Loading...
HomeMy WebLinkAbout20130412 Ver 1_Biological Eval Assessment June 2017_20180207Strickland, Bev From: Aaron Aho <aaho@uniqueplacesllc.com> Sent: Wednesday, February 07, 2018 5:08 PM To: Williams, Andrew E CIV USARMY CESAW (US) Cc: Goss, Stephanie; Haupt, Mac; Jeffrey A. Fisher; Michael Scisco Subject: [External] Re: SAW -2017-00511 Hoosier Dam Removal Project INCOMPLETE NOTIFICATION Attachments: Supplemental Narrative - Updated 2nd Submittal - 02072018.doc; Figure 5. Hoosier Dam Removal Impacts.pdf, Hoosier Dam Removal Plans_2_6_18.pdf; Figure 6. Hoosier Crib Dam Removal Impacts.pdf, Figure 7. USACEpermitting.pdf, Appendix G - Biological Assessment.pdf External email. Do not click links or open attachments unless verified. Send all suspicious email as an attachment to Report Spam. Andrew, See our response below in blue and also the attached documents that address document update needs. This should address everything except for #8, which we are still putting together. Please, let us know if this satisfies the points addressed. 1. In several locations within the PCN, including the PCN supplemental narrative and attached plans sheets, the project is referred to as a "bank" or "mitigation bank". Please clarify whether or not the applicant is proposing this as a mitigation bank. A mitigation bank is not being proposed. The property was purchased by Rocky River Hydro, LLC on December 31, 2012. At the time, the plan was to remove the dam in order to establish o mitigation bank. Efforts were mode in that direction, thus some of the consultation documents talk about o mitigation bank, but the effort was abandoned in July 2016 when o NFWF grant was approved to remove the dam. These consultation documents ore still relevant to our purposes of removing the dam and remain in their original wording but the purpose is to remove the dam for the positive environmental impact and not os o mitigation bank. 2. Please provide specific control measures to be implemented to alleviate any severe or long term impacts to the Cape Fear Shiner critical habitat, as mentioned in the supplemental narrative (page 2). A Biological Assessment has been submitted to USFWS regarding specific control measures to alleviate severe or long term impacts to the Cope Fear shiner. We hove attached o copy of this for you with this submittal. 3. Page 3 of the supplemental narrative mentions the stabilization of streambanks, post -dam removal and stabilization of stream bed using grade control structures. Streambank and streambed impacts are shown/mentioned at the location of the old crib dam. It is unclear if any additional stream bank/stream bed work will take place within the footprint of the project area. If so, please specify the location, type and amount of impacts associated with any additional streambank and grade control structures along other sections of the project area. If so, these impacts should be listed in the PCN. After the completion of dewatering of the impoundment, and inspection of the stream upstream and downstream, it was determined that instreom habitat structures would not be necessary for this project. The bed material is heterogeneous and several bedrock seams act os grade control for the project. This language has been updated in the supplemental narrative. Streambank grading will occur along the area upstream of the dam if mechanical sediment removal is required by permit as part of this project. This area will be stabilized with erosion control matting and seeded according to the plans and specifications for the project. This area is shown in the grading plan with proposed contours and has been included in a temporary impact on the PCN in Figure 5. Similar stabilization will occur on the streambanks at the Hoosier Dam location. This is shown in the grading plan (Sheets 1.1 —1.4) and called out in Figure 5 of the PCN. 4. Section 133e of the supplemental narrative mentions the removal of the rock dam (crib dam). Please indicate if any temporary impacts (fill for pump around or for double handling material) will be necessary. If so, please indicate the location, and amount (linear feet and/or acres) on the plans. No temporary fill of material will be required. Material will be taken from the channel and placed above the ordinary high water mark along the stream banks during deconstruction. From there it will be placed in the permanent stockpile areas shown on the plans. Temporary impacts associated with grading and placing of rock along the toe of banks is shown on the construction plans and in Figure 6 of the PCN. 5. Section 133e of the supplemental narrative mentions the removal of the powerhouse and dam and the construction of a causeway abutting the dam. Please indicate the causeway location on the proposed plans and indicted the amount of fill within jurisdictional areas. The causeway is shown on Sheet 1.3 of the construction plans (hatched with a gravel pattern) with a call out of the cubic yardage of fill required. This is noted as a temporary impact on the PCN in Figure 5. 6. The supplemental narrative mentions dam material falling on the downstream side of the dam during demolition. This may result in temporary fill at this location. Please estimate the location, amount of fill (cubic yards and acreage) and the method of removal for any of this material. It should be shown as a temporary impact on the PCN. This is the causeway mentioned in Question 5, above. The temporary fill is estimated at 1,880 Cubic Yards. The area is inclusive of where material may fall during demolition. Material will be removed mechanically according to Stage 3 of the dam removal in the construction plans. This has been shown as a temporary impact on the PCN in Figure 5. 7. Page 5 of the supplemental narrative mentions habitat structure implementation. Specific structures include rocky riffle and lunker logs (instream). Please provide a plan sheet showing the location of these structures and the amount of fill associated with them. These should be accounted for on the PCN. Please see Question 3. This approach has been adjusted since dewatering. Unique Places and the design team feel it is the best approach for the Cape Fear shiner and sensitive mussel species to impact as little of the riverbed as necessary to create a stable and thriving habitat. 8. During several pre -applications meetings, compensatory mitigation was discussed. While the language within NWP 53 states that in general, compensatory mitigation will not be required, it does not preclude it completely. As such, during the pre -application meetings, monitoring of the existing on site wetlands was discussed. Methods discussed included creating and implementing a schedule for verifying hydrology indicators of the current wetlands and making routine wetland determinations for any newly formed wetlands. Please provide a statement and plan regarding the monitoring wetlands that will potentially be impacted by this project and those that may form, post dam removal. Please be aware that the Corps of Engineers may condition the permit verification to provide compensatory mitigation at a later date, depending upon the final amount of wetland loss (if any) associated with this project. We are still composing this response. 9. Please modify Figure 7 by using different labels, colors, hatching, etc. to distinguish between wetlands that you have classified as follows: a. functional/hydrological change b. likely removed from jurisdiction c. no change This has been updated in Figure 7 and labeled to correspond with the PCN and JD 10. Please clarify if the applicant is the entity known as 130 Chatham or Rocky River Hydro, LLC. Also, please provide a contact name, email address and phone number for the applicant. Unique Places, LLC is consulting on this project for Tim Sweeney. Mr. Sweeney is the managing member of both 130 of Chatham, LLC and Rocky River Hydro, LLC. Several of the consultation reports hove been commissioned under 130 of Chatham, LLC for this project, however, Rocky River Hydro, LLC is the correct applicant for this project. Rocky River Hydro owns the two parcels immediately on either side of the Hoosier Dom and oll direct impacts associated with demolition will occur on these two parcels. This is not the case with the upstream crib dam, which sits between o parcel owned by 130 of Chatham and another private landowner. Impacts will occur on 130 of Chatham property for the removal of the crib dam. Contact information: Tim Sweeney Phone: 919-632- 0161 11. We recognize and appreciate that this project has been extensively coordinated with the US Fish and Wildlife Service (USFWS) regarding the Cape Fear Shiner. However, please be aware that no activity is authorized under any NWP which "may affect" a listed species or critical habitat, unless ESA section 7 consultation addressing the effects of the proposed activity has been completed. Direct effects are the immediate effects on listed species and critical habitat caused by the NWP activity. Indirect effects are those effects on listed species and critical habitat that are caused by the NWP activity and are later in time, but still are reasonably certain to occur. We will coordinate with USFWS to complete Section 7 consultation. In cases where the non- Federal applicant has identified listed species or critical habitat that might be affected or is in the vicinity of the activity, and has so notified the Corps, the applicant shall not begin work until the Corps has provided notification that the proposed activity will have "no effect" on listed species or critical habitat, or until ESA section 7 consultation has been completed. Noted and understood 12. We recognize and appreciate that this project has been coordinated with the State Historic Preservation Office (SHPO) regarding the dam and powerhouse. In cases where the district engineer determines that the activity may have the potential to cause effects to properties listed, or eligible for listing, in the National Register of Historic Places, the activity is not authorized, until the requirements of Section 106 of the National Historic Preservation Act (NHPA) have been satisfied. We will coordinate with SHPO to complete Section 106 consultation. For non-federal permittees, the district engineer will notify the prospective permittee within 45 days of receipt of a complete pre -construction notification whether NHPA section 106 consultation is required. If NHPA section 106 consultation is required, the district engineer will notify the non- Federal applicant that he or she cannot begin the activity until section 106 consultation is completed. Noted and understood 191 Aaron Aho Land and Resource Associate Unique Places LLC PO Box 52357 Durham, NC 27717 p919.491.1964 uniqueplacesllc.com On Fri, Jan 19, 2018 at 3:28 PM, Williams, Andrew E CIV USARMY CESAW (US) <Andrew.E.Williams2@usace.army.mil> wrote: Mr. Aho: The Pre -construction notification (PCN) for the Rocky River Hydro, LLC Hoosier Dam Removal Project (SAW -2017- 00511), received on December 21, 2017 is incomplete. In order for use to continue evaluating the proposed project, please provide/clarify the following information/issues: 1. In several locations within the PCN, including the PCN supplemental narrative and attached plans sheets, the project is referred to as a "bank" or "mitigation bank". Please clarify whether or not the applicant is proposing this as a mitigation bank. 2. Please provide specific control measures to be implemented to alleviate any severe or long term impacts to the Cape Fear Shiner critical habitat, as mentioned in the supplemental narrative (page 2). 3. Page 3 of the supplemental narrative mentions the stabilization of streambanks, post -dam removal and stabilization of stream bed using grade control structures. Streambank and streambed impacts are shown/mentioned at the location of the old crib dam. It is unclear if any additional stream bank/streambed work will take place within the footprint of the project area. If so, please specify the location, type and amount of impacts associated with any additional streambank and grade control structures along other sections of the project area. If so, these impacts should be listed in the PCN. 4. Section 133e of the supplemental narrative mentions the removal of the rock dam (crib dam). Please indicate if any temporary impacts (fill for pump around or for double handling material) will be necessary. If so, please indicate the location, and amount (linear feet and/or acres) on the plans. 5. Section 133e of the supplemental narrative mentions the removal of the powerhouse and dam and the construction of a causeway abutting the dam. Please indicate the causeway location on the proposed plans and indicted the amount of fill within jurisdictional areas. 6. The supplemental narrative mentions dam material falling on the downstream side of the dam during demolition. This may result in temporary fill at this location. Please estimate the location, amount of fill (cubic yards and acreage) and the method of removal for any of this material. It should be shown as a temporary impact on the PCN. 7. Page 5 of the supplemental narrative mentions habitat structure implementation. Specific structures include rocky riffle and lunker logs (instream). Please provide a plan sheet showing the location of these structures and the amount of fill associated with them. These should be accounted for on the PCN. 8. During several pre -applications meetings, compensatory mitigation was discussed. While the language within NWP 53 states that in general, compensatory mitigation will not be required, it does not preclude it completely. As such, during the pre -application meetings, monitoring of the existing on site wetlands was discussed. Methods discussed included creating and implementing a schedule for verifying hydrology indicators of the current wetlands and making routine wetland determinations for any newly formed wetlands. Please provide a statement and plan regarding the monitoring wetlands that will potentially be impacted by this project and those that may form, post dam removal. Please be aware that the Corps of Engineers may condition the permit verification to provide compensatory mitigation at a later date, depending upon the final amount of wetland loss (if any) associated with this project. 9. Please modify Figure 7 by using different labels, colors, hatching, etc. to distinguish between wetlands that you have classified as follows: a. functional/hydrological change b. likely removed from jurisdiction c. no change 10. Please clarify if the applicant is the entity known as 130 Chatham or Rocky River Hydro, LLC. Also, please provide a contact name, email address and phone number for the applicant. 11. We recognize and appreciate that this project has been extensively coordinated with the US Fish and Wildlife Service (USFWS) regarding the Cape Fear Shiner. However, please be aware that no activity is authorized under any NWP which "may affect" a listed species or critical habitat, unless ESA section 7 consultation addressing the effects of the proposed activity has been completed. Direct effects are the immediate effects on listed species and critical habitat caused by the NWP activity. Indirect effects are those effects on listed species and critical habitat that are caused by the NWP activity and are later in time, but still are reasonably certain to occur. We will coordinate with USFWS to complete Section 7 consultation. In cases where the non- Federal applicant has identified listed species or critical habitat that might be affected or is in the vicinity of the activity, and has so notified the Corps, the applicant shall not begin work until the Corps has provided notification that the proposed activity will have "no effect" on listed species or critical habitat, or until ESA section 7 consultation has been completed. 12. We recognize and appreciate that this project has been coordinated with the State Historic Preservation Office (SHPO) regarding the dam and powerhouse. In cases where the district engineer determines that the activity may have the potential to cause effects to properties listed, or eligible for listing, in the National Register of Historic Places, the activity is not authorized, until the requirements of Section 106 of the National Historic Preservation Act (NHPA) have been satisfied. We will coordinate with SHPO to complete Section 106 consultation. For non-federal permittees, the district engineer will notify the prospective permittee within 45 days of receipt of a complete pre -construction notification whether NHPA section 106 consultation is required. If NHPA section 106 consultation is required, the district engineer will notify the non- Federal applicant that he or she cannot begin the activity until section 106 consultation is completed. If you have any questions or concerns, please contact me. Thanks. Andrew Williams Regulatory Project Manager US Army Corps of Engineers Wilmington District, Raleigh Regulatory Field Office 3331 Heritage Trade Drive, Suite 105 Wake Forest, North Carolina 27587 919-554-4884 ext. 26 Appendix G Biological Assessment UniqueftcesLLC.com Unique Places Land Conservation, Restoration & Management Biological Evaluation/ Assessment June 2017 Prepared By: Unique Places, LLC PO Box 52357 Durham, NC 27717 Phone: 919-724-0676 Wildlands Engineering, Inc 312 W. Millbrook Rd., Suite 225 Raleigh, NC 27609 Phone: 919-851-9986 Hoosier Dam Removal Project Chatham County, NC Cape Fear River Basin HUC 03030003 Prepared For: US Fish and Wildlife Service 551 Pylon Drive Raleigh, NC 27606 Phone: 919-856-4520 Appendix G - Biological Assessment G - 1 I. Description of the Proposed Restoration/Recovery Action [include maps, photographs, diagrams, etc. as appropriate] A. Description of the Restoration/Recovery Objective(s) 1. Briefly describe the restoration and specific recovery action (citing source document when applicable) and its intended beneficial impact to the species. The Hoosier Dam is a 94 -year-old hydroelectric dam located on the Rocky River 5 %2 miles upstream of its confluence with the Deep River in Chatham County, North Carolina. The dam is being proposed for removal as part of a National Fish and Wildlife Foundation (NFWF) grant to restore the Rocky River from its currently impounded state back to a free-flowing state. Hoosier Dam and its impoundment, Reeves Lake, are responsible for the loss of natural flow regime, sediment regime, and shallow water habitat to approximately 18,138 linear feet of stream ecosystem (16,060 linear feet within the Rocky River and 2,078 linear feet of perennial tributaries). The U.S. Fish & Wildlife Service (USFWS) has designated sections of the Rocky River upstream of the impoundment and downstream from Hoosier Dam, as well as a section of Bear Creek just below the dam, as Critical Habitat for the Cape Fear shiner, a federally listed endangered species (USFWS, 1988). The non -impounded sections of the Rocky River and Bear Creek exhibit very high quality riverine habitat that supports a diverse collection of aquatic species including the Cape Fear shiner and other species of concern, such as the eastern creekshell (Villosa delumbis), the Carolina creekshell (Villosa vaughaniana), the Savannah Lilliput (Toxolasma pullus), and an undescribed Lampsilis sp... The dam represents a significant blockage to aquatic species ability to disperse freely and exchange genetic material with neighboring populations and as a result, USFWS has documented declines in the disconnected Cape Fear shiner population upstream of the dam (USFWS, 1988). Removal of the blockage created by the dam to provide access to these high-quality reaches would be of substantial long-term benefit to aquatic communities including the Cape Fear shiner. The recovery goals for the Cape Fear shiner, as listed in the 1988 USFWS report are: 1. Protection of existing populations and successful establishment of reintroduced populations and current habitat; 2. Evaluating feasibility of introducing species into historic habitat; 3. Searching for additional suitable habitat for re -introduction; 4. Monitoring existing populations biannually; and 5. Evaluating the recovery program on an annual basis. The removal of the Hoosier Dam, and restoration of the Rocky River in the vicinity of the dam will address the habitat recovery goals of the Cape Fear shiner listed above. Post -dam removal, the previously impounded stretch of the Rocky River will return to its historic wide, shallow, and rocky state. This will immediately provide 3.4 additional miles of historic habitat for the Cape Fear shiner that is directly connected to existing habitat and known populations of the species. This expansion of available habitat is expected to be naturally repopulated as shiners move into the area. Impoundments and siltation from impoundments is listed as one of the key elements in the decline of the Cape Fear shiner population (USFWS 1988.) This project will directly address such an impact. Removing the dam will prevent further siltation of habitat within the currently impounded reach of the Rocky River. The construction plan itself will address the existing sediment wedge behind the dam. The wedge will be removed prior to construction if testing of the wedge after dewatering confirms a dominant fine silt/clay/sand texture. Sediment in the wedge will be pulsed through the system during construction if testing confirms the wedge to be a medium gravel to cobble texture. Appendix G - Biological Assessment G-2 Removal of the dam will restore a natural sediment regime to the Rocky River. The current impoundment not only traps fine sediment, but also the gravels and cobbles that comprise the preferred Cape Fear shiner habitat. Currently, if gravel and cobbles are washed downstream in the habitat below the dam, they are not being replaced by new material entering the system, damaging existing habitat. 2. Include a description of anticipated habitat improvements, and/or expected increases in species fitness, survivorship, etc. that are consistent with the recovery needs of the species. The impounded portion of the Rocky River, shown in the photo to the left, is an open, freshwater, lentic habitat. Water depth is approximately 25 feet at the upstream face of the dam and gradually decreases in the upstream direction. The impoundment is narrow through the majority of the river length and widens for the last 1,000 feet before the dam. Habitat is suitable for lentic species of fish, macroinvertibrates, vegetation, and waterfowl. Draining the impoundment and removing the dam is expected to return the Rocky River to its historic bed conditions. These conditions are likely to mimic those upstream of the impoundment and downstream of Hoosier dam (pictured right). The river will have wide, shallow waters interspersed with bedrock outcrops, pools, natural riffle features, and deposits of large woody debris. This is consistent with the habitat needs of the Cape Fear shiner. In addition to geomorphic habitat restoration, the removal of Hoosier Dam will restore many natural processes that will benefit the Cape Fear shiner and other sensitive aquatic species. Water temperature and oxygen levels will change in the Rocky River's impounded reach once the dam is removed. Previous temperature and dissolved oxygen stratification testing done by Wildlands Engineering (Wildlands) in 2013 within the impoundment showed stratification of temperatures ranging from 26.8 °C at the surface to 22.2 °C at a depth of 19 ft. In a study of the Cape Fear shiner by Hewitt et al. (2006), the habitats with the best survivability and growth rate had temperatures ranging from 26.4°C to 28.1°C. This range was only achieved on three sampling dates and only within the top four feet of lake depth. Since the river will be restored to a shallow water condition, it is more likely to maintain these temperature ranges preferred by the shiner and provide suitable habitat for species re- establishment. Wildlands 2013 dissolved oxygen (DO) samples showed a dramatic decrease in DO concentrations in the first six feet of depth, typically dropping from 8 mg/L to 5 mg/L within the first four feet of depth. The aforementioned study by Hewitt et al. (2006) indicated the best habitat for Cape Appendix G - Biological Assessment G - 3 Fear shiner has a DO range of 5.8 — 12.5 mg/L. Restoration of a shallow free-flowing river will improve habitat conditions within the vicinity of the impounded reach by increasing DO levels and eliminating the drastic stratification existing in the impoundment. Natural sediment transport processes will be restored through removal of the Hoosier Dam. As discussed in the section above, reintroduction of a natural sediment regime will enhance habitat located in the impoundment by flushing fines and removing the sediment wedge, but it will also allow gravels and cobbles that have been trapped behind the dam to coarsen downstream riffles located in the Critical Habitat Area that have been previously starved of sediment. Pebble Counts conducted above and below the impoundment show that riffles below the dam have smaller amounts of coarse gravel and small cobbles, confirming the effect of an interrupted sediment regime. Additional details on sediment composition can be found in the Sediment Management Plan. 3. Explain why there is a high certainty that implementation of the proposed action is likely to achieve its intended restoration/recovery objective under the second Criterion for Inclusion. This explanation should rely on either a proven track record or a high level of certainty that the habitat improvements are likely to cause the desired species response. Dam removals have been performed extensively throughout the United States to remove barriers to aquatic organism passage and return impounded waters to historic lotic conditions. In North Carolina, the Carbonton Dam was removed under similar conditions and project goals to this project including benefits to Cape Fear shiner habitat. The Carbonton Dam was a run of the river hydroelectric dam facility located on the Deep River approximately nine miles west of Sanford North Carolina. The concrete buttress dam was built in 1921, averaged 27 feet in height, and had a crest of 260 feet (Restoration Systems, 2005). Similarly, the Hoosier Dam is a run of the river hydroelectric dam facility with a concrete buttress structure. Hoosier Dam was built in 1922, averages 25 feet in height, and has a crest of 235 feet. The Carbonton Dam removal was part of a NCDEQ-Division of Mitigation Services full delivery project created to deliver mitigation credits for impacts to waters of the United States. Project goals for the Carbonton Dam removal were similar to this project and included restoration of a lotic ecosystem and provision of habitat for the endangered Cape Fear shiner. The project was monitored for five years post- dam removal. After two years, the Cape Fear shiner presence was recorded at eight of their 14 monitoring stations, with available habitat increasing each monitoring year (Restoration Systems, 2010). The project can be considered a success for the restoration of Cape Fear shiner habitat. The Hoosier Dam removal will occur under similar conditions. It is in the same geographic and geologic region, with similar potential for restoration of shallow, wide, rocky habitat for the Cape Fear shiner. Potential risk factors for the project, such as temporary sedimentation, are accounted for in conservation management measures discussed in Section 1D, below. No risk factors are evident that would inhibit the development of a lotic ecosystem with a variety of habitat niches for aquatic species. The presence of Cape Fear shiner in the previously impounded section of the Deep River within two years of dam removal indicates that the species will enter adjacent newly available habitat. 4. Describe over what time frame the conservation benefits of the proposed action are expected to accrue. The Rocky River will experience immediate alteration upon removal of the Hoosier dam and the small remnant dam upstream. The geomorphology, flow regime, and sediment regime will adjust back towards conditions present in the river prior to the construction of Hoosier Dam. It is anticipated that within the first six months, half of the sediment affected by the dam removal will be pulsed through the system as a result from the change in geomorphology (an increase in channel slope from the removal of Appendix G - Biological Assessment G-4 the impoundment). Then over time the remaining sediment may flush through the system on an episodic basis corresponding to large storm events (Collins et al., 2017; Pearson et al., 2011.). This process is expected to return the Rocky River to a shallow water system with a gravel substrate suitable for the colonization of the Cape Fear Shiner. The Cape Fear shiner can migrate into the previously impounded section of the Rocky River from existing populations located upstream of the impoundment and downstream of the dam. This may take place over a number of years, eventually fully connecting the Upper Rocky River Aquatic Habitat to the Lower Rocky River/Lower Deep River Aquatic Habitat and the Bear Creek Aquatic Habitat, greatly expanding the available habitat and spawning areas for the Cape Fear shiner. The timeframe it may take to reestablish the shiner population throughout the former impoundment is unknown, however, there are no projected impacts to the river that would prevent this progress. B. Define the Action Area Construction activities will be isolated to the lower section of the impoundment and the area immediately surrounding Hoosier Dam (approximately 1,000LF) to perform the dam removal, potential removal of the sediment wedge, streambank stabilization, bed stabilization, habitat structure construction, and re -vegetation. Revegetation may also take place upstream in areas affected by the drawdown of the impoundment. The entirety of the impoundment (with an upstream boundary just below Pittsboro Goldston Road and a downstream boundary just below Hoosier Dam) will be directly and indirectly affected by the removal of the Hoosier Dam. The entire impounded area, including tributaries, will by hydrologically affected by the removal of the dam. A lotic flow regime will be reestablished and the channel cross-sections will alter to adjust to the new hydrology. Shallow, rocky sections of river may be exposed and the habitat niches will transition from lentic to lotic. Short term impacts may occur directly downstream of the dam as the Rocky River adjusts to the geomorphic change in the river following removal of the dam. The following is the proposed project timeline: Dewatering of the impoundment: June 2017 -July 2017 o Actions concurrent with dewatering: ■ Relocation of mussel species affected by dewatering; ■ Seeding and stabilizing exposed streambanks; ■ Evaluation of sediment wedge upstream of dam; and ■ Continual monitoring of turbidity. Collection of sensitive mussel species below the dam for relocation: Prior to dam removal, July/August 2017. Removal of Hoosier Dam and Powerhouse Structure: August/September 2017 o Actions concurrent with dam removal: ■ Removal of sediment wedge (if wedge is fine sediment), pulsing of sediment (if wedge is course sediment); ■ Removal of the remnant rock dam located approximately 4,800 feet upstream of Hoosier Dam (incorporate these boulders into habitat enhancement structures on Rocky River) ■ Stabilization of streambanks post -dam removal; ■ Stabilization of stream bed using grade control structures; ■ Implementation of habitat structures within stream bed/banks; and ■ Re-establishment of a riparian buffer with planting of native woody species along streambanks. 4 Appendix G - Biological Assessment G - 5 C. Project Implementation The following federal agencies are involved in permitting and approving the Hoosier Dam Removal Project. Communication and correspondence with all agencies discussed below, in Table 1, is ongoing. Pre -application meetings with agencies have been held and dates are included in the Table. Table 1: Federal Agencies involved in Hoosier Dam Removal - Hoosier Dam Removal Project The removal of the Hoosier Dam will follow the procedure and timeline outlined in Section 1.13, above. Table 2, below, lists the activities associated with the project that are likely to have a temporary or long term beneficial or adverse impact to the Cape fear shiner. Appendix G - Biological Assessment G-6 Associated Permits/ Federal Agency submittals Required Action Status Nationwide 53 (dam removal), Nationwide 27 Coordination and receipt Pre -application meeting US Army Corps of (stream restoration of appropriate permits with USACE held March Engineers activities) and/or prior to dam removal and 15, 2017. Permits to be Nationwide 13 (Bank restoration activities applied for June 2017. Stabilization) Biological Assessment for the Cape Fear shiner, Submittal of Biological US Fish and Wildlife consultation on Assessment so USFWS can BA submitted to USFWS Service dewatering plan and submit Biological Opinion May 30, 2017 sediment management to USACE for permitting plan Submittal of Drawdown Request prior to Drawdown request Federal Energy Drawdown Request, drawdown of submitted June 12, 017. Regulatory Surrender of FERC impoundment, and FERC variance approved Commission Exemption submittal of FERC June 15, 2017. Exemption variance prior to dam removal Submittal of no -rise Coordinated with local Federal Emergency technical memo prior to Floodplain Administrator. Management Agency Dam removal is exempt restoration activities and Submitting No -Rise May CLOMR post restoration 30, 2017. activities The removal of the Hoosier Dam will follow the procedure and timeline outlined in Section 1.13, above. Table 2, below, lists the activities associated with the project that are likely to have a temporary or long term beneficial or adverse impact to the Cape fear shiner. Appendix G - Biological Assessment G-6 Table 2: Project Activities and Their Potential Impact - Hoosier Dam Removal Project Appendix G - Biological Assessment G - 7 Potential Project Activity Activity Description Description of Potential Impact to Species Description of Potential Impact to Effect on Habitat Cape Fear shiner During dewatering, turbidity and effluent flowrate will be monitored to keep at levels set by USFWS (< 50 NTUs, and approximately 50 cfs above baseflow, respectively) in order May Affect Dewatering of Dewatering of to reduce potential impact to aquatic life. Drawdown but not Reeves Lake Impoundment. should maintain a rate of approximately one foot per day. likely to (impoundment) High turbidity levels (>50 NTU) and changes to flow regime Adversely due to dewatering could force species to move Affect downstream from immediate vicinity of Dam. An adaptive management plan will be in place to respond to any rises in Potential increase in turbidity may turbidity during dewatering. have an effect of temporarily silting in Cape Fear shiner habitat. In addition to installing and maintaining erosion and However, any siltation would likely sediment control devices during construction, turbidity be flushed out during the next storm Installing erosion and within the river will be monitored directly downstream of event. May Affect Erosion and sediment control the dam removal. Construction protocol will follow the but not Sediment devices prior to start of same protocol set forth in the dewatering plan, where if the likely to Control/Site setup construction activities turbidity increases above 50 NTUs construction will cease Adversely and maintaining them and any sediment input will be addressed (if caused by Affect during construction construction and not natural hydrologic events). It is likely that turbidity will increase during construction even with the presence of erosion and sediment control devices. Removal of the dam will benefit stream temperatures, Dam will be removed dissolved oxygen levels, hydrologic regime, and sediment Dam removal will open up 3.4 miles Removal of from the Rocky River regime within previously impounded reach and of potential habitat for the Cape May Affect Hoosier Dam according to Final downstream reach of Rocky River. The initial act of removal Fear shiner. Construction Plans could have a temporary impact or take of the species due to construction activities. Appendix G - Biological Assessment G - 7 Appendix G - Biological Assessment G-8 Potential Project Activity Activity Description Description of Potential Impact to Species Description of Potential Impact to Effect on Habitat Cape Fear shiner Removal of the hydroelectric powerhouse will allow for the Deconstruction and Rocky River to have a more stable planform with less Removal of the powerhouse allows Removal of removal of the potential for bank erosion and downstream sedimentation for complete removal of the May Affect Powerhouse hydroelectric post -dam removal. The initial act of removal could have a structure and opens up further powerhouse temporary impact or take of the species due to habitat for the shiner. construction activities If sediment wedge behind dam is found to Sediment will not be pulsed be coarse, sediment If sediment behind the dam is found to be coarse in nature, downstream if it has a high potential May Affect Potential pulsing of may be pulsed there is less danger of it affecting the Cape Fear shiner of silting in shiner habitat. There but not sediment downstream during population. However, there could be a temporary impact as may be temporary deposition of likely to downstream deconstruction. sediment pulses through the system within the first few sediment within the system, but it Adversely months after removal. would be flushed out with the next Affect storm event. This change in bed formation will benefit the Cape Fear After removal of the shiner as it will greatly increase the amount of riffle habitat Reformation of dam, the riverbed will within the newly drained impoundment. Channel bed Reformation of the channel will not channel banks and be stabilized with rock material will coarsen overtime within the previously impact any existing shiner habitat, bed (with structures if needed. If impounded section of Rocky River and the baseflow level but will create potential shiner May Benefit hydrologic regime bedrock is exposed, it will decrease in depth similar to upstream and downstream habitat. change) will remain in place as conditions. Available habitat will also increase for the a natural grade control American Water Willow (Justicia Americana), a native plant species present in the Cape Fear shiner habitat. Stabilization of exposed banks through Re -vegetating stream banks will limit potential for erosion Bank stabilization and re -vegetation Bank Stabilization revegetation and and sedimentation in the Rocky River. This will help will not negatively impact any and re -vegetation potential grading. Re- maintain a coarse bed material texture. Re -vegetating will existing shiner habitat, but may May Benefit vegetation of newly also provide areas of refuge along the streambanks for improve quality in potential shiner exposed floodplains aquatic species including the Cape Fear shiner. habitat. Appendix G - Biological Assessment G-8 Appendix G - Biological Assessment G - 9 Potential Project Activity Activity Description Description of Potential Impact to Species Description of Potential Impact to Effect on Habitat Cape Fear shiner Installation of instream or streambank Habitat structures including rocky riffle and lunker logs Implementation of habitat Habitat Structure structures for the provide instream and near streambank habitat for aquatic structures will not negatively impact May Benefit implementation purpose of providing species including the Cape Fear shiner any existing shiner habitat but may habitat niches within create potential shiner habitat. the Rocky River Appendix G - Biological Assessment G - 9 D. Conservation Measures Specific management practices will be put in place for the demolition of Hoosier Dam and restoration of Rocky River to avoid and minimize adverse impacts to the Cape Fear shiner and its habitat. These are discussed below. Management of Dewatering Dewatering the impoundment is the first phase of the project. The timing of dewatering is critical to minimizing impact on Cape Fear shiner populations downstream of the impoundment. Summer was chosen for drawdown based on consultation with the USFWS for the following reasons: • Baseflow in the channel is at its lowest between June and September. This allows for better control over dewatering and limits the likelihood of the impoundment levels rising and falling, potentially harming aquatic species with the water level fluctuations. Low baseflow conditions also allow for better access to exposed sediments behind the dam, aiding in mechanical removal if deemed necessary. • The summer timeframe is after the window of spring reproductive activity when sensitive life stages associated with spawning and larval development of rare mussels and Cape Fear shiner occur. • Aquatic species surveys are easier in the summer months. Water temperatures allow for human access for species surveys and relocations. The rate of dewatering was developed after consultation with USFWS to limit impact on aquatic species. The drawdown rate will be kept at a maximum of one vertical foot per day. This will allow for stabilization of streambanks with grasses and the collection of any stranded mussels along the impoundment. Turbidity monitoring will be conducted daily during the drawdown period and will commence two weeks before drawdown and extend two weeks following completion of the dewatering. The turbidity will be sampled approximately 100 feet downstream of the power facility. An additional turbidity measurement will be taken weekly within the impoundment that will be sampled from the catwalk attached to the powerhouse. Based on feeback from NC Wildlife Resource Commission (NCWRC) and USFWS a maximum threshold of 50 NTUs will be adhered to during the dewatering process. It is understood that mussels can tolerate short term spikes in turbidity and that it may not be advisable in a high turbidity event to maintain open flow conditions (i.e. not mechanically reduce or stop flow). If turbidity approaches the 50 NTU threshold, Unique Places (UP) staff will immediately contact the NCWRC and USFWS staff to discuss the situation. An action plan will be developed and formalized based on current river conditions, expected rain falls, gauge station data, etc. The prescribed actions to adjust flow (if any) will be implemented immediately by UP staff. Additional information on dewatering is discussed in detail in the dewatering plan. Management of Construction Removal of the Hoosier Dam and the restoration of the Rocky River will adhere to a permitted erosion and sediment control plan through the NCDEQ Division of Energy, Mineral, and Land Resources. Dam removal will be completed to limit impact and contact of equipment, sediment, and materials with the river bed and water column. During dam removal, streamflow will be routed through the existing powerhouse. This will leave dry access to the dam itself. The dam will be removed from the top of the dam down, in small vertical sections. Once material is removed it will be placed in the river within the 0 Appendix G - Biological Assessment G-10 footprint of the dam itself, to allow construction equipment to walk across the streambed on a concrete pad. Once the dam is fully deconstructed, the pad will be removed. Water will then be turned into the center of the channel, and the powerhouse will be removed. The ability to continue a natural flow regime during dam removal will reduce potential impact on downstream aquatic species. Not having to utilize pumps protects aquatic species from being inadvertently pumped through the system. Additional erosion control features will include silt fence along any staging and stockpile areas and stabilizing exposed banks with erosion control matting and temporary and permanent seed. All erosion control features will be monitored regularly as well as turbidity downstream of the construction site for the purpose of preventing sedimentation of downstream aquatic habitat. Turbidity protocol and management will follow that outlined in the dewatering plan. E. Monitoring and Reporting Plan Monitoring of the Cape Fear Shiner will take place for three years following removal of the dam to document project success. Three locations have been chosen because they have existing survey data on the Cape Fear shiner that can be used for comparison. The fourth will be within the previously impounded reach. Sampling locations are: 1. Upstream of the bridge crossing at Pittsboro-Goldston Road (Upsteam of impoundment) 2. The previously impounded reach 3. In the trailrace of the dam 4. At Chatham Church Road Monitoring will be conducted via seining suitable habitats for a standard time duration and number of seining efforts (to be determined). All monitoring will be performed by a qualified and permitted crew once a year for up to three years. If Cape Fear shiner are detected at Pittsboro-Goldston Road, the trailrace of the dam, and Chatham Church Road during the first or second year of monitoring, then sampling in these areas may be discontinued early. Sampling in the impounded reach should continue for the full three years. II. Status of the Species and Critical Habitat in the Action Area- Environmental Baseline Table 3: Federally Listed Species Status - Hoosier Dam Removal Project Species Habitat Association Federal Status Suitable Habitat in Action Area Cape Fear shiner (Notropis Gravel, cobble, and boulder substrate mekistocholas) around aquatic vegetation found in slow Endangered Yes moving pools, riffles, and slow runs. Suitable habitat for the Cape Fear shiner is located within the Action area for this project. The suitable habitat area is located at the base of the dam and continues downstream of the project. The Cape Fear shiner habitat upstream of the impoundment will not be impacted by the activities associated with this project. A. Notropis mekistocholas (Cape Fear shiner) The Notropis mekistocholas, endemic to the Cape Fear River basin, has sustained segmented populations for several decades; however, environmental stressors are still contributing to the species decline. Dams and impoundments that create habitat fragmentation and degradation are the primary culprit for these restricted populations. Currently, the Hoosier Dam and its impoundment is hindering potential connectivity for the Cape Fear shiner. Limited genetic variation can be detrimental to the survivability of a population. Considering the life span of the Cape Fear shiner is approximately 2-3 years, both existing and developing stressors prevent research and 10 Appendix G - Biological Assessment G - 11 monitoring opportunities to learn more about their behavior, biology and ecology. The Cape Fear shiner has not been found in the impoundment; however, populations have been confirmed upstream and downstream. Currently, the Hoosier Dam has altered the riverine habitat resulting in demographic consequences for the aquatic species, especially the Cape Fear shiner. Within confirmed locations, the Cape Fear shiner has been seined in shallow waters around American water -willow (Justicia Americana). Emergent vegetation provides mesohabitats serving as refuge, possible food source and locations for depositing and attaching eggs to the substrate associated around willow beds and other riparian vegetation. The existing lentic ecosystem of Reeves Lake has engulfed all microhabitats which are necessary for distribution and reproduction of the Cape Fear shiner and similar species. Furthermore, impoundments act as a reservoir for predators such as the Roanoke bass (Ambloplites cavifrons), crappie (Pomoxis sp.) and the flathead catfish (Pylodictis olivaris), which is an introduced obligate carnivorous species (Hewitt et al., 2009 and USFWS, 1988). While the adult catfish do not occupy the same habitat as the Cape Fear shiner, the juvenile catfish do share habitat and could pose as potential threat. Dams also act as a holding tank for contaminants which ultimately affect water quality. Suitable habitats required for early development may be essential for this species' success. The Cape Fear shiner has been found in slow pools, shallow side waters and run/riffle complexes throughout their range indicating velocity breaks with healthier water quality and various depths with mixed substrates are indicative of suitable habitat for the life stages of this species (USFWS, 1988). Removal of the Hoosier Dam and restoring riverine habitat within a lotic ecosystem will allow natural features that establish vegetation growth, provide proper spawning grounds, and decrease predation risks. The project would contribute to long-term conservation efforts of the Cape Fear shiner and provide the historical habitat that is necessary to support their population recovery. B. Cape Fear Shiner Critical Habitat As defined in the Cape Fear Shiner Recovery Plan, USFWS designated sections of the Rocky River upstream of Reeves Lake and downstream of the Hoosier Dam, along with a section of Bear Creek just below the dam, as Critical Habitat for the Cape Fear shiner (USFWS, 1988). According to USFWS, "the constituent elements for the Cape Fear shiner include clean streams with gravel, cobble and boulder substrates with pools, riffles, shallow runs and slow water areas with large rock outcrops, side channels and pools with good water quality and relatively low silt loads." Due to the Hoosier Dam, this particular section of the Rocky River does not contain any of the constituent elements but instead the impoundment has inundated the natural features and accumulated a sediment load behind the dam. III. Effects of the Action and Cumulative Effects A. Notropis mekistocholas (Cape Fear Shiner) Any potential adverse impacts are believed to be temporary. During the dewatering process, the drawdown of approximately one foot per day will expose streambanks, some turbidity will occur and the potential effluent flowrates could push the species downstream. The main area of concern will be immediately downstream of the dam removal where fine sediment could be displaced. Measures will be set forth to control and prevent mass erosion or excessive turbidity. For example, seeding will be placed along streambanks to provide streambank stability and decrease siltation. There should be very limited take, if any, upstream of the Hoosier Dam removal. The controlled lowering of the impoundment would provide opportunity for the Cape Fear shiner to reach maximum dispersal distances over time having a positive impact on population levels. The sediment management 11 Appendix G - Biological Assessment G - 12 plan and the scheduling of the project will prevent adverse impacts to the population downstream and would be minimal, if any take does occur. The alteration from a lentic ecosystem to a lotic ecosystem will manipulate the existing habitat and its function. However, the lotic ecosystem will develop and enhance habitat and the habitat function for both aquatic and terrestrial species, serving as a wildlife corridor upstream, downstream and across, whereas the impoundment and Reeves Lake is currently an obstacle for wildlife species. The action will create a permanent gain of habitat and habitat function. The project will develop long-term beneficial impacts by connecting approximately three miles of improved riverine habitat which will allow for demographic dispersal, genetic diversity and species richness. Specifically, characteristics such as higher dissolved oxygen levels, stable water temperatures, consistent hydrologic and sediment regime will establish microhabitats within and around run/riffles complexes, shallow pools and woody debris throughout the reach. The establishment of new vegetation along streambanks, on bars and islands of rock outcrops will provide refuge from predation for aquatic species, including the Cape Fear shiner, which is crucial for larval and young to reach their first year of reproductive maturity. The beneficial cumulative effects such as reducing predation, healthier water qualities, and extending the upstream riverine habitat downstream to the confluence of the Deep River and Rocky River would enhance the Cape Fear critical habitat through the Action Area and provide grounds for further research and monitoring of Cape Fear shiner populations. The long-term benefits are expected to outweigh the short-term impacts to the species. B. Caae Fear Shiner Critical Habitat If any adverse impacts should occur within the critical habitat, they should be short-term and small in magnitude since controlled measures will be implemented to alleviate any severe or long-term impacts; therefore, this project and its temporary in -water work actions should not result in Adverse Modification to designated Cape Fear shiner Critical Habitat. As mentioned earlier, erosion and sediment control devices will be utilized and monitoring turbidity levels will be on-going throughout the process to reduce potential impact to the aquatic species, along with seed application to streambanks to provide bank stabilization. Restoring the essential habitat features, primary constituent elements (PCEs) and/or physical or biological features (PBFs) is the goal of this project. This project should allow enhancement of the conservation support function by establishing connectivity between the upstream and downstream critical habitat. Returning the river to its historical habitat, within the Action Area, will provide another migration site for the Cape Fear shiner or facilitate the augmentation of reintroduced populations. There will be a gain of critical habitat and functional value of critical habitat over time. These beneficial effects to the species will be long-lasting. The negative effects associated with the dam and its impoundment will be removed with the demolition of the dam. Construction itself, and potential associated sediment loads, may cause temporary stress to any Cape Fear shiner in the immediate vicinity of the dam. However, stress should be temporary in duration. The outcome of this project will re-establish the primary constituent elements of the designated critical habitat essential to the conservation of the Cape Fear shiner. IV. Conclusion -Determination of Effect The removal of the Hoosier Dam and restoration of the Rocky River is likely to have an overall, long term, beneficial effect on the Cape Fear shiner population and available habitat. Demolition and construction activities discussed herein May Affect and are Likely to Adversely Affect the Cape Fear 12 Appendix G - Biological Assessment G - 13 shiner. Incidental take is possible in the form of harassment due to machinery and noise in the immediate area, and potential harm/death during the dewatering and demolition/construction stages of the project, but the take will not rise to the level of jeopardy of the Cape Fear shiner, nor will it adversely modify or destroy the designated critical habitat upstream and downstream of the project areas Management practices will be used to prevent incidental take as much as possible. V. List of References and Personal Communications Collins, M.J., Snyder, N.P., Boardman, G., Banks, W.S.L., Andrews, M., Baker, M.E., Conlon, M., Gellis, A, McClain, S., Miller, A., and Wilcock, P., 2017. Channel response to sediment release: insights from a paired analysis of dam removal. Earth Surface Processes and Landforms, doi: 10.1002/esp.4108 Hewitt, Amanda H. et al. 2006. Influence of Water Quality and Associated Contaminants on Survival and Growth of the Endangered Cape Fear shiner (Notropis Mekistochoias). Environmental Toxicology and Chemistry. 25:9. Pp. 2288-2298. Hewitt, Amanda H., Kwak, Thomas J., Cope, W. Gregory, and Pollock, Kenneth H. 2009. Population Density and Instream Habitat Suitability of the Endangered Cape Fear Shiner. Transactions of the American Fisheries Society. 136:6. Pp 1439-1457. Pearson, A.J., Snyder, N.P., and Collins, M.J., 2011. Rates and processes of channel response to dam removal with a sand -filled impoundment. Water Resources Research 47:W08504, doi: 10.1029/2010W R009733 Restoration Systems, LLC and Ecoscience Corporation. 2005. Carbonton Dam — Deep River Restoration Site. Restoration Plan. Project No. 05-235. Accessed May 17, 2017. https://ncdenr.s3.amazonaws.com/s3fs- public/Mitigation%20Services/GIS DATA/CarbontonDam 92268 MP 2005.pdf Restoration Systems, LLC. 2010. Carbonton Dam — Deep River Watershed Restoration Site 2010 Annual Monitoring Report (Year 5). NCDMS Project No. D -04012A. Accessed May 17, 2017. https://ncdenr.s3.amazonaws.com/s3fs- public/Mitigation%20Services/GIS DATA/Carbonton%20Dam 92268 %20MY5 2010.pdf USFWS (U.S. Fish and Wildlife Service). 1988. Cape Fear shiner recovery plan. USFWS, Atlanta. Wildman, Laura A.S. and James G. MacBroom. 2005. The evolution of gravel bed channels after dam removal: Case study of the Anaconda and Union City Dam Removals. Geomorphology 71. pp. 245- 262. Note: Previous correspondence with the USFWS and NCWRC took place when this project was being pursued as a mitigation bank, and therefore, all aspects may not be relevant to the current project. However, they do discuss the requirement for this Biological Assessment and associated Section 7 consultation with USFWS as well as the requirement for a Tier 1 evaluation and acceptance of the Tier 1 evaluation. 13 Appendix G - Biological Assessment G - 14 USFWS Communication and Meeting Notes Appendix G - Biological Assessment UniqueftcesLLCcom UnPaue� Pces Land Conservation, Restoration & Management Topic: NFWF Kick Off Meeting with USFWS Date: August 29, 2016 Attendees/Role: Sara Ward USFWS- services coordinator for the NFWF process. Contaminants Background. Dale Suiter USFWS - plant background interested in Harperella restoration possibilities. Chris Flowers - Unique Places - Project Manager Jeff Fisher - Unique Places CEO John Hutton - Wildlands - VP Angela Allen - Wildlands - Designer Emily Wells USFWS - involved in the mitigation bank option Van Stancil - NCWRC - Mike Wicker - USFWS - experience is dam removal projects particularly demolition aspects. Sarah McRae USFWS - Lead for Cape Fear Shiner Johnny Randall - NC Botanical Garden - harperella reintroduction into the deep river 2nd island - funded by NFWF - expertise in this area. Mike Kunz - Botanical Garden -Harperella experience Trip Bolton - fish passage, fish habitat coordination/maintenance Jeff - Unique Places role is to • Manage the project • Determine how to get the dam down in the most economic way • Be a steward of Tim's interests • Leverage the funds as far as possible to achieve the max conservation impact Jeff mentioned that Tim Sweeney wants Deep to be a wild and scenic river. Brought up the possibility of taking an additional upstream dam out and potential grant funding to complete that work. Jeff put forward the idea of an "executive team" that would consist of highly involved staff members from the represented agencies. It was essentially determined that staff will be involved as much as their time allows within their specific discipline. 3 goals for the meeting were put forth. 1. Next Step - Set up a site visit. 2. Who is on the executive team. 3. How involved will the different agencies be in assisting with this project. Project History: Provided by Wildlands (included site photographs) • 25' tall, slab and buttress design, • turbines can be released to draw water down. • FERC license is already surrendered. Appendix G - Biological Assessment G - 16 • as much as 15K cu of sediment accumulated upstream of the dam. • Tier 1 analysis is complete and showing no risk of contaminants. • John Alderman thought that the dam was a sink for contaminants. • Wildlands collected water quality data to prove that it, if anything, it is actually a source though not statistically significant). Water Quality sampled during July and August. • Wildlands looked for a depth of refusal in the sediment with probe rods. • Impoundment is about 16,000 feet long. Wetlands • 404 and 401 permit will be required. • USACE agent is now David Bailey (formerly Andy Williams) • Approved WL JD is still needed. • The question of a permit being required for dewatering came up with the specific context of the hydrologically dependent fringe wetlands around the impoundment. After much discussions it was largely agreed that up -front discussions with the USACE should happen as soon as practical. • The project timeline will vary greatly depending on the 404 permit required (nationwide v. individual) • This should be determined as soon as possible. • The biological assessment will follow the same process as it would in the Mitigation Bank Scenario. Sediment Analysis • Wildlands has done a Tier 1 sediment report. Modeling has not been done yet. • A Tier 2 analysis is not likely to be necessary due to the lack of contaminants Species Issues • USFWS suggests that there are some mussel issues downstream. • USFWS needs mussel surveys done prior to leaf fall though a spring survey is fine if necessary. • Sara McRae and NCWRC may be able to assist with the mussel survey though this is more likely for a spring survey than this fall. • Shooting for demo by the end of next summer. • Two questions came up regarding sediment that affect aquatic species. • How do we deal with sediment • When do we de -water relative to taking down the dam. • Harperella - Botanical Garden will need some lead time. they have some live populations and seed bank but will need a year to prepare for that. • Mike at Botanical garden - there is a lot of good habitat in the Deep. Would be interested in a survey of this reach. Too late this year. • Unique places will pull the NHP data to determine what rare species are in the dataset for this reach. • There is usually an invasive species removal component as part of the plan. Appendix G - Biological Assessment G - 17 • Dewatering is not dependent on downstream mussel surveys, so long as turbidity does not create a problem. USFWS suggested that the restoration plans should show how the Cape Fear Shiner will re-establish into the reach (connectivity between the upper and lower populations). Atlantic Pigtoe and the Brook Floater are additional mussel species to consider. One (or both?) of these are expected to be listed early next year. One option would be to "assume" and impact and prepare a restoration plan. Mussels could be "grown" but will require significant time to produce a community suitable for restoration. Construction • Trip Bolton's group can handle the construction and has experience in removing equivalent and larger dams. This would constitute a large cost savings to the budget which could be utilized for subsequent conservation efforts. • Trip Bolton USFWS walter—boltin@usfws.gov • 843-819-1229- will send us some info regarding dam removal. Can handle the Dam removal (construction). Fish Passage program is a 50/50 match. ««««« NEXT STEPS »»»»»»» Sediment Analysis - UP wildlands have already scheduled Executive team site meeting - UP will schedule this asap and will communicate the date to all. Mussel Survey - downstream of the dam (Sarah McRae will confirm the length of survey reach needed) UP will send a letter to the IRT recipients to let them know the Mit bank is offline and the new objectives of the project. Loop Misty from NCNHP into this project. Gather additional budget information for Mussel Restoration Gather additional budget information for USFWS dam removal services (from Trip) Appendix G - Biological Assessment G - 18 kt� WILDLAND5 ENGINEERING July 21, 2014 Mr. Andrew Williams U.S. Army Corps of Engineers Raleigh Regulatory Field Office 3331 Heritage Trade Drive, Suite 105 Wake Forest, NC 27587 Subject: Response to Public Notice Comments Hoosier Dam Mitigation Bank Wildlands Engineering Project No. 005-14005 Dear Mr. Williams, We have reviewed the comments from the public notice period for the Hoosier Dam Mitigation Bank dated June 5, 2014. Below are the responses to each of the regulatory agency comments. For your convenience, the comments are reprinted with our responses in italics. Comments by Karen Higgins, NCDENR April 15, 2014 I. The majority of the proposed mitigation units (Table 3) are based on improving the water quality of the Rocky River and its tributaries. Monitoring (both pre- and post-removal) should be performed to assess water quality and aquatic function of the impounded reaches and their post -impoundment condition. Physicochemical monitoring should follow up on temperature and nutrient data collected and presented in the Prospectus. Extensive baseline and post -dam removal monitoring programs have been developed for the Hoosier Dam Mitigation Bank based on previous dam removal projects and input from the US Fish and Wildlife Service. A supplemental monitoring document has been attached, which will be included in the Final Mitigation Plan. Water quality monitoring protocol and associated success criteria are located in Sections 2.1.2 and 2.2.4. Monitoring will be done seasonally each monitoring year at seven stations and include sampling of temperature and dissolved oxygen, as the goals of the project is to ameliorate temperature and dissolved oxygen stratification within the previously impounded sections of the Rocky River. Biological monitoring should focus on improvement of water quality through conversion from a lentic to a lotic system. Parameters for monitoring should include macrobenthos and fish. Performance standards should be crafted to document improvements in physicochemical parameters and to the biotic community. Meeting each individual performance standard over the course of the monitoring period should have an associated percentage of the total water quality improvement credit. Aquatic biological community sampling protocol and success criteria are described in Sections 2.1.4 and 2.2.2 in the attached supplemental monitoring document. Sampling will include macroin vertebrates, snails, mussels and fish surveys along with habitat evaluations at each sampling station. Wildlands Engineering, Inc. • phone 919-851-9986 • fax 919-851-9987 • 312 W Millbrook St Suite 225 • Raleigh, NC 27609 Appendix G - Biological Assessment G - 19 DWR recommends consulting the Milburnie Dam Draft Mitigation Plan dated March, 2014 for an example of performance standards and associated credit yield. While the performance standards and credit yield presented in this plan may not be appropriate for the Hoosier Dam project, the concepts may provide useful in development the Hoosier Dam mitigation plan. As the Milburnie Dam Draft Mitigation Plan is not an approved document it could not legally be made available to Wildlands. To mitigate this, Wildlands is consulting with the IRT agencies on aspects of the Milburnie plan they wish to include on this project. 2. The total proposed potential credit for the project raises a concern that has been the topic of discussions among the IRT in the past. Specifically, if it is appropriate for the DE to allow for more credit to be generated by a dam removal project than the amount of the mitigation that would be required if the dam was constructed now. The mitigation plan (Table 3) indicates the total maximum potential credit for the project is 24,105 LF (24,105 credits). The impounded reach of the river and associated tributaries has been calculated to be 22,425 LF. If the project were proposed today, based on DE requirements on other impoundment projects, the mitigation required would likely be as follows: Impact Type Impact Amt (LF) DA Multiplier Mitigation Requirement Fill (Dam Footprint) 200 Lf* 2:1 400 LF Inundation 22,225 LF 1:1 22,225 LF Total Mitigation Required 22,625 LF *Approximate based on aerial photography According to the proposed maximum potential credit from the mitigation plan, the Sponsor would potentially be awarded 1,480 more linear feet of credit (24,105-22,625) than the mitigation that would potentially be required to permit the construction of the dam and impoundment of 22,425 LF of river and tributaries. As this issue has not been resolved, this should be discussed by the IRT at the next regularly scheduled meeting. The additional credits requested by the Bank Sponsor reflect the proposal for the establishment of riparian buffer conservation easements along Rocky River and its tributaries as discussed in Section 3.2.4 of the Prospectus. The easements, on lands already purchased by the Sponsor, will protect over 35% of the riparian buffer along the Rocky River within the bank limits, 100% of the riparian buffer along Tributaries 3 and 4, and 33% along Tributary 2 (tributary credit will be requested only in cases where an easement can be recorded on both sides). Wildlands and the Bank Sponsor agree that the easements are important in protecting this water resource during its conversion from a lotic to lentic system and in perpetuity to protect Cape Fear shiner habitat. The Bank Sponsor intends to protect the riparian buffers along their properties during their ownership of the lands, however, only a conservation easement will ensure permanent protection. The Sponsor requests compensation for easements in the form of Mitigation Credits. If no credits are awarded, easements will not be recorded on the Rocky River as proposed and the credit request will be altered. 3. Monitoring activities should also include stability monitoring of all formerly -impounded tributaries proposed for credit. Lowering of the water level after dam removal has the potential to expose unvegetated streambanks, which could result in streambank erosion/headcutting. Appendix G - Biological Assessment G - 20 As described in the attached supplemental monitoring plan (Sections 2.1.1 and 2.2.1), geomorphic monitoring stations will be established on all tributaries where credits are requested, spaced 25 bankfull widths apart. These stations will be monitored directly after dewatering and then annually during the monitoring period. 4. The standard service area for mitigation banks in North Carolina is the eight -digit HUC in which the bank is located. The location of the bank site at the southeastern end of 0303003 and its close proximity to 0303004 makes the proposed service area feasibly. DWR would support the primary service area for this bank to include all of 03030003 and the Piedmont portion of 0303004. The proposal is to include only the Piedmont portion of 0303004 in the bank service area. This will be made clearer in the text and figures of the Mitigation Plan. Figure 3 from the Prospectus will be altered to highlight this distinction. 5. We strongly encourage the bank Sponsor to continue to acquire property along the Rocky River and associated bank tributaries, and inclusion of such lands within the bank conservation easement. The Bank Sponsor continues to pursue the purchase of land along the impoundment of Reeves Lake. They have recently purchased two parcels along the right bank of the impoundment approximately 2,500 linear feet upstream of the dam and adjacent to previously purchased parcels. As long as mitigation credits will be awarded for conservation easements, as discussed in the response to above Question 2, they will be included in the Hoosier Dam Mitigation Bank. Comments from Shari Bryant, NCWRC April 10, 2014 1. Section 1.0 Introduction (p.1): "The dam impounds approximately 22,425 feet of Rocky River and six perennial tributaries". This sentence is confusing because it can be read that the dam impounds 22,425 feet of Rocky River. We suggest this sentence is changed to reflect that the dam impounds 16,060 linear feet of Rocky River and 6,365 linear feet of perennial tributaries. This language will be clarified in the Mitigation Plan 2. Section 1.3, Bank Objectives (p.2-3): Table 1 describes the bank goals and methods of achievement. Six goals are listed for the bank; however, several of these goals are restatements. For example, goals 2, 3, and 6 all refer to restoring natural flow regime, managing sediment, and or/improving habitat. In comments from the USACE on the Draft Prospectus, they requested that we "reword and restructure [our] bank objectives to match those deemed applicable within the 2008 [Dam Removal] Guidance because those objectives reflect successful targets identified years ago by the resource agencies". For that reason, the Bank Objectives Section is presented in the format seen in the Final Prospectus. 3. Section 2.2, Assurance of Sufficient Water Rights (p.4): Indicated the hydro facility was bought by the Bank Sponsor. The FERC library does not show any records of transfer of the exemption. Please provide additional information regarding the transfer of the FERC exemption between the previous owner and the Bank Sponsor. A letter notifying FERC of the change in ownership was submitted by Timothy Sweeny on May 14, 2014. Mr. Sweeny has since received notification that it was accepted by FERC and should now show up in the library. Appendix G - Biological Assessment G - 21 4. Section 2.3, Proposed Service Area (p.5): The bank Sponsor is requesting the proposed service area for this mitigation bank include Cape Fear HU 03030003, and the urban growth areas of Cape Fear HU 03030004. The Bank Sponsor indicates these two HUs have the same physiographic characteristics and the HU boundary is arbitrary. Generally, we believe the service area should be designated based on the location of the mitigation bank (i.e. Cape Fear HU 03030003), and using credits outside of the service area should be determined on a case-by-case basis. However, if additional information is included that documents the physiographic and ecological similarities between the original HU and the urban growth areas of Cape Fear HU 03030004, then it can be considered. The draft mitigation plan will include a section that describes the similarities between HU 03030003 and the urban growth areas within the piedmont of HU 03030004 in order to supplement our request for the applicability of the mitigation bank to both service areas. 5. Section 2.4.2, Feasibility (p.7): Under Phase III it indicates removal of the remaining portions of the dam. Although it appears to be indicated in previous sections (e.g. Section 1.0), we recommend the entire powerhouse is removed as well as the dam. The entire powerhouse will be removed with the dam. This will be explained clearly in the demolition plan within the Mitigation Plan. 6. Section 2.4.2, Feasibility (p.7): Under Phase III it indicates removal of the remnant rock dam upstream of Hoosier Dam. The boulders from this dam would be incorporated into habitat enhancement measures on Rocky River. We recommend the boulders are placed to mimic natural stream conditions and appropriate instream habitat rather than randomly placing the boulders in the stream channel. Care will be taken to place remnant rock material throughout the drained impoundment region in such a way that it mimics naturally occurring rock features on other portions of Rocky River. 7. Section 3.2, Baseline Site Conditions (p.8): A discussion of the baseline site conditions is included for water quality and threatened and endangered species. However, there is no discussion of the existing aquatic community (i.e, benthic macroinvertebrates, fish, and freshwater mussels). Baseline (i.e., pre -removal) data for the aquatic community should be collected to develop success criteria and document the specific changes that occur in the aquatic community following dam removal. The pre -removal (baseline) and post-removal survey designs should be coordinated with the IRT prior to data collection to ensure appropriate data is collected to document success criteria have been met. Pre -removal and post-removal data should be collected in Rocky River and any tributaries where mitigation credit is sought. All surveys should be conducted by biologists with both state and federal endangered species permits. Also, exotic aquatic or terrestrial plant or animal species (e.g., flathead catfish) that may be present within the mitigation bank, or that may be introduced to the mitigation bank by removal of the dam should be identified. An extensive biological monitoring plan including baseline and post -dam removal has been developed based on previous dam removal projects and input from the US FWS. Wildlands has attached this plan that discusses each of these concerns including monitoring protocol, success criteria, and the handling of endangered species by companies with state and federal endangered species permits. This discussion can be found in Sections 2.1.4, 2.2.2 and 2.2.3. Appendix G - Biological Assessment G - 22 8. Section 3.2.4, Existing Riparian Buffer Vegetation (p.8-9): The Bank Sponsor Indicates approximately 35% of the riparian buffer along Rocky River within the bank limits has been purchased or protected. In addition, 100% of the buffer along Tributaries 3 and 4, and approximately 33% of the buffer along Trubutary 2 has been purchased and protected. Information regarded how these riparian buffers are protected (e.g. permanent conservation easement) should be included. Please refer to the response to the NCDENR comment #2. The land has been purchased by the Bank Sponsor. If mitigation credits are awarded for the establishment of conservation easements, then the Bank Sponsor will place conservation easements along the Rocky River according to the percentages described above. Conservation easements will be recorded on both sides of any tributaries for which credit is requested. Final copies of these easements will be provided in the final mitigation plan. 9. Section 3.2.5, Water Quality (p.9): Baseline water quality data was collected in the summer of 2013 within the reservoir, upstream of the reservoir, and downstream of the dam. It is likely additional water quality sampling will be needed to establish an adequate baseline. In addition, specific water quality improvements that will be achieved by removal of the dam (i.e., success criteria) should be defined. The pre -removal (baseline) and post- removal survey designs should be coordinated with the IRT prior to data collection to ensure appropriate data is collected to document success criteria have been met. Also, in addition to collecting water quality data in Rocky River, pre- and post-removal water quality data should be collected in any tributaries where mitigation credit is sought. The baseline and annual monitoring protocol and success criteria for water quality are discussed in Sections 2.1.2 and 2.2.4 of the attached supplemental monitoring guidelines. They include collecting water quality data along the tributaries where mitigation credit is sought. These protocols will be discussed with the IRT prior to implementation to establish a final agreed upon monitoring plan. 10. Section 3.2.6, Sediment Characterization and Management (p.13): Indicates a bathymetric survey, Tier 1, and possibly Tier 2 analysis of sediment will be performed, and a Sediment Management Plan will be developed. We are concerned about sediment and its impact on downstream aquatic resources. In addition to the Cape Fear shiner, there are several state listed freshwater mussel species downstream. The volume, level of contamination, and potential risks to downstream aquatic resources will determine how the sediment should be managed. However, in the past, sediments were required to be removed (dredged) prior to dam removal in a watershed that supported federally listed species downstream of the project. On July 16, 2014 Wildlands met with USFWS staff to discuss the sediment wedge upstream of the Hoosier dam and the possible impacts it may have on downstream aquatic wildlife populations including the endangered Cape Fear shiner. It was determined that Wildlands will perform a Tier 1 evaluation, which investigates potential sources of contamination within the contributing drainage area, the physical characteristics of the sediment behind the dam and a bathymetric study to determine the volume of the wedge. This evaluation will then be submitted to the USACE with a determination of whether a Tier 1 evaluation is sufficient or a Tier 2 evaluation should be completed in order to further rule out contamination. The USACE will then provide the document to the USFWS who will do their own evaluation to determine if the dam removal is likely to have a positive or negative effect on fish populations including the cape fear shiner. This evaluation will determine whether sediment will be dredged from behind the dam. 11. Section 3.2.7, FERC License (p.13): It states the Bank Sponsor will surrender the Exemption #3586 to the FERC License in Compliance with the FERC Regulation 4.102. According to the FERC regulations, the exemption holder must consult with the fish and wildlife agencies on the plans for disposition of facilities and site Appendix G - Biological Assessment G - 23 restoration. Also, the exemption holder must fulfill any obligations imposed by FERC and the fish and wildlife agencies for disposition of facilities and site restoration. It is our understanding the application to be filed with FERC is essentially the same as a relicensing application, and includes an environmental assessment of the dam removal and restoration. Yes, the above process description is the one that will be followed by the Bank Sponsor. 12. Section 4.0, Mitigation Work Plan (p.15): Under Dam Demolition and Dewatering Work Plan it indicates the initial dewatering of Reeves Lake would occur in a manner that minimizes water quality and ecological impacts to downstream water bodies and aquatic communities while maintaining instream flows. Also, in Section 2.4.2, Feasibility (p.6), under Phase I it indicates reservoir draining would occur in late fall through early winter through the existing powerhouse. Detailed information regarding the proposed dewatering of Reeves Lake should be included. We support dewatering the impoundment during late fall through early winter. Dewatering should occur in a slow controlled manner that will not result in the scouring or erosion of downstream habitat, and will not result in the downstream flushing of sediment from within the reservoir. In addition, details describing how the impoundment will be drawn down, the proposed drawdown schedule that includes the release flow (CFS) for the impounded waters, and how minimum flows downstream of the dam will be maintained during the entire dam removal process to minimize impacts to aquatic resources should be included. Also, we request the Bank Sponsor notify NCWRC regarding the date and time of dewatering of Reeves Lake is initiated. We would like the opportunity to relocate any freshwater mussels that may be stranded during the dewatering. There will be a section of the Mitigation Plan dedicated to demolition and dewatering that will explain the process in detail. Per your request, NCWRC will be notified regarding the date and time of dewatering of Reeves Lake providing enough time for relocation procedures. 13. Section 4.0, Mitigation Work Plan (p.15): Under Wooded Buffer Restoration Plans it indicates planting lists and details will be included. We recommend re -vegetation of riparian buffers with native trees and shrubs. A reference site located within, near, or adjacent to the bank should be used to develop the plant list for re - vegetating riparian buffers within the bank. In addition, if it is determined these riparian buffers will be used for mitigation credit, then success criteria will need to be developed. Wildlands will follow the methods used in their previous riparian buffer restoration projects for the design and establishment of riparian buffers along Rocky River and its tributaries. It should be noted that the majority of the riparian buffer along Reeves Lake and its tributaries is currently vegetated with mature bottomland hardwood species. Adjacent native vegetative communities will be used as a guideline for the plant list along with species with high survivability noted on previous riparian buffer restoration projects. The mitigation plan will outline the success criteria for these buffers. 14. Section 4.0, Mitigation Work Plan (p. 15): Under Monitoring Plan it indicates pre- and post- removal monitoring will include geomorphic surveys. If the success criteria for the tributaries will include channel stability, then stream geomorphology data should be collected immediately after the reservoir is drawn down for use as pre -removal (baseline) data. Appendix G - Biological Assessment G - 24 Wildlands will follow the above procedure as part of the baseline data collection. This is described in Section 2.2.1 of the attached supplemental monitoring plan. 15. Section 5.0 Determination of Mitigation Credit (p.15): It states "The upstream limits of the impounding effect of the Hoosier Dam on Rocky River and six perennial tributaries were initially estimated based on the water level of Reeves Lake and LIDAR data for the tributaries. The upper limits of these inundated areas were visited, photographed, and field verified using hand-held global positioning system equipment... The final lengths for the Rocky River and each of the six tributaries will be confirmed by topographic survey of the limits of the impounded area." In the past, determining impoundment limits has been problematic particularly on short tributaries. Detailed information describing how the impoundment limits were determined should be included. This will be included in the Mitigation plan. 16. Section 5.0, Determination of Mitigation Credit (p.16): Table 3 shows mitigation criteria for improving water quality, rare, endangered, and threatened species, and protecting wooded buffers. The table does not show "establishing an appropriate aquatic community" as part of the mitigation criteria. Establishing an appropriate aquatic community is listed as a goal in Table 1, and is an important component in determining the success of a dam removal project. Also, the aquatic community was not discussed under baseline site conditions. Please provide additional information regarding how "establishing an appropriate aquatic community" will be determined and how it fits the mitigation criteria. This criteria will be evaluated with biological surveys conducted pre- and post- dam removal to determine if the species composition has shifted in representation from lentic to lotic. The protocol for aquatic community sampling is discussed in Sections 2.1.4, 2.2.2 and 2.2.3 of the attached supplemental monitoring plan. 17. Section 5.0, Determination of Mitigation Credit (p.16): Table 3 shows credit for Rare, Endangered, and Threatened Species for the Rocky River and each of the six tributaries. We question whether all of these tributaries will provide suitable habitat for rare, threatened, or endangered species. Generally, restoration of the tributaries following dam removal is not as effective as restoration of the main channel where the dam was located. If credit is sought for each of the tributaries, then pre -removal and post-removal data will need to be collected in each of the tributaries to document success criteria were met in each tributary. Collection of data in the tributaries is discussed in the attached supplemental monitoring plan. We will not claim credit if success criteria are not met within the tributaries. 18. Section 5.0, Determination of Mitigation Credit (p. 16): It states "Based on initial comments from the IRT, generation of stream mitigation credits for water quality improvements and restoration of rare, threatened, and endangered species for the Rocky River and the six perennial tributaries will not exceed a ratio of 1:1. The Bank Sponsor proposes to preserve riparian buffers along a significant portion of the mainstem of Rocky River and its tributaries. This approach to preserving buffers along the mainstem has not been undertaken on any previously approved dam removal mitigation projects. For this reason, we propose to generate credit above the base 1:1 ratio following the methodology in the rescinded dam removal guidance." This was a possibility in the rescinded dam removal guidance (i.e., Determining Appropriate Compensatory Mitigation Credit for Dam Removal Projects in North Carolina, June 19, 2008). However, it was anticipated the buffer credits generated would compensate for tributaries that most likely would not meet all three success Appendix G - Biological Assessment G - 25 criteria (i.e., water quality, aquatic community, rare, threatened and endangered species) and therefore would not qualify for the 1:1 ratio. Tributaries are more easily impacted and wooded buffers provide additional protection to the tributaries. We question whether mitigation credit should be given for any of the tributaries unless they have protected wooded buffers. Review of previous dam removal mitigation banks has shown tributaries without protected wooded buffers often have significant degradation of aquatic habitat. We believe further discussion with the IRT is needed regarding mitigation credit for tributaries and/or wooded buffers. Also, there appears to be some discrepancy between the percentages of buffer protected on each of the tributaries as described in Section 3.2.4 (p. 8-9) and Table 3 (p. 16). The Bank Sponsor is not claiming credit on any tributaries without a proposed riparian buffer and easement. Any discrepancies between Section 3.2.4 and Table 3 will be reconciled in the draft mitigation plan. As mentioned in the response to NCDENR question #2 and NCWRC question #8, conservation easements will be recorded on the Rocky River if the Bank Sponsor is compensated with mitigation credit. Comments from Pete Beniamin, USFWS April 10, 2014 1. During the draft prospectus review meeting, Emily Jernigan expressed the Service's concerns with removing the sizeable dam in such a sensitive area for the Cape Fear shiner and numerous other Federally At Risk and State rare species. The concerns primarily stem from the lack of available scientific data in regards to the exact quantity and quality of sediments and nutrients the dam is holding back (NPDES discharges, runoff, etc.); and how the release of the impounded water and sediments could potentially negatively affect the downstream ecosystem as a whole. Specific concerns are for the potential impacts to the Cape Fear shiner and its designated downstream Critical Habitat associated with the dam removal. In addition to the Cape Fear shiner, there are several Federal At Risk species that live downstream of the Hoosier Dam including: Atlantic pigtoe (Fusconaia masoni); brook floater (Alasmidonta varicosa); and the Septima's club tail (Gomphus septima). North Carolina rare species found downstream of the dam include: the panhandle pebblesnail (Somatogyrus virginicus); notched rainbow (Villosa constricta); triangle floater (Alasmidonta undulata); Carolina creekshell (Villosa vaughaniana); eastern creekshell (Villosa delumbis); and the creeper (Strophitus undulatus). As discussed during our May 13, 2013 meeting, the Service recommends the Corps request to begin the consultation process, as the proposed activities may affect the Cape Fear shiner, and may adversely modify the designated Critical Habitat downstream of the dam location depending on the actions taken. This process will be the most appropriate avenue to adequately address all of the potential concerns in addition to the desired species benefits associated with this proposed project. Wildlands and the Bank Sponsor have begun the consultation process with Emily Jernigan as requested. The first meeting took place July 16, 2014 to discuss the Tier 1 evaluation for sediment behind the dam as well as potential impact the sediment and dam removal itself may have on aquatic life including the Cape Fear shiner. Wildlands and the Bank Sponsor will continue the consultation process throughout the project to ensure all concerns regarding aquatic life are addressed. 2. The Service is pleased to know the prospectus states that a sediment management plan will be established in the Mitigation Plan, and will be developed such that the risk of short-term impacts to sensitive aquatic communities downstream is minimized, and long-term impacts are avoided altogether. A sediment management plan should be based on site-specific assessment of sediment quantity and quality. It should discuss how sediment is to be managed before and during the removal and include the anticipated impacts of sediment movement post-removal (on upstream and downstream sediment loading, bank stability, and sediment and water quality), particularly as related to Cape Fear shiner habitat. Any proposed mitigative measures and monitoring should also be included. Appendix G - Biological Assessment G - 26 Wildlands will follow the suggestions above in developing the sediment management plan to be included in the draft mitigation plan. 3. The Service applauds the Bank Sponsor's initial efforts to acquire the majority of the Rocky River mainstem and associated tributary buffers, and encourages these efforts to continue to incorporate additional buffers along the entire project reach; as it will benefit the Cape Fear shiner's habitat and additional aquatic and terrestrial species as a whole. Wildlands Engineering has indicated that more conservation easements are in the process of being acquired along the project reach, and the Service supports these conservation efforts. The Service recommends that in order to receive credit for the approximately 6,365 linear feet of tributaries proposed, the tributaries should be protected with conservation easements which include a buffer on each side of the channel; preferably a 300 -foot forested buffer wherever this is possible. We also encourage the establishment of 300 -foot forested buffers and conservation easements on as much of the Rocky River mainstem as possible. Even with forested buffers and conservation easements, the Service would be concerned about allowing 1:1 credit ratios for tributary reaches that are deeply incised, or observed to be lacking in desired natural aquatic functions. We look forward to viewing the impounded areas, reviewing the total property easement acquisitions, and discussing potential credit ratios. As mentioned in the response to NCDENR question #2 and NCWRC question #8 and #18, conservation easements will be recorded on the Rocky River if the Bank Sponsor is compensated with mitigation credit. The bank sponsor has not yet decided on the width of buffer to be protected but will take the USFWS comment under advisement. Geomorphic surveys will be conducted on the tributaries and Wildlands will coordinate with the IRT regarding the suitability of these systems for credit generation. 4. In general, the Service does not have concerns with structuring available credits around goals of the project (reestablishment of flow, endangered species habitat improvement, water quality improvement, fish passage, etc.). However, we caution that all goals and success criteria should be quantifiable and reasonable, and the amount of credits offered for reaching the goals should be appropriate for the level of effort and measured level of improvement. We look forward to discussing potential goals, success criteria, and available credits in an effort to retain consistency with other proposed dam removal projects. Success criteria have been outlined in regards to aquatic communities, water quality, geomorphology and the re - colonization of rare, threatened and endangered species in the attached supplemental monitoring document. Success criteria in the monitoring document are quantifiable based on monitoring data and have been modeled after previous dam removal projects. Wildlands intends to discuss this document at the IRT meeting on July 22, 2014 before inclusion of these criteria into the draft mitigation plan. 5. The Service anticipates that the Mitigation Plan will include, at a minimum, proposals for monitoring of fish passage and habitat quality for the Cape Fear shiner and other rare native aquatic species, water quality, sediment quantity, quality, and movement, vegetation recruitment and invasive plants, and shoreline stability. We recommend using appropriate native vegetative species that would benefit the Cape Fear shiner and the Rocky River system, such as American water willow (Justicia americana), when preparing the replanting component of the mitigation plan. In addition, remedial plans should be included, should the provider fail to meet stated goals The mitigation plan will address the topics listed above including planting of native vegetation, success criteria and long term management plans. Appendix G - Biological Assessment G - 27 Comments by Renee Gledhill -Early. SHPO. March 17. 2014 I. There are no recorded archeological sites in the project vicinity, but the document states that a Phase I cultural resources investigation is anticipated to be undertaken. We concur with this recommendation and look forward to review of the document. The investigations should include background research documenting the history of the dam and the power generating facilities, as well as a pedestrian survey of the project area of potential effect (APE). The aerial photograph noted Henley's Mill. If a mill exists, background research should be conducted and the structure or remains investigated. Potential project effects to this mill should be assessed. We would suggest that the applicant, or their archaeological contractor, meet with staff of the Office of State Archaeology prior to undertaking the Phase I investigation to ensure that all expectation concerning the investigation are anticipated. Two copies of the resulting cultural resource report, as well as one copy of the appropriate site forms, should be forwarded to us for review and comment as soon as they are available and well in advance of project implementation. Wildlands and Unique Places will continue to coordinate with SHPO throughout the Phase 1 cultural resources investigation and provide the requisite copies of the resulting cultural resource report the SHPO office and the IRT. Comments by Jean Gibbv. USACE June 5. 2014 I. In an electronic correspondence dated July 3, 2013 regarding this project, the Corps of Engineers requested that a jurisdictional determination be conducted for this project and included in the prospectus. To date, a jurisdictional determination for this site has not been conducted. You must identify and quantify all jurisdictional waters within the project area and include the source of hydrology for each. As part of your jurisdictional determination, you should complete USACE and North Carolina Division of Water Resources (NCDWR) stream forms, upstream of the impounded areas, in order to describe the anticipated return of functions. You will also need to assess the potential impacts to all wetlands from the proposed dam removal. Any wetland impacts that cannot be avoided may require a separate compensatory mitigation plan. Furthermore, depending upon the amount of loss of wetland resources, and/or adverse impacts to other aquatic resources, and individual DA permit may be required for this project. Please be aware that even if a Mitigation Banking Instrument (MBI) and mitigation plan for this proposed project is approved, the DA individual permit authorization would be issued or denied based upon criteria as determined by our Section 404(b)(1) guidelines and public interest review. A wetland and stream delineation is currently being conducted for this site and a jurisdictional determination will be requested (estimated completion date August 1, 2014). The corresponding forms mentioned above will be included in the draft mitigation plan. Discussion and analysis of wetland impacts will also be included in the mitigation plan. 2. Additional information regarding impacts of the proposed work on the six (6) tributaries will need to be addressed in the draft mitigation plan. As impact to the tributaries has not yet been addressed, the amount of credit, if any, to be provided by these tributaries will need to be determined after review of the draft plan. As mentioned by the North Carolina Wildlife Resources Commission (NCWRC) in their April 10, 2014 letter, Appendix G - Biological Assessment G - 28 additional information regarding the establishment of the impoundment limits of the tributaries, establishment of appropriate aquatic communities, determination of habitat for threatened and endangered species within the tributaries and the use of wooded buffers will be necessary regarding the final establishment of potential credits (see also number 5 below). The draft mitigation plan will address impacts and proposed worked on the six tributaries. As you mentioned, some IRT members voiced concerns over the tributaries. Those regarding biological community, water quality, endangered species, and geomorphic stability monitoring and success criteria are addressed in the attached supplemental monitoring document. Wildlands will gather input from the IRT regarding the monitoring document before the completion of our baseline monitoring and include that input into the draft mitigation plan. Also as previously discussed, credit will only be sought for tributaries that include riparian buffers in conservation easements. 3. Please be aware that the credit release schedule and service area have not been determined. These items still need to be resolved and will depend, in part, on much of the information that will be included in the draft mitigation plan and draft mitigation banking instrument. This is noted, and we will continue to communicate with the IRT throughout this process. 4. Based on comments received from the U.S. Fish and Wildlife Service (USFWS), we have initiated informal consultation regarding the Cape Fear Shiner by letter dated June 5, 2014. Please consider all information provided during this process and incorporate it into your draft mitigation plan and draft MBI. Wildlands has begun to consult with USFWS and had a meeting regarding the Cape Fear Shiner on July 16, 2014. Discussions in this meeting led to the development of the attached monitoring document. Wildlands will continue to work closely with USFWS throughout the project and will incorporate methods for protecting the Cape Fear shiner pre, during, and post dam removal in the draft mitigation plan. 5. As indicated in your prospectus and the April 15 letter from the NCDWR and the April 10, 2014 letter from NCWRC, additional water quality monitoring, aquatic community data and geomorphic data (both pre and post removal) will be necessary to aid in the development of performance standards and credit determination. This data collection should be coordinated with the IRT as the draft mitigation plan and draft MBI are developed. Wildlands has provided the attached supplemental monitoring doument in order to get a consensus from the IRT moving forward on acceptable monitoring protocols and success criteria. The draft mitigation plan will include the monitoring protocol as agreed upon by the IRT. 6. As indicated in your prospectus, a more detailed evaluation of sediment quantity and quality above the Hoosier Dam must be completed and a more detailed sediment management plan must be developed. As indicated by the USFWS and the NCWRC in their April 10, 2014 letters, the plan should discuss how much sediment is to be managed before and during the removal and include the anticipated impacts of sediment movement post-removal. You should also include any proposed mitigation and monitoring associated with sediment removal. The subjects mentioned above will be included in the draft mitigation plan. Wildlands is currently performing a bathometric study of the impounded sediment and is starting a Tier 1 evaluation of the impoundment, which, along with consultation from the USFWS, will drive the development of the sediment management plan. Appendix G - Biological Assessment G - 29 7. Please continue to coordinate with the State Historic Preservation Office regarding potential impacts to cultural resources. Coordination will continue with the SHPO and information regarding correspondence will be provided to the IRT. 8. Please consider and address the recreational uses of the existing resource by the adjacent property owners/citizens expressed in the attached letters. The concerns regarding the recreational uses of the existing resources and other comments from adjacent property owners/citizens is being addressed in a separate comment response letter, which will be provided to the USACE at a later date. Please contact me at 919-851-9986 x 102 if you have any questions. Sincerely, John Hutton Title Enclosure: Monitoring Document Appendix G - Biological Assessment G - 30 310 305 300 295 ----STA= ELEV = 290 285 280 275 270 EXISTING GRADE PROPOSED GRADE °°' --------- o oo �jll FEMA 100 -NEAR FLOODPLAIN EXTENT o° /.. / o^ _ CONSTRUCTION ACCESS FROM / CHATHAM CHURCH ROAD TEMPORARY IMPACT FOR DAM DEMOLITION ------ Sq F ,8 - TE FILL) `I (8 427 T, 1,880 CY MP ---------- % / ---------- ; II , I / 'I ----------------- ------------- BOUNDARY OF TOPOGRAPHIC SURVEY °° - ;' i a____, / / ; GRADING 3(H):1(V) SIDESLOPES F/ / GRA DING 4IH):1)V)$IDESLOPE$ t� it r Js1' J i JEJ 1 � '� `�'\:a`�9��:a� �� ��a rte.. . a� � ��:��.w.,.� �.,.•� 'I I .• ' "I I .' :• • ••• --------------- GRADING 4(H):11V) SIDESLOPES TOP OF DAM ELEV. 302.4 EXISTING DAM STRUCTURE 310 305 300 295 290 285 280 275 270 I� •l zo opo Z ry LL _ oZN z 2.e., Al� aw 9 z 0' 40' 120' (HOR-14TAL) 0. 4, B, 12' (VERTICAL) EXISTING GRADE PROPOSED GRADE °°' --------- o oo �jll FEMA 100 -NEAR FLOODPLAIN EXTENT o° /.. / o^ _ CONSTRUCTION ACCESS FROM / CHATHAM CHURCH ROAD TEMPORARY IMPACT FOR DAM DEMOLITION ------ Sq F ,8 - TE FILL) `I (8 427 T, 1,880 CY MP ---------- % / ---------- ; II , I / 'I ----------------- ------------- BOUNDARY OF TOPOGRAPHIC SURVEY °° - ;' i a____, / / ; GRADING 3(H):1(V) SIDESLOPES F/ / GRA DING 4IH):1)V)$IDESLOPE$ t� it r Js1' J i JEJ 1 � '� `�'\:a`�9��:a� �� ��a rte.. . a� � ��:��.w.,.� �.,.•� 'I I .• ' "I I .' :• • ••• --------------- GRADING 4(H):11V) SIDESLOPES TOP OF DAM ELEV. 302.4 EXISTING DAM STRUCTURE 310 305 300 295 290 285 280 275 270 I� •l zo opo Z ry LL _ oZN z 2.e., Al� aw 9 TEMPORARY IMPACT TO CRIB DAM (5,076 SQ FT) EXCESS MATERIAL, NOT USED FOR ROCK TOE, TO BE SPOILED OUTSIDE OF FLOODPLAIN HILL SHAYNA 1 j 418 THOMAS MILL DR PIN: 9639-60-2899 ANK - NOTES. I I I I \ 1. SITE TO BE ACCESSED FROM THOMAS MILL DRIVE AS PRIMARY ACCESS AND WOODY DAM ROAD AS ------ - SECONDARY ACCESS IF NECESSARY. t --- 2. THOMAS MILL DR AND ACCESS ROUTES TO BE LEFT IN AS GOOD OR BETTER CONDITION THAN \ PRE -CONSTRUCTION. '- 3. MATERIAL FROM CRIB DAM TO BE RE -USED AS ROCK TOE PROTECTION ON SURROUNDING STREAM BANKS. 4. ANY ADDITIONAL MATERIAL TO BE STOCKPILED ON THE RIGHT SIDE OF THE ROCKY RIVER ON PROPERTY OWNED BY 130 OF CHATHAM. ALL MATERIAL MUST BE STOCKPILED OUTSIDE OF THE 100 -YEAR FEMA FLOODPLAIN (SEE SHEET 5.2). HILL SHAYNA 1 j 418 THOMAS MILL DR PIN: 9639-60-2899 ANK ------ --------------- --_ --- \ 1 \ -- -------------- EXISTING DAM CRIB WALL REMNANTS ` (TO BE REMOVED) Go- / OD�Loo lOD I PROPOSED RELOCATION AREAS FOR ROCK FROM CRIB DAM DEMOLITION AS TOE STABILIZATION PERMANENT IMPACT (7,296 SQ FT) I LOD \ � 1 \\ 1 1 1 \ PRIVATE DRIVEWAY PROPOSE-- ----------------- -- ------ -------------------- I I I I \ FEMA 100 -YEAR FLOODPLAIN ------ --------------- --_ --- \ 1 \ -- -------------- EXISTING DAM CRIB WALL REMNANTS ` (TO BE REMOVED) Go- / OD�Loo lOD I PROPOSED RELOCATION AREAS FOR ROCK FROM CRIB DAM DEMOLITION AS TOE STABILIZATION PERMANENT IMPACT (7,296 SQ FT) I LOD \ � 1 \\ 1 1 1 \ PRIVATE DRIVEWAY PROPOSE-- ----------------- -- ------ -------------------- ---- - -- --- PROPOSED ACCESS ROAD ' ---- ----------------------------- ---------------------------------- ---------------- PROPOSED LOD --— --------------- — ----- ,_--- -------- -------------- ------ _ ----- ----- ------- '7Vmo z P��LL �z a -o -ZZ ' -Z mN Z �� LL u V cz cz o c 03 r :2 >..,, Impoundment Boundary 0 Returning Wetlands (2.12 Acres) Existing Wetlands (5.34 ac) ` Likely Functional Chane 0.75 ac Likely Removed from JD (2.03 ac) Wetland to Remain JD (2.56 ac) WLAC g. WL AB WLZ - WL AA 1 WLX Ka" q WILY WL W WL U x WILT WL M WLR WL S WL P WL N WL Q WL U WL L WL K WL O WL I WL J WL E WL G WL F Estimated 1 WLA Estimated 2 WL B Estimated 3 � �r • ��' � Hoosier Dam „ y f I., 4 WL D A , Figure 7: Existing and Probable Returning Wetlands WILD LANDS Hoosier Dam Removal Project ENGINEERING � 750 I I I 1,500 Feet I I t Chatham County, NC Hoosier Dam Removal Project Cape Fear River Basin 03030003 Chatham County, North Carolina for National Fish and Wildlife Foundation F� F Pp �Qp p2p THOMAS MILL �ON�O ROAD GO��S CRIB DAM - i 7q 1 Pp HOOSIER DAM v N \ WOODY DAM RD -- D Vicinity Map Not to Scale BEFORE YOU DIG! CALL 1-800-632-4949 N.C. ONE -CALL CENTER IT'S THE LAW! 0 CONSTRUCTION PLANS ISSUED FEBRUARY 6, 2018 Sheet Index Title Sheet 0.1 Project Overview 0.2 General Notes and Symbols 0.3 Hoosier Dam Demolition 1.1-1.4 Rocky River Plan & Profile 2.1 Crib Dam Demolition 3.1-3.2 Planting Plan 4.1-4.2 Erosion and Sediment Control 5.1-5.2 Details 6.1-6.3 Project Directory Engineering: Wildlands Engineering, Inc License No. F-0831 312 W. Millbrook Road, Suite 225 Angela N Allen, PE 919-851-9986 Surveying: Infinite Land Design, P.C. 117 North Chatham Avenue Siler City, NC 27344 Charles O. Eliason, PLS 919-663-2708 Owner: 130 of Chatham, LLC 3409 Birk Bluff Court Cary, NC 27518 Tim Sweeney 919-632-0161 USACE Action ID SAW -2017-00511 NFWF Project ID # 8020.16.054047 \ \ / \ \ / BARRY Bi PHYLLIS I / DEED BO Q I / O �.1- 3.3 CRIB DAM -REMOVAL / 5.1 AND 5.3 SEDIMENT AND EROSION CONTROL \ / VIRGINIA HILL AND SHAYNA HILL / ACCESS ROUTE DEED BOOK 1579, PAGE 386 H MATTHEW T. SCHLAGEL DEED BOOK 709, PAGE 340 / I RIB DAM I / II I II �� 130 NTHAM LLC II D BOOK 1677, PAGE 955 I' I� II II I �I I I I I' I I I I I I I' I I I I I I I' I' I' I I I' I ROUTE HRISTINAS. BOWMAN AND/ VID E. BOWMAN D D BOOK 703, PAGE 87� ANGELA THOMAS PARKER AND AUSTIN LYNN PARKER DEED BOOK 1397, PAGE 277 JACK MATT DEED Ij 130 CHATHAM LLC II II 130 OF CHATHAM \ DEED BOOK 1750, PAGE 767 \ / \ \ II DEED 1727, PAGE 687 \ II \ I i 130 CHATHAM LLC DEED BOOK 1750, PAGE 7C7_ _ _ _ _AU lz PL LUBY, CAROLE LUBY, \ MOLLY C. LUBY, AND JEFFREY b. GA DEED BOOK 1245, PAGE 782 \ LLC BOOK16 BOOK 1699, PAGE 1035 130 CHATHAM LLC / \\ \ DEED BOOK 1750, PAGE 767 \ / OCA \ \ Ij 130 CHATHAM LLC II II 130 OF CHATHAM \ DEED BOOK 1750, PAGE 767 \ / \ \ II DEED 1727, PAGE 687 \ II \ I i 130 CHATHAM LLC DEED BOOK 1750, PAGE 7C7_ _ _ _ _AU lz PL LUBY, CAROLE LUBY, \ MOLLY C. LUBY, AND JEFFREY b. GA DEED BOOK 1245, PAGE 782 \ LLC BOOK16 BOOK 1699, PAGE 1035 130 CHATHAM LLC / \\ \ DEED BOOK 1750, PAGE 767 \ / / o' 250' Soo' 750' (xOniroxTaL) 1.1 HOOSIER D MOO RVIEW \ \ DONALD CHEEK 1.2 STAGE 1 D/AM RE AL DEED BOOK 1042, PAGE 38 1.3 STAGE 2 DAM REM VAL 1.4 STAGE 3 DAM REM VAL ACCESS ROUTE 2.1 ROCKY RIVER PLAN ROFILE \ -42-�LANG PLAN / 5.1- 5.2 SEDIMENT AND ERO \ N CONTROL \ a) O i ROCKY IVER HYDRO LLC \— DEED BO 1660 z �✓ PAGE / \ / 130 CHATHAM LL DEED BOOK 17 V / y IPAGE 707 C p \ \ 30 CHATHA L C Q U .4 DEED BOOK 17 AGE 707 \ JOSEPH R. EL — \ ANNA S. ELLEN tt \ EED BOOK 474, PAGE 7 O x \ U ANDREW G. SIEGNER III AND BONNIE E. SIEGNER \ \ HOOSIER DAM Opp DEED BOOK 663, PAGE 509 \ DAVID LOUIS HINTON DEED BOOK 698, PAGE 153 \JOHN HOW RD LLEY III DEED BOOK 796 \ AGE 352 \ I \ I \ IJOHN HOWARD TALLEY III DEED BOOK 796, PAGE 352 \ I IN / o' 250' Soo' 750' (xOniroxTaL) Stream grading; channel grading and material spoiling will follow the general notes below in addition to directions outlined in the specifications. General Construction Notes for All Reaches 1. All erosion and sediment control practices shall comply with the North Carolina Erosion and Sediment Control Planning and Design Manual. 2. No material excavated from the Rocky River may be spoiled within the regulated floodplain area. 3. In grading the Rocky River, Contractor shall disturb only as much channel bank as can be stabilized with temporary seeding, mulch, and a sod mat or erosion control matting by the end of each work day. 4. Clearing and grubbing activities shall not extend more than 150 linear feet ahead of in -stream work. 5. All graded areas with slopes steeper than 3:1 will be stabilized within seven (7) working days. All other areas will be stabilized within 14 working days. 6. Locations for staging and stockpile areas and temporary stream crossings have been provided on the Plans. Additional or alternative staging and/or stockpile areas and stream crossings may be used by the Contractor provided that all practices comply with the North Carolina Erosion and Sediment Control Planning and Design Manual and that the areas are approved by the Engineer prior to implementation. 7. Contractor is to make every effort to avoid damaging or removing existing trees. 8. Under no circumstances will the Contractor exceed the limits of disturbance as shown on the Plans. Initial Site Preparation 1. Contact North Carolina "One Call" Center (1.800.632.4949) before any excavation. 2. Contact Division of Energy, Mineral and Land Resources (919-791-4200) before any work begins on the project and notify them of the start date. 3. Mobilize equipment and materials to the Site. 4. Identify and establish construction entrance, staging and stockpile areas, haul roads, silt fence, tree protection fencing, and temporary stream crossings as indicated on the Plans for work areas. 5. All haul roads shall be monitored for sediment loss daily. In the event of sediment loss, silt fence or other acceptable sediment and erosion control practices shall be installed. Silt fence outlets shall be located at points of low elevation or a minimum spacing of 150 ft. 6. Set up temporary facilities, locate equipment within the staging area, and stockpile materials needed for the initial stages of construction within the stockpile area(s). 7. Install and maintain an onsite rain gauge and log book to record the rainfall amounts and dates. Complete the self -inspection as required by NCDEQ permit. HOOSIER DAM REMOVAL For instructions on the removal of Hoosier Dam, please see Sheets 1.1-1.4 and corresponding specifications. Existing Features Existing Property Boundary 0 /PS ------- Existing 5' Major Contour * /PF Existing 1' Minor Contour 0 RRS Existing Thalweg * RRF Existing Utility Easement 0 ECM ROCKY RIVER CHANNEL GRADING 8. Grading along the Rocky River includes the removal of the sediment wedge created by the Hoosier Dam within the active channel. The profile for the river is approximate and based on best available knowledge of the streambed slopes upstream and downstream and mechanical borings of depth to bedrock. The actual depth to bedrock along the entire proposed surface may vary greatly from what is proposed. If this is the case, the sediments should be excavated down to the depth of refusal or presence of coarse bed material, and banks graded back at a minimum 3(H):1(V) slope to the tie-in point on the existing surface. 9. All graded streambanks will be matted with erosion control matting per detail. 10. Seed (with specified temporary seed and permanent seed mix) and straw mulch areas where the coir fiber matting is to be installed. 11. Install coir fiber matting according to plans and specifications. 12. Seed floodplain with specified temporary and permanent seed mix and mulch. 13. Install livestakes and herbaceous plugs along the stream banks and bare root trees within the floodplain, according to the plans and specifications. rrih n.m P.m .i- 14. Remove rocks from crib dam according to design on plan sheets. 15. Rocks may be used as toe stabilization along streambanks within the limits of disturbance. 16. No material may be spoiled within the regulated floodplain limits. Construction Demobilization 17. Remove temporary stream crossings. 18. The Contractor shall ensure that the site is free of trash and leftover materials prior to demobilization of equipment from the site. 19. Complete the removal of any additional stockpiled material from the site. 20. Demobilize grading equipment from the site. 21. All areas outside the grading areas shall be returned to pre -project conditions or better. 22. Seed, mulch, and stabilize staging areas, stockpile areas, haul roads, and construction entrances. IRON PIPE SET 3/4" IRON PIPE FOUND RAIL ROAD SPIKE SET RAIL ROAD SPIKE FOUND EXISTING CONCRETE MONUMENT 0 CMP COMPUTED POINT Existing Wetlands X FENCING OVHD . OVERHEAD UTILITY LINES p p Existing Treeline NCoor NCDOT EASEMENT LINE UTILITY POLE W/ OVERHEAD LINES Existing Tree OO See Detail 2, Sheet 6.2 ® WATER SUPPLY WELL PERK SITE Proposed Features Proposed Stream Alignment Proposed 5' Major Contour Proposed 1' Minor Contour Erosion Control Features I Proposed Haul Road Proposed Stockpile/ Staging Area Proposed Limits Of Disturbance SAF Proposed Tree Protection Fencing See Detail 3, Sheet 6.1 Q zz Wo 4 r -i Ili XF Ap ilo� Proposed Construction Entrance See Detail 1, Sheet 6.2 Proposed Silt Fence See Detail 2, Sheet 6.2 ® Proposed Stone Outlet See Detail 3, Sheet 6.3 I Proposed Haul Road Proposed Stockpile/ Staging Area Proposed Limits Of Disturbance SAF Proposed Tree Protection Fencing See Detail 3, Sheet 6.1 Q zz Wo 4 r -i Ili XF Ap ilo� PARCEL ID: 0073197 DONALD CHEEK DEED BOOK 1042 PAGE 38 PLAT BOOK 97 PAGE 113 PARCEL ID: 0066913 ROCKY RIVER HYDRO LLC DEED BOOK 1660 PAGE 903 LIMITS OF DISTURBANCE = 0.94 ACRES DAM CENTERLINE ALIGNMENT IRON PIN NORTHING: 686442.1374 EAST I N G: 1937482.0502 PARCEL ID: 0018083 JACK L. MILLER AND MATTIE B. MILLER DEED BOOK 731 PAGE 61 PLAT BOOK 27 PAGE 54 X MARK ON ROCK NORTHING: 686068.3256 EAST I N G: 1937349.7532 0� TOP EL 302 85 CONCRETE SIDEWALL PARCEL ID: 0066913 ROCKY RIVER HYDRO LLC DEED BOOK 1660 PAGE 903 IRON PIN NORTHING: 685981.1724 EAST I N G: 1937254.3522 GRAVEL DRIVE PARCEL ID: 0018261 ? ANDREW G. SIEGNER AND _- ---- BONNIE E. SIEGNER DEED BOOK 663 PAGE 509 - PARCEL ID: 0060266 DAVID LOUIS HINTON / DEED BOOK 698 PAGE 153 PLAT BOOK 30 PAGE 58 EDGE OF WATER _ - EDGE OF WATER 1 , / I /ROCKY RIVER I - c FIE _ I =' I I I I 1 / / / 111 , I \ I / i I '- I CONCRETE SPILLWAY TOP EL 302 W X MARK ON CONCRETE - NORTHING: 686294.3548 _ EASTING: 1937134.9813 - r EL 305.62 CONCRETE PAD EL 303 97 FLOATING DEBRIS BOOM CONCRETE PAD v EL 310.22 TOP EL\ 306.48`' , I 67 11 lj 1 I EDGE OF WATER 1 ' I' EXISTING SITE PLAN SCALE: 1'=40' o ao' 80 NAIL IN CENTER OF BRIDGE NORTHING: 686060.3180 FASTING: 1936984.8600 OLD FOUNDATION RUINS TREE LINE POWER HOUSE FIFE EL 312.57 CONCRETE LANDING EL 306.37 _ CONCRETE LANDING EL 300.53 — CONCRETE SIDEWALK — FENCE rIAPARCEL ID: 0018352 ROCKY RIVER HYDRO LLC DEED BOOK 1660 PAGE 903 - _= / 1 I I \ \ \ \I 1 1 WOODY DAM ROAD GRAVEL/UNPAVED 60' PUBLIC RAN IRON PIN NORTHING: 686285.0270 EASTI NG: 1936944.0010 PARCEL ID: 0018233 JOHN HOWARD TALLEY III DEED BOOK 796 PAGE 352 PLAT BOOK 98 PAGE 183 ROCK OUTCROP 'EDGE OF WATER 2E LINE'S _ ___ ✓ - _ _ �� v �v - -OUTCROP I - c FIE _ I =' I I I I 1 / / / 111 , I \ I / i I '- I CONCRETE SPILLWAY TOP EL 302 W X MARK ON CONCRETE - NORTHING: 686294.3548 _ EASTING: 1937134.9813 - r EL 305.62 CONCRETE PAD EL 303 97 FLOATING DEBRIS BOOM CONCRETE PAD v EL 310.22 TOP EL\ 306.48`' , I 67 11 lj 1 I EDGE OF WATER 1 ' I' EXISTING SITE PLAN SCALE: 1'=40' o ao' 80 NAIL IN CENTER OF BRIDGE NORTHING: 686060.3180 FASTING: 1936984.8600 OLD FOUNDATION RUINS TREE LINE POWER HOUSE FIFE EL 312.57 CONCRETE LANDING EL 306.37 _ CONCRETE LANDING EL 300.53 — CONCRETE SIDEWALK — FENCE rIAPARCEL ID: 0018352 ROCKY RIVER HYDRO LLC DEED BOOK 1660 PAGE 903 - _= / 1 I I \ \ \ \I 1 1 WOODY DAM ROAD GRAVEL/UNPAVED 60' PUBLIC RAN IRON PIN NORTHING: 686285.0270 EASTI NG: 1936944.0010 PARCEL ID: 0018233 JOHN HOWARD TALLEY III DEED BOOK 796 PAGE 352 PLAT BOOK 98 PAGE 183 GENERALNOTES 1OVA 1. EXISTING TOPOGRAPHIC DATA, LOCATION OF SITE FEATURES, WERE PROVIDED BY INFINITE LAND DESIGN, P.C. (117 NORTH CHATHAM AVENUE, SILER CITY, NORTH CAROLINA) ON JANUARY 16, 2015. THE HORIZONTAL COORDINATES SHOWN HEREON ARE NAD83 NORTH CAROLINA STATE PLANE COORDINATES (US FEET). THE VERTICAL DATA SHOWN IS NAVD88. 2. NOT ALL UTILITIES ARE SHOWN. / 3. THE CONTRACTOR IS RESPONSIBLE FOR VERIFYING THE EXISTING UTILITY INFORMATION PRESENTED ON THESE DRAWINGS. / ANY DISCREPANCIES SHALL BE ADDRESSED TO THE ENGINEER IN WRITING. THE CONTRACTOR IS RESPONSIBLE FOR NOTIFYING AND COORDINATING WORK WITH THE AFFECTED UTILITY COMPANIES. 1� 4. ALL PUBLIC ROADWAYS SHALL REMAIN OPEN AT ALL TIMES. IT IS THE CONTRACTOR'S RESPONSIBILITY TO MAINTAIN ROAD \I SURFACES CLEAN AND FREE OF CONSTRUCTION SEDIMENT AND DEBRIS AT ALL TIMES. 5. ALL WORK SHALL BE PERFORMED IN ACCORDANCE WITH APPLICABLE LOCAL, CITY, STATE AND FEDERAL REGULATIONS AND PERMIT REQUIREMENTS. LD z AWA .f c w z u 6 Nw 1 L `J / TRANSFORMERPAD; 'EDGE OF WATER I Y \\ \ oy PARCELID:0018231 ELLEN JOSEPH RJR AND ELLEN ANNA S� DEED BOOK 1984 PAGE 474 ` GENERALNOTES 1OVA 1. EXISTING TOPOGRAPHIC DATA, LOCATION OF SITE FEATURES, WERE PROVIDED BY INFINITE LAND DESIGN, P.C. (117 NORTH CHATHAM AVENUE, SILER CITY, NORTH CAROLINA) ON JANUARY 16, 2015. THE HORIZONTAL COORDINATES SHOWN HEREON ARE NAD83 NORTH CAROLINA STATE PLANE COORDINATES (US FEET). THE VERTICAL DATA SHOWN IS NAVD88. 2. NOT ALL UTILITIES ARE SHOWN. / 3. THE CONTRACTOR IS RESPONSIBLE FOR VERIFYING THE EXISTING UTILITY INFORMATION PRESENTED ON THESE DRAWINGS. / ANY DISCREPANCIES SHALL BE ADDRESSED TO THE ENGINEER IN WRITING. THE CONTRACTOR IS RESPONSIBLE FOR NOTIFYING AND COORDINATING WORK WITH THE AFFECTED UTILITY COMPANIES. 1� 4. ALL PUBLIC ROADWAYS SHALL REMAIN OPEN AT ALL TIMES. IT IS THE CONTRACTOR'S RESPONSIBILITY TO MAINTAIN ROAD \I SURFACES CLEAN AND FREE OF CONSTRUCTION SEDIMENT AND DEBRIS AT ALL TIMES. 5. ALL WORK SHALL BE PERFORMED IN ACCORDANCE WITH APPLICABLE LOCAL, CITY, STATE AND FEDERAL REGULATIONS AND PERMIT REQUIREMENTS. LD z AWA .f c w z u 6 Nw 1 L `J FENCE (TO BE REMOVED) ------------ I 1 11 \\ I ROCK OUTCROPS _ I 1 \ 1 \ \ I I (z, - - - ROCK OUTCROP I I I ' ____ ______ / _ _ROCKY RIVER I ,� ROCK OUTCROP \\ �-EXISTING SIDEWALL TO BE DEMOLISHED. ------------ II i 6AMCENTERLINE ALIGNMENT _ \, a 1+00 -------------------------------- ALIGNMENT=DAM FASTING=19 73 273' - / ALL TREES AND/WOODY VEGETATION WITHIN THE LIMITS OF EXCAVATION � _- / SHALL BE CLEARED AND GRUBBED AND; ------- DISPOSED OF OFFSITE. ` / \ \ \ v v / v v v STAGE'1 DAM REMOVAL SEQUENCE: 1. THE CONTRACTOR IS TO NOTIFY AND PROVIDE THE ENGINEER WITH THE REQUIRED SUBMITTALS FOR APPROVAL FOR WORK AT LEAST 7 DAYS PRIOR TO MOBILIZATION ON THE SITE AND INSTALLING ANY EROSION CONTROL MEASURES. 2. FLAG ALL LIMITS OF DISTURBANCE. 3. INSTALL ALL EROSION AND SEDIMENT CONTROL MEASURES IN ACCORDANCE WITH THE APPROVED EROSION AND SEDIMENT CONTROL PLAN. 4. CLEAR AND GRUB ALL TREES AND WOODY VEGETATION INSIDE THE EXCAVATION LIMITS AS SHOWN ON THE LEFT ABUTMENT. DISPOSE OF CLEARED AND GRUBBED TREES AND WOODY VEGETATION IN AN APPROVED OFFSITE LOCATION. 5. DIVERT FLOW THROUGH THE POWERHOUSE GATES. MAINTAIN THE WATER LEVEL AT EL 274 USING PUMPS AS REQUIRED. THE CONTRACTOR SHALL ENSURE RIVER FLOW IS THROUGH THE POWERHOUSE GATES DURING STAGE 1 DAM REMOVAL. 6. EXCAVATE THE LEFT ABUTMENT AND DEMOLISH THE EXISTING LEFT SIDEWALL. STOCKPILE THE EXCAVATED EARTHEN MATERIAL AND CONCRETE RUBBLE FOR ESTABLISHING FINAL GRADES. 7. SEPARATE ALL EMBEDDED STEEL FROM THE CONCRETE RUBBLE AND DISPOSE OF IN AN APPROVED OFFSITE LOCATION. 8. DEMOLISH THE DAM FROM THE LEFT ABUTMENT TO THE POWERHOUSE AT STATION 4+73.94 IN FIVE FOOT LIFTS. THE DAM SHALL BE REMOVED IN A MANNER SO THAT THE RUBBLE FROM THE DEMOLITION WILL CREATE A WORKING PAD OFF OF WHICH DEMOLITION EQUIPMENT CAN WORK. - ---- I 1 1 _ '.,ri `J 1 \) (,1 I�, .1 F;A 1 I F :'A 'fit -- - \ USE DEMOLISHED CONCRETE TO BUILD A WORKING PAD FOR DEMOLITION 1 \ I 1 ' 1 I EQUIPMENT I n! ;1 I --- 1 i 11 FLOATING DEBRIS BOOM CHANNELTOBE EXCAVATED` t BY OTHERS DURING I) UPSTREAM`, ,( \ -- 1 \\ 1 , r, i;' 1, v SEDIMENT REMOVAL- - LIMITS OF DISTURBANCE _ 094 ACRES �I STAGE 1 DAM REMOVAL PLAN J SCALE: 1"=20' FLOW 0 20' 40' VOLUMES STAGE 1 EXCAVATION = 5,380 CUBIC YARDS (CUT) SPILLWAY AND LEFT ABUTMENT SIDEWALL CONCRETE DEMOLITION =1,880 CUBIC YARDS i� / i / / I / 1 I I I I 1 / I I GRAVEL DRIVE OLD FOUNDATION RUINS THE EXISTING POWERHOUSE ELECTRICAL, MECHANICAL AND BUILDING WILL BE REMOVED PRIOR TO MOBILIZATION OF CONTRACTOR. ` \ ' THE CONTRACTOR IS RESPONSIBLE FOR DEMOLITION AND REMOVAL OF THE POWERHOUSE CONCRETE SUPPORT STRUCTURE, CONCRETE SIDEWALL AND WALKWAY, 1 3 AND MISCELLANEOUS STEEL STRUCTURES. _ ��- , _ , , /— FENCE (TO REMAIN) ;;' ----------------`r`, -- GN)v1ENT=PAM,CENTERLIIVEI ', _-- \TION=4+73.941 SEt=0.p0- RTHlNG*686�84 75 3(ING=19$71441 38 _— ,"g "" x I' - X W DY AD 00 ADAM R l O f GRAVEL/UNPAVED 60' PUBLIC RNV — -- YT , ���®®�STAGE 1 DEMOLITION 111SENS , F oda N 310 305 300 295 290 285 280 275 270 265 310 305 300 295 290 285 280 275 270 265 0+00 0+50 1+00 1+50 2+00 2+50 3+00 3+50 4+00 4+50 5+00 5+50 6+00 6+50 7+00 7+50 8+00 8+50 9+00 9+50 10+00 10+50 11+00 11+50 12+00 12+50 13+00 13+50 14+00 14+50 15+0015+29 ----------------- ------------ --------------------------------- _ -, _ ---- _-- --------------- -- ; FEMA 100 -YEAR FLOODPLAIN EXTENT - ���- --_ _________________ ____________________-- ; ' _ = -------------- ----------------- _- --------- --- _- - 1 - - BOUNDARY FT P OF -TOPOGRAPHIC SURVEY 'O O OG C GRADING 3(H):1(V) SIDESLOPES `29p ` Win, �_\ ",`^`\ - _ 285 - : , / - `�` •__ 007 J 00 °Rl\` 29p GRADING 2.75(H)'A(V) SIDESLOPES 0' 40' 80' 120' 11 ;_c_=_ / 4\a` r�`•; s. - \ _ L°. D' 4' (HORIZONTAL) B' 12' -------, \\ \ ,. BOUNDARY OFTOPOGRAPHIC SURVEY O^ - T --------------- - / ------------------- �.. ---------------------- ------------ ' AREA TO BE GRADED DURING , " -- - STAGE 3 OF DAM REMOVAL: SEE SHEET 1.4'\\ _ f `" rte\ 'v" CONSTRUCTION ACCESS FROM _ �— \I - 'Iri \\. CHATHAM CHURCH ROAD \` -- -__ ;., 1 GRADING 4(H) 1(V) $IDESLOPE/ ------------- ------------ ._� = ----------- ------------- GRADING 4(H):1(V)SIDESLOPES -----r-GRADING 3(H):1(V) SIDESLOPES------- ---------------- ------------ _ l8+00 --- -A�r- _ 290 ``- — _ 29p _ - _ - — GRADING 3(H):1(V) SIDESLOPES V) SIDESLOPES , " ' Lo — " O O 1/ v TOP OF DAM ELEV. 302.4 f o v, � N EXISTING DAM STRUCTURE m rn J u STA = 0+00.86 F w ELEV = 283.614 EXISTING GRADE v v oo PROPOSED GRADE J 310 305 300 295 290 285 280 275 270 265 0+00 0+50 1+00 1+50 2+00 2+50 3+00 3+50 4+00 4+50 5+00 5+50 6+00 6+50 7+00 7+50 8+00 8+50 9+00 9+50 10+00 10+50 11+00 11+50 12+00 12+50 13+00 13+50 14+00 14+50 15+0015+29 ----------------- ------------ --------------------------------- _ -, _ ---- _-- --------------- -- ; FEMA 100 -YEAR FLOODPLAIN EXTENT - ���- --_ _________________ ____________________-- ; ' _ = -------------- ----------------- _- --------- --- _- - 1 - - BOUNDARY FT P OF -TOPOGRAPHIC SURVEY 'O O OG C GRADING 3(H):1(V) SIDESLOPES `29p ` Win, �_\ ",`^`\ - _ 285 - : , / - `�` •__ 007 J 00 °Rl\` 29p GRADING 2.75(H)'A(V) SIDESLOPES 0' 40' 80' 120' 11 ;_c_=_ / 4\a` r�`•; s. - \ _ L°. D' 4' (HORIZONTAL) B' 12' -------, \\ \ ,. BOUNDARY OFTOPOGRAPHIC SURVEY O^ - T --------------- - / ------------------- �.. ---------------------- ------------ ' AREA TO BE GRADED DURING , " -- - STAGE 3 OF DAM REMOVAL: SEE SHEET 1.4'\\ _ f `" rte\ 'v" CONSTRUCTION ACCESS FROM _ �— \I - 'Iri \\. CHATHAM CHURCH ROAD \` -- -__ ;., 1 GRADING 4(H) 1(V) $IDESLOPE/ ------------- ------------ ._� = ----------- ------------- GRADING 4(H):1(V)SIDESLOPES -----r-GRADING 3(H):1(V) SIDESLOPES------- ---------------- ------------ _ l8+00 --- -A�r- _ 290 ``- — _ 29p _ - _ - — GRADING 3(H):1(V) SIDESLOPES V) SIDESLOPES , " ' too — " O O too A m z z i l I iil'i i/i i/ ' l m l 3' 1/ v f y;� A m z z i l I iil'i i/i i/ ' l m l 3' o� I 1 11 1 OF FLOODPLAIN SEE SHEET 5.2 HILL SHAYNA 418 THOMAS MILL DR PIN: 9639-60-2899 ____- i t 1 1 I I — I, 11 I I )0 -YEAR FLOODPLAIN - ---------- EXISTING - EXISTING DAM CRIB WALL REMNANTS (TO BE REMOVED) / I \ Dol LOD lOD 1 kS FOR LVI.I. FIaJIVI I.LIU LlMM ULIVI%.JLITION AS TOE STABILIZATION I r / l PROPOSED ACCESS ROAD / I PROPOSED LOD " I ______ -------------- ------ —\ t PRIVATE \DRIVEWAY ` -i 1_ t LOD -- --- ------ -- \\I ---------------- --- - - NOTES: h 1. SITE TO BE ACCESSED FROM THOMAS MILL DRIVE AS PRIMARY ACCESS AND WOODY DAM ROAD AS ______ SECONDARY ACCESS IF NECESSARY. --- 2. THOMAS MILL DR AND ACCESS ROUTES TO BE LEFT IN AS GOOD OR BETTER CONDITION THAN PRE -CONSTRUCTION. 3 3. MATERIAL FROM CRIB DAM TO BE RE -USED AS ROCK TOE PROTECTION ON SURROUNDING STREAM Y BANKS. 1 \ ,I 4. ANY ADDITIONAL MATERIAL TO BE STOCKPILED ON THE RIGHT SIDE OF THE ROCKY RIVER ON PROPERTY _ OWNED BY 130 OF CHATHAM. ALL MATERIAL MUST BE STOCKPILED OUTSIDE OF THE 100 -YEAR FEMA FLOODPLAIN (SEE SHEET 5.2). HILL SHAYNA 418 THOMAS MILL DR PIN: 9639-60-2899 ____- i t 1 1 I I — I, 11 I I )0 -YEAR FLOODPLAIN - ---------- EXISTING - EXISTING DAM CRIB WALL REMNANTS (TO BE REMOVED) / I \ Dol LOD lOD 1 kS FOR LVI.I. FIaJIVI I.LIU LlMM ULIVI%.JLITION AS TOE STABILIZATION I r / l PROPOSED ACCESS ROAD / I PROPOSED LOD " I ______ -------------- ------ —\ t PRIVATE \DRIVEWAY ` -i 1_ t LOD -- --- ------ -- \\I ---------------- --- - - cV h l E 3 Y C Section A -A' Q o 4 o 301 Z ^m W� awZz oZi 1. Z 0 �zrE Hw 3 LL 300 m 299 298 tioo4�0� 297 Cod 296 295 294 4 0 10 20 30 40 50 60 70 80 90 100 110 120 130 136 p^ U 4.1 >� o � o 72 U O � x � Section B -B' U 304 EXISTING GRADE 303 302 E N C 301 0 10 20 30 40 50 60 70 8084 g - § 0' 1' 2' 3' ` v (VERTICAL)(VERTICAL)cAL) M 8 ` J 20' 30' - E W (HORIZONTAL) w 3 n � PROPOSED GRADE �-- `�--- EXISTING GRADE � 1 PROPOSED GRADE PROPOSED GRADE Permanent Riparian Seeding -without additional flowers Pure Live Seed (201bs/ acre) Approved Date Species Name Common Name Stratum Density (lbs/acre) All Year Panicum rigidulum Redtop Panicgrass Herb 2.0 All Year Agrostis hyemalis Winter Bentgrass Herb 4.0 All Year Chasmanthium latifolium River Oats Herb 2.5 All Year Rudbeckia hirta Blackeyed Susan Herb 1.5 All Year Coreopsis lanceolata Lanceleaf Coreopsis Herb Q m 12 ft. 6-12 ft. 0.25"-1.0" Canopy 15% Liriodendron tulipifera Tulip Poplar 12 ft. 6-12 ft. 0.25"-1.0" Canopy 10% Quercus michauxii Swamp Chestnut Oak ' m 1 00 d 6-12 ft. 0.25"-1.0" Canopy 15% Fraxinus pennsylvanica Green Ash 12 ft. 6-12 ft. 0.25"-1.0" Canopy 15% Lobelia cardinalis Cardinalflower Herb 0.3 �w mrym ' Echinacea purpurea Pale Purple Coneflower Herb 0.8 oZi 1. Z -a mm � Q_ �w�zrE 3 LL m Buffer Planting Zone Bare Root Species Common Name Max Indio. Min. Stratum # of Stems Spacing Spacing Caliper Size Quercus phellos Willow Oak 12 ft. 6-12 ft. 0.25"-1.0" Canopy 10% Platanus Sycamore 12 ft. 6-12 ft. 0.25"-1.0" Canopy 20% occidentalis Betula nigra River Birch 12 ft. 6-12 ft. 0.25"-1.0" Canopy 15% Quercus pagoda Cherry GP U � O 1 Planting Tables � Planting Tables � U 5.2 Not to Scale 5.2 Not to Scale tt a�- 'A Q U � .1-4 c5 � O x X U b "s - 'e V h 8 3 Plantin Tables 5.2 Not to Scale Planting Tables E a 3 a 2 2 5.2 Not to Scale Permanent Riparian Seeding -without additional flowers Pure Live Seed (201bs/ acre) Approved Date Species Name Common Name Stratum Density (lbs/acre) All Year Panicum rigidulum Redtop Panicgrass Herb 2.0 All Year Agrostis hyemalis Winter Bentgrass Herb 4.0 All Year Chasmanthium latifolium River Oats Herb 2.5 All Year Rudbeckia hirta Blackeyed Susan Herb 1.5 All Year Coreopsis lanceolata Lanceleaf Coreopsis Herb bark Oak 12 ft. 6-12 ft. 0.25"-1.0" Canopy 15% Liriodendron tulipifera Tulip Poplar 12 ft. 6-12 ft. 0.25"-1.0" Canopy 10% Quercus michauxii Swamp Chestnut Oak 12 ft. 6-12 ft. 0.25"-1.0" Canopy 15% Fraxinus pennsylvanica Green Ash 12 ft. 6-12 ft. 0.25"-1.0" Canopy 15% Permanent Riparian Seeding -without additional flowers Pure Live Seed (201bs/ acre) Approved Date Species Name Common Name Stratum Density (lbs/acre) All Year Panicum rigidulum Redtop Panicgrass Herb 2.0 All Year Agrostis hyemalis Winter Bentgrass Herb 4.0 All Year Chasmanthium latifolium River Oats Herb 2.5 All Year Rudbeckia hirta Blackeyed Susan Herb 1.5 All Year Coreopsis lanceolata Lanceleaf Coreopsis Herb 1.0 All Year Carex vulpinoidea Fox Sedge Herb 3.0 All Year Panicum clandestinum Deertongue Herb 3.5 All Year Elymus virginicus Virginia Wild Rye Herb 2.5 Streambank Planting Zone Live Stakes Species Common Name Max Spacing Indio. Spacing Min. Size Stratum % of Stems Salix nigra Black Willow 8 ft. 2-8 ft. 0.5"-1.5" cal. Shrub 15% Cornus ammonium Silky Dogwood 8 ft. 2-8 ft. 0.5"-1.5" cal. Shrub 35% Salix sericea Silky Willow 8 ft. 2-8 ft. 0.5"-1.5" cal. Shrub 35% Sambucus nigra American Elderberry 8 ft. 2-8 ft. 0.5"-1.5" cal. Shrub 15% Permanent Riparian Seeding -with additional flowers Pure Live Seed (201bs/ acre) Approved Date Species Name Common Name Stratum Density (lbs/acre) All Year Panicum rigidulum Redtop Panicgrass Herb 1.5 All Year Agrostis hyemalis Winter Bentgrass Herb 4.0 All Year Chasmanthium latifolium River Oats Herb 2.0 All Year Rudbeckia hirta Blackeyed Susan Herb 1.5 All Year Coreopsis lanceolata Lanceleaf Coreopsis Herb 1.0 All Year Carex vulpinoidea Fox Sedge Herb 3.0 All Year Panicum clandestinum Deertongue Herb 3.5 All Year Elymus virginicus Virginia Wild Rye Herb 2.0 All Year Asclepias syrica Common Milkweed Herb 0.2 All Year Baptisia australis Blue False Indigo Herb 0.2 All Year Lobelia cardinalis Cardinalflower Herb 0.3 All Year Echinacea purpurea Pale Purple Coneflower Herb 0.8 Y ,, t. - ia #° 1 a• ! py, { 'v.K �Yy�: ,�+�y'�r� F Y �.,r ��� ,,�,.: � �t�:L; •�ti�st � �f � eft.,'„ i� • R14 arl'�=��i,�k � ` 'o'�".a�"�g _ .r.''� � +!j �"^.�..ra -,..ice[• 1 Li,— ""% MA' 5 W ; tip ,, sfl7rw wrr?OTT,�i :'' `; _ 4 a T 0► q ak mv ay y.r. Z��i4 '`° x•14 ofMi f �a t�ati. �3 y:l I I 'y fill ROCKY RIVER 00 0� G0 ■: ------------ ------- Approved Species Name Common Name Stratum Density Date (lbs/acre) Aug 15- - Secale cereale Rye Grain May Herb 140 May 1 - Aug I S Setaria italim German Millet Herb 10 u '_^\ ) ---------- ------------- Y I - _ - �. ... --------------- ----------------------- - ------------- -- --------------- I _- ------ - , ---------- _=-- - - - -- - - -- -? -------------- PROPOSED ROCK TOE AREA (TYP.) -------------- - _ STAGING AND STOCKPILE AREA (TYP.) - o CRIB DAM 001 ------ ----------------------- ----- lob i:a LAA ,\ -'i it r LOD 'J - \ o ACCESS ROUTE FROM WOODY DAM RD 4' i / o --100 I I�'-° Ii 1rY� Iii 16 ♦ W / - " J ,\ - - SEE SHEET 0.2 FOR ENTRANCE --- ------------ Lr , r, , r i O I- c I ' - . r _ ------- ----------- ------------ ------- --- /r \ — ; -_ goo _ _ l/ " - I I - r,_ 'ii 100; /' r'i ;/ - _ l / `� rr - I/ / Ir/------ __ - _- . r� _ r/ , _ - ---------------/ , ' ------------ '_ -- J ' I , i ir r , - _------_"------ _ - - -' -_ -------- _- Temporary Seeding Pure Live Seed Approved Species Name Common Name Stratum Density Date (lbs/acre) Aug 15- - Secale cereale Rye Grain May Herb 140 May 1 - Aug I S Setaria italim German Millet Herb 10 NOTES: 1. CONTRACTOR TO STOCKPILE AND SPOIL ANY DAM MATERIALS AND RIVER SEDIMENTS OUTSIDE OF THE 100 -YEAR FLOODPLAIN EXTENTS. 2. ALL DISTURBED AREAS TO BE SEEDED AND STABILIZED ACCORDING TO SEEDING SCHEDULE AND EROSION CONTROL MATTING DETAILS. 3. REFER TO PLANTING PLAN FOR PERMANENT SEEDING SCHEDULE. 4. CONTRACTOR TO SELECT STREAM CROSSING TYPE AND LOCATION BASED ON CURRENT FLOW CONDITIONS. 0' 50' 100, 150' CROSSING THE CHANNEL SHOULD BE MINIMIZED DURING SEDIMENT REMOVAL AS MUCH AS POSSIBLE. (HORIZONTAL) 2 XF N N u '_^\ ) E W 3 " FFER WIDTH DIBBLE BAR I -I m 'z0 VARIES o awzuz �z�� QZ HO far£ PLANTING BAR SHALL HAVE A 3 LL i BANKFULL BLADE WITH ATRIANGULAR NOTES: CROSS-SECTION, AND SHALL BE 12 ``i��iU INCHES LONG, 4INCHES WIDE AND36 11NCH THICK AT CENTER. 1. ALL SOILS WITHIN THE BUFFER qco Q� 1 RESTORED `iV `i� ` ���!``jT`���!Y�� ',�`X`�� VVI i`�!TyT PLANTING AREAS HALL DISKED, AS y\<y �a EROSION CONTROL CHANNEL � REQUIRED, A O PLANTING. MATTING 2. SHALL ALL PLANTS SHALL BE PROPERLY (SEE DETAIL) ROOTING PRUNING HANDLED PRIOR TO INSTALLATION TO INSURE SURVIVAL. TOPOFBANK SPACING PER PLANTING PLAN ALL ROOTS SHALL BE PRUNED TO LIVE STAKE TYP iv vv v`vi`vio �fi Section View AN APPORIATE LENGTH TO �/�/i✓iG �"VAAlam PREVENTI-ROOTING. \ TOE OF SLOPE \ Section View w� T LIVE STAKE (TYP) TOP OF BANK DIAMETER a o A A to 3�_ Live Stake Detail INSERTTHE DIBBLE, OR REMOVE THE DIBBLE, OR INSERTTHE DIBBLE, OR PUSH THE DIBBLE, OR PULL BACK ON THE HANDLE TO REMOVE THE DIBBLE, OR & & SHOVEL, STRAIGHT DOWN SHOVEL, AND PUSH THE SHOVEL, SEVERAL INCHES IN SHOVEL, DOWN TO THE CLOSE THE BOTTOM OF THE SHOVEL, AND CLOSE AND FIRM INTO THE SOIL TO THE FULL SEEDLING ROOTS DEEP INTO FRONT OF THE SEEDLING FULL DEPTH OF THE BLADE. PLANTING HOLD. THEN PUSH UP THE OPENING WITH YOUR DEPTH OF TH E BLADE AND THE PLANTING HOLE. PULL THE AND PUSH THE BLADE FORWARD TO CLOSE THE TOP, HEEL. BE CAREFUL TO AVOID PULL BACK ON THE HANDLE SEEDLING BACK UP TO THE HALFWAY INTO THE SOIL. ELIMINATING AIR POCKETS DAMAGING THE SEEDLING. TO OPEN THE PLANTING CORRECT PLANTING DEPTH TWIST AND PUSH THE AROUND THE ROOT. TOE OF SLOPE Plan View HOLE. (DO NOT ROCK THE (THE ROOT COLLAR SHOULD BE HANDLE FORWARD TO SHOVEL BACK AND FORTH 1 TO 3 INCHES BELOW THE SOI L CLOSE TH E TOP OF THE SLIT NOTE: ASTHISCAUSES SOILINTHE SURFACE). GENTLYSHAKETHE TO HOLD THE SEEDLING IN PLANTING HOLE TO BE SEEDLING TO ALLOW THE PLACE. 1. LIVE STAKES TO BE PLANTED IN AREAS AS SHOWN ON COMPACTED, INHIBITING ROOTS TO STRAIGHTEN OUT. PLANSAND DIRECTED BYTHE ENGINEER. ROOTGROWTH. DO NOTTWIST OR SPIN THE SEEDLING OR LEAVE THE ROOTS Root Planting Staking 1 -ROOTED. (2)Bare /—,--,Live 6.1 of to bcale 6.1 Not to Scale RADIUS OF TREE PROTECTION BARRIER PER PLANS. V MIN. OVERLAP IN �-DOWNSTREAM DIRECTION AT MAT ENDS --� STAKE (TYP) TOP OF BANK SPg4, G Plan View TOE OF SLOPE � 6' WOODEN OR METAL "T" POSTS Plan View SHALL BE USED AS STANDARDS. 1.25" SAFETY FENCE SHALL BE ATTACHED TO STANDARDS TO FORM BARRIER. REMOVE ALL BRUSH AND DEBRIS FROM INSIDE DRIPLINE. EROSION CONTROL MATTING (TYP) TOP OF BANK V. .6" 0.4" m STAKE (TYP) ASV AC V \ \\` TOE OF SLOPE NOTES: - 1. ALL TREE PROTECTION BARRIERS SHALL BE REMOVED PRIOR j �v `< Typical Stake TO CONTRACTOR DEMOBILIZATION. \/�VA�\ \���V 2. SEE PLANS FOR LOCATION OF ALLTREE PROTECTION NOTE: BARRIERS. Section View 1. PER SPECIFICATIONS, ALL EROSION CONTROL MATTING SHALL BE COMPOSED OF NATURAL FIBERS. Section View 3 Tree Protection i41 Erosion Control Matting 6.1 Not to Scale 6.1 Not to Scale m I -I m 'z0 .00mo o awzuz �z�� QZ HO far£ w 3 LL i 710 m Q Do P� I—I m zO oomo �wo6 QO a w z c o� Z `g _ Q O H =mm �E .2 w 3 LL J0 Q S�, G� 8' MAX. WITH WIRE MIDDLE AND VERTICAL WIRES SHALL BE 12 S GAGE MIN. FILTER FABRIC 11-701 —1 TOP AND BOTTOM STRAND 24 MAX SHALL BE 10 GAUGE MIN. (18" MIN.) 2"-3" DIAMETER COARSE AGGREGATE STONE ,. r,. �. �r,�,. :Y. ����,. :Y. ✓,�,. Y,. 8" MIN. DEPTH WIRE NOTES: FILTER FABRIC 1. PROVIDE TURNING RADIUS SUFFICIENT TO ACCOMMODATE LARGE NOTES: COMPACTED FILL EXISTING GROUND TRUCKS. 2. LOCATE CONSTRUCTION ENTRANCE AT ALL POINTS OF INGRESS AND 1. USE WIRE A MINIMUM OF 32" IN WIDTH AND EGRESS UNTIL SITE IS STABILIZED. PROVIDE FREQUENT CHECKS OF THE WITH A MINIMUM OF 6 LINES OF WIRES WITH 12" DEVICE AND TIMELY MAINTENANCE. STAY SPACING. 3. MUST BE MAINTAINED IN A CONDITION WHICH WILL PREVENT TRACKING 2. USE FILTER FABRIC A MINIMUM OF 36" IN WIDTH7FABRIC OR DIRECTFLOW OF MUD ONTO STREETS. PERIODIC TOP DRESSING WITH AND 18" IN HEIGHT, AND FASTEN ADEQUATELYSTONEWILLBE NECESSARY. aa ENGINEER.SEDIMENT 4. ENTRANCEWILLBE EXTENDEDAS NEEDED TO PROVIDE ADEQUATE EXTHEWIRES FABRICAMINITHE 3. EXTEND FILTER FABRICAMINIMUM OF4' INTO REMOVAL. TRENCH. EXTE4 J 5. ANY MATERIAL TRACKED ONTO THE ROADWAY MUST BE CLEANED 4. PROVIDE 5' STEEL POST OF THE SELF -FASTENER INTO TRENCH N IMMEDIATELY. ANGLE STEEL TYPE. 6. USE 2"-3" DIAMETER COARSE AGGREGATE STONE APPROVED BY THE ENGINEER. 7. PLACE FILTER FABRIC BENEATH STONE. Temporary Silt Fence 2 Construction Entrance 6.2 Not to Scale 1 6.2 Not to Scale NOTES: f~ 2' WOOD STAKE 1. STRUCTURAL STONE SHALL BE (CLASS "B") STONE FOR POST ® fix] WOOD STAKE EROSION CONTROL PURPOSES. SILT FENCE 2. SEDIMENT CONTROL STONE SHALL BE NO. 5 OR NO. 57 STRAW WATTLE STRAW WATTLE STONE. EXISTING GROUND EXISTING GROUNDUZIRN TOP VIEW z_ 2' SILT FENCE Section View Section View A -A' V-6"VIN. T OVERLAP STRAW WATTLE WOOD STAKE FRONT VIEW SILT FENCE F—A SEDIMENT CONTROL A' V- 6" MIN. STONE NOTE: 3'-4' 71 F\ OW ti 1 3'MAX. 1. SECURE THE WATTLE WITH 24" STAKES EVERY 3'-4' AND WITH A STAKE ON EACH END. STAKES SHOULD BE DRIVEN THROUGH THE MIDDLE OF THE WATTLE LEAVING AT LEAST 2"-3" OF STAKE EXTENDING ABOVE THE WATTLE. STAKES SHOULD BE DRIVEN PERPENDICULAR TO SLOPE FACE. CROSS-SECTION VIEW STRUCTURAL STONE Temporary Straw Wattle Stone Outlet 62 Not to Scale 3 6.2 Not to Scale Do I—I m zO oomo �wo6 o a w z c o� Z `g _ Q O H =mm �E .2 w 3 LL i 710 M N Q I I I / I I � I I -I m z0 oomo �w m o a w oz cq � Z s `g Q H� =mm .2 E w 4" WOODEN BOARD ON OUTSIDE Z EDGE OF MAT TO PREVENT RUNOFF m MUD MATS Q S DIM d I I° WATER DIVERSION CHANNEL I I v 8 MAINTAIN LOW FLOW THALWEG THROUGH CROSSING SUPPORT LOG FILTER FABRIC Plan View 12" 0 MIN. CLASS B STONE NOTE: 1. CONSTRUCT STREAM CROSSING WHEN FLOW 15 AT NORMAL BASEFLOW. 2. MINIMIZE CLEARING AND EXCAVATION OF STREAMBANKS. DO NOT EXCAVATE CHANNEL BOTTOM. CLASS A/B STONE 3. INSTALL STREAM CROSSING PERPENDICULAR TO THE FLOW. 4. MAINTAIN CROSSING 50 THAT RUNOFF IN THE CONSTRUCTION ROAD DOES NOT ENTER EXISTING CHANNEL. _ 5. STABILIZE AN ACCESS RAMP OF CLASS B STONE TO THE EDGE OF THE MUD MAT. WATER DIVERSION WATER DIVERSION 6. CONTRACTOR SHALL DETERMINE AN APPROPRIATE RAMP ANGLE CHANNEL CHANNEL = ACCORDING TO EQUIPMENT UTILIZED. NOTES: 1. FORD CROSSING SHALL BE INSTALLED PERPENDICULAR TO CHANNEL BANKS. 2. MAINTAIN DIVERSION CHANNELTO INSURE RUNOFF DOES NEL Tem Ford Crossin �+ MudMat Temporary Stream Crossing - Mud Mat HALL DETERMINOT E 3. CONTRACTOR SHALL DETERMINE 1 orar 2 APPROPRIATE FORD DIMENSIONS. 6.3 Not to Scale 6.3Not to 5cale RIP -RAP COVERED BY APPROPRIATELY LARGE COARSE AGGERGATE 30 ANGULAR ROCK. a� d� vLE zo 25' MIN. 25' MIN. A m NOTES: a O d 1. THIS TYPE OF CROSSING CAN BE INSTALLED IN Or BOTH A WET OR DRY WEATHER STREAM Plan View CONDITIONS. 2. USE SERIES OF PARALLEL PIPES DEPENDING ON COARSE AGGREGATE 6" MIN. 48" PIPE DIAMETER BASE FLOWRATE AT TIME OF CONSTRUCTION. MINIMUM PIPE DIAMETER OF 48' 1/2 DIAMETER OF PIPE OR 12", EARTH FILL COVERED BY 3. REMOVE DURING CLEANUP. WHICHEVER IS GREATER APPROPRIATELY 4. CONTRACTOR MAV ELECTTO USE A TEMPORARY LARGE ANGULAR ROCK. BRIDGE CROSSING. IF HE/SHE DOES, IT MUST CONFORM TO THE "MANUAL FOR EROSION AND SEDIMENT CONTROL IN [STATE]". r Section View Stream Crossing - Culvert 3 )Temporary 6.3 Not to Scale Cn I -I m z0 oomo �w m o a w oz cq � Z s `g Q H� =mm .2 E w 3 LL i 710 m N Q Unique Places February 6, 2017 Subject: Supplemental Narrative to PCN Form. Project: USACE Action ID# SAW -2017-0051 1, NFWF Project ID #8020.16.054047 Baa. The project site located within the Piedmont physiographic region and the Carolina Slate Belt, which is characterized by low summertime base flows. The Rocky River originates in the eastern portion of Forsyth County and flows southeast through Guilford, Randolph, Chatham, and Lee counties before its confluence with the Deep River. The Rocky River has a watershed area of approximately 200 square miles at Hoosier Dam. The project is located within Cape Fear River subbasin 03-06-12 (NCDWQ 2005). The population within the subbasin in Year 2000 was approximately 20,000 residents. Land use within the subbasin is predominately forest (70 percent) and agriculture (27 percent), with less than 2 percent urban development. Hoosier Dam is a concrete buttress dam with an attached hydroelectric powerhouse. The dam was built in 1922, and is constructed of reinforced concrete, with a total length (including the powerhouse), of 235 feet and an average structural height of 25 feet. The hydroelectric facility at Hoosier Dam contains three small turbines that were operated by Hoosier Hydroelectric, Inc., as a small renewable energy producer. In October, 2012, the renewable energy contract with Progress Energy Carolinas was terminated, and in 2013 a new contract between Rocky River Hydro LLC (the current owner) and Duke Energy Progress was established. The dam continued to operate as a hydroelectric producer until 2015. Land use directly adjacent to the project is predominantly undisturbed woodland, with areas of pasture and pine plantations. The entire impoundment is bordered by a mature riparian buffer that varies in width from 40 feet to over 200 feet. Hoosier Dam and Reeves Lake are responsible for the loss of natural flow regime and shallow water habitat to approximately 22,425 linear feet of stream ecosystem (16,060 linear feet within the Rocky River and 6,365 linear feet of perennial tributaries). B3d. The purpose of the project is the remove Hoosier Dam and a rock crib dam located approximately 1 mile upstream. Hoosier Dam and Reeves Lake are currently a barrier between two critical habitat areas for the Cape Fear shiner, a federally -listed endangered species that only occurs only in North Carolina. The dam currently isolates two distinct populations of the Cape Fear shiner which impairs the species chances of long-term survival. The crib dam was formerly under the surface level of Reeves Lake. Due to the dewatered condition of the lake the crib dam is currently acting as a fish barrier. Going from a lentic ecosystem to a lotic ecosystem will manipulate the existing habitat and its function. However, the lotic ecosystem will develop and enhance habitat and the habitat function for both aquatic and terrestrial species, serving as a wildlife corridor upstream, downstream and across, whereas the impoundment and Reeves Lake is currently an obstacle for wildlife species. The action will create a permanent gain of habitat and habitat function. The project will develop long-term beneficial impacts by connecting approximately three miles of improved riverine habitat which will allow for demographic dispersal, genetic diversity and species richness. Specifically, characteristics such as higher dissolved oxygen levels, stable water temperatures, consistent hydrologic and sediment regime will establish microhabitats within and around run/riffles complexes, shallow pools and woody debris throughout the reach. The establishment of new vegetation along streambanks, on bars and islands of rock outcrops will provide refuge from predation for aquatic species, including the Cape Fear shiner, which is crucial for larval and young to reach their first year of reproductive maturity. The beneficial cumulative effects such as reducing predation, healthier water qualities, and extending the upstream riverine habitat downstream to the confluence of the Deep River and Rocky River would enhance the Cape Fear critical habitat through the project area and provide grounds for further research and monitoring of Cape Fear shiner populations. If any adverse impacts should occur within the critical habitat, they should be short-term and small in magnitude since controlled measures will be implemented to alleviate any severe or long-term impacts; therefore, this project and its temporary in -water work actions should not result in Adverse Modification to designated Cape Fear shiner Critical Habitat. The negative effects associated with the dam and its impoundment will be removed with the demolition of the dam. Construction itself, and potential associated sediment loads, may cause temporary stress to any Cape Fear shiner in the immediate vicinity of the dam. However, stress should be temporary in duration. The outcome of this project will re-establish the primary constituent elements of the designated critical habitat essential to the conservation of the Cape Fear shiner. B3e. The dewatering of Reeves Lake was initiated in June 2017 and followed the attached Dewatering Plan. The construction aspects of the project, dam removal and channel restoration, will be completed as follows.: 1. Removal of Hoosier Dam and Powerhouse Structure 2. Removal of sediment wedge immediately upstream of the dam 3. Removal of the remnant rock (crib) dam located approximately 1 mile upstream of Hoosier Dam 4. Stabilization of streambanks post -dam removal 5. Re-establishment of a riparian buffer with planting of native woody species along streambanks. 6. Harperella sp. planting effort Dam and Power House Removal The removal of the power house will commence prior to the removal of the dam. A private contractor will remove the brick structure, exterior steel components, and interior equipment. This will be accomplished by use of excavator situated on a building pad created upstream and abutting the portion of the top of Hoosier dam that is anchored into the south slope. Soil will be borrowed from a nearby site to create the pad which will be located in the former Reeves lake but outside of the current ordinary high water mark. The bricks will be removed in clean chunks by use of an excavator with a hydraulic thumb. The excavator will demolish the structure by pulling the brick back towards the foundation and upland areas thereby minimizing the amount of brick falling into the downstream river system. The removed brick, steel and other salvageable materials will be scrapped. Non- salvageable materials, if any, will be properly disposed of by a licensed NC demolition contractor. The dam itself will be removed by the US Fish and Wildlife Fish Passage Program. The removal will be accomplished by excavators. Causeways will be built up abutting the dam with on-site soil or concrete allowing the excavators to reach out over the dam with a ram -hoe attachment (See construction plans Sheet 1.3). The dam will be "pulled back" to the upstream side as much as is practical though dam materials are anticipated to fall in the immediate vicinity of the downstream side of the dam. The causeway and area downstream that may encounter falling debris is identified as a temporary impact in the PCN. Concrete rubble will be loaded into an off-road dump truck and transported to the on-site disposal area. A fleet of two excavator and one or two off road trucks is anticipated to be necessary. The demolition of Hoosier Dam is expected to take 3 weeks to accomplish. Disposal of dam material will occur at the location specified on figures 5.1 and 5.2 of the Erosion and Sediment Control Plans. All disposal material will be placed outside of the 100 -year FEMA floodplain. Sediment Removal See the attached Sediment Management Plan Crib Dam Removal The rock crib dam will be removed by excavator. Most of the rock will be disposed of in upland areas outside of the regulated floodplain limits. Wetland areas have been delineated in the area and will be avoided. Some rock may be left in place or placed appropriately along the stream bank to encourage stable bank conditions following the removal of the crib dam. This stabilization is noted as an impact in the PCN. Streambank and Stream Bed Stabilization Project work within the Rocky River may include the removal of the sediment wedge created by the Hoosier Dam within the active channel (dependent on the Biological Opinion from Section 7 consultation). The profile for the river is approximate and based on best available knowledge of the streambed slopes upstream and downstream and mechanical borings of depth to bedrock. The actual depth to bedrock along the entire proposed surface may vary greatly from what is proposed. If this is the case, the sediments should be excavated down to the depth of refusal or presence of coarse bed material, and banks graded back at a minimum 3(H):I (V) slope to the tie-in point on the existing surface. All graded streambanks will be matted with erosion control matting. Additionally, the excavated banks will be seeded with the temporary seed and permanent seed mix specified in the plans. Seeded areas and coir fiber matting areas will be covered with straw mulch. Grading activities are noted as temporary impacts in the PCN. Coir fiber matting will be installed according to plans and specifications. The recently dewatered floodplain will also be seeded with specified temporary and permanent seed mix and mulch. Live stakes and herbaceous plugs will be installed along the stream banks along with bare root trees within the floodplain, according to the plans and specifications. Harperella Planting The North Carolina Botanical garden will be coordinating a planting of Harperella (Ptilimnium nodosum) across the restored section of the Rocky River. Botanical Garden staff and volunteers will survey the dewatered/restored reach of the Rocky River to survey for potential habitat areas. Plant material will be grown in the botanical garden greenhouses. DI The project in its very nature will remove substantial "impacts" (impoundment, fish barriers) to aquatic ecosystems. During the project design phase all project elements were looked at from an avoidance and minimization perspective. Because the project is a removal and restoration effort the primary avoidance and minimization measures are associated with the construction techniques described below in D1 b. D1 b The project followed a strict dewatering protocol that included several elements specifically designed to minimize impacts to ecological resources and preserve water quality. The protocol included the below elements. Additional detail is provided in the attached Dewatering Plan. A maximum drawdown of 1 vertical foot per day to allow mussels to "walk" to deeper water. Daily turbidity monitoring with a management protocol to adjust for high turbidity measurements if needed. A mussel recovery effort managed by NCWRC aided by Unique Places, LLC and contractors. Mussels were physically relocated to deeper waters or to downstream or upstream riverine environments. A seeding effort was accomplished to stabilize the exposing floodplains and stream banks. Brown Top Millet was cast by hand several times a week via canoe. Additional mussel collection will be completed at the base of the dam to prevent mussel mortality due to falling debris when the power house and the concrete dam are demolished. A NCDEQ approved sediment and erosion control plan will be implemented throughout the duration of the project. D2a Given that the net increase in ecological functions and services to the Rocky River and streams anticipated from this project (which are endorsed by partners like the NC Wildlife Commission and the US Fish and Wildlife Service), compensatory mitigation should not be required. The Hoosier Dam removal is an ecological restoration initiative and the NWP 53, which covers the primary activity associated with the project (dam removal), directs that compensatory mitigation is not required, unless the district engineer determines that the dam removal, as outlined in this proposal, would result in more than minimal adverse environmental effects. More specifically, the NWP 53 states: "Because the removal of the low -head dam will result in a net increase in ecological functions and services provided by the stream, as a general rule compensatory mitigation is not required for activities authorized by this NWP. However, the district engineer may determine for a particular low -head dam removal activity that compensatory mitigation is necessary to ensure the authorized activity results in no more than minimal adverse environmental effects. " Not only will the riverine and stream habitat improve significantly, it is estimated that wetlands that return as a result of the dewatering and dam removal will be comparable to, and ecologically and functionally superior to, the man-made wetlands that were created by the unnatural water impoundment caused by the Hoosier Dam. The removal of Hoosier Dam will restore 16,000 linear feet of critical habitat for Cape Fear Shiner and state listed mussel species. The net functional uplift of the project will undoubtedly be positive. Wetlands created by the impoundment will be lost, however an unknown amount of "returning" wetlands will be restored by the removal of the dam. Some of these "returning" wetlands are already easily identifiable in the field and on recent aerial imagery. The attached Figure 7 depicts the existing wetlands as identified in the JD submittal and the wetlands that have returned as a result of the draining of Hoosier dam. The attached Table 1 lists the existing wetlands and assigns each a predicted long-term result from the hydrologic effect of removing the dam. The results are categorized into three groups as follows: • No Change Functional/Hydrologic Change (remains jurisdictional) Likely Removed from Jurisdiction Qualified environmental scientists based the assignments on a field analysis of each individual wetland area and a review of the topographic and elevation characteristics of the wetlands during the spring and summer of 2017. Following are some key quantification of wetlands and their predicted effects as a result of the project. Pre -Dewatering Wetland Totals: 232,964.9 sf (5.35 ac) Wetlands expected to have no change: 27,304.1 sf (0.63 ac) Wetlands expected to have function change (remain jurisdictional): 32,612.6 sf (0.75 ac) Wetlands expected to be removed from jurisdiction: 88,268.6 sf (2.03 ac) Returning Wetlands as of December 2017 (formerly impounded): 92,347.2 sf (2.12 ac) The above estimates suggest that the actual square footage of wetland loss will be comparable to the wetland that returns as a result of the dewatering and dam removal, resulting in an overall functional improvement of wetlands and aquatic habitat in the project area. Additionally, it is expected that additional returning wetlands will form over the next several years following the dam removal. Given the exceptional river function uplift and the resulting habitat increases for aquatic species, notably the Cape Fear shiner, the project will undeniably have a significant net benefit to the ecosystem. Sincerely, Aaron Aho Project Manager Unique Places, LLC