HomeMy WebLinkAboutSWA000066_5147-19-014_Fort Bragg CWS - Sequence of Construction_1/27/2020Candlewood Suites Hotel - Hardy Hall and Moon Hall Fort Bragg, NC Sequence of Construction: This project will be complete in three separate but continuous phases: - Firstly, the existing western building (Hardy Hall) will be removed. Secondly, a new Candlewood Suites Hotel building will be constructed (along with associated parking areas and utilities) at the location of this removed building. Thirdly, the eastern building (Moon Hall) will be removed and a new Candlewood Suites Hotel building will be constructed (along with associated parking areas and utilities) at the location of this removed building. PHASE 1: SEQUENCE OF CONSTRUCTION FOR HARDY HALL DEMOLITION: INITIAL SEDIMENT AND EROSION CONTROL MEASURES: 1. INSTALL TEMPORARY GRAVEL CONSTRUCTION EXIT(S). REMOVE PAVEMENT AS NEEDED TO ACCOMMODATE CONSTRUCTION EXIT. 2. INSTALL TEMPORARY PERIMETER SEDIMENT BARRIERS (SILT FENCE, COMPOST SOCK, ETC.). 3. CONSTRUCT TEMPORARY SKIMMER SEDIMENT BASIN, INSTALL BAFFLES AND SKIMMER. COMPLETE ALL DEMOLITION OF STORMWATER STRUCTURES, STORMWATER PIPES, UTILITIES AND TREES AS NEEDED TO CONSTRUCT TEMPORARY SKIMMER SEDIMENT BASIN. 4. DEMOLITION AND REMOVAL OF EXISTING BUILDING, PAVEMENT, UTILITIES AND SIDEWALK AS NOTED ON THE DEMOLITION PLAN. 5. INSPECT AND MAINTAIN ALL SEDIMENT AND EROSION CONTROL MEASURES THROUGHOUT THE CONSTRUCTION PERIOD PER THE SWPPP REQUIREMENTS. CONSTRUCTION SEDIMENT AND EROSION CONTROL MEASURES: 1. AS DEMOLITION PROGRESSES, REMOVE SILT AND SEDIMENT BUILD-UP AT ALL TEMPORARY SEDIMENT BARRIERS, TEMPORARY INLET PROTECTION, AND TEMPORARY SKIMMER SEDIMENT BASIN. 2. COMPLETE BACKFILL AND TEMPORARY SOIL STABILIZATION OF DISTURBED AREAS AS REQUIRED. (TEMPORARY SEEDING AND MULCH) 3. AT THE COMPLETION OF DEMOLITION AND BACKFILL ACTIVITIES, AND PRIOR TO COMMENCING NEW BUILD CONSTRUCTION ACTIVITIES, REINSPECT AND REPAIR AS NEEDED ALL SEDIMENT AND EROSION CONTROL MEASURES. S&ME, Inc. 1 658 Grassmere Park Drive, Suite 100 1 Nashville, TN 37211 1 p 615.385.4144 1 www.smeinc.com Candlewood Suites Hotel Fort Bragg, NC S&ME Project No. 5147-19-014 PHASE 2: SEQUENCE OF CONSTRUCTION FOR HARDY HALL - NEW CANDLEWOOD SUITES HOTEL CONSTRUCTION: INITIAL SEDIMENT AND EROSION CONTROL MEASURES: 1. INSPECT AND REPAIR AS NEEDED ALL EXISTING SEDIMENT AND EROSION CONTROL MEASURES (MEASURES THAT WERE INSTALLED AS PART OF HARDY HALL DEMOLITION.) 2. INSTALL ANY ADDITIONAL SEDIMENT AND EROSION CONTROL MEASURES AS NEEDED FOLLOWING SITE INSPECTIONS. 3. INSTALL TEMPORARY GRAVEL CONSTRUCTION EXIT. REMOVE PAVEMENT AS NEEDED TO ACCOMMODATE CONSTRUCTION EXIT. 4. INSTALL TEMPORARY TREE PROTECTION AND TEMPORARY PERIMETER SEDIMENT BARRIERS. 5. ENSURE TEMPORARY SKIMMER SEDIMENT BASIN, BAFFLES, AND SKIMMER CONSTRUCTED AS PART OF HARDY HALL DEMOLITION IS CLEAN AND IN GOOD WORKING ORDER. 6. CONSTRUCT TEMPORARY DIVERSION SWALES. 7. INSTALL TEMPORARY SEDIMENT BARRIERS FOR TEMPORARY STOCKPILE AREA. 8. STRIP AND STOCKPILE TOPSOIL. TEMPORARY SEED TOPSOIL STOCKPILE AREA. 9. DEMOLITION AND REMOVAL OF EXISTING PAVEMENT, UTILITIES AND SIDEWALKS AS NOTED ON THE DEMOLITION PLAN. (DO NOT DEMOLISH THE EXISTING 24" RCP FROM STORM STRUCTURE D1 TO C0.1 UNTIL AFTER FINAL SITE STABILIZATION.) 10. MAINTAIN ALL SEDIMENT AND EROSION CONTROL MEASURES THROUGHOUT THE CONSTRUCTION PERIOD. Ato] ►[.��:ali��[•]►[.��.71► 1�►�ra►1.l�:t•L�[•]►[�L•]►��:Z•]�► I�_[.Y�1:�X.� 1. MAINTAIN ALL SEDIMENT AND EROSION CONTROL MEASURES THROUGHOUT THE CONSTRUCTION PERIOD. 2. COMMENCE MASS GRADING. 3. PROVIDE TEMPORARY OR PERMANENT STABILIZATION OF DISTURBED AREAS AS REQUIRED. (TEMPORARY SEEDING, MULCH, EROSION CONTROL BLANKETS OR SOD.) 4. AS CONSTRUCTION PROGRESSES, REMOVE OR FIELD ADJUST ROUTE / LOCATION OF TEMPORARY SWALES AS NEEDED TO DIRECT / ROUTE STORMWATER RUNOFF TO THE TEMPORARY SKIMMER SEDIMENT BASIN. 5. INSTALL STORM DRAINAGE (EXCEPT D1 TO D1.1 AND C1 TO C0.1), SANITARY SEWER AND OTHER UTILITIES. DO NOT INSTALL STORMTECH CHAMBER SYSTEM. (DIRECT STORMWATER RUNOFF FROM D1 TO THE EXISTING 24" RCP TO TEMPORARILY REMAIN.) 6. INSTALL TEMPORARY INLET PROTECTION AT ALL NEW STORMWATER STRUCTURES 7. GRADE AND PLACE MINERAL AGGREGATE BASE AT PAVEMENT AREAS. 8. CONSTRUCT CANDLEWOOD SUITES HOTEL. 9. PAVE PARKING AREAS AND FIRE LANES. 10. AS CONSTRUCTION PROGRESSES, REMOVE SILTAND SEDIMENT BUILD-UP AT ALL TEMPORARY SEDIMENT BARRIERS, TEMPORARY SKIMMER SEDIMENT BASIN AND TEMPORARY DIVERSION SWALES TO MAINTAIN ADEQUATE SEDIMENT CONTROL MEASURES. 11. THE TEMPORARY SKIMMER SEDIMENT BASIN (BAFFLES AND SKIMMER) MAY BE REMOVED WHEN THE CONTRIBUTING NON -STABILIZED DRAINAGE AREA IS LESS THAN ONE (1) ACRE. REMOVE EXISTING STORMWATER PIPE TO BACK OF NEW CURB. Page 2 Candlewood Suites Hotel Fort Bragg, NC S&ME Project No. 5147-19-014 12. BEGIN FINAL LANDSCAPING AND SITE STABILIZATION. SEE SHEET L-100-H FOR FINAL SITE STABILIZATION MEASURES. 13. CONSTRUCT STORMTECH CHAMBER SYSTEM BUT DO NOT DIRECT STORMWATER RUNOFF TO SYSTEM UNTIL FINAL SITE STABILIZATION. 14. ONCE FINAL STABILIZATION OF CONTRIBUTING DRAINAGE AREA TO THE STORMTECH CHAMBER SYSTEM HAS BEEN ACHIEVED AND APPROVED BYTHE D/B CONTRACTOR, INSTALL STORM DRAINAGE PIPES FROM D1 TO D1.1 AND C1 TO C0.1 AND DIRECT STORMWATER RUNOFF TO STORMTECH CHAMBER SYSTEM. 15. DEMOLISH THE EXISTING 24" RCP FROM STORM STRUCTURE D1 TO C0.1. 16. WHEN CONSTRUCTION IS COMPLETED, FINAL STABILIZATION OF THE ENTIRE SITE HAS BEEN ACHIEVED AND APPROVED BY THE D/B CONTRACTOR, REMOVE ALL TEMPORARY SEDIMENT AND EROSION CONTROL MEASURES AND STABILIZE ALL AREAS DISTURBED BY THESE TEMPORARY MEASURES. 16. FINAL SITE CLEAN UP. ►1:1•1114►101*01r4L01►I;39I&IT49101►IfelALTA Cd01►1:/_1Im►I4vdLdk1►111114TdLd01111-1911111*i:1011r4414L•1►1.19: *49101►F 1►1��ra�.��.11► 1�►�ra►1.l�:t•L�[•1►[�L•1►��:Z•1�► I�_[.Y�1:1IX.� 1. INSPECT AND REPAIR AS NEEDED ANY EXISTING SEDIMENT AND EROSION CONTROL MEASURES. (MEASURE THAT WERE INSTALLED AS PART OF HARDY HALL CONSTRUCTION.) 2. INSTALL ANY ADDITIONAL SEDIMENT AND EROSION CONTROL MEASURES AS NEEDED FOLLOWING SITE INSPECTIONS. 3. INSTALL TEMPORARY GRAVEL CONSTRUCTION EXIT. REMOVE PAVEMENT AS NEEDED TO ACCOMMODATE CONSTRUCTION EXIT. 4. INSTALL TEMPORARY TREE PROTECTION AND TEMPORARY PERIMETER SEDIMENT BARRIERS. 5. INSTALL TEMPORARY SEDIMENT BARRIERS FOR TEMPORARY STOCKPILE AREA. 6. STRIP AND STOCKPILE TOPSOIL. TEMPORARY SEED TOPSOIL STOCKPILE AREA. 7. DEMOLITION AND REMOVAL OF EXISTING BUILDING, PAVEMENT, UTILITIES AND SIDEWALK AS NOTED ON THE DEMOLITION PLAN. 8. MAINTAIN ALL SEDIMENT AND EROSION CONTROL MEASURES THROUGHOUT THE CONSTRUCTION PERIOD. L41610���:ai.>I��•1►���.11►1�►era►1.>t:z•1,�t•1►�.1.1►��:z•1�►1�_��a:� 1. MAINTAIN ALL SEDIMENT AND EROSION CONTROL MEASURES THROUGHOUT THE CONSTRUCTION PERIOD. 2. COMMENCE MASS GRADING. 3. PROVIDE TEMPORARY OR PERMANENT STABILIZATION OF DISTURBED AREAS AS REQUIRED. (TEMPORARY SEEDING, MULCH, EROSION CONTROL BLANKETS OR SOD.) 4. INSTALL STORM DRAINAGE SYSTEM BUT DO NOT CONNECT TO EXISTING STORMTECH CHAMBER SYSTEM. INSTALL TEMPORARY STORMWATER STRUCTURES T1, T2, & T3 (AND CONNECTING STORMWATER PIPES) SO AS TO DIRECT CONSTRUCTION STORMWATER RUNOFF AROUND THE STORMTECH CHAMBER SYSTEM. REFER TO SHEET C-602-M FOR STORMWATER SYSTEM DETAILS. INSTALL ADS BARRACUDA S8 SEPARATOR (STRUCTURE D3). 5. INSTALL SANITARY SEWER AND OTHER UNTILITIES. 6. INSTALL TEMPORARY INLET PROTECTION AT ALL NEW STORMWATER STRUCTURES. Page 3 Candlewood Suites Hotel Fort Bragg, NC S&ME Project No. 5147-19-014 7. GRADE AND PLACE MINERAL AGGREGATE BASE AT PAVEMENT AREAS. 8. CONSTRUCT CANDLEWOOD SUITES HOTEL. 9. PAVE PARKING AREAS AND FIRE LANES. 10. AS CONSTRUCTION PROGRESSES, REMOVE SILTAND SEDIMENT BUILD-UP AT ALL TEMPORARY SEDIMENT BARRIERS AND TEMPORARY ROCK CHECK DAMS TO MAINTAIN ADEQUATE SEDIMENT CONTROL MEASURES. 11. BEGIN FINAL LANDSCAPING AND SITE STABILIZATION. SEE SHEET L-100-M FOR FINAL SITE STABILIZATION MEASURES. 12. ONCE FINAL STABILIZATION OF CONTRIBUTING DRAINAGE AREA TO THE STORMTECH CHAMBER SYSTEM HAS BEEN ACHIEVED AND APPROVED BY THE D/B CONTRACTOR, INSTALL STORM DRAINAGE PIPE FROM T3 TO D3.1 AND DIRECT STORMWATER RUNOFF TO THE STORMTECH CHAMBER SYSTEM. 13. CAP INVERT AT STORM STRUCTURE T3 TO STRUCTURE T2. CAP INVERT ST STORM STRUCTURE T1 FROM STRUCTURE T2. DEMOLISH STRUCTURE T2 AND STORM PIPES FROM T1 TO T2 TO T3. 14. WHEN CONSTRUCTION IS COMPLETED, FINAL STABILIZATION OF THE ENTIRE SITE HAS BEEN ACHIEVED AND APPROVED BY THE D/B CONTRACTOR, REMOVE ALL TEMPORARY SEDIMENT AND EROSION CONTROL MEASURES AND STABILIZE ALL AREAS DISTURBED BY THESE TEMPORARY MEASURES. 15. FINAL SITE CLEAN UP. Page 4