HomeMy WebLinkAboutNC0020737_authorization to construct_20120530 A;A
ffl�
NCDENR
North Carolina Department of Environment and Natural Resources
Division of Water Quality
Beverly Eaves Perdue Charles Wakild, P.E. Dee Freeman
Governor Director, Secretary
May 30, 2012
Mr. Dennis Wells
City of Kings Mountain
101 W. Gold Street
Kings Mountain, North Carolina 28086
SUBJECT: Authorization to Construct
A to C No. 020737A03
City of Kings Mountain
Pilot Creek WWTP
Dear Mr. Wells:
A letter of request for an Authorization to Construct was received May 2, 2012, by the
Division of Water Quality(Division), and final plans and specifications for the subject project
have been reviewed and found to be satisfactory. Authorization is hereby granted for the
construction of modifications to the existing 6.0 MGD Wastewater Treatment Plant, with
discharge of treated wastewater into Buffalo Creek in the Broad River Basin.
This authorization results in no increase in design or permitted capacity and is awarded
for the construction of the following specific modifications:
Replacement of an existing manual bar screen with a new mechanical bar screen
with a peak design flow of 15.2 MGD, in conformity with the project plans,
specifications, and other supporting data subsequently filed and approved by the
Department of Environment and Natural Resources.
This Authorization to Construct is issued in accordance with Part III, Paragraph A of
NPDES Permit No. NCO020737 issued July 6, 2010, and shall be subject to revocation unless the
wastewater treatment facilities are constructed in accordance with the conditions and limitations
specified in Permit No. NC0020737.
In the event that the facilities fail to perform satisfactorily, including the creation of
nuisance conditions, the Permittee shall take immediate corrective action, including those as may
be required by the Division, such as the construction of additional or replacement wastewater
treatment or disposal facilities.
1617 Mail Service Center,Raleigh,North Carolina 27699.1617
Location:512 N.Salisbury St.Raleigh,North Carolina 27604 011e
Phone:919-807-63001 FAX:919-807.6492 NorthC yarofii.na
Internet:www rtcwateraualitv.org AaAt al&
An Equal Opportunity\Affirmative Action Employer
Mr. Dennis Wells
May 30, 2012
Page 2
The Mooresville Regional Office, telephone number (704) 663-1699, shall be notified at
least forty-eight (48)hours in advance of operation of the installed facilities so that an on site
inspection can be made. Such notification to the regional supervisor shall be made during the
normal office hours from 8:00 a.m. until 5:00 p.m. on Monday through Friday, excluding State
Holidays.
Upon completion of construction and prior to operation of this permitted facility, a
certification must be received from a professional engineer certifying that the permitted facility
has been installed in accordance with the NPDES Permit, this Authorization to Construct and the
approved plans and specifications. Mail the Certification to: Infrastructure Finance Section,
DWQ/DENR, 1633 Mail Service Center, Raleigh, NC 27699-1633.
Upon classification of the facility by the Certification Commission, the Permittee shall
employ a certified wastewater treatment plant operator.to be in responsible charge (ORC) of the
wastewater treatment facilities. The operator must hold a certificate of the type and grade at
least equivalent to or greater than the classification assigned to the wastewater treatment
facilities by the Certification Commission.
The Permittee must also employ a certified back-up operator of the appropriate type and
grade to comply with the conditions of T15A:8G.0202. The ORC of the facility must visit each
Class I facility at least weekly and each Class II, III and IV facility at least daily, excluding
weekends and holidays, must properly manage the facility, must document daily operation and
maintenance of the facility, and must comply with all other conditions of T15A:8G.0202.
A copy of the approved plans and specifications shall be maintained on file by the
Permittee for the life of the facility.
During the construction of the proposed additions/modifications, the permittee shall.
continue to properly maintain and operate the existing wastewater treatment facilities at all times,
and in such a manner, as necessary to comply with the effluent limits specified in the NPDES
Permit.
You are reminded that it is mandatory for the project to be constructed in accordance
with the North Carolina Sedimentation Pollution Control Act, and when applicable, the North
Carolina Dam Safety Act. In addition, the specifications must clearly state what the contractor's
responsibilities shall be in complying with these Acts.
Prior to entering into any contract(s) for construction, the recipient must have obtained all
applicable permits from the State.
Failure to abide by the requirements contained in this Authorization to Construct may
subject the Permittee to an enforcement action by the Division in accordance with North
Carolina General Statute 143-215.6A to 143-215.6C.
Mr. Dennis Wells
May 30, 2012
Page 3
The issuance of this Authorization to Construct does not preclude the Permittee from
complying with any and all statutes, rules, regulations, or ordinances which may be imposed by
other government agencies (local, state, and federal) which have jurisdiction.
One (1) set of approved plans and specifications is being forwarded to you. If you have
any questions or need additional information, please contact Seth Robertson,P.E. at telephone
number(919) 707-9175.
Sincerely,
��76 Charles Wakild,P.E.
MM:sr
cc: Joel E. Wood, P.E. - Joel E. Wood &Associates, Clover, SC
Cleveland County Health Department
DWQ Mooresville Regional Office, Surface Water Protection
Technical Assistance and Certification Unit
Point Source Branch, NPDES Program
Michelle McKay, E.I.
ATC File