HomeMy WebLinkAbout520013_Plan of Action_20200218Feb 18 2020 15:04 Meherrin 252-448-1323 page 2
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
Facility Number: Sz - Ij County: 1_ G n
Facility Name: &Aa/6 A/4J
Certified Operator Name: /J_1U_1,4A( ,::9mApeZ y Aj1L4J Operator #
,??g5yj
1. Current liquid level(s) in inches as measured from the current liquid level in the lagoon to the
lowest point on the top of the dam for lagoons without spillways; and from the current liquid level
in the lagoon to the bottom of the spillway for lagoons with spillways.
Structure 1 Structure 2 Structure 3 Structure 4 Structure 5 Structure 6
Lagoon NamelIdentifier (ID): '#
Spillway (Yes or No): /ya
Level (inches): %$ n
2. Check all applicable items
Liquid level is within the designed structural freeboard elevations of one or more structures. Five
and 30 day Plans of Action are attached. Hydraulic and agronomic balances are within
acceptable ranges.
Liquid level is within the 25 year 24 hour storm elevations for one or more structures. A 30 day
Plan of Action is attached. Agronomic balance is within acceptable range.
Waste is to be pumped and hauled to off site locations. Volume and PAN content of waste to
pumped and hauled is reflected in section III tables. Included within this plan is a list of the
proposed sites with related facility number(s), number acres and receiving crop information.
Contact and secure approval from the Division of Water Resources prior to transfer of
waste to a site not covered in the facility's certified animal waste management plan.
Operation will be partially or fully depopulated.
- attach a complete schedule with corresponding animal units and dates for depopulation
- if animals are to be moved to another permitted facility, provide facility number, lagoon
freeboard levels and herd population for the receiving facility
3. Earliest possible date to begin land application of waste: _ 20 j 202 -D
I hereby certify that I have reviewed the information listed above and included within the attached Plan
of Action, and to the best of my knowledge and ability, the information is accurate and correct.
7)dAW16 A4JUJ Phone: 9/0 -J'f 6
Facility Owner/Manager (print)
Date: Fa, go '40"
Facility Owner/Manager (signature)
PoA Cover Page 2121100
Feb 18 2020 15:04 Meherrin 252-448-1323 page 3
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
THIRTY (30) DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID): */ 51113
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker /S- 0 inches
b. designed 25 yr./24 hr. storm & structural freeboard .21.5 inches
c. line b - line a (inches in red zone) = 6-5- inches
d. top of dike surface area according to design 6937(o ft2
(area at below structural freeboard elevation)
e. line c x line d x 7,48 gallon s = I, /Z.Z gallons
12 ft3
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design /cgs days
g. volume of waste produced according to structural design //6, JZy ft3
h. actual waste produced = current herd # x line g = g97// ft3
certified herd #
i. volume of wash water according to structural design d ft3
j. excess rainfall over evaporation according to design 541M ft3
k. (lines h + i +i) x 7.48 x 30 days = /4/, 438 gallons
line f
4. Total PAN to be land applied during draw down period
I. current waste analysis dated W2.1. 1 1.16 Ib/1000 gal.
m. (lines e + k) x line 1 = 637. L lb PAN
1000
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE
II. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARD AND/OR 25 YR.124
HR. STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY
PoA (30 Day) 2/21100 1
Feb 18 2020 15:04 Meherrin 252-448-1323 page 4
1.
structure ID:
line m = 637. Z.
lb PAN
2.
structure ID:
line m =
lb PAN
3.
structure ID:
line m =
lb PAN
4.
structure ID:
line m =
Ib PAN
5.
structure ID:
line m =
lb PAN
6.
structure ID:
line m =
lb PAN
n.
lines 1+2+3+4+6+6 =
&37Z
lb PAN
III. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAYDRAW
DOWN
PERIOD.
DO NOT LIST FIELDS TO WHICH PAN CAN
NOT BE APPLIES DURING THIS 30 DAY PERIOD.
MEN
PAN
balance
(Iblacr_
'BALANCE
1 FOR FIELD
.:
oolumnrxs
applicationIRR-2
window'
•state current crop ending application date or next crop application beginning date for available receiving
crops during 30 day drawn down period
v. Total PAN available for all fields (sum of column t) = r♦ 166.9 0 Ib. PAN
IV. FACILITY'S PoA OVERALL PAN BALANCE
PoA (30 Day) 2121/00 2
Feb 18 2020 15:04 Meherrin 252-448-1323 page 5
w. Total PAN to be land applied (line n from section II) _
x. Crop's remaining PAN balance (line v from section III) _
y. Overall PAN balance (w - x) _
L37.20 lb. PAN
11 (04 �qD lb. PAN
• S'Z 9 • 7 D lb. PAN
Line y must show as a deficit. 1f line y does not show as a deficit, list course of action here
including pump and haul, depopulation, herd reduction, etc. For pump & haul and herd
reduction options, recalculate new PAN based on new information. If new fields are to be
included as an option for lowering lagoon level, add these fields to the PAN balance table and
recalculate the overall PAN balance. If animal waste is to be hauled to another permitted
facility provide information regarding the herd population and lagoon freeboard levels at the
receiving facility.
NARRATIVE:
PoA (30 Day) 2121I00 3