Ok, here are the SW conditions:
The Division approves the Stormwater Management Plan (SMP) consisting of three (3) Bioretention Cells and
all associated stormwater conveyances, inlet and outlet structures, and the grading and drainage patterns
depicted on plan sheets dated October 1, 2019, which are incorporated by reference and are enforceable by
the Division. The following conditions also apply [15A NCAC 02H .0506(b)(5)]:
• The maximum allowable drainage area for the approved Bioretention Cells #1, #2, and #3 shall be
569,111 square feet, 308,042 square feet, and 616,521 square feet, accordingly. The maximum
allowable built -upon area within those drainage areas shall be 1,780,297 square feet. Any changes to
these allowable maximum areas shall require the applicant to submit and receive approval from the
Division prior to any construction or modification of the current site.
• The footprint of all stormwater management device(s) as well as an additional 10-foot wide area on all
sides of the device(s) shall be located in either public rights -of -way, dedicated common areas or
recorded easement areas. The final plats for the project showing such rights -of -way, common areas
and easement areas, shall be in accordance with the approved plans. I think we don't need this
condition for this project since it's in the airport area. If you agree, please remove. Thanks!
• The approved SMP shall be constructed and operational before any permanent building or other
structure is occupied at the site.
• The SMP may not be modified without prior written authorization from the Division.
• Maintenance activities for stormwater management device(s) shall be performed in accordance with
the notarized 0&M agreements signed by Mr. Alex Rosser (from Piedmont Triad Airport Authority) on
October 17, 2019. The 0&M agreement shall transfer with the sale of the land or transfer of
ownership/responsibility for the approved SMP. The Division shall be notified promptly of every
transfer.
• Upon completion of construction and prior to operation of the approved stormwater control device(s),
an as -built drawings and a certification from an appropriate designer/engineer for the device certifying
that it has been installed in accordance with the approved plans, specifications, and other supporting
documentation, shall be submitted to the Division (C/O Chonticha McDaniel; 1617 Mail Service Center,
Raleigh, NC 27699-1617).
Thanks!
Chonticha McDaniel
401 Stormwater Engineer
401 & Buffer Permitting Branch
Division of Water Resources
Department of Environmental Quality
919-707-3634 office
chonticha.mcdaniela-ncdenr.gov
Mailing Address - 1617 Mail Service Center, Raleigh, North Carolina, 27699-1617
Street Address - 512 N. Salisbury St. (Floor 9th), Raleigh, North Carolina, 27604
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
From: Homewood, Sue
Sent: Wednesday, February 19, 2020 3:50 PM
To: Mcdaniel, Chonticha <chonticha.mcdaniel@ncdenr.gov>
Subject: RE: [External] GSO Rental Car Facilities Relocation; DWR#20191081; SAW-2017-00103
0
I am drafting up the approval letter this week. Sorry, I just realized I didn't have your final comments until I went looking
for them and found this email.
Sue Homewood
Division of Water Resources, Winston Salem Regional Office
Department of Environmental Quality
336 776 9693 office
336 813 1863 mobile
Sue. Homewood@ncdenr.gov
450 W. Hanes Mill Rd, Suite 300
Winston Salem NC 27105
From: Mcdaniel, Chonticha <chonticha.mcdaniel@ncdenr.gov>
Sent: Friday, November 15, 2019 8:35 AM
To: Homewood, Sue <sue.homewood@ncdenr.gov>
Cc: ali.boga@mbakerintl.com; RDarling@mbakerintl.com
Subject: RE: [External] GSO Rental Car Facilities Relocation; DWR#20191081; SAW-2017-00103
Sue,
I have no further questions on the SMP for this project. Let me know when you are close to issuing the 401 certification
so I can send the applicable stormwater conditions to you. Thanks!
Chonticha McDaniel
401 Stormwater Engineer
401 & Buffer Permitting Branch
,ivision of Water Resources
Department of Environmental Quality
919-707-3634 office
chonticha.mcdanielamcdenr.gov
Mailing Address - 1617 Mail Service Center, Raleigh, North Carolina, 27699-1617
Street Address - 512 N. Salisbury St. (Floor 9t"), Raleigh, North Carolina, 27604
1���Nothing Compares.
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
From: Darling, Richard [mailto:eFTP@mbakerintl.com]
Sent: Monday, October 28, 2019 12:57 PM
To: Mcdaniel, Chonticha <chonticha.mcdaniel@ncdenr.gov>
Cc: Homewood, Sue <sue.homewood@ncdenr.gov>; David. E.Bailey2@usace.army.mil; rossera@gsoair.org;
el morel@gsoair.org; akinsl@gsoair.org; hodgesk@gsoair.org; ali.boga@mbakerintl.com; mwaibel@mbakerintl.co
thollida(cDmbakerintl.com
Subject: [External] GSO Rental Car Facilities Relocation; DWR#20191081; SAW-2017-00103
External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
report.spam@nc.gov
IN TERNAT10NAC
RDarling(a�mbakerintl.com has sent you an attachment(s) using Baker eFTP
Chonticha:
Responses to your comments of 101912019 on the subject Stormwater
Message Management Report and Plans. The application will be re -submitted
Text: in its entirety shortly, including the attached. Please let me or Ali
Boga(ali.boga@mbakerintl.com know any additional concerns at your
earliest convenience. Thanks again for your attention to this proposed
project:
1. The submitted O&M agreement has not been signed/notarized.
Also, note that the newer version of the O&M form is available at
https://deg.nc.gov/about/divisions/energy-mineral-and-land-
resou rces/stormwater/stormwater-program/post-construction.
Signed and sealed O&M agreement added to SWM Report Appendix
A-7
2. Please complete and provide the most up-to-date Supplemental
EZ form for each Bioretention cell. The form is available at
https://deg.nc.gov/about/divisions/energy-mineral-and-land-
resources/stormwater/stormwater-program/post-construction. If you
have any trouble using the form, please feel free to contact me.
Signed and sealed Supplement EZ form added to SWM Report
Appendix A-7
3. A soil report and/or hydrogeological investigation is needed in
order to ensure that the required minimum separation between the
Seasonal High Water Table (SHWT) and the lowest point of the bio cell
can be met. In addition, determination of the in -situ soil infiltration rate
is needed for evaluation of the proposed design.
Added in the SWM Report AppendixA-8
4. Please provide detailed planting plan that meet the minimum
design criteria of the Stormwater Design Manual for Bioretention Cell.
Note added on Sheet C-400 "All SCMs bottom shall be sodded using
non -clumping, deep rooted species"
5. The submitted Stormwater Management Report and engineering
plans have not been signed/sealed by a NC licensed professional
engineer.
SWM Plans, Report sealed by NC — PE
Richard
Richard Darling I Project Manager - Environmental
200 Centreport Drive, Suite 350 1 Greensboro, NC 27409 1 [O] 919-481-57401
[M] 808-366-1971
rdarling@mbakerintl.com I www.mbakerintl.com
To retrieve your attachment(s), click on the secure link below.
https:HeFTP.mbakerintl.com/message/LkiPemxPGBZSUl HsIbAiLN
Access to this information will expire on 2019-11-27
First time user of the Michael Baker Intl. eFTP system? Click this link for assistance with the
new user creation process. If you are unable to access this website, contact the Michael
Baker IT Support Desk at 1-866-447-6333 or e-mail us at ITServices(a�mbakerintl.com
Legal Disclaimer:
This website is intended solely for use by the Michael Baker Corporation, its affiliates, clients,
subcontractors, and other designated parties. All information utilized on this website is for
designated recipients only. Any dissemination, distribution or copying of this material by any
individual other than the said designated recipients is strictly prohibited. The Michael Baker
Corporation, its affiliates and employees, makes no representation or warranty (express or
implied) as to the merchantability or fitness for a particular purpose of any documents or
information available from this website and therefore assumes neither legal liability nor
responsibility for the accuracy, completeness, technical/ scientific quality or usefulness of
said documents or information