February 14, 2020
TOWN OF NORWOOD
WASTEWATER TREATMENT PLANT RENOVATIONS
EMC SOC WQ S18-011
QUARTERLY REPORT — March 2020
Mooresville Regional Supervisor
Division of Water Resources
Water Quality Operations Section
610 East Center Avenue, Suite 301
Mooresville, NC 28115
Water Quality Permitting Section/NPDES
1617 Mail Service Center
Raleigh, NC 27699-1617
Dear Sirs:
On August 12, 2019 the Town was approved for a State Reserve Loan (SRP) from the Water
Infrastructure Fund in the amount of $4,271,000. Design is submitted by Willis Engineers for
the renovation project which consists of constructing a new headworks, aeration basin weirs,
splitter box, clarifiers, sludge pump station, chlorine contact chamber, and other site
improvements. On October 30, 2019 Willis Engineers, Inc. submitted the construction drawings
and contract documents and final design package to the DWR for review which met the
November 1, 2019 deadline. On January 22, 2020 the Town of Norwood received a request for
additional information from the Wastewater Projects Unit. A response is due by March 2, 2020.
Willis Engineers is completing this response and will return the requested information. Please
let me know if you have any questions.
Sincerely,
Town of Norwood
Scott Howard
Town Administrator