From: wyatt brown <brownenvgrp@gmail.com>
Sent: Monday, January 27, 2020 6:35 PM
To: Goss, Stephanie
Cc: Hopper, Christopher D CIV (USA); lannycliftonbuilder@gmail.com
Subject: Re: [External] FW: SAW-2019-00882 / Everwood Subdivision Phase II / Johnston
County - INCOMPLETE NOTIFICATION
• External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
�Mff—rt—s—pam@aL.gov
Stephanie
We are working on the response to the Corps of Engineers, I will send you a copy when I send it to the
them.thanks
Wyatt
On Mon, Jan 27, 2020 at 4:48 PM Goss, Stephanie <stephanie. oss o,ncdenr.gov> wrote:
Wyatt,
On December 11, 2019, the Division of Water Resources (Division) received your application requesting a 401
Water Quality Certification and Riparian Buffer Authorization from the Division for your project. The
Division has determined that your application is incomplete and cannot be processed. The application is on -
hold until the following information is received:
1. Please provide the Division a copy of your response from the U.S. Army Corps of Engineers requesting
additional information. [15A NCAC 02H .0502(c)]
Please contact me if you have any questions or concerns.
Stephanie Z. Goss
Environmental Specialist II
Division of Water Resources
Raleigh Regional Office
3800 Barrett Drive
Raleigh, NC 27609
919-791-4256
E-mail correspondence to and from this address may be subject to the
North Carolina Public Records Law and may be disclosed to third parties
-----Original Message -----
From: Hopper, Christopher D CIV (USA) <Christopher.D.Hopper o,usace.army.mil>
Sent: Monday, January 27, 2020 10:20 AM
To: Goss, Stephanie <stephanie. oss o,ncdenr.gov>
Subject: [External] FW: SAW-2019-00882 / Everwood Subdivision Phase II / Johnston County -
INCOMPLETE NOTIFICATION
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious
email as an attachment to report. spam o,nc.gov<mailto:report.spam o,nc.gov>
-----Original Message -----
From: Hopper, Christopher D CIV (USA)
Sent: Thursday, January 9, 2020 4:12 PM
To: brownenvgLrp@gmail.com
Cc: Williams, Andrew E CIV USARMY CESAW (USA) <Andrew.E.Williams2@usace.army.mil>
Subject: SAW-2019-00882 / Everwood Subdivision Phase II / Johnston County - INCOMPLETE
NOTIFICATION
Good Afternoon, Wyatt:
Thanks for your time this afternoon. Per our conversation, the Pre -construction Notification (PCN) for the
proposed Everwood Subdivision - Phase II (SAW-2019-00882), dated December 11, 2019 is incomplete. To
facilitate our documentation of the proposed project's compliance with requirements and conditions for use of
Nationwide Permit 29, please provide the following information:
1) NWP General Condition 15: Single and Complete Project,
a. Please provide either construction or grading plans to demonstrate that lots and their individual
septic systems would be constructed without crossing stream and/or wetland areas, or include these crossings
in this application. Report unavoidable crossings with both construction (temporary) and access
(permanent/maintenance).
i. Based on our conversation earlier today, I've attempted to identify lots that appear to require
wetland crossings. Those include 43-45, 53-55, 69-77, 81, 82, and 935.
b. An explanation of how cumulative impacts will be avoided on this project in the future (e.g.
methods to avoid impacts may include deed restrictions, conservation easements, etc)-
C. Identify water and power utility tie-ins on project plans.
2) A preliminary jurisdictional determination is on file for this phase of the Everwood Subdivision (Phase
II), but we are unable to locate mapping for Phase L If a determination or delineation concurrence has been
provided on Phase I, please forward that for our records. Per our conversation, I'll look at the calendar and look
for a date we can schedule a site visit for this site and the Barnes Landing site just east of this project.
3) The PCN application states that no federally protected species or habitat occurs in or near the project, but
that the USFWS has not been contacted. A review of the USFWS IPaC website identifies several federally
protected species potentially affected by activities in this location. Please visit the USFWS IPaC website and
provide text justification for the claim no impacts would result (https://ecos.fvvs.gov/i/ipac/location/index). We
will use this information in our request to USFWS for concurrence with this project.
Please provide the requested information within 30 days, or your application will be withdrawn. Feel free to
contact me with any questions or concerns.
Regards,
Chris
Christopher D. Hopper
Regulatory Specialist
U.S. Army Corps of Engineers
Regulatory Division
3331 Heritage Trade Drive, Suite 105
Wake Forest, NC 27587
(919) 554-4884, Ext. 35
Wyatt Brown, LSS, CPESC
Brown's Environmental Group, Inc
919-524-5956