i1Y Easement qq,���— (SR 115010 ELKIN GEENWAV) JamesPIN 4M42-97-Psam429 1,a RB 065 PG 293 \.���,//� E%�100 YR FLOOD PLAIN STA 304001 `., RB 1464 PG 975 / \ (APPROX. LOCATION) RAW WATER LINE LOCATION sae also. Easements to the Town o& PIN 9941-0&97-G891 rnn �r w;IE we=r erq. dcroelo MARKER - VALVE BOX WI TRACER Elkin for Reereaflard Tr411 and A -ass \ Brian C. WilhBe , (Rel hE p aNel.l ` — ' \ I. e 1150 RB 1152 MI 751 _ \ WIRE, SEE DETAIL DWG. C2.6 R8 14119 P(i 598 \ \ +4� 935 Z STA. 23+401 w _ y > r X APPROXIMATE LOCATION '4 Z HDD ENTRY (10') _ _ m rc .: a PROPOSED STREAM CROSSING 02 O o• — Om > m ..�0 (NO IMPACT) ��1lz0 mp X00 -z io 930 S ZWa =0o 0 3 Jo �171lmrQ +�+ mZg4� r +%mvpl —�Z.,z P� lrV NE too FL000 d w a o a STA. 27+zot U) o¢. i so Q p<U= APPROXIMATE LOCATION y w_ F p W F O 1 O UP 1 1 u1aUm w 0 HDD EXIT (10•) X I I I p11 . RAW WATER Y MIN. COVER UN GRAPHIC SCALE 40' 0 40• �. HORIZONTAL 4' 0 4' 6' VERTICAL NOTE: PROPOSED EASEMENT LIMITS ARE GOVERNED BY THE PROPOSED 12' EMERGENCY RAW WATER LINE AT DEFLECTIONS AND BENDS WHERE COORDINATES ARE PROVIDED UNLESS OTHERWISE NOTED. LOCATION LM■■■■■■■■■■■■■■■■■■■■■■■■■■■■■■■IllD.I.P. WATER LINE FROM iIIIA'IIIA■■■■►■■■NNOOM■■■■�11t111611111�■■�■■■■■■■■■■■■■■■■■■■■■■■■■■■■■ EXISTING UTILITIES. UNLESS SHALL BE: STORM PIPING 18"MIN. �,w.■■■■■■■■1 1 11 1 11 1 11 1 11 1 11 1 II 1 11 1 11 1 11 1 915 910 905 900 895 D8 CKSON uaty mf -- Om. conwllanls 401 4TH STREET SW SUITE 201 HICKORY, NORTH CAROLINA 28602 (1)828.327411 (0828327-9164 W W W.WKDICKSON.COM NC LICENSE NO.F-0374 °{PN Ws'HgC'F 35 •• tY.�Y�4L� & PROFESSKMUL SEAL O U III U 4 c IIIIIIiI� Ln H Z W o :2 + W � fr v Z ~) LL J O 20 cr CD Q N + W U Z C) c= O Q U) Cc (n 1?�_ O W Z J Q Z O J a W Z Q Z w Z Z J ~ v W z 'o a a o PROD. MGR.: CRF DESIGN 8Y: CH DRAWN BY: ICH PROD. DATE: I JUNE 2017 DRAWING NUMBER: C2.3 OF 29 WKD PROJ. NO.: 20160049.00.H1 CROSS OVER EX. 24" RAW WATER LINE RESTORE EXISTING WOOD SEE PROFILE. (CONTRACTOR TO FIELD R PIN 4951.09-06-6955 BENCH AND SEATING AREA VERIFY DEPTH AND LOCATION OF EXISTING Clerks R Forcer TO ORIGINAL CONDITIONS - RAW WATER LINE) RESTORE GREENWAY PATH RB 1350 PG 28 STA 34+05* r STA 31+65* TO ORIGINAL CONDITIONS. DEFLECT PIPE PROPOSED RJ MJ 45' BEND SEE DETAIL DWG. C2.5 N:918837.19 qb / N:917053.11 \ E:145081fi.05 E:1450509.99 --xlx---__. xM Aaoar:ct DO NOT DISTURB / \ CONCRETE STRUCTURE - - --w/'''-/ STA. 32+13i IN TRAIL TEND RESTRAINED JOINT PIPE w. - - _ __ FE — PE 1 -PE- PEP IR \ 3' 33-00 1 OCATION) +00 r z i " is-_"- -o / _ \—Y�\\\ - - i " 1 Y� i i 25' i `PROPOSED TEMPORARY SILT 1(r EX 100 YR FLfMO PWN FENCE, TYP. STA. 34+34* APPROX. LOCATION) BEGIN RESTRAINED JOINT PIPE ( _.. _- SEE DETAIL DWG. 6-3 _- _ I - _ _.. STA 31+501 �^/ L�If PROPOSED RJ MJ 45" BEND &ry 20' N:917057.64 _ - ''Pp APPROX. LOCATION EXISTING 24 - E:1450496�58 ALUM SLUDGE PIPE (FIE D VERIFY - - _ EX 24" RAW WATER LINE LOCATION AND DEPTH) STA. 31+022 - = - STA. 35+35* STA 35+48* DEFLECT PIPE-- —PROPOSED RJ 90' MJ BEND N:918719.39 N916708.31 E:1450870.72 E:1450675AO GL FUWrc TraM1m nL�nn _ -.. -- - • _ - It1 - Duko Power 6-p E8 RIY4 n�..L ti ti `�T' l�4'eace sNe ai GLl nix ----- r Stream Impact `6N 49511 C511B9 _ �RB 10155 PGPG 932 PROPOSED STONE OUTLET, TYP. s > _ SEE DETAIL DWG. G3 PROPOSED STREAM CROSSING #3, SEE DETAIL DWG. C2.8 =STA 36+68± 'PROPOSED RJ 22.5' W BEND N:916656.06 `. (APPROX. L BEGIN RESTRAINED JOINT PIPE .--- —ss 19 X E:1450569.75 _ J—�`,._n��_ w�J-r-- x ---w IN 4951 09-08-36-4 l l 1 \ \ 1 (Wafer rli lPlanr S") DS 271 PG 544 447 PG 1273 �( EX. 100 YR FLOOD PLAIN aafP (APPRO%. LOCATION) \-'ter- STA 36+763.\ 11 \ 1 STA. 36+88± PIN 494112.974299\ X\faonr ,a-' 1 1 .lances 1- Pe97- 10p1A----`^tea 140`1*' \ ` y. PROPOSED 3' SINGLE BODY �1 PROPOSED 16ALVE 12" TEE — 93 a� - COMBINATION AIR VALVE k `\ W712' GATE VALVE' - _6r,_ RB 14114 PG 978 ; 1qb4a`\ SEE DETAIL DWG. C2.7 \ ` END RESTRAINED JOINTPIPE is wm wan a49a al c,aau �)`` and moa W<Of01 \ ` 1 II WATER TREATMENT I s 1 PIN 4951.09-0636-411 PLANT \ Town o/ E1Wn fffl (Waun Filler P/enl Sile) + } s EX. 16" WATER UNE 111 \ RB 4471 PG PG 273 \ \\ (APPROX LOCATION) 11 I \` CONTRACTOR TO VERIFY AT INERSECTION W/ N�1 1 WATER LINE 920 STA 31+49* STA - PROP. RJ 45' MJ BEND PROP. RJ 45' MJ BEND W W � l 11_ Q � %IS CR m N5 915 g WaW3 N Z m> �p +I u10 O SNNC twn FL __ �m NNW ��W- WWnyQ�QxH L 0 0 L OD '+a�a+m�m amL �m am+d R4I'M c� M0. y0.> y6> In1 y > y6 y U3y y 910 AND 905 895 VERTICAL SEPARATION OF PROPOSED D.I.P. WATER LINE FROM EXISTING UTILITIES, UNLESS 880 OTHERWISE NOTED, SHALL BE: SANITARY SEWER- 18" MIN. STORM PIPING -18" MIN. GAS PIPING -12" MIN. D 12' DIP EMERGI RAW WATER 3' MIN. COVER UN 30+50 31+00 31+50 32+00 32+50 33+00 33+50 34+00 ALUM SLUDGE PIPE ITRACTOR TO REL) FY LOCATION AND GRAPHIC SCALE 40' 0 40' W. HORIZONTAL 4- 0 4' 6 VERTICAL NOTE: PROPOSED EASEMENT LIMITS ARE GOVERNED BY THE PROPOSED 12' EMERGENCY RAW WATER LINE AT DEFLECTIONS AND BENDS WHERE COORDINATES ARE PROVIDED UNLESS OTHERWISE NOTED. PROPOSED STREAM CROSSING #3, SEE DETAIL DWG. C2.8 34+50 35+00 35+50 36+00 36+50 37+00 37+50 905 885 880 875 �DICKSON mo-nsaac onsdlanl5 401 4TH STREET SW SUITE 201 HICKORY, NORTH CAROLINA 28602 (t)828.32711 (WB327-9164 WWW.WKDICKSON.COM NC LICENSE NOY-0374 N Wn'HgGr9. ��JP �' iesgyEF n %3/ 1111IFFSSIDNALSEAL O GC 2 U 00 ir Z 0 U 0 I o U Illlllll.- Ir 0 LL w I_ < Z w w GO J 2 + w w m 12 >a I— 0 Z v~i 0 D _, o Z �O o } CV I � Q + J Lu O Z CD Z = O Q 0 cn 'r >_ f4 w O LU _j 00 IL >� Y a D w z EL Q a 2 ft z T 11! z EL w � �a > z J F w 15 w z ID � 3 a 0 M o LL 1 PROJ. MGR.: CRF (� DESIGN BY: CH Z DRAWN BY: CH PROD. DATE: JUNE 2017 DRAWING NUMBER: Q o C2.4 OF 29 J WKD PROD. NO.: Z 20160049.00A LL SEWER (UNDER) 10'-0• WATER (OVER) WATER -SEWER WATER F b SEE WATER SEWERNOTE SEWER 7-0• y k � SEE NOTE � NOTE: SEWER WATER WATER SEWER WHEN WATER MAIN IS ABOVE SEWER, BUT WITH LESS THAN IT CLEARANCE, OR WHEN THE SEWER IS ABOVE THE WATER MAIN, BOTH THE WATER MAIN AND THE SEWER LINE SHALL BE CONSTRUCTED OF FERROUS MATERIALS WITH JOINTS EQUIVALENT TO WATER MAIN STANDARDS FOR A MINIMUM LATERAL DISTANCE, MEASURED AT RIGHT ANGLES TO THE SEWER, OF 10 FEET ON EACH SIDE OF THE CROSSING. RELATION OF WATER MAINS TO SEWER MAINS NOT TO SCALE } UNDISTURBED SOIL (TYP.) { A A PLAN -BENDS 45' m m 18' MW: 1P DIA. OR LESS 24• MINA 7DIA. OR GREATER SECTION X -X BENDS & TEES X A A X PLAN -TEES 18* MIN. I I--24'B•MIN.. IT DIA, I 12 6 UP 6 LESS _ Aff r U � C�PLAN D•ELEVATION PLAN & ELEVATION PLUGS �0000a0000000 2000 PSF SOIL (SAND S GRAVEL WITH CLAY) NOTES: 1. BASED ON 200 PSI STATIC PRESSURE PLUS AW WA WATER HAMMER ALLOWANCE. 2. ALL BEARING SURFACES TO BE CARRIED TO UNDISTURBED GROUND. 3. THRUST BLOCKS TO BE USED AT ALL LINES OPERATING UNDER PRESSURE. 4. KEEP ALL PIPING JOINTS CLEAR OF CONCRETE THRUST BLOCKS. THRUST BLOCKING DETAIL NOT TO SCALE WATER MAIN OR SAN RARY J STORM SEWER - SEWER MAIN WATER MAIN '— STORM SEWER OR SANITARY SEWER MAIN NOTE: WHEN A WATER MAIN OR SANITARY SEWER MAIN CROSSES OVER OR UNDER A STORM SEWER AND CONDITIONS PREVENT THE REQUIRED 1B• MIN VERTICAL SEPARATION, THE WATER MAIN ORB ITARY SEWER MAIN SHALL BE CONSTRUCTED OF DUCTILE IRON PIPE WITH JOINTS EQUIVALENT TO WATER MAIN STANDARDS FOR A MINIMUM DISTANCE OF 10 FEET ON EACH SIDE OF THE POINT OF CROSSING. RELATION OF WATER & SEWER MAINS TO STORM SEWERS NOT TO SCALE WIDTH VARIES 4 -THICK MECHANICALLY COMPACTED BACKFILL, 8' LAYERS. 95% STANDARD PROCTOR (PASHTO T-99) UNDISTURBED 1r IT TYPE 4 PIPE BEDDED IN SAND, GRAVEL, OR CRUSHED STONE TO A DEPTH OF 118 PIPE DIAMETER, 4- MINIMUM WITH BACKFILL COMPACTED TO TOP OF PIPE. (APPROXIMATELY W PERCENT STANDARD PROCTOR. AASHTO T-98) TYPE 3 PIPE BEDDED IN 4• MINIMUM LOOSE SOIL WITH BACKFILL LIGHTLY CONSOLIDATED TO TOP OF PIPE (LOOSE SOIL IS DEFINED AS NATIVE SOIL EXCAVATED FROM THE TRENCH, FREE OF ROCK, ORGANIC MATERIAL, FOREIGN MATERIALS AND FROZEN EARTH.) a TYPE 5 PIPE BEDDED TO IT'S CENTERUNE IN COMPACTED GRANULAR MATERIAL, 4' MINIMUM UNDER PIPE. COMPACTED GRANULAR OR SELECT MATERIAL TO TOP OF PIPE. (APPROXIMATELY 90 PERCENT STANDARD PROCTOR, AASTO TAB) (SELECT MATERIAL G DEFINED AS NATIVE SOIL EXCAVATED FROM THE TRENCH. FREE OF ROCKS, ORGANIC MATERIAL, FOREIGN MATERIALS AND FROZEN EARTH) NOTES: 1. TYPE 2 AND TYPE 3 SHALL BE THE SELECTED EMBEDMENT CONDITION FOR ALL DUCTILE IRON MAIN 144NCH AND URGER UNLESS ACTUAL LAYING CONDITIONS REQUIRE MORE STRINGENT (TYPE 4 OR 5) EMBEDMENT. 2 CONSIDERATION OF THE PIPE -ZONE EMBEDMENT CONDITIONS INCLUDED IN THIS FIGURE MAY BE INFLUENCE BY FACTORS OTHER THAN PIPE STRENGTH. FOR ADDITIONAL INFORMATION ON PIPE BEDDING AND BACKFILL, SEE ANSIIAWWAC000. 3. TRENCHES REQUIRING SHORING AND BRACING, DIMENSIONS SHALL BETAKEN FROM THE INSIDE FACE OF THE SHORING AND BRACING. 4. NO ROCKS OR BOULDERS 4' OR LARGER TO BE USED IN INITULL BACKFILL. 5. ALL BACKFILL MATERIAL SHALL BE SUITABLE NATIVE MATERIAL. S. BACKFILL SHALL BE TAMPED IN S' LIFTS IN TRAFFIC AREAS, 12' IN NON -TRAFFIC AREAS. 7. ACHIEVE 80% COMPACTION IN NON -TRAFFIC AREAS. AND OVA COMPACTION IN TRAFFIC AREAS. 8. IF IN EASEMENT 4' TOPSOIL, ANO 12' CLEAN SELECT FILL IS R 110K ED 9. NO BOULDERS B' IN DIAMETER OR GREATER ALLOWED IN FINAL BACKFILL. TYPICAL DUCTILE IRON MAIN EMBEDMENT DETAIL NOT TO SCALE CRUSHED STONE tGRAOE TO DRAIN MIN 17 jEMBEDMENTZONE 1•— VARIES TYPICAL TRENCH BACKFILL GRAVEL GREENWAY TRAIL REPAIR NOT TO SCALE yp. �- BOTTOM OF EXCAVATION (SEE NOTE 3 BELOW) NOTES: 1. BACKFILL TO 95% OF MAXIMUM DENSITY WHERE EXCAVATIONS CUT THROUGH PAVEMENTS. CURBS. DRIVEWAYS AND SIDEWALKS, AND UNDER OR ADJACENT TO STRUCTURES. 2. STONE TO BE SIZE 117 701-1/2', WELL TAMPED. 3. STONE IS REWIRED TO B• BELOW PIPE WHERE WET CONDITIONS OR ROCK IS ENCOUNTERED, ONLY AS DIRECTED. 4. HANG SHAPE TRENCH BOTTOM FOR LOWER QUADRANT OF PIPE AND BELLS. 5. PROVIDE MINIMUM Y'COVER OVER PIPE. CARRIER PIPE STANDARD WATER LIN_ E TRENCH NOT TO SCALE MUr RESTORE GRADE TO ORIGINAL -0'MIT / GROUND SURFACE ELEVATION. SEE NOTE 3 (VARIES WITH PIPE BACKFILL CLASS) NOTE 2 7TE1 NON -WOVEN ' 1 GEOTI. EXTI FABRIC FILTER NOTES: 1, S' DEEP NO. 57 STONE OR EQUAL WRAPPED IN NON -WOVEN GEOTEXTILE FILTER FABRIC LIGHTLY COMPACTED. OVERLAP FABRIC By MINIMUM ONE PIPE O.D. 2, 4- DEEP NO. 57 STONE OR EQUAL LIGHTLY COMPACTED PIPE BEDDING, 3. GENERALBACKFILL COMPACTED T09D% STANDARD PROCTOR DENSITY IN 6- MAXIMUM LIFTS. TYPICAL TRENCH BACKFILL UNSUITABLE SUBGRADE NOT TO SCALE z _O I- 0 Z) Lcr- ,,r^^ vJ z /O V O u- 0 W Q W J W L= O z WK CKSON i Ini—i—tum Wnsdwnm 401 4TH STREET SW SUITE 201 HICKORY, NORTH CAROLINA 28602 0)828.327-6911 (0628.327-9164 WW. W WKDICKSON.COM NC LICENSE NO.F-0374 nHAO�ce PROFESSIONAL SEAL Ix W � ZQ O � s Q G illlllllg U) z w 2 W OQ CL Z D_ J J 20 cr Q 0 W U w Z ccl: Q mO a W Z J W Q C WW UJ z J z J F W z 8 a O PROJ. MGR.: ' CRF DESIGN BY: CRF DRAWN BY: CH/RJL PROJ. DATE: I JUNE 2017 DRAWING NUMBER: C2.5 OF 29 WKD PROJ. NO.: 20160049.00.1-11 2000 PSF SOIL (SAND S GRAVEL WITH CLAY) NOTES: 1. BASED ON 200 PSI STATIC PRESSURE PLUS AW WA WATER HAMMER ALLOWANCE. 2. ALL BEARING SURFACES TO BE CARRIED TO UNDISTURBED GROUND. 3. THRUST BLOCKS TO BE USED AT ALL LINES OPERATING UNDER PRESSURE. 4. KEEP ALL PIPING JOINTS CLEAR OF CONCRETE THRUST BLOCKS. THRUST BLOCKING DETAIL NOT TO SCALE WATER MAIN OR SAN RARY J STORM SEWER - SEWER MAIN WATER MAIN '— STORM SEWER OR SANITARY SEWER MAIN NOTE: WHEN A WATER MAIN OR SANITARY SEWER MAIN CROSSES OVER OR UNDER A STORM SEWER AND CONDITIONS PREVENT THE REQUIRED 1B• MIN VERTICAL SEPARATION, THE WATER MAIN ORB ITARY SEWER MAIN SHALL BE CONSTRUCTED OF DUCTILE IRON PIPE WITH JOINTS EQUIVALENT TO WATER MAIN STANDARDS FOR A MINIMUM DISTANCE OF 10 FEET ON EACH SIDE OF THE POINT OF CROSSING. RELATION OF WATER & SEWER MAINS TO STORM SEWERS NOT TO SCALE WIDTH VARIES 4 -THICK MECHANICALLY COMPACTED BACKFILL, 8' LAYERS. 95% STANDARD PROCTOR (PASHTO T-99) UNDISTURBED 1r IT TYPE 4 PIPE BEDDED IN SAND, GRAVEL, OR CRUSHED STONE TO A DEPTH OF 118 PIPE DIAMETER, 4- MINIMUM WITH BACKFILL COMPACTED TO TOP OF PIPE. (APPROXIMATELY W PERCENT STANDARD PROCTOR. AASHTO T-98) TYPE 3 PIPE BEDDED IN 4• MINIMUM LOOSE SOIL WITH BACKFILL LIGHTLY CONSOLIDATED TO TOP OF PIPE (LOOSE SOIL IS DEFINED AS NATIVE SOIL EXCAVATED FROM THE TRENCH, FREE OF ROCK, ORGANIC MATERIAL, FOREIGN MATERIALS AND FROZEN EARTH.) a TYPE 5 PIPE BEDDED TO IT'S CENTERUNE IN COMPACTED GRANULAR MATERIAL, 4' MINIMUM UNDER PIPE. COMPACTED GRANULAR OR SELECT MATERIAL TO TOP OF PIPE. (APPROXIMATELY 90 PERCENT STANDARD PROCTOR, AASTO TAB) (SELECT MATERIAL G DEFINED AS NATIVE SOIL EXCAVATED FROM THE TRENCH. FREE OF ROCKS, ORGANIC MATERIAL, FOREIGN MATERIALS AND FROZEN EARTH) NOTES: 1. TYPE 2 AND TYPE 3 SHALL BE THE SELECTED EMBEDMENT CONDITION FOR ALL DUCTILE IRON MAIN 144NCH AND URGER UNLESS ACTUAL LAYING CONDITIONS REQUIRE MORE STRINGENT (TYPE 4 OR 5) EMBEDMENT. 2 CONSIDERATION OF THE PIPE -ZONE EMBEDMENT CONDITIONS INCLUDED IN THIS FIGURE MAY BE INFLUENCE BY FACTORS OTHER THAN PIPE STRENGTH. FOR ADDITIONAL INFORMATION ON PIPE BEDDING AND BACKFILL, SEE ANSIIAWWAC000. 3. TRENCHES REQUIRING SHORING AND BRACING, DIMENSIONS SHALL BETAKEN FROM THE INSIDE FACE OF THE SHORING AND BRACING. 4. NO ROCKS OR BOULDERS 4' OR LARGER TO BE USED IN INITULL BACKFILL. 5. ALL BACKFILL MATERIAL SHALL BE SUITABLE NATIVE MATERIAL. S. BACKFILL SHALL BE TAMPED IN S' LIFTS IN TRAFFIC AREAS, 12' IN NON -TRAFFIC AREAS. 7. ACHIEVE 80% COMPACTION IN NON -TRAFFIC AREAS. AND OVA COMPACTION IN TRAFFIC AREAS. 8. IF IN EASEMENT 4' TOPSOIL, ANO 12' CLEAN SELECT FILL IS R 110K ED 9. NO BOULDERS B' IN DIAMETER OR GREATER ALLOWED IN FINAL BACKFILL. TYPICAL DUCTILE IRON MAIN EMBEDMENT DETAIL NOT TO SCALE CRUSHED STONE tGRAOE TO DRAIN MIN 17 jEMBEDMENTZONE 1•— VARIES TYPICAL TRENCH BACKFILL GRAVEL GREENWAY TRAIL REPAIR NOT TO SCALE yp. �- BOTTOM OF EXCAVATION (SEE NOTE 3 BELOW) NOTES: 1. BACKFILL TO 95% OF MAXIMUM DENSITY WHERE EXCAVATIONS CUT THROUGH PAVEMENTS. CURBS. DRIVEWAYS AND SIDEWALKS, AND UNDER OR ADJACENT TO STRUCTURES. 2. STONE TO BE SIZE 117 701-1/2', WELL TAMPED. 3. STONE IS REWIRED TO B• BELOW PIPE WHERE WET CONDITIONS OR ROCK IS ENCOUNTERED, ONLY AS DIRECTED. 4. HANG SHAPE TRENCH BOTTOM FOR LOWER QUADRANT OF PIPE AND BELLS. 5. PROVIDE MINIMUM Y'COVER OVER PIPE. CARRIER PIPE STANDARD WATER LIN_ E TRENCH NOT TO SCALE MUr RESTORE GRADE TO ORIGINAL -0'MIT / GROUND SURFACE ELEVATION. SEE NOTE 3 (VARIES WITH PIPE BACKFILL CLASS) NOTE 2 7TE1 NON -WOVEN ' 1 GEOTI. EXTI FABRIC FILTER NOTES: 1, S' DEEP NO. 57 STONE OR EQUAL WRAPPED IN NON -WOVEN GEOTEXTILE FILTER FABRIC LIGHTLY COMPACTED. OVERLAP FABRIC By MINIMUM ONE PIPE O.D. 2, 4- DEEP NO. 57 STONE OR EQUAL LIGHTLY COMPACTED PIPE BEDDING, 3. GENERALBACKFILL COMPACTED T09D% STANDARD PROCTOR DENSITY IN 6- MAXIMUM LIFTS. TYPICAL TRENCH BACKFILL UNSUITABLE SUBGRADE NOT TO SCALE z _O I- 0 Z) Lcr- ,,r^^ vJ z /O V O u- 0 W Q W J W L= O z WK CKSON i Ini—i—tum Wnsdwnm 401 4TH STREET SW SUITE 201 HICKORY, NORTH CAROLINA 28602 0)828.327-6911 (0628.327-9164 WW. W WKDICKSON.COM NC LICENSE NO.F-0374 nHAO�ce PROFESSIONAL SEAL Ix W � ZQ O � s Q G illlllllg U) z w 2 W OQ CL Z D_ J J 20 cr Q 0 W U w Z ccl: Q mO a W Z J W Q C WW UJ z J z J F W z 8 a O PROJ. MGR.: ' CRF DESIGN BY: CRF DRAWN BY: CH/RJL PROJ. DATE: I JUNE 2017 DRAWING NUMBER: C2.5 OF 29 WKD PROJ. NO.: 20160049.00.1-11 NOTES: 1. SEE PLANS AND SPECIFICATIONS FOR HOPE PIPE SIZE AND PRESSURE RATING. 2. CONTRACTOR SHALL ALLOW SUFFICIENT TIME FOR HOPE PIPE TO REBOUND AFTER PULLING PIPE THROUGH BORE. ::ITTIT:%:%:O-I IZ:! RESTRAINED JOINT RESTRAINED JOINT FOR NEXT (5) JOINTS CREEK BE" FOR NEXT (5) JOINTS HDPE TO DIP FLANGE ADAPTER RESTRAINED RETAINING GLAND - DUCTILE IRON GLAND RING IW MIN. HOPE PIPE WATER LINE DUCTILE IRON HDPE PIPE PIPE OR PVC PIPE S.S. REINFORCED SUPPORT RING FLANGE ADAPTER DETAIL CREEK CROSSING - HDPE HORIZONTAL DIRECTIONAL BORE NOT TO SCALE 24• A PAVEMENT WATER PLAN QF('TIf1N 0-0 A i' CHAMFER ALL SIDES ;.• CLASS A CONCRETE AIR ENTRAINED 3500 P.S.1 STANDARD VALVE BOX PROTECTOR NOTTO MSCALE THE ABOVE VALUES ARE BASED ON THE FOLLOWING DESIGN PARAMETERS, ANY VARIATION IN THESE DESIGN PARAMETERS DIRECTLY EFFECTS THE LENGTH OF REQUIRED RESTRAINED JOINT PIPE: -FLAT BOTOM TRENCH. BACKFILL LIGHTLY CONSOLIDATED TO CENTERLINE OF PIPE (WORST CASE) -CLAY OF MEDIUM TO LOW PLASTICITY, LIQUID LIMIT <50, <25% COARSE PARTICLES (CL -ML) -LAYING CONDITION: TYPE 2 SAFETY FACTOR: 1.5 SOIL DESIGNATION: CLAY 1 -DESIGN PRESSURE: 200 psl -DEPTH OF COVER: 3 FEET -TYPE OF PIPE: DUCTILE IRON PROTECTOR, VALVE BOXUNWSULATED STUSOUTTRACE WIRE TYPICAL COPPER TRACE TO TOP OF VALVE BOX WIRE. TYPICAL (2 PER BOX, TYPJ WATERLINE N N WATERLINE GATE VALVE SECTION/ELEVATION WATER LINE TRACE WIRE DETAIL NOT TO SCALE RESTRAINED JOINT TABLE NOTES: 1. THE LENGTH OF RESTRAINED JOINT PIPE (FLIP) ON THE BRANCH OF A TEE ASSUMES A MINIMUM OF 10 -FEET OF JOINTLESS PIPE ON EACH SIDE OF THE RUN. 2. ALL RESTRAINED LENGTHS (FT) REQUIRED EACH SIDE OF FITTING. 3THIS TABLE SHALL BE USED TO DETERMINE THE LENGTH OF FLIP IF FIELD CONDITIONS REQUIRE ADDITIONAL FITTINGS. SHOULD A CONFLICT EXIST BETWEEN THE PLAN DRAWINGS AND THIS TABLE. THE MORE STRINGENT SHALL GOVERN. NOT IN PAVEMENT IN PAVEMENT TYPE OF FITTING TRACER ASPHALT VALVE BOX WIRE LOOP THICKNESS AND COVER (VARIES) COMBINED VERTICAL OFFSET (UNDER OBJECT) COMBINED VERTICAL OFFSET (OVER OBJECT) ENTIRE PIPELINE 24' x 24" x 8" (MIN.) CONCRETE PAD OR AS DIRECTED BY ENGINEER BLUE INSULATED 14 GA COPPER TRACER WIRE TAPED TO PPE ENTIRE PIPELINE MIN 10 FT SPACING NOTES: HORIZONTAL THE PROPOSED DW RAW WATER LINE. VERTICAL UP BEND VERTICAL DOWN BEND Li fL POLY 90' BEND 45° BEND 22-12' BEND 11-1N' BEND DEAD 90° BEND 45' BEND 22-112° BEND 11-1/4' BEND 90' BEND 45' BEND 22.1/2' BEND 11-114' BEND 90' BEND 45° BEND 22-1/2' BEND 11-114' BEND 90' BEND 45' BEND 22.1/2' BEND 11.114° BEND NOM. SIZE WRAPPED HORIZ) (HORZ) (HORIZ) TEE (HORIZ)END (VERT) (VERT (VERT) ER (VERT) (VERT) (VERT) (VERT) (VERT) (VERT) (VERT) VERT) (VERT) (VERT) (VERT) (VERT) NO 114 48 23 12 78 SO 114 48 23 12 159 BB 32 16 127 58 27 90 41 18 1T YES 146 61 29 15 111 114 146 81 28 15 227 94 45 23 183 85 40 118 53 24 THE ABOVE VALUES ARE BASED ON THE FOLLOWING DESIGN PARAMETERS, ANY VARIATION IN THESE DESIGN PARAMETERS DIRECTLY EFFECTS THE LENGTH OF REQUIRED RESTRAINED JOINT PIPE: -FLAT BOTOM TRENCH. BACKFILL LIGHTLY CONSOLIDATED TO CENTERLINE OF PIPE (WORST CASE) -CLAY OF MEDIUM TO LOW PLASTICITY, LIQUID LIMIT <50, <25% COARSE PARTICLES (CL -ML) -LAYING CONDITION: TYPE 2 SAFETY FACTOR: 1.5 SOIL DESIGNATION: CLAY 1 -DESIGN PRESSURE: 200 psl -DEPTH OF COVER: 3 FEET -TYPE OF PIPE: DUCTILE IRON PROTECTOR, VALVE BOXUNWSULATED STUSOUTTRACE WIRE TYPICAL COPPER TRACE TO TOP OF VALVE BOX WIRE. TYPICAL (2 PER BOX, TYPJ WATERLINE N N WATERLINE GATE VALVE SECTION/ELEVATION WATER LINE TRACE WIRE DETAIL NOT TO SCALE RESTRAINED JOINT TABLE NOTES: 1. THE LENGTH OF RESTRAINED JOINT PIPE (FLIP) ON THE BRANCH OF A TEE ASSUMES A MINIMUM OF 10 -FEET OF JOINTLESS PIPE ON EACH SIDE OF THE RUN. 2. ALL RESTRAINED LENGTHS (FT) REQUIRED EACH SIDE OF FITTING. 3THIS TABLE SHALL BE USED TO DETERMINE THE LENGTH OF FLIP IF FIELD CONDITIONS REQUIRE ADDITIONAL FITTINGS. SHOULD A CONFLICT EXIST BETWEEN THE PLAN DRAWINGS AND THIS TABLE. THE MORE STRINGENT SHALL GOVERN. NOT IN PAVEMENT IN PAVEMENT CAST IRON TRACER ASPHALT VALVE BOX WIRE LOOP THICKNESS AND COVER (VARIES) MARKER TAPE ENTIRE PIPELINE 24' x 24" x 8" (MIN.) CONCRETE PAD OR AS DIRECTED BY ENGINEER BLUE INSULATED 14 GA COPPER TRACER WIRE TAPED TO PPE ENTIRE PIPELINE MIN 10 FT SPACING NOTES: 1, TRACER WIRE SHALL BE PLACED ALONG THE ENTIRE LENGTH OF THE PROPOSED DW RAW WATER LINE. TRACER WIRE IN VALVE BOX NOT TO SCALE 7�N WATER 5.75" DROP LID p. 5.314' 7yg" Hi IIS--I-II BOTTOM SECTION 1/4• 3118' I 8.125" I e" TOP SECTION �•��j 9.1rz• 10-v4. NOTES: 1. LID CASTING TO BE TYLER MANUFACTURE NO. 6850-SERIES. 5-114- DROP LID OR APPROVED EQUAL. 2. BODY CASTING TO BE TYLER MANUFACTURE NO.6955•SERIES, 5-1/4' SHAFT, SLIP OR SCREW TYPE, OR APPROVED EQUAL. 3. THIS VALVE BOX ACCOMODATES 4• THRU 12' VALVES. STANDARD THREE PIECE VALVE BOX NOT L WK CKSON unit Inllest—l—co05ulleft 401 4TH STREET SW SUITE 201 HICKORY, NORTH CAROLINA 28602 8)828-327-6911 (n828327-9164 W W W. WKDiCKSON.COM NC LICENSE NO.F-0374 w� W nHA w, 'OLPN•'ss�' �F9 $ fl FUSION& 8 o z O o IIIIIIIIZ Z Lu Lu cr Z D_ J J c- O a CQ 0 LliU z } ¢ O Q L1J z Q Z Q J ¢ LU Q L.U. Z i Y J W LL) 2 a �¢ a o PROD. MGR.: CRF DESIGNBY: CRF DRAWN BY: &lRJL PROD. DATE: JUNE 2017 DRAWING NUMBER: C2.6 OF 29 WKD PROJ. NO.: 20160049.00. HI TYP KEY IN MATTING PER MANUFACTURFAS WSTNUCTKINS- LIVE STAIQ PIANTWGS BEE DETAIL DWG. GI – COIR FIBER M1WTTING I4Wym') COIR FIBER ROLL TO BE MELD IN PUCE WITH WOODEN STARES PER MANUFACTURERS NSTRUGTKINS GRAVEL SUBSTRATE 50180 MO( OF N SRU SOIL ANO k 5 STONE FLOW B NOTE: PRIORT0 ANY LAND DISTURBING ACTIVITIES. CONTRACTOR SHALL CLEARLY MARK WITH ORANGE FABRIC FENCING ALL WETLANDS, STREAMS, SURFACE WATERS, AND RIPARIAN BUFFERS LOCATED ON THE PROJECT SITE WHERE IMPACTS ARE NOT ALLOWED. A GRADE CONTROL ROCK 50/50 MIX CLASS B / 1 RIP RAP j, STOP Of BWK I zj WIDTH OF DISTURBANCE �aLL. SEE aTREAM BED CONTROL DETAIL LIMBED TO 16' Y1: MATCH ExISTING STREAM BE GRADE A M STREAM BED CONTROL -PLAN VIEW CREEK CROSSING STABILIZATION EROSIONCONTROLMATTING — EROSION CONTROL MATTING MATCH EXISTING CHANNEL FULLBANK WIDTH (SEE—ILSHEETOJ IWMI NOT TO SCALE - (SEE DETAIL SHEET G3) ) L.l BANKFULL ELEVATION ISM. INVERT SET AT PROFILE DEFLECTION SEW CONSTRUCTED GRADE NOTES: FROM SALVAGED RIVER BED BOULDERS 1) CONTRACTOR SHALL FOLLOW CONSTRUCTION SEQUENCE AS NOTSOON CONTRACT DRAWINGS, 2) EXCAVATION SPOIL 15 TO BE LOCATED OUTSIDE PLAN NCOOT F5 OR #67 FB.TER�� 2.0 OF 100 YEAR FLOODWAY. WASHED STONED FABRIC• (C MIR) GRAVEL SUBSTRATE GRADE CONTROL ROC( I Yd• 2.N CAPACITY OF PIPE CULVERT 50/50 MIX OFIN SITU SOIL 60/50 MIX CUSS B/1 RP RAP POLY ETHYLENE MEMBRANE ON ' tO YEAR STORM ANDBS STONE FACE 20 MIL THICK I LEVEL WITH TOP OF BMa( OR AS NECESSARY CLASS 11 EROSION STONE STREAM BEO CONTROL • SECTION A -A •yjpp _ _ BANKFULL ELEVATION O((7'•• 0 1 �� – – TOP OF RIFFLE ROW SOTTOMOFRIFFLE (MATCH EXISTING ELEV.) (MATCH EXISTING ELEV.) n •a ,p •a T�� �– — SLOPE VARIES FOESIGSURFACEED •9 p CLAS RIP RAP. NJ BARRIER – �O to OR GiJ OR OTHER APPROVED MATERIAL – $�p D •p ELEVATION R� •p B r/ 25 LF OF 30' HDPE PIPE FLOW 1. M P ' I7 sa SEELPROFILE FOR NCOOT p5011tl57 I ` I TCN EXISTING GRADE ELEVATION WASHED STONED CUSS II EROSION STORE FILTER P A FABRIC GRAVEL SUBSTRATE Y W I W MBX GF N SRU SOK GRADE CONTROL ROCK —_ -- AND 45 STONE 50150 MOX CLASS B /1 RIP RAP SANDBAGS. C1A531 qIP RPP IV -15' STREAM BED CONTROL - PROFILE B -B OR OTHER NONSROUIBLE MATERIAL SYWHETICFlLTERFABRIC SECTION A �G:.F STREAM BEN COCALE DETAIL 25'MIN, 25'MIN.COFFER DAM — HORSESHOE BANK J�"""EL OP OF BANK MATCH EXISTING GRADE PLAN NOT TO SCALE PROPOSED CREEK CROSSING (TEMPORARY) NOT TO SCALE CHANNEL SEEDING TEMPORARY SEED MIX UTE WINTERIEARLY SPRING AYE (GRAIN) 0 120 LB/ACRE SUMMER CONSTRUCTION NOTESNOTES: -GERMAN MILLET 040 LB/ACRE 1. INSTALL EROSION CONTROL MEASURES AND TREE SUDANGRASS 050 L&ACRE (AS A SUBSTITUTE) PROTECTION AS SHOWN ON PLAN. THE CONTRACTOR MAY MODIFY OR RELOCATE EROSION CONTROL MEASURES TO MAKEADJUSTMENTS FOR UNFORESEEN FIELD ROpp FALL CONDITIONS. ALL RELOCATION SHALL HAVE THE -RYE (GRAIN) 0120 LBIACRE APP2, CLEARR AND GRUB AREAOVAL OF THE OF ALL TRASH ANO EXOTICINVASIVE VEGETATION. / PERMANENT RIPARIAN SEED MIX (IDEALLY PUNTED EITHER 3. STABILIZE GRADED BANKS WITH SEED AND MULCH. LSTONESIZE GATE- AUG -SEPT OR MAR -APR) 4. INSTALL COIR FIBER MAT PER MANUFACTURER'S S' AEOTOP 0 7 LSIACRE INSTRUCTION, -SWITCH GRASS 050 LBIACRE 5. INSTALL PLANTSAS DESCRIBED IN PUNTING NOTES ON DWG. G4. SEDGE ® 10 LSIACRE "THICK RICE CUTGRASS 0 20 LB/ACRE MINIMUM L GE TEXTILE FABRIC INSTALLED MAINTENANCE: UNDER CONSTRUCTION ENTRANCE MAINTAIN THE GRAVEL PAD IN A CONDITION TO PREVENT MUD OR SEDIMENT FROM LEAVING THE CONSTRUCTION SITE, THIS MAY REQUIRE PERIODIC TOP DRESSING WITH 24NCH STONE. AFTER EACH RAINFALL, INSPECT ANY STRUCTURE USED TO TRAP SEDIMENT AND CLEAN IT OUT AS NECESSARY. IMMEDIATELY REMOVE ALL OBJECTIONABLE MATERIALS SPILLED, WASHED, OR TRACKED ONTO PUBLIC ROADWAYS. TEMPORARY GRAVEL CONSTRUCTION ENTRANCE NOT TO SCALE NOTE: ALTERNATIVE SPECIES MAY BE USED UPON APPROVAL BY THE ENGINEER, STREAM STABILIZATION NOTES NOT TO SCALE DWK DICKSON mmmunitvhastluc mp h nW 401 4TH STREET SW SUITE 201 HICKORY, NORTH CAROLINA 286G2 p1e28-327$911 (0828-327-9164 W W W.WKDICKSON.COM NC LICENSE NO.F-0374 .MP. iEaS W,: F4' N n lul llm��c� PROFESSIONAL SEALEE U) F– z Lu 2 Lu CC z mi 0 15 cr G Q 0 Lu U z Z In cr O �O Q UL z �Q Q Z W J W Q cr w Z w H z J ~ W W Z Q a o PROJ. MGR.: CRF DESIGN BY: CRF DRAWN BY: CHIRJL PROD. DATE: JUNE 2017 DRAWING NUMBER: C2.8 OF 29 WKD PROJ. NO.: 20160049.00.HI O 8w� ¢ O � O O 941.08-99-4023 ' ^ - - \\\ \�\� \ \ , Town of Elkin _ - - _ - --5. UNLESS NOTED OTHERWISE, FILL MATERIAL GENERATED FROM UNNAMED TRIBUTARY CHANNEL EXCAVATION AND _ STABILIZATION SHALL BE PLACED INSIDE THE EXISTING CHANNEL TO BE ABANDONED AT AN ELEVATION THAT PROVIDES 'zC{7* \ \\ \\�\�\\� \� \\\� = \ \ - RB 1460 PG 942 POSITIVE DRAINAGE TOWARDS THE PROPOSED CHANNEL. 6. DISTURBED BANKS ARE TO BE STABILIZED WITH SEEDING, MATTING AND LIVE STAKES PER "CREEK CROSSING STABILIZATION" \�\ \\ = = \� \ \\ \\'=_ _ �` / // DETAIL AND STREAM STABILIZATION NOTES" ON DRAWING C2.8. DISTURBED AREAS BEYOND THE BANKS ARE TO BE �_ ` = = ` = _ 85p� / / / i STABILIZED WITH SEEDING PER 'TEMPORARY SEEDING SCHEDULE" AND "PERMANENT SEEDING SCHEDULE" ON DRAWING G4. 926.85` �_- \\ \ � �-------� \•9 \ - -^``\ -^^�^ -_^\__ _-_� �- �-/CST AREK 0/1�' PROPOSED 32 LFt BOI]LDEf� \ \ \^\,.a\ \\� `�� -__� �;� 58RFBAR \ \ \\\� ( \ TOE PROTECTION #3 W/ROOT WAD. \ \ \ -- __-'-��^----__--// -\926 / \ \ \ \ / v \ BOULDER SIZE 4'x3'x2' HIGH, ^ -Z'- ^ ^� _ _ --� �; ^� \ = / i / / / / /.85 - \\\ ^ ^ ^ - _= ^ � ^ ^ ^ ^ ^ / / / ' x %r! / \ SEE QETAIL C3.4 \ \ i / / / / / / r A/ /� \,\\\v� ^\� - ^_= Stream Impact S5 sxzs.es/ � \\ \ TOP 920:5 - 00 \ A\\ INV 918.5 /� 4p5 ,- \\ `\ \\ \\ = \ `•-:- /i// �'� - - - - / // OOJ 928.85 '�ROF'OBED ROCK J -HOOK #1 / <� \ \ \TOP 920.5 \ \ •COO \ x �\ \ \�\ TOTAL: NE LF 9173 _ OPOSED R KJ -6.00% \^�\\ RMDETAIL84 L� SLOPE ARM VANE: LF 8.00%SLOP / SFS DETAIL 4 925 \ Ex. 24" RA'i/\ .`w\ \\ '_ \\\\\\\ \\ \ \\ \ WATER LINE \ \�-' \ \ \ \ - - 3y \\\ \ ^-- TOTAL: 98 ROCK,(-HOOKi ^�\ \\ \\\\ `\\\ \\ / (\ 75� \ �- ---__� -ARM VANE:7 F@6.00%SLOPE^ 'L00 Y�/3i/sy/` // y\0r// //� �i�` /;'• \^ ZO SEE D AIL C3. TOP -FT LOD LID `B�ioLWA6, TVR \\� � �(O0 \\ \K•` \\\ ^^-/ .w \ \\ ` �\ �` \ \ 912. PROPOSED 72 LFt BOULDER \,, J ^11V TOE PROTECTION #2 W/ROOT WAD '-'-Z _ _ __ - _ _ -_ BOULDER SIZE 4'x3'x2'HIGH --'--- -- i \ \ \\ \ \ \ LL \ \ \W SEE DETAIL C3.4 PROVIDE ADDITIONAL TIER OF \ \ \ \ BOULDERS UNDER J -HOOK AT \ \ \\ TRIBUTARY OUTFALL IO FEET g3 O EACH SIDE OFCENTERLINE (20- \\\\\ FEET TOTAL) SL OF 'bSED hT' EME�GENFV \ \ \ \ \ \ ` \ COD \ \ \ PROPOSED CHANNEL ROV WATERLINE \ \ \ \ Op \ `\ \ REALIGNMENT \ \\ \ \\ 9g0\4DIVISI9N 2)\\\ \ \ \\ \\\\\ \ \ ^ \ \\ L \�SYE DRAWING C3.3 LOD PROPOSED 111111 PROPOSED CHANNELyLUG, \ \ \ \ \ \ \ \ \ I SEE DETAIL C3.6 /\ / BIG ELKIN CREEK RESTORATION >/L+ SCALE: 1"=20' 925 920 915 910 905 EX 24" RAW / WATER LINE /CSC1 E 7:7- LODD SEB All. C3.5 / Stream Impact S2 NACIEU TTARY 00 ELKIN CREEK 1r Ld0 A / //A NOTES' PROPOSED ROCK J -HOOK #3 - -50 - EXISTING CONTOUR MINOR -- 1. IN GENERAL, STREAM CONSTRUCTION SHALL PROCEED FROM AN UPSTREAM TO DOWNSTREAM DIRECTION. ^�� ^ \�� ` _ _-_--__r__ _ �_ ^-� �� �^ 2. ALL EXCAVATED MATERIAL MUST BE PLACED WITHIN DESIGNATED STOCKPILE AND.'OR STAGING AREAS LOCATED ON-SITE. SEE DETAIL Q3.4 - 3. ALL IMPERVIOUS DIKES AND BYPASS PUMPING EQUIPMENT FOR UNNAMED TRIBUTARY SHALL BE MODIFIED AT THE END OF TOP 920.5 EACH DAY TO RESTORE NORMAL FLOW BACK TO THE CHANNEL. 97S D TOP 920.5 4. CONTRACTOR SHALL NOT COMPACT SOIL AROUND ROOTS OR TREES TO REMAIN, AND SHALL NOT DAMAGE SUCH TREES IN PROPOSED CHANNEL PLUG ANY WAY. EXCAVATED OR OTHER MATERIAL SHALL NOT BE PLACED, PILED OR STORED WITHIN THE CRITICAL ROOT ZONE P/N4 AREA OF THE TREES TO BE SAVED. 941.08-99-4023 ' ^ - - \\\ \�\� \ \ , Town of Elkin _ - - _ - --5. UNLESS NOTED OTHERWISE, FILL MATERIAL GENERATED FROM UNNAMED TRIBUTARY CHANNEL EXCAVATION AND _ STABILIZATION SHALL BE PLACED INSIDE THE EXISTING CHANNEL TO BE ABANDONED AT AN ELEVATION THAT PROVIDES 'zC{7* \ \\ \\�\�\\� \� \\\� = \ \ - RB 1460 PG 942 POSITIVE DRAINAGE TOWARDS THE PROPOSED CHANNEL. 6. DISTURBED BANKS ARE TO BE STABILIZED WITH SEEDING, MATTING AND LIVE STAKES PER "CREEK CROSSING STABILIZATION" \�\ \\ = = \� \ \\ \\'=_ _ �` / // DETAIL AND STREAM STABILIZATION NOTES" ON DRAWING C2.8. DISTURBED AREAS BEYOND THE BANKS ARE TO BE �_ ` = = ` = _ 85p� / / / i STABILIZED WITH SEEDING PER 'TEMPORARY SEEDING SCHEDULE" AND "PERMANENT SEEDING SCHEDULE" ON DRAWING G4. 926.85` �_- \\ \ � �-------� \•9 \ - -^``\ -^^�^ -_^\__ _-_� �- �-/CST AREK 0/1�' PROPOSED 32 LFt BOI]LDEf� \ \ \^\,.a\ \\� `�� -__� �;� 58RFBAR \ \ \\\� ( \ TOE PROTECTION #3 W/ROOT WAD. \ \ \ -- __-'-��^----__--// -\926 / \ \ \ \ / v \ BOULDER SIZE 4'x3'x2' HIGH, ^ -Z'- ^ ^� _ _ --� �; ^� \ = / i / / / / /.85 - \\\ ^ ^ ^ - _= ^ � ^ ^ ^ ^ ^ / / / ' x %r! / \ SEE QETAIL C3.4 \ \ i / / / / / / r A/ /� \,\\\v� ^\� - ^_= Stream Impact S5 sxzs.es/ � \\ \ TOP 920:5 - 00 \ A\\ INV 918.5 /� 4p5 ,- \\ `\ \\ \\ = \ `•-:- /i// �'� - - - - / // OOJ 928.85 '�ROF'OBED ROCK J -HOOK #1 / <� \ \ \TOP 920.5 \ \ •COO \ x �\ \ \�\ TOTAL: NE LF 9173 _ OPOSED R KJ -6.00% \^�\\ RMDETAIL84 L� SLOPE ARM VANE: LF 8.00%SLOP / SFS DETAIL 4 925 \ Ex. 24" RA'i/\ .`w\ \\ '_ \\\\\\\ \\ \ \\ \ WATER LINE \ \�-' \ \ \ \ - - 3y \\\ \ ^-- TOTAL: 98 ROCK,(-HOOKi ^�\ \\ \\\\ `\\\ \\ / (\ 75� \ �- ---__� -ARM VANE:7 F@6.00%SLOPE^ 'L00 Y�/3i/sy/` // y\0r// //� �i�` /;'• \^ ZO SEE D AIL C3. TOP -FT LOD LID `B�ioLWA6, TVR \\� � �(O0 \\ \K•` \\\ ^^-/ .w \ \\ ` �\ �` \ \ 912. PROPOSED 72 LFt BOULDER \,, J ^11V TOE PROTECTION #2 W/ROOT WAD '-'-Z _ _ __ - _ _ -_ BOULDER SIZE 4'x3'x2'HIGH --'--- -- i \ \ \\ \ \ \ LL \ \ \W SEE DETAIL C3.4 PROVIDE ADDITIONAL TIER OF \ \ \ \ BOULDERS UNDER J -HOOK AT \ \ \\ TRIBUTARY OUTFALL IO FEET g3 O EACH SIDE OFCENTERLINE (20- \\\\\ FEET TOTAL) SL OF 'bSED hT' EME�GENFV \ \ \ \ \ \ ` \ COD \ \ \ PROPOSED CHANNEL ROV WATERLINE \ \ \ \ Op \ `\ \ REALIGNMENT \ \\ \ \\ 9g0\4DIVISI9N 2)\\\ \ \ \\ \\\\\ \ \ ^ \ \\ L \�SYE DRAWING C3.3 LOD PROPOSED 111111 PROPOSED CHANNELyLUG, \ \ \ \ \ \ \ \ \ I SEE DETAIL C3.6 /\ / BIG ELKIN CREEK RESTORATION >/L+ SCALE: 1"=20' 925 920 915 910 905 EX 24" RAW / WATER LINE /CSC1 E 7:7- LODD SEB All. C3.5 / Stream Impact S2 NACIEU TTARY 00 ELKIN CREEK 1r Ld0 A / //A I PROFILE SCALE: HORIZONTAL: 1"=40' j VERTICAL: 1"=4' 17+00 16+00 15+00 913. �Dii/iii i V811.8 iGi/ice ii � ILL AREA 0. 0' � -IiA A. 911.1 y 'i9"/'� / / X i 'PROPOS 12" EMERGENCY RA TER LINE / SION 2) / / PROTECTION D 100 LFyBOUJ.DER / PROTECJION #1 BOl1LDE"IZE 4' 'HIGH, / E,DETAIL C814 / / / LEGEND PROP" ED J -HOOK #2 72 LF a 6.00%SLOPE SEE DETAIL C3.4 PROPOSED ROCK J -HOOK #1 TOP 919.6 83 LF@6.00%SLOPE TOP 919.7 � SEE DETAIL C3.4 �= TOP 919.6 TOP 919.1 PROPOSED GRADE ------ \� (BIG ELKIN CREEK) INV 913.8 INV- 911.7 - PROPOSED 100 LFt BOULDER J TOE PROTECTION #1 BOULDER SIZE 4'x35(2' HIGH, SEE DETAIL C3.4 `- INV 911.1 INV 911.6 925 920 915 910 905 LIMITS OF DISTURBANCE - LOD LOD - PROPOSED ROCK J -HOOK #3 - -50 - EXISTING CONTOUR MINOR -- 72 LF @ 6.00% SLOPE - ' - LU SEE DETAIL Q3.4 j TOP 920.5 x 2.055 TOP 920 9' D TOP 920.5 z PROPOSED CHANNEL PLUG a (SEE DETAIL DWG C3.5) ' EXISTING CR`RE K (BIG ELKIN CREEK) Q cc W Z INV 918.5 O > J � W W cc U O Y W F zcr w U ..INV 9185 a ¢ INV 914.9 PROPOSED 32 LF3 BOULDER T PROTECTION #3; BLDER SIZE 4'XNX2' HIGH, Z PROPOSED 72 LFt BOULDER - TOE PROTECTION #2; SEE DETAIL C3 4 -.. _ -_- - BOULDER SI F 4 X32' HIGH U SEE DETAIL C3.4 I PROFILE SCALE: HORIZONTAL: 1"=40' j VERTICAL: 1"=4' 17+00 16+00 15+00 913. �Dii/iii i V811.8 iGi/ice ii � ILL AREA 0. 0' � -IiA A. 911.1 y 'i9"/'� / / X i 'PROPOS 12" EMERGENCY RA TER LINE / SION 2) / / PROTECTION D 100 LFyBOUJ.DER / PROTECJION #1 BOl1LDE"IZE 4' 'HIGH, / E,DETAIL C814 / / / LEGEND PROP" ED J -HOOK #2 72 LF a 6.00%SLOPE SEE DETAIL C3.4 PROPOSED ROCK J -HOOK #1 TOP 919.6 83 LF@6.00%SLOPE TOP 919.7 � SEE DETAIL C3.4 �= TOP 919.6 TOP 919.1 PROPOSED GRADE ------ \� (BIG ELKIN CREEK) INV 913.8 INV- 911.7 - PROPOSED 100 LFt BOULDER J TOE PROTECTION #1 BOULDER SIZE 4'x35(2' HIGH, SEE DETAIL C3.4 `- INV 911.1 INV 911.6 925 920 915 910 905 LIMITS OF DISTURBANCE - LOD LOD - EXISTING CONTOUR MAJOR - -50 - EXISTING CONTOUR MINOR -- -- -- --- 46 - -- - PROPOSED CONTOUR MAJOR LU PROPOSED CONTOUR MINOR y� PROPOSED SPOT SHOT x 2.055 PROPOSED CENTERLINE OF D CHANNEL z PROPOSED CHANNEL PLUG a (SEE DETAIL DWG C3.5) z LOG SILL (SEE DETAIL DWG C3.5) LOG SILL (PROFILE) J -HOOK VANE STRUCTURE LU (PROFILE) LL BOULDER a ROOT WAD D �DICKSON 401 4TH STREET SW SUITE 201 HICKORY, NORTH CAROLINA 28602 tt)W8327-6911 (Q828327-9164 W W W.WKDICKSON.COM NO LICENSE NO.F-0374 41, `` p. ......,0U . �ppE83/p'' Q1 SEAL /I 13 IIUU �xnx min�`„w� �•I7.2o1"} PROFESSIONALSEAL CO Z W 2 LU W LL =Z a CL M 20 D oCC0 z W() Z a U)=0 Er z i Q cc W Z O > J � W W cc U O Y W F zcr w U a ¢ O� W U E w s �o I I�Ig CO Z W 2 LU W LL =Z a CL M 20 D oCC0 z W() Z a U)=0 Er z Ln O Q cc W Z O > J � W W cc U Y W F zcr w PROJ. MGR.: CRF DESIGN BY: CRF DRAWN BY: -'-JLOD PR. DATE: JUNE 2017 DRAWING NUMBER: C3.1 OF 29 WKD PROJ. NO.: 20160049.00.H1 NOTES: 1. IN GENERAL, STREAM CONSTRUCTION SHALL PROCEED FROM AN UPSTREAM TO DOWNSTREAM DIRECTION. \ 2. ALL EXCAVATED MATERIAL MUST BE PLACED :NITHIN DESIGNATED STOCKPILE AND/OR STAGING AREAS LOCATED ONSITE. 3. ALL IMPERVIOUS DIKES AND BYPASS PUMPING EQUIPMENT FOR UNNAMED TRIBUTARY SHALL BE MODIFIED AT THE END OF EACH DAY TO RESTORE NORMAL FLOW BACK TO THE CHANNEL. 4. CONTRACTOR SHALL NOT COMPACT SOIL AROUND ROOTS OR TREES TO REMAIN, AND SHALL NOT DAMAGE SUCH TREES IN ANY WAY. EXCAVATED OR OTHER MATERIAL SHALL NOT BE PLACED, PILED OR STORED WITHIN THE CRITICAL ROOT ZONE AREA OF THE TREES TO BE SAVED. 5. UNLESS NOTED OTHERWISE, FILL MATERIAL GENERATED FROM UNNAMED TRIBUTARY CHANNEL EXCAVATION AND STABILIZATION SHALL BE PLACED INSIDE THE EXISTING CHANNEL TO BE ABANDONED AT AN ELEVATION THAT PROVIDES \ POSITIVE DRAINAGE TOWARDS THE PROPOSED CHANNEL 6. DISTURBED BANKS ARE TO BE STABILIZED WITH SEEDING, MATTING AND LIVE STAKES PER "CREEK CROSSING STABILIZATION" DETAIL AND "STREAM STABILIZATION NOTES" ON DRAWING C2.8. DISTURBED AREAS BEYOND THE BANKS ARE TO BE STABILIZED WITH SEEDING PER "TEMPORARY SEEDING SCHEDULE" AND "PERMANENT SEEDING SCHEDULE" ON DRAWING G4. -- - - - - - - - - - - - - — — - 930 - — — — — — — _ _ -__ _-�_ -- / \92s�.y — — — 925 �9' m 'L-; Wetland Impact Sl —915 !V —— ------ —'�/ --- --- -- ST _ _D __-1-0O��ti5u7�FSr— —_---- ------------------- ___WLB OD S� _---___ E%. 24 RAW Z — — — -WATER LINE " '� \ tY] \ — tiv� - .-----•---- • •- ---b /---•----- -----w-- -�-' ---•--`•----- --\ - ----- --- --------•--- -- -� • --r-----•---- -- -� -- - -��- y --- -- -- W— ---w----W--- -- --�•— -- --w --w —w—� W----- 7— — —w---- g�--- \ --W-----W 1 / / \ ----�L _ / 1 \\s �W��'! EX 24' AW `+•4JJ- LOD 4LWATEI:UNE— —_- -_g3- _ — — _ — == =QN— eRIncE31F8 B EUI'-, ti -I PIER—.--- — _ 1 E. EMERGENCY WATERLINE_ --- iDI0�2) — LEGEND BIG ELKIN CREEK RESTORATION SCALE: 1"=20' LIMITS OF DISTURBANCE — LOD LOD — EXISTING CONTOUR MAJOR — — — 50 — — — EXISTING CONTOUR MINOR — — --- — — 46 PROPOSED CONTOUR MAJOR w PROPOSED CONTOUR MINOR PROPOSED SPOT SHOT X 2.055 PROPOSED CENTERLINE OF CHANNEL PROPOSED CHANNEL PLUG (SEE DETAIL DWG C3.5) LOG SILL (SEE DETAIL DWG C3.5) LOG SILL (PROFILE) J -HOOK VANE STRUCTURE I I (PROFILE) Tu(' BOULDER ROOT WAD MWDIKCKSON - �esvucloreconeunenm 401 4TH STREET SW SUITE201 HICKORY, NORTH CAROLINA 29602 (t)62a 32711 MS26,327-9184 W W W.WKDICKSON.COM NC LICENSE NOT -0374 \N\NNlllllllllblbl ��•(H CARO�� :A O.•'F683 SEAL ,9�' Ci1NE o,4n� N inNN PROFESSIONAL SEAL Ir 0 U W m¢ o 14 cc w U) H z W 2 W crZ z 20 5 ma M o w U z 1= >- I— O_ Icc ~ N W O L Q Z W J U W W Z ZrJ LU 2 a � a o PROD. MGR.: CRF DESIGN BY: CRF DRAWN BY: CH/RJL FRQI. DATE: JUNE 2017 DRAWING NUMBER: C3.2 OF 29 WKD PROJ. Ni 20160049.00.H1 -PROPOSED BIG ELKIN •4.4. r � 3 'STA. 10+30 1 / /PROPOSED LOG SILL, SEE DETAIL DWG. C .5 x� 5 LOD LOD ME=* I//, / — LOD 'L DWXiOATWLIW- ��� / CFjANNgL4LUG� SEC3,5'�%/����' / STA. PROPOSED LOG SILL, 3.5 SEE DETAIL DWG. /RFROM STAR/TACHANNEL / IIIIIIIII LOD .06 L'09 /R/pp4E61fEypTjI"RY CHANNEL / !, \ \ 1-----L_7_— E%IS NG 2" HDPEi UNNAMED TRIBUTARY TO BIG ELKIN CREEK RE -ALIGNMENT SCALE: 1"=10' PROPOSED GRADE, TYP..r EXISTING GRADE, TYP. — — L VARIES 2:1 I 2:1 1 TYPICAL CHANNEL CROSS SECTION UNNAMED TRIBUTARY TO BIG ELKIN CREEK SCALE: HORIZ. 1"=20' VERT. 1"=2' NOTES: 1. IN GENERAL, STREAM CONSTRUCTION SHALL PROCEED FROM AN UPSTREAM TO DOWNSTREAM DIRECTION. 2. ALL EXCAVATED MATERIAL MUST BE PLACED WITHIN DESIGNATED STOCKPILE ANDIOR STAGING AREAS LOCATED ONSITE. 3. ALL IMPERVIOUS DIKES AND BYPASS PUMPING EQUIPMENT FOR UNNAMED TRIBUTARY SHALL BE MODIFIED AT THE END OF EACH DAY TO RESTORE NORMAL FLOW BACK TO THE CHANNEL. 4. CONTRACTOR SHALL NOT COMPACT SOIL AROUND ROOTS OR TREES TO REMAIN, AND SHALL NOT DAMAGE SUCH TREES IN ANY WAY. EXCAVATED OR OTHER MATERIAL SHALL NOT BE PLACED, PILED OR STORED WITHIN THE CRITICAL ROOT ZONE AREA OF THE TREES TO BE SAVED. S. UNLESS NOTED OTHERWISE, FILL MATERIAL GENERATED FROM UNNAMED TRIBUTARY CHANNEL EXCAVATION AND STABILIZATION SHALL BE PLACED INSIDE THE EXISTING CHANNEL TO BE ABANDONED AT AN ELEVATION THAT PROVIDES POSITIVE DRAINAGE TOWARDS THE PROPOSED CHANNEL. 6. DISTURBED BANKS ARE TO BE STABILIZED WITH SEEDING. MATTING AND LIVE STAKES PER'CREEK CROSSING STABILIZATION' DETAIL AND *STREAM STABILIZATION NOTES' ON DRAWING C2.8. DISTURBED AREAS BEYOND THE BANKS ARE TO BE STABILIZED WITH SEEDING PER 'TEMPORARY SEEDING SCHEDULE' AND'PERMANENT SEEDING SCHEDULE' ON DRAWING G4. LEGEND H LIMITS OF DISTURBANCE — LOD LOD EXISTING CONTOUR MAJOR — 930 EXISTING CONTOUR MINOR -- -- -- - - 46 - - - - - PROPOSED CONTOUR MAJOR 930 PROPOSED CONTOUR MINOR y PROPOSED SPOT SHOT EXISTING UNNAME6 TRIBUTARY TO BIG ERIN CRgK PROPOSED CENTERLINE OF PROPOSED NEW GRADE = U 0cc w (UNNAMED TRIBUTARY i TO BIG 2 Q C7 Z 925 . _.- -- - - --I----- - -. 925 I I , Z W Z w Or >Q > J } Cc , W H I D] PROOOSED J-HOOKVANE 43 920 ___ -..._. _ �.._. _:_. .-..- -- ----_.__ _ TOP 8197 .- ---- 920 Y J W PROPOSED LOG SILL,; O a $' o SEE DETAIL DWG. Cl. 1 1 ) I I I //�I'\/'�/1� II NG BIG ELKIN CR --I &SIEI PROPOSED 12" EMERGENCY " RAW WATER LINE (DIVISION 2) 1 -i PROPOSED LOG SILL, SEE DETAIL DWG. C35 I 915 . _.- '�, - -.. ---- -- 'I ---- 915 EXISTING 24" DIP RAW WATER LINE (APPROX. LOCATION AND DEPTH) I i 910 910 m 0 a N � 11+00 10+00 UNNAMED TRIBUTARY TO BIG ELKIN CREEK SCALE: HORIZ. 1"=20' VERT. 1"=2' NOTES: 1. IN GENERAL, STREAM CONSTRUCTION SHALL PROCEED FROM AN UPSTREAM TO DOWNSTREAM DIRECTION. 2. ALL EXCAVATED MATERIAL MUST BE PLACED WITHIN DESIGNATED STOCKPILE ANDIOR STAGING AREAS LOCATED ONSITE. 3. ALL IMPERVIOUS DIKES AND BYPASS PUMPING EQUIPMENT FOR UNNAMED TRIBUTARY SHALL BE MODIFIED AT THE END OF EACH DAY TO RESTORE NORMAL FLOW BACK TO THE CHANNEL. 4. CONTRACTOR SHALL NOT COMPACT SOIL AROUND ROOTS OR TREES TO REMAIN, AND SHALL NOT DAMAGE SUCH TREES IN ANY WAY. EXCAVATED OR OTHER MATERIAL SHALL NOT BE PLACED, PILED OR STORED WITHIN THE CRITICAL ROOT ZONE AREA OF THE TREES TO BE SAVED. S. UNLESS NOTED OTHERWISE, FILL MATERIAL GENERATED FROM UNNAMED TRIBUTARY CHANNEL EXCAVATION AND STABILIZATION SHALL BE PLACED INSIDE THE EXISTING CHANNEL TO BE ABANDONED AT AN ELEVATION THAT PROVIDES POSITIVE DRAINAGE TOWARDS THE PROPOSED CHANNEL. 6. DISTURBED BANKS ARE TO BE STABILIZED WITH SEEDING. MATTING AND LIVE STAKES PER'CREEK CROSSING STABILIZATION' DETAIL AND *STREAM STABILIZATION NOTES' ON DRAWING C2.8. DISTURBED AREAS BEYOND THE BANKS ARE TO BE STABILIZED WITH SEEDING PER 'TEMPORARY SEEDING SCHEDULE' AND'PERMANENT SEEDING SCHEDULE' ON DRAWING G4. LEGEND H LIMITS OF DISTURBANCE — LOD LOD EXISTING CONTOUR MAJOR — — —50 — — — EXISTING CONTOUR MINOR -- -- -- - - 46 - - - - - PROPOSED CONTOUR MAJOR y - PROPOSED CONTOUR MINOR y PROPOSED SPOT SHOT x 2.055 PROPOSED CENTERLINE OF CHANNEL = U PROPOSED CHANNEL PLUG H (SEE DETAIL DWG C3.5) DRAWN BY: LOG SILL PROJ. DATE: DRAWING NUMBER (SEE DETAIL DWG C3.5 W LOG SILL (PROFILE) J -HOOK VANE STRUCTURE I I (PROFILE) ILrll}� BOULDER ROOT WAD = U z O U F— Z 0 U cr0 LL LLL Q W J W cc � I KSON- 401 tiTH STREET SW SUITE 201 HICKORY, NORTH CAROLINA 28602 0)828327-6911 (9628-327-9164 WWW.WKDICKSON.COM NC LICENSE NO F-0374 PROJ. MGR.: CRF H CRF DRAWN BY: Z PROJ. DATE: DRAWING NUMBER JUNE 2017 W OF 29 2 W -J Z z (r = U 0cc w 2 Q C7 Z Lu U Z z o W=O CC U On Z W Z w Or >Q > J } Cc W H D] Or Z z ul Y J W F z O a $' o PROJ. MGR.: CRF OESIGN BY: CRF DRAWN BY: CH/RJL PROJ. DATE: DRAWING NUMBER JUNE 2017 C3.3 OF 29 20160049.00.H1 ROOT WAD, TYP. RES I FLOW (STRUCTUR SKF EXISTING BASALRES ER OF EANKLING CONSTRUCTION NOTE: 10-M INCHES STABLE FILL FACE TOPSOIL DEPTH SHALL BE SUFFICIENT T / IE BOULDERS SHALL BE ROTATED INTO THE O (COMPACTED TO 95%, EXCEPT FOR BANK DURING PLACEMENT SUCH THAT THE „ SUPPORT STASILIZING VEGETATION THE TOP 6, PER THE STANDARD HEADER BLOCKS OVERLAP THE FOOTER PROCTOR TEST) BANKFULL BMKFULL BLOCKS BY A MINIMUM OF 31NCS (BCM) d LEAVE 1' - T BOULDERS SHALL BE BLOCKY GEOTEXTILE TO PREVENT PUMPING LIMITS IN SHAPE(APPROX. 4Y312') 1'0 OF FINES. TYP (VARIES) GAPS ON AND HAVE NO MORE BTHAN A / TOP DYER • BATTER (SETBACK) DRAINING BACKFILL — STRE / COMPOSED OF GRAVEL (MAX OF 5%FINES) _ EXISTING 24V 20' RAW WATER LINE MIN BACKFILL BEHIND CHANNEL BFO PIPE (WHERE PIPE IS WITHIN J INCH OVERLAP W FILL AREA) CURVED REACHES EXISTING TOE CLASS A RIP RAP 8' MIN BAC PROPOSED TOE 'S I, S KFILL BENEATH FLOW BOTTOM BOULDER AND EXISTING PIPE A A. PLAN VIEW SECTION VIEW VARIES NOTES (SEE PUN VIE" 1. TOP OF BOULDER WALL SWILL BE A MI 1-1 :J= 18' ABOVE CHANNEL BED ELEVATION 2 FOOTER WIELDER SHALL BE SET 18" BELOW CHANNEL BED. BOULDER TOE PROTECTION NOT TO SCALE LIMITSlTs BMJ o � NOTE&. 1.EXCAVATION SHALL BE PERFORMED ONLY IN DRY AND/OR ISOLATED SECTIONS OF CHANNEL 2. IMPERVIOUS DIKES SHOULD BE USED TO ISOLATE WORK AREAS FROM STREAM FLOW. 3. THE CONTRACTOR SHALL NOT DISTURB MORE AREA THAN CAN BE STABILIZED IN ONE WORKING DAY. A MAXIMUM OF 200 FEET MAY BE DISTURBED AT ANY ONE TIME. 4, THE CONTRACTOR SHALL BE RESPONSIBLE FOR DETERMINING PUMP SIZE SUFFICIENT TO PUMP BASE FLOW. 5. DIKE MUST BE CONSTRUCTED OF NON -ERODIBLE MATERIALS SUCH AS SANDBAGS. BEQUENCE OF CONSTRUCTION FOR TYPICAL PUMP AROUND 1. INSTALL STILLING BASIN AND STABILIZED OUTFALL USING CLASS A RIP RAP TO A DEPTH OF 1Y AT THE DOWNSTREAM END OF THE DESIGNATED PROJECT WORKING AREA. 2. THE CONTRACTOR SHALL INSTALL THE PUMP AROUND PUMP AND THE TEMPORARY PIPING THAT WALL CONVEY THE BASE FLOW FROM UPSTREAM OF THE WORK AREA TO THE STABILIZED OUTFALL. 3. INSTALL UPSTREAM IMPERVIOUS DIKE AND BEGIN PUMPING OPERATIONS FOR STREAM DIVERSION. 4. INSTALL THE DOWNSTREAM IMPERVIOUS DIKE AND DEWATERING PUMPING APPARATUS IF NEEDED TO DEWATER THE ENTRAPPED AREA. THE PUMP AND HOSE FOR THIS PURPOSE SHALL BE OF SUFFICIENT SIZE TO DEWATER THE WORK AREA. THIS WATER WALLALSO BE PUMPED TO M OUTFALL STABILIZED WITH CLASS A RIP RAP, 5. THE CONTRACTOR SHALL EXCAVATE ANY ACCUMULATED SILT AND DEWATER BEFORE REMOVAL OF THE IMPERVIOUS DIKE. WHEN DEWATERING AREA, ALL DIRTY WA R MUST BE PUMPED THROUGH A SILT BAG. REMOVE IMPERVIOUS DIKES. PUMPS. AND TEMPORARY FLEXIBLE HOSEIPIPING STARTING WITH THE DOWNSTREAM DIKE FIRST. B. ONCE THE WORKING AREA IS COMPLETED, REMOVE ALL RIP RAP AND IMPERVIOUS DIKES AND STABILIZE DISTURBED AREAS WITH SEED AND MULCH. 7. ALL WORK IN CHANNEL MUST BE COMPLETED BEFORE REMOVING IMPERVIOUS DIKE. FLOW 6 /INTAKE HOSE 15 -CLASS A STONE PUMPAROUND 9 PUMP II PUMP SANDBAG - IMPERVIOUS DIKE IMPERVIOUS DIKE DISCHARGE HOSE CLASS A STONE NOTE: HOSE SHOULD BE KEPT OUTSIDE OF WORK SILT BAG AREA LOCATION STABILIZED OUTFALL FILTER FABRIC 15'DEPTH OF CLASS STONE M(e.2.11CU552) 15'TOW OUTFALL CUSS A STONE L -FILTER FABRIC LB' OF CLASS A (BM.2.11 CLASS 2) STONE EXISTING CHANNEL SILT BAG PROFILE PUMP AROUND & DEWATERING DETAIL NOTES FOR ALL VANE STRUCTURES. 1. THE J -HOOK VANE SHALL BE CONSTRUCTED WITH FLAT SIDED BOULDERS OF A SIZE (LENGTH, WIDTH AND DEPTH) AS SPECIFIED BY THE ENGINEER. BOULDERS MUST BE AT LEAST 4lXa', 2. FILTER FABRIC OF A TYPE AND SIZE SPECIFIED BY THE ENGINEER SHALL MUSED TO SEK THE GAPS BETWEEN THE BOULDERS AND UNDER THE COARSE BACKFILL MATERIAL OF THE VANE ARM. THERE SHALL BE NO FILTER FABRIC VISIBLE IN THE FINISHED WORK, EDGES SWILLL L BE FOLDED, TUCKED OR TRIMMED AS NEEDED. INSTALL, FILTER FABRIC FOR DRAINAGE BEGINNING AT THE MIDDLE OF THE HEADER ROCKS AND EXTEND DDW WVARD TO THE DEPTH OF THE BOTTOM FOOTER ROCK, AND THEN UPSTREAM TO A MINIMUM OF TEN FEET. 3, COARSE BACKFILL OF THE BOULDER J -NOOK VANE ARM SHALL BE OF TYPE, SIZE, AND GRADATKRI AS SPECIFIED BY THE DESIGNER. COARSE BACKFILL SHALL BE PLACED TO A THICKNESS EQUAL TO THE DEPTH OF THE HEADER AND FOOTER BOULDERS AND SHALL EXTEND OUT FROM THE VANE ARMS TO THE STREAM BANK. 1. USE NATURAL STONE CLASS 1 TO FILL GAPS ON UPSTREAM SIDE OF BOULDERS, AND NATURAL STONE CLASS A TO FILL GAPS ON UPSTREAM SIDE OF NATURAL STONE CLASS 1. 5. BOULDER }HOOK VANES SHALL BE BUILT TYPICALLY AS FOLLOWS: A. OVER -EXCAVATE STREAM BED TO A DEPTH EQUAL TO THE TOTAL THICKNESS OF THE HEADER AND FOOTER BOULDERS B. PLACE FOOTER BOULDERS FOR THE HOOK, THE VANE MM. AND FLOODPLAIN SILL. THERE SHALL BE NO GMS SETWEEN BOULDERS. C. INSTAL FILTER FABRIC. D. PLACE COARSE BACKFILL BEHIND THE FOOTER BOULDERS. E. INSTALL HEADER BOULDERS ON THIS HOOK, VME ARM AHO FLOODPLAIN SILL ON TOP OF AND SET SLIGHTLY BACK FROM THE FOOTER BOULDERS (SUCH THAT PMT OF THE HEADER BOULDER IS RESTING ON THE COARSE BACKFILLJ. HEADER BOULDERS SHALL SPM THE SEAMS OF THE FOOTER BOULDERS. THERE SHALL BE NO GAPS SETWEEN BOULDERS THE SLOPE OF THE VANE ARM IS MEASURED ALONG THE VANE MM WHICH IS INSTALLED AT M ANGI-E TO THE STREAM BANK AND PROFILE. F. PLACE COARSE BACKFILL BEHIND HEADER BOULDERS ENSURING THAT MY VOIDS BETWEEN THE BOULDERS ARE FILLED. S. AFTER ALLSTONE HAS BEEN PLACEO, FILL IN THE UPSTREAM SIDE OF THE STRUCTURE. 7. IF MY EROSION CONTROL MATTING IS SPECIFIED FOR USE IN THE VICINITY OF THE VANE MM INTERCEPT POINTS MD FLOODPLAIN SILLS THE MATTING EDGES SFALL BE NEATLY SECURED MOUND THE BOULDERS. FLOW X10 (SEE BANKFULL PLAN VIEW BANKFULL (SEE NOTE 3) X1 -RIGHT OR LEFT INTERCEPT CONTROL POINT ELEVATION VARIES a-za NOFT/iOO�E) POOL X4 X24-OOL CONTROL POINT ELEVATION (SEE NOTE 2) SECTION B- B' --- VMWIl IIIIII�� p1EMN IvALDEETOaERroVIDm BYDERI_) YKJEs TYPICAL Vi1I 9CRNigN JJKIDK N JJID01[ 1NOOI !! A 2 x1 919.6 918.8 919.7 FT.(NAVD) LEFTOR RIGHT VANE ARM INTERCEPT CONTROL POINT ELEVATION x2 9115 912.3 912• FT (NAND) POOLCONTR m.T ELEVATION X3 u R 45 FT. .—IJLL WIDTH x4 9 Te 7.2 FT. MAX.- POOL DEPTH FROM VANE ARM INTERCEPT ODNTTROL POINT ELEVATION X6 M 72 72 IT VANE ARM LENGTH x9 1 1 4 N. Deg OF COARSE I—KFBL xl e e 4 FT. LENGTH OF FLOODPWN SIL xe 20 N 29 DEGREES VANE ARMANOLE WITH 6TRFAM SANK x9 WA NB Wn FT. DIFFERENCE BtTWEEN BANKFUITAND VANE ARM INTERCEPT POINT x19 e e e PERCENT VANE ARM SLOPE X114 Q 4 4 FT. BOULDER LENGTH X12 e e J FT. 60ULDERWOTH x16 ) 2 2 FT BOIP_DER THKJ(NE58 X14 a e 6 N HEADER BOLLOER SETBACK VANE ARM SECTION A- A' J -HOOK VANE NIS (SEE NOTE 7) AM POOL �D CKSON �' inheutrlLctMe rcvsWlAn6 401 4T H STRiET SW SUITE 201 HICKORY, NORTH CAROUNA 26&!2 m62&327-0811 (1) 7-9164 WWW WKDICKSON.COM NC LICENSE NO.F-0374 •�SH1�Rp� •'�,, 20 FEs�i�. -sk sm . /h�03 /T!•�{•; i '''•,,,q��...... i.,25 D I IT Li (i i R 1�NWW�A�. Al 201 PROFESSIONKSEAL U IIIIII�� Z W 2 W z E� W D- J s� O _ Cc Q M W U Z m 2 W Z Q Z O� Y J 2� W Q O w Z a z Y J G w 4J D� O Q 1 1 1 1 1 1 I _Zd U Z W 2 W cr Z D- J MO _ Cc Q M W U Z m OO W Z Q Z Y J 2� W Q w Z a z Y J G w ELI Cc a D� O 1 PROJ. MGR.: CRF DESIGN BY: CRF DRAWN BY: CHJRJL PROJ. DATE: JUNE 2017 DRAWING NUMBER: C3.4 OF 29 WKD PROJ. NO.: 20160049.00.1-11 A,r CROSS SECTION B - B' LOG SILL NOT TO SCALE NOTES. 1. A LOU SILL MAY BE USED ALONE OR IN COMBINATION WITH A CONSTRUCTED RIFFLE. 2. THE USE OF LOGS IN THE STREAM BED SHALL BE UNITED TO PERENNIAL WATERBOOIES ONLY. 3. AN ELEVATION CONTROL POINT SMALL BE DESIGNATED AT THE CENTER OF THE SILL TO ESTABLISH PART OF THE PROFILE. POOL ELEVATION CONTROL POINTS OR EXCAVATION TO A SPECIFIEO MAXIMUM POOL DEPTH SHALL BE DESIGNATED TO ESTABLISH THE REMAINMG PROFILE. SURVEY OF CONTROL POINTS SHALL BE REQUIRED TO ESTABLISH ACCURATE INSTALLATION SMTHIN THE TOLERANCE SPECIFIED BY THE DESIGNER. 4. NO PART OF THE SILL SHALL BE PLACED ABOVE THE ELEVATION OF THE STREAM BED. 5. IF PLANS DESIGNATE TME USE OF MULTIPLE LOG SILLS A TABLE OF ALL STATION LOCATIONS AND CONTROL PoINT ELEVATIONS SHALL BE PROVIDED IN THIS DETAIL OR PROVIDED ELSEWHERE IN THE PLANS AND REFERENCED HEREIN. 6, TYPICAL RIFFLE AND POOL CROSS SECTIONS SMALL BE PROVIDED ELSEWHERE IN THE PLANS TO ESTABLISH THE DIMENSIONS OF THE CHANNEL GRADING INTO WHICH THE LOG SILLS ARE TO BEINSTALLED. T LOGS SHALL BE OF A LENGTH AND DIAMETER SPECIFIED BY THE DESIGNER AND BE RELATIVELY STRAIGHT HARDWOOD, RECENTLY HARVESTED. THE LENGTH OF THE SILL EMBEDDED INTO EACH BANK SHALL EQUAL OR EXCEED THE WIDTH OF THE CHANNEL S. A SINGLE LOG MAY BE USED IN LIEU OF A HEADER/FOOTER LOG COMBINATION. 9. FILTER FABRIC OFA TYPE AND SIZE SPECIFIED BY THE DESIGNER SHALL BE USED TO SEAL THE GAPS BETWEEN THE LOG(S) AND THE STREAM BED, UNDER THE COARSE BACKFILL MATERIAL. THE FABRIC SHALL BE NAILED TO THE ENTIRE LENGTH HEADER LOG USING A GALVANIZED MAIL WTTH A PLASTIC CAP. THE SIZE AND GAGE OF MAIL AND NAIL SPACING SFIALL BE SPECIFIED BY THE DESIGNER. THERE SHALL BE NO FILTER FABRIC VISIBLE IN THE FINISHED WORK; EDGES SFALL BE FOLDED, TUCKED, OR TRIMMED AS NEEDED. 10. COARSE BACKFILL OF THE LOG SILL SHALL BE OF A TYPE, SIZE. AND GRADATION AS SPECIFIED BY THE DEKF SIGNER. COARSE BACKFILL SMALL BE PLACED TO A THICKNESS EQUAL TO THE DEPTH OF THE HEADER (AFD ANY FOOTER) LOGS AND SHALL EXTEND UPSTREAM FROM THE SILL A DISTANCE SPECIFIED BY THE DESIGNER. 11. THE LOG SILL IS GENERALLY CONSTRUCTED AS FOLLOWS: A. OVER -EXCAVATE STREAM BED TO A DEPTH EQUAL TO THE TOTAL THICKNESS OF THE HEADER (AND FOOTER IF SPECIFIED) LOGS. S. PLACE FOOTER LOGS, IF SPECIFIED. A LAYER OF BEDDING MATERIAL UNDER THE FOOTER LDG MAY BE SPECIFIED BY THE DESIGNER C. INSTALL HEADER LOG ON TOP OF THE FOOTER LOG. HEADER LOG MAY BE SET FORWARD OR BACK FROM FOOTER LOG AS AN OPTION. D. NAIL FILTER FABRIC TO THE HEADER LOG. E. PLACE COARSE BACKFILL BEHIND LOGS) ENSURING THAT ANY VOIDS BETWEEN THE LOGS ARE FILLED. F. TRIM ANY EXPOSED FILTER FABRIC AROUND THE SILL INSTALLATION. 12. STREAM BANK STAWLIZATION, IF SPECIFIED, SHALL BE ADDED TO THIS DETAIL OR DETAILED SEPARATELY AND REFERENCED HEREIN, DBIIENSIONS (VALUES TO BE PROVIDED BY DESIGNER) COARSE BACKFILL (SEE NOTE 10) APPROXIIMTE BASE STA11H30 STA.1M76 VALUES VALUES TYPICAL UNIT FLOW WATER LEVEL Xt 920 \ %1 -CONTROL POINT ELEVATIONCOARSE DACKFlLL (SEE NOTE 10) %3 X2 WA WA STREAM SED HEADER LOG (SEE NOTES ],BAND 11C) POOL CONTROL POINT ELEVATION X3 FLOW Xt-SILL CONTROL POINT FT. STREAM BED WIDTH ELEVATION (SEE NOTE 3) I I }HOOK VANE ARM FT. CHANNELWIDTH X5 10 10 z.x] LENGTH OF SILL EMBEDDED IN BANK IIA i 10 10 FT. LENGTH OF COARSE BACKFILL B 12 B' IN. LOG DAMETE(t XB � 0.11 0.11 FILTER FABRIC APPFDXIAW7E 845E PLOW DEPTH (SEE NOTE 9) X7 X6 FOOTER LOG NOTES: (SEE NOTE 7,6) t. LINE ALL CHANNEL BANKS WITH EROSION CONTROL MATTING. %5 XS I PROFILE A - A' APPROXIMATE BASE FLOWWATERLEVEL MINIMUM OF 2/3 OF LOG 2. DRIVE STAKES THROUGH COIR FIBER LOG APPROXIMATELY 12" FROM EXISITING GROUND TOP OF BANK y STREAM BANK STABILIZATION, A' I LOG SILL (SEE NOTE 21 IF SPECIFIED (SEE NOTE 12) TOE OF SLOPE -' - - '- DIAMETER BEDDED BELOW EACH END OF LOG, AND ADDITIONALLY EVERY 36". HEADER LOG (SEE NOTES ] AND e) EXISTING CHANNEL INVERT STREAM BANK TYPICAL .y 70P OF BANK, 3. COR FIBER ROLLS SHALL BE PLACED IN DIRECT CONTACT WITH THE LOG TOE PROTECTION 1Y SOIL ALONG THEIR ENTRE LENGTH; ROLLS SHALL NOT BRIDGE OVER INIM (f Y LIFTS) 1.56 MINIMUM TYPICAL MINIMUM LOG DIAMETER (TYP.) ANY VOIDS OR NATURAL OBSTACLES SUCH AS STUMPS OR ROCK FLOW II 15' _ TOE OF BANK, TYPO AL PLAN VIEW X7 XS X5 0\ NEW CHARNEL BED SHALL STREAM BED (SEE NOTE 4) CROSS SECTION B - B' LOG SILL NOT TO SCALE NOTES. 1. A LOU SILL MAY BE USED ALONE OR IN COMBINATION WITH A CONSTRUCTED RIFFLE. 2. THE USE OF LOGS IN THE STREAM BED SHALL BE UNITED TO PERENNIAL WATERBOOIES ONLY. 3. AN ELEVATION CONTROL POINT SMALL BE DESIGNATED AT THE CENTER OF THE SILL TO ESTABLISH PART OF THE PROFILE. POOL ELEVATION CONTROL POINTS OR EXCAVATION TO A SPECIFIEO MAXIMUM POOL DEPTH SHALL BE DESIGNATED TO ESTABLISH THE REMAINMG PROFILE. SURVEY OF CONTROL POINTS SHALL BE REQUIRED TO ESTABLISH ACCURATE INSTALLATION SMTHIN THE TOLERANCE SPECIFIED BY THE DESIGNER. 4. NO PART OF THE SILL SHALL BE PLACED ABOVE THE ELEVATION OF THE STREAM BED. 5. IF PLANS DESIGNATE TME USE OF MULTIPLE LOG SILLS A TABLE OF ALL STATION LOCATIONS AND CONTROL PoINT ELEVATIONS SHALL BE PROVIDED IN THIS DETAIL OR PROVIDED ELSEWHERE IN THE PLANS AND REFERENCED HEREIN. 6, TYPICAL RIFFLE AND POOL CROSS SECTIONS SMALL BE PROVIDED ELSEWHERE IN THE PLANS TO ESTABLISH THE DIMENSIONS OF THE CHANNEL GRADING INTO WHICH THE LOG SILLS ARE TO BEINSTALLED. T LOGS SHALL BE OF A LENGTH AND DIAMETER SPECIFIED BY THE DESIGNER AND BE RELATIVELY STRAIGHT HARDWOOD, RECENTLY HARVESTED. THE LENGTH OF THE SILL EMBEDDED INTO EACH BANK SHALL EQUAL OR EXCEED THE WIDTH OF THE CHANNEL S. A SINGLE LOG MAY BE USED IN LIEU OF A HEADER/FOOTER LOG COMBINATION. 9. FILTER FABRIC OFA TYPE AND SIZE SPECIFIED BY THE DESIGNER SHALL BE USED TO SEAL THE GAPS BETWEEN THE LOG(S) AND THE STREAM BED, UNDER THE COARSE BACKFILL MATERIAL. THE FABRIC SHALL BE NAILED TO THE ENTIRE LENGTH HEADER LOG USING A GALVANIZED MAIL WTTH A PLASTIC CAP. THE SIZE AND GAGE OF MAIL AND NAIL SPACING SFIALL BE SPECIFIED BY THE DESIGNER. THERE SHALL BE NO FILTER FABRIC VISIBLE IN THE FINISHED WORK; EDGES SFALL BE FOLDED, TUCKED, OR TRIMMED AS NEEDED. 10. COARSE BACKFILL OF THE LOG SILL SHALL BE OF A TYPE, SIZE. AND GRADATION AS SPECIFIED BY THE DEKF SIGNER. COARSE BACKFILL SMALL BE PLACED TO A THICKNESS EQUAL TO THE DEPTH OF THE HEADER (AFD ANY FOOTER) LOGS AND SHALL EXTEND UPSTREAM FROM THE SILL A DISTANCE SPECIFIED BY THE DESIGNER. 11. THE LOG SILL IS GENERALLY CONSTRUCTED AS FOLLOWS: A. OVER -EXCAVATE STREAM BED TO A DEPTH EQUAL TO THE TOTAL THICKNESS OF THE HEADER (AND FOOTER IF SPECIFIED) LOGS. S. PLACE FOOTER LOGS, IF SPECIFIED. A LAYER OF BEDDING MATERIAL UNDER THE FOOTER LDG MAY BE SPECIFIED BY THE DESIGNER C. INSTALL HEADER LOG ON TOP OF THE FOOTER LOG. HEADER LOG MAY BE SET FORWARD OR BACK FROM FOOTER LOG AS AN OPTION. D. NAIL FILTER FABRIC TO THE HEADER LOG. E. PLACE COARSE BACKFILL BEHIND LOGS) ENSURING THAT ANY VOIDS BETWEEN THE LOGS ARE FILLED. F. TRIM ANY EXPOSED FILTER FABRIC AROUND THE SILL INSTALLATION. 12. STREAM BANK STAWLIZATION, IF SPECIFIED, SHALL BE ADDED TO THIS DETAIL OR DETAILED SEPARATELY AND REFERENCED HEREIN, FLOW DBIIENSIONS (VALUES TO BE PROVIDED BY DESIGNER) VARIABLE STA11H30 STA.1M76 VALUES VALUES TYPICAL UNIT DESCRIPTION Xt 920 920.9 FT, (NAVD) SILL CONTROL POINT ELEVATION X2 WA WA FT. (NAVD) POOL CONTROL POINT ELEVATION X3 5 5 FT. STREAM BED WIDTH X4 21 21 FT. CHANNELWIDTH X5 10 10 FT. LENGTH OF SILL EMBEDDED IN BANK X6 10 10 FT. LENGTH OF COARSE BACKFILL X7 12 12 IN. LOG DAMETE(t XS 0.11 0.11 FT. APPFDXIAW7E 845E PLOW DEPTH FLOW OLD CHANNEL TO BE PROPOSED TOP O BANK PLUGGED EXISTNG CHANNEL SHALL BE PLACED BY OVERLAPPING !/ WITH THE FLOW OF WATER MIW 60°h COMPACTION BANKFULL ELEVATION COMPACTED BACKFILL PROFILE VIEW (12" LIFTS) EROSION CONTROL MATTING O m NO E$. Q 1. FILL EXISTING CHANNEL TO PROPOSED RANKFULUTOP OF BANK ELEVATION IN ALLAREAS WHERE THE PROPOSED CHANNEL IS TO BE CONSTRUCTED IN FILL. Z P 2. CHANNEL MUST BE FILLED 1N MAXIMUM 12' LIFTS. PLAN VIEW CHANNEL BACKFILL NIS CHANNELPLUG NTS MDICKSON munite irl(veshuc[wP_ u_IB,Y3 401 4TH STREET SW SURF_ 201 HICKORY, NORTH CAROLINA 28602 (1)82832711 (Q828-327-9164 WWW.WKDICKSON.COM NC UCENSE NO.F-0374 '1'� •��FESS/p' . ,y*c "� �gi01 Oi1xr,,;A\1AA� •(�"%OP- PROFESSIONAL SEAL O S C a 2 m O Q D) I Q = O O Q O N Z cw G w O: Z CL _I CC 0 CQ LY) LU U Z rn u) = Q /n cr 0 0 W Z Q Z Y J �w Q z FZ J W w $ a p PROD. MGR.: CRF DESIGN BY: CRF DRAWN BY: CH/RJL PROD. DATE: JUNE 2017 DRAWING NUMBER: C3.5 OF 29 WKD PROJ. NO.: 20160049.00.H1 OLD CHANNEL TO BE PLUGGED FILTER FABRIC FOR DRAINAGE SHALL BE PLACED BY OVERLAPPING WITH THE FLOW OF WATER BANKFULL ELEVATION 1° EROSION CONTROL MATTING DRIVE STAKE ALONG TOP OF COIR LOG 50 THE STAKE TOP IS LEVEL CHANNEL PLUG UNDISTURBED SOIL WITH THE LOG TOP NEW CHANNEL TO BE �tS CONSTRUCTED •l IMTOla FCOIRFIBERLOG DIAMETER CAN BE EXPOSED PLAN VIEW PROPOSED BED STAKE 24"-36" MIN. LENGTH (TYP ) NOTES: t. LINE ALL CHANNEL BANKS WITH EROSION CONTROL MATTING. MINIMUM OF 2/3 OF LOG 2. DRIVE STAKES THROUGH COIR FIBER LOG APPROXIMATELY 12" FROM -' - - '- DIAMETER BEDDED BELOW EACH END OF LOG, AND ADDITIONALLY EVERY 36". MIN. 9516 COMPACTION EXISTING CHANNEL INVERT COMPACTED BACKFILL U CTED BACKFILL BANKFULL ELEVATION 3. COR FIBER ROLLS SHALL BE PLACED IN DIRECT CONTACT WITH THE LOG TOE PROTECTION 1Y SOIL ALONG THEIR ENTRE LENGTH; ROLLS SHALL NOT BRIDGE OVER INIM (f Y LIFTS) 1.56 MINIMUM MINIMUM LOG DIAMETER (TYP.) ANY VOIDS OR NATURAL OBSTACLES SUCH AS STUMPS OR ROCK FLOW II 15' _ FINISHED GRADE � NEW CHARNEL BED SHALL BE TREATED AS SPECIFIED IN PLANS COIR FIBER TOE PROTECTION MR OR CABLE NTS AN ANCHOR CHANNEL INVERT TYPICAL SECTION Loc roE CHANNELPLUG NTS MDICKSON munite irl(veshuc[wP_ u_IB,Y3 401 4TH STREET SW SURF_ 201 HICKORY, NORTH CAROLINA 28602 (1)82832711 (Q828-327-9164 WWW.WKDICKSON.COM NC UCENSE NO.F-0374 '1'� •��FESS/p' . ,y*c "� �gi01 Oi1xr,,;A\1AA� •(�"%OP- PROFESSIONAL SEAL O S C a 2 m O Q D) I Q = O O Q O N Z cw G w O: Z CL _I CC 0 CQ LY) LU U Z rn u) = Q /n cr 0 0 W Z Q Z Y J �w Q z FZ J W w $ a p PROD. MGR.: CRF DESIGN BY: CRF DRAWN BY: CH/RJL PROD. DATE: JUNE 2017 DRAWING NUMBER: C3.5 OF 29 WKD PROJ. NO.: 20160049.00.H1