January 30, 2020
LETTER OF APPROVAL WITH MODIFICATIONS
Cape Hatteras Electric Cooperative (CHEC)
Attn: Mr. J. Mark Rhyne, PE, Manager of Engineering
47109 Lightplant Road
Buxton, NC 27920
RE: Project Name: Structures 75 & 82 Reroute - Pea Island 115kV Transmission Line
Project ID: Dare-2020-006
County: Dare Acres Approved: 3.0
Address: NC Hwy 12
City: Rodanthe
River Basin: Pasquotank
Date Received by LQS: January 28, 2020
Submitted By: Booth & Associates, LLC
Plan Type: New/Express
Dear Sir,
This office has reviewed the subject erosion and sedimentation control plan. We find the plan to
be acceptable and hereby issue this Letter of Approval. The enclosed Certificate of Approval must
be posted at the job site. This plan approval shall expire three (3) years following the date of
approval, if no land -disturbing activity has been undertaken, as is required by Title 15A NCAC
413 .0129.
As of April 1, 2019, all new construction activities are required to complete and submit an
electronic Notice of Intent (NOI) form requesting a Certificate of Coverage (COC) under the
NCGO10000 Construction Stormwater General Permit. This form MUST be submitted prior to the
commencement of any land disturbing activity on the above named project. The NOI form may be
accessed at deq.nc. og vINCG01. Please direct questions about the NOI form to Annette Lucas at
Annette. lucaskncdenr.go_v or Paul Clark at Paul.clarkna,ncdenr.gov. After you submit a complete
and correct NOI Form, a COC will be emailed to you within three business days. Initially, DEMLR
will not charge a fee for coverage under the NCGO1 permit. However, on or after May 1, 2019, a
$100 fee will be charged annually. This fee is to be sent to the DEMLR Stormwater Central Office
staff in Raleigh.
Title 15A NCAC 4B .0118(a) and the NCGO 1 permit require that the following documentation be
kept on file at the job site:
D E Q North Carolina Department of Environmental Quality I Division of Energy, Mineral and Land Resources
Washington Regional Office 1 943 Washington Square Mail I Washington, North Carolina 27889
NORTH C F"JNA �
M^1�0_^��•� �'� 252.946k,l8i
1. The approved E&SC plan as well as any approved deviation.
2. The NCGO1 permit and the COC, once it is received.
3. Records of inspections made during the previous 30 days.
Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection
to ensure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance -oriented, requiring
protection of existing natural resources and adjoining properties. If, following the commencement
of this project, the erosion and sedimentation control plan is inadequate to meet the requirements
of the Sedimentation Pollution Control Act of 1973 (North Carolina General Statute 113A-51
through 66), this office may require revisions to the plan and implementation of the revisions to
insure compliance with the Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State
water quality laws, regulations, and rules. In addition, local city or county ordinances or rules may
also apply to this land -disturbing activity. This approval does not supersede any other permit or
approval.
Please note that this approval is based in part on the accuracy of the information provided in the
Financial Responsibility Form, which you provided. You are requested to file an amended form
if there is any change in the information included on the form. In addition, it would be helpful if
you notify this office of the proposed starting date for this project. Please notify us if you plan to
have a preconstruction conference.
Sincerely,
/. 4� V-'
Samir Dumpor, PE
Regional Engineer
cc w/o enc: Mark Rhyne, PE, Cape Hatteras Electric Cooperative (email)
WaRO Division of Water Resources (email)
1. The developer is responsible for the control of sediment on -site. If the approved erosion
and sedimentation control measures prove insufficient, the developer must take those
additional steps necessary to stop sediment from leaving this site (NCGS 113A-57(3)).
Each sediment storage device must be inspected after each storm event (NCGS 113A-
54.1(e)). Maintenance and/or clean out is necessary anytime the device is at 50% capacity.
All sediment storage measures will remain on site and functional until all grading and final
landscaping of the project is complete (15A NCAC 04B .0113).
2. The developer is responsible for obtaining all permits and approvals necessary for the
development of this project prior to the commencement of this land disturbing activity.
This could include our agency's Stormwater regulations and the Division of Water
Resources' enforcement requirements within Section 401 of the Clean Water Act, the U.S.
Army Corps of Engineers' jurisdiction of Section 404 of the Clean Water Act, the Division
of Coastal Management's CAMA requirements, the Division of Solid Waste
Management's landfill regulations, the Environmental Protection Agency and/or The U.S.
Army Corps of Engineers jurisdiction of the Clean Water Act, local County or
Municipalities' ordinances, or others that may be required. This approval cannot supersede
any other permit or approval.
3. Adequate and appropriate measures must be properly installed downstream, within
the limits of disturbance, of any land disturbing activity to prevent sediment from
leaving the limits of disturbance, entering existing drainage systems, impacting an on -
site natural watercourse or adjoining property. (NCGS 113A-57)
PROJECT INFORMATION SHEET
APPROVAL DATE:
RESPONSIBLE PARTY:
PROJECT NAME:
COUNTY:
OFF -SITE BORROW
AND/OR DISPOSAL SITE:
START-UP DATE:
CONTRACTOR:
ON -SITE CONTACT:
ON -SITE PHONE NO.:
OFFICE PHONE NO.:
anuary 30, 2020
Cane Hatteras Electric Cooperative (CHEC
Structures 75 & 82 Reroute -- Pea Island 115kV
Transmission Line
Dare NO.: Dare-2020-006
NO.
COMPLETE & RETURN THIS FORM
PRIOR TO THE START F CONSTRUCTION TO:
N.C.D.E.Q.
LAND QUALITY SECTION
ATTN: James Edwards
943 WASHINGTON SQUARE MALL
WASHINGTON, NORTH CAROLINA 27889
james.edwards@ncdenr.gov