HomeMy WebLinkAbout01b_NCS000250 Construction Program Overview 2019NORTH CAROLINA Department of Transportation Construction Program September 2019 Agenda • Permit Requirements • Program Accomplishments • Considerations for the Future 2 Program Objectives • Continue to control development activities disturbing one or more acres of land surface including activities by NCDOT contractors. • Require construction site operators to implement appropriate erosion and sediment control (ESC) practices. • Require site inspection and enforcement of control measures. • Establish requirements for construction site operators to control waste that may cause adverse impacts to water quality such as discarded building materials, concrete truck washout, chemicals, litter, and sanitary waste at the construction site. • Continue to implement ESC measures and reclamation plans on all borrow pit and waste site projects, including activities at Ferry Terminals associated with dredging activities and contractor owned or leased borrow pits associated with NCDOT projects in keeping with the ESC program delegated by North Carolina Sedimentation Control Commission. 3 Permit Requirements .. Maintain theme Implementation of NCDEQ DEMLR ESC Program delegated to NCDOT by delegation agreement Sedimentation Control Commission (SCC) in February, 1991... for NCDOT with NCDEQ DEMLR construction projects and implementation of the applicable requirements of ESC Program on an General Permit NCG010000 effectively meets the objectives above by annual basis. permitting and controlling development activities disturbing one or more acres of land surface and those activities less than one acre that are part of a larger common plan of development. This program is authorized under the Sediment Pollution Control Act of 1973 and Chapter 4 of Title 15A of NCAC. This program includes procedures for public input, sanctions to ensure compliance, requirements for construction site operators to implement appropriate E&SC practices, review of site plans which incorporates consideration of potential water quality impacts, and procedures for site inspection and enforcement of control measures. This program has been delegated to and implemented by NCDOT. Maintain compliance NCDOT shall incorporate the applicable requirements of NCG010000... into with the applicable its delegated ESC Program, pursuant to "NCDOT Applicable Requirements requirements of the from NPDES General Permit No. NCG010000 for Construction Activities and General Permit Guidance for Complying with Those Applicable Requirements" in the NCG010000. memorandum dated June 9, 2014 or as updated. Permit Requirements Implement ESC measures on NCDOT shall implement ESC measures on all non-commercial all non-commercial borrow pits/waste sites. Implement approved reclamation plans on all non- commercial borrow pits/waste sites. borrow pit and waste site projects. The measures utilized shall be in keeping with the ESC program established by the North Carolina Sedimentation Control Commission. NCDOT shall implement the approved reclamation plan on all non- commercial borrow pit/waste site projects. The reclamation measures utilized shall be in keeping with the reclamation program established by the North Carolina Mining and Energy Commission. Borrow Pit Discharge NCDOT in coordination with DEMLR will implement the Borrow Pit Management Program Discharge Management Program. This process will consist of the following tasks: • Implement appropriate management measures to treat borrow pit wastewater for given conditions. • Implement an inspection and maintenance program. • Maintain training material and instruct field personnel overseeing borrow pit operations. • Evaluate and implement appropriate new/innovative technologies. Construction Program Overview • NCDOT's Construction Program controls potential impacts to water quality from land disturbance at construction sites and from borrow pit and waste site activities. • NCDOT implements the ESC Program, which incorporates NCGO10000 requirements on construction projects. 6 Delegation Agreement • Allows NCDOT to review and approve ESC plans based on compliance with SPCA, water quality regulations, and permit conditions for each project. • Authorizes NCDOT to perform inspections for land disturbing activities associated with Highway construction. • Did not grant enforcement authority, so policies and procedures were developed to correct compliance issues with NCDOT construction projects. Delegation Annual Review Annual Reviews are presented at the Sedimentation Control Commission Meeting each year Daily Project Inspection • Project personnel inspects and monitors the construction of a project daily and records daily activities and rainfall amounts. • Responsible for NCG01 record keeping. • If a compliance issue develops, project personnel in conjunction with the contractor will address the issue and corrective actions are made. • If the corrections are deemed severe by the project engineer, then operations on the project are suspended until the compliance issue is rectified. 9 Monthly Project Inspections • There are 7 REU Field Operations offices, each covering 2 of the 14 highway divisions in the State. Each office has at least two engineers per office. • REU Field Operations staff performs monthly site reviews on all DOT land disturbing projects to determine if the ESC plans and permits are implemented accordingly, and that the necessary maintenance is occurring. • NCG01 documentation is reviewed and any deficiencies are identified. • Each project is evaluated on a scale of 1-10 for installation of measures, maintenance of measures, effectiveness of measures, plan implementation and overall project evaluation. • If the site review identifies a situation that is not being corrected, then an Immediate Corrective Action (ICA) notice can be issued. An overall score of 6 or less results in the issuance of an ICA report. 10 Immediate Corrective Action • Issued when project is out of compliance with SPCA/NCG01 • ICA alerts NCDOT Management of an issue that needs immediate attention. • Establishes corrective action timeframe • Notifies DEMLR and/or DW R of project status North Carolina Department of Transportation Roadside Environmental Unit Erosion & Sedimentation ! Stormwater Report !CA Immediate Corrective Action This project does not comply with the North Carolina Erosion and Sedimentation Con Voi laws. In mediale Gorr Vve Action is needed to resolve the situation to tuff compliance with the Law: JIM: 04B. 0000). Project Information Inspection Date: 0810212016 Evaluator: Phil Suggs Project #: 34839.3.GVS4 TIP #: U-2579B Division #: 9 County: Forsyth Project Type: Contract Engineer: Winston Salem Res. (Cragmore) Project Length: 4.00 Disturbed Acres: 100 River Basin: Yadkin HQW Zone: Na Trout Zone: NO Location Winston Salem Northern Beltway Eastern section US 158 to Bus 421 and 140 Description: Project Evaluation Report Type: ❑Routine ✓❑ICA ❑ICAExlst ❑ICAEx2nd ❑CICA-SWD ❑PCN ❑ECPAR Installation Maintenance Effectiveness Plan Overall Project Length Section of BMIPs of BMPs of BMPs Implementation Evaluation 0.1 Sile10 and 2, 6 6 6 6 6 approaching slopes 3.9 Remainder of Project 8 8 a a 8 Grading S-f, 0 - 8 = Immediate C—dive Action Pi qurred, 7 = Fair, 8 = Good, 9 = VrJy Good, 10 = E—Nenf 11 ICA Terms • ICA Ex = Immediate Corrective Action Extension • Continuing ICA • CICA-SWO = Continuing ICA Suspension of Work Operations • PCN = Permit Consultation Needed • ECPAR = Erosion Control Plan Audit Request Field Operations Site Reviews July 1, 2018—June 30, 2019 Project Types Contract Construction Projects Maintenance Projects Vertical Construction Projects Bridge Maintenance Projects Resurfacing Projects Site Reviews 47763 194 27 844 AN 13 Reclamation Process • NCDOT operates under its exemption from the Mining Act for borrow sites provided all materials are used "in connection with the construction, repair, and maintenance" of our road system. • Reclamation sites follow all requirements for ESC and fall under NCDOT's delegated program based on the Mining Act and SPCA 14 Reclamation Process • NCDOT requires reclamation plans for all waste/borrow sites that exceed project limits regardless of size • Environmental Evaluations are conducted on all sites before approved for use to confirm that sites do not impact any jurisdictional areas or federally protected species. • An EC plan is designed and implemented at each site • Final inspections are conducted on all waste/borrow sites or prior to project completion if property owners elect to take responsibility of the site. 15 Reclamation Process • Reclamation sites that require dewatering operations will require an evaluation to determine setbacks to minimize the risk of impacts to adjacent jurisdictional areas. • Effluent from dewatering operations will be monitored and the appropriate management procedures will be used to make sure NCDOT is in compliance with the applicable regulations. 16 Training • NCDOT ESC/Stormwater Certification Program conducted through NCSU's BAE and Soil Science Department • NCDOT REU Field Operations staff performs specialized training sessions for DOT/contractors/consultants as needed. 9 Field Ops conducts on site calibrations with regulatory agencies to ensure consistency 17 NCDOT ESC/Stormwater Certification Prog.ram • NCSU's Biological & Agricultural Engineering and Soil Science Departments have partnered with NCDOT to offer ESC/Stormwater Certification Program to ensure personnel are trained to comply with ESC/stormwater provisions on NCDOT projects. • NCDOT requires all contractors and NCDOT personnel to have a certified Level II supervisor and foreman to oversee operations on NCDOT projects. • Certification must be renewed every three years. • Must be Level II certified to perform NCG01 site inspections and record keeping Certification Levels Level Description # Persons Currently Certified ESC/SW Inspector/Installer 1183 II ESC/SW Site Management 5102 III Designers of ESC Plans 868 New Technology • Researching UAV technologies for site inspections and monitoring. REU has purchased its own UAV. • Research and field trials are beneficial with evaluating new technologies and determining how well it performs under real world conditions. ncdot-gov Program Accomplishments AWLWAW� MrAft AN SHOW .4 .. w Research Projects Research projects performed by Dr. Richard A. McLaughlin at NCSU as part of NCDOT's Construction Program: Recently Completed Projects • Performance Standards for Straw Mulch Binding Agents • Evaluation of Flocculants: Optimizing Characteristics and Screening Methods • Comparing Low -Cost Methods to Stabilize Temporary Diversions and Ditches • Erosion, Sediment, and Turbidity Control and Monitoring Research to Meet Water Quality Goals Active Projects • Reducing the Environmental Impact of Road Construction • Improved Approaches to Environmental Compliance during Highway Construction 21 Performance Standards for Straw Mulch Binding Agents • Determine viable straw tackifier options to replace emulsied asphalt • Tackifiers were tested using a wind tunnel • Results concluded that there are several options that can withstand steady winds while not prohibiting vegetation germination 22 Evaluation of Flocculants • Collected 22 different soil samples from across the state • Evaluated effectiveness of current flocculants available • PAM performance is strongly dependent on the soil type • Even with PAM, fine particles can be difficult to flocculate 23 Comparing Low Cost Methods to Stabilize Temporary Diversions and Ditches • Field lab tested and project tested several different liners and mattings in ditches • Liners greatly reduced erosion in areas of concentrated flow r _Y 8 24 Erosion, Sediment and Turbidity Control and Monitoring Research to Meet Water Quality Goals • Tested four different surface skimmer devices • Constructed a rainfall simulator for erosion testing _ • Two flocculant dosers were constructed and tested • PAM toxicity testing on = freshwater mussels Considerations for the Future • NCDOT will continue to maintain the ESC Program's existing policies and procedures for inspections, reclamation process, training, and research • NCDOT will continue to develop new ESC BMP details as needed to address unique needs. • NCDOT continues to evaluate the program's internal processes to identify any new opportunities for improvement. 26 Ongoing Accomplishments • New product inventory database • Update the Level III Certification • Update the NCDOT Best Management Practices for Construction and Maintenance Activities Manual BEST MANAGEMENT PRACTICES FOR CONSTRUCTION AND MAINTENANCE ACTIVITIES NORTH CAROLINA DEPARTMENT OF TRANSPORTATION August2003 27 ncdvt.gvv DVP.YVIF. 61IM11r1[!11[0 F r- Construction Program Summary • L A ncdvt.gvv Construction Program Summary 0