HomeMy WebLinkAboutNCC200875_ESC Approval Submitted_20200305ROY COOPER
Govemor
KCHAEL'S REGAN
Secrerary,
4RIAN CNN
Acova ectoe
Smithfield Farmland Corp.
Attn: Corey Ragole, Construction Manager
200 Commerce Street
Smithfield, VA 23430
NORTH: CAPOUNA
February 12, 2020
LETTER OF APPROVAL
Express Option
RE: Project Name: Smithfield Foods Expansion
Acres Approved: 6
Project ID: BLADE-2020-006
County: Bladen, City: Tar Heel, Address: NC 87
River Basin: Lumber
Stream Classification: Other
Submitted By: Kimley-Horn and Associates, Inc.
Date Received by LQS: February 12, 2020
Plan Type: Express
Dear Mr. Ragole:
This office has reviewed the subject erosion and sedimentation control plan. We find the plan to be acceptable and hereby
issue this Letter of Approval. The enclosed Certificate of Approval must be posted at the job site. This plan shall expire
three (3) years following the date of approval, if no land disturbing activity has been undertaken, as required by Title 15A
NCAC 4B.0129.
As of April 1, 2019, all new construction activities are required to complete and submit an electronic Notice of Intent (NOI)
form requesting a Certificate of Coverage (COC) under the NCG010000 Construction Stormwater General Permit. This
form MUST be submitted and COC issued prior to the commencement of any land disturbing activity on the above -named
project. The NOI form may be accessed at deg.ne.gov/NCGOI. Please direct questions about the NOI form to Annette
Lucas at Annette. lucas cr,ncdenr.gov or Paul CIark at Paul. clark c@ncdenr.gov. After you submit a complete and correct NOI
Form, a COC will be emailed to you within three business days. A $100 fee will be charged annually until a Notice of
Termination is issued. This fee is to be sent to the DEMLR Stormwater Central Office staff in Raleigh.
North Carolina Department of Environmental Qiality I Divislan of Energy, Mineral and"L:and Respurees
FayetteAlle Regional Office 1225 Green"Stmet; Suite 714 ( Fayetteviā˛¢e,.North Carolina 28301
910.433,3300
Letter of Approval
Smithfield Farmland Corp.
February 12, 2020
Title 15A NCAC 4B .0118(a) and the NCGOI permit require that the following documentation be kept on file at the job
site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCGO1 permit and the COC, once it is received.
3. Records of inspections made during the previous 12 months.
This letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection to ensure compliance with the
approved plan.
Title 15A NCAC 4B .0118(a) requires that a copy of the approved erosion control plan be on file at the job site. Also, this
letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection to ensure compliance with the
approved plan.
North Carolina's Sedimentation Pollution Control Act is performance -oriented, requiring protection of existing natural
resources and adjoining properties. If, following the commencement of this project, it is determined that the erosion and
sedimentation control plan is inadequate to meet the requirements of the Sedimentation Pollution Control Act of 1973 (North
Carolina General Statute 113A-51 through 66), this office may require revisions to the plan and implementation of the
revisions to ensure compliance with the Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State water quality Iaws,
regulations, and rules. In addition, local city or county ordinances or rules may also apply to this land -disturbing activity.
This approval does not supersede any other permit or approval.
Please note that this approval is based in part on the accuracy of the information provided in the Financial Responsibility
Form, which you provided. You are requested to file an amended form if there is any change in the information included on
the form. This permit allows for a Iand-disturbance, as called for on the application plan, not to exceed the approved acres.
Exceeding the acreage will be a violation of this permit and would require a revised plan and additional application fee. In
addition, it would be helpful if you notify this office of the proposed starting date for this project. Please notify us if you
plan to have a preconstruction conference.
Your cooperation is appreciated.
Sincerely,
Jodi Pace, EI
Regional Engineering Associate
DEMLR
Enclosures: Certificate of Approval
NPDES NCGO1 Fact Sheet
cc: Matthew Anderson, Kimley-Horn and Associates, Inc. (electronic copy)
Matthew Chadwick, Building Inspector (electronic copy)
DEMLR - Fayetteville Regional Office File