HomeMy WebLinkAbout20170694 Ver 2_PJD_20191223PRELIMINARY JURISDICTIONAL DETERMINATION (PJD) FORM
BACKGROUND INFORMATION
A. REPORT COMPLETION DATE FOR PJD: June 25, 2017
B. NAME AND ADDRESS OF PERSON REQUESTING PJD: Pulte Homes Company, LLC Attn: Chris Raughley
1225 Crescent Green Dr., suite 250 Cary, NC 27518
C. DISTRICT OFFICE, FILE NAME, AND NUMBER: CESAW-RG-R, Stonewood subdivision, SAW-2017-01306
PROJECT LOCATION(S) AND BACKGROUND INFORMATION: The project site is approximately 213 acres bordered to
the west by Purfoy Rd. and to the east by NC Hwy 55, near the town of Fuquav Varina, Wake County, North Carolina. Aquatic
resources on site flow to Neills Creek in the Neuse River basin, identified by PINS 0675141029, 0675232939, 0675230880,
0665849465, and 0665746312. Please see the attached table and map entitled "Figure 3-Sketch Mad' dated 2/16/17 for
approximate size and locations of aquatic resources on site.
(USE THE TABLE BELOW TO DOCUMENT MULTIPLE AQUATIC RESOURCES AND/OR
AQUATIC RESOURCES AT DIFFERENT SITES)
State: North Carolina County/parish/borough: Wake City: Fuquav Varina
Center coordinates of site (lat/long in degree decimal format): Lat.: 35.54770 Long.:-78.76130
Universal Transverse Mercator:
Name of nearest waterbody: Neills Creek
D. REVIEW PERFORMED FOR SITE EVALUATION (CHECK ALL THAT APPLY):
® Office (Desk) Determination. Date: June 25, 2017
❑ Field Determination. Date(s): March 3, 2016
TABLE OF AQUATIC RESOURCES IN REVIEWAREA WHICH "MAY BE" SUBJECT TO REGULATORY
JURISDICTION.
Site
Number
Latitude (decimal
degrees)
Longitude
(decimal degrees)
Estimated amount of
aquatic resources in
review area (acreage
and linear feet, if
applicable
Type of aquatic
resources (i_e.,
wetland vs. non-
wetland waters)
Geographic authority to
which the aquatic resource
-may be" subject (i.e.,
S ection 4D4 or Section
10/404
A
35.548634
-78.766354
2.625 LF
Stream
Sactwn 4D4
B
35.551339
-78.762046
812 LF
Stream
Section4D4
C
35.550258
-73.759485
473 LF
Stream
Section404
D
35.548559
-78.763090
972 LF
Stream
Section404
E
35.546571
-78.765099
604 LF
Stream
Section404
F
35.544450
-78.763200
91 LF
Stream
Section404
G
35.547531
-78.770447
983 LF
Stream
Section4D4
H
35.547299
-73.774776
528 LF
Stream
Section4D4
W 1
35.546841
-78.774413
3.48 Acres
Watland
Section 404
W2
35.547097
-78.770476
2.69 Acres
Wetland
Section 404
W 3
35.54871;
-78.76a802
8.96 Acres
Wetland
Section 404
W4
35.55492S
-78.762663
0.11 Acres
Watland
Section 404
W 5
35.550774
-78.760156
0.42 Acres
Watland
Section 404
W6
35.54M99
-78.763762
0.04 Acres
Wetland
Section 404
�V7
35.5488Q5
-78.763216
0.09 Acres
Wetland
Section 404
WS
35.548534
-78_761746
0.72 Acres
Wetland
Section 404
4'4
35.547061
-78.763711
0.26 Acres
Wetland
Section 404
w 10
35. 546799
-78.764.412
0.01 Acres
Watland
W11
35.546527
-78.765806
0.03Acres
�,;' etlany.
non404
w 12
35.54448v
-78.762682
0.56 Acres
Wetland
Section 404
W 13
35.544527
-78.761743
0.24 Acres
Wetland
Section 404
W 14
35.545212
-78.760957
0.27 Acres
Wetland
Section 404
Food 1
35.545181
-78.762442
4.50 Acres
1}ood
Section 404
Fond `
35.548463
-78.760961
2.31 Acres
1}oad
Section 404
Food 3
35.545967
-78.760408
230 Acres
Po=d
Section 404
1) The Corps of Engineers believes that there may be jurisdictional aquatic resources in the
review area, and the requestor of this PJD is hereby advised of his or her option to request
and obtain an approved JD (AJD) for that review area based on an informed decision after
having discussed the various types of JDs and their characteristics and circumstances when
they may be appropriate.
2) In any circumstance where a permit applicant obtains an individual permit, or a Nationwide
General Permit (NWT) or other general permit verification requiring "pre- construction
notification" (PCN), or requests verification for a non -reporting NWP or other general permit,
and the permit applicant has not requested an AJD for the activity, the permit applicant is
hereby made aware that: (1) the permit applicant has elected to seek a permit authorization
based on a PJD, which does not make an official determination of jurisdictional aquatic
resources; (2) the applicant has the option to request an AJD before accepting the terms and
conditions of the permit authorization, and that basing a permit authorization on an AJD could
possibly result in less compensatory mitigation being required or different special conditions;
(3) the applicant has the right to request an individual permit rather than accepting the terms
and conditions of the NWP or other general permit authorization; (4) the applicant can accept
a permit authorization and thereby agree to comply with all the terms and conditions of that
permit, including whatever mitigation requirements the Corps has determined to be necessary;
(5) undertaking any activity in reliance upon the subject permit authorization without
requesting an AJD constitutes the applicant's acceptance of the use of the PJD; (6) accepting a
permit authorization (e.g., signing a proffered individual permit) or undertaking any activity in
reliance on any form of Corps permit authorization based on a PJD constitutes agreement that
all aquatic resources in the review area affected in any way by that activity will be treated as
jurisdictional, and waives any challenge to such jurisdiction in any administrative or judicial
compliance or enforcement action, or in any administrative appeal or in any Federal court;
and (7) whether the applicant elects to use either an AJD or a PJD, the JD will be processed
as soon as practicable. Further, an AJD, a proffered individual permit (and all terms and
conditions contained therein), or individual permit denial can be administratively appealed
pursuant to 33 C.F.R. Part 331. If, during an administrative appeal, it becomes appropriate to
make an official determination whether geographic jurisdiction exists over aquatic resources
in the review area, or to provide an official delineation of jurisdictional aquatic resources in
the review area, the Corps will provide an AJD to accomplish that result, as soon as is
practicable. This PJD finds that there "may be" waters of the U.S. and/or that there "may be"
navigable waters of the U.S. on the subject review area, and identifies all aquatic features in
the review area that could be affected by the proposed activity, based on the following
information:
SUPPORTING DATA. Data reviewed for PJD (check all that apply)
Checked items should be included in subject file. Appropriately reference sources below where
indicated for all checked items:
® Maps, plans, plots or plat submitted by or on behalf of the PJD requestor:
Map: "Figure 3-Sketch Map" dated 2/16/17
® Data sheets prepared/submitted by or on behalf of the PJD requestor.
® Office concurs with data sheets/delineation report.
❑ Office does not concurwith data sheets/delineation report. Rationale:
❑ Data sheets prepared by the Corps:
❑ Corps navigable waters' study:
® U.S. Geological Survey Hydrologic Atlas: Simsuite NHD dataset
® USGS NHD data.
❑ USGS 8 and 12 digit HUC maps.
® U.S. Geological Survey map(s). Cite scale & quad name: Fuquay Varina Quad
® Natural Resources Conservation Service Soil Survey. Citation: Wake County 1970, sheet 102
® National wetlands inventory map(s). Cite name:
❑ State/local wetland inventory map(s):
® FEMA/FIRM maps:
❑ 100-year Floodplain Elevation is: (National Geodetic Vertical Datum of 1929)
® Photographs: ®Aerial (Name & Date): undated
or ❑Other (Name & Date):
❑ Previous determination(s). File no. and date of response letter:
❑ Other information (please specify):
IMPORTANT NOTE: The information recorded on this form has not necessarily been
verified by the Corps and should not be relied upon for later iurisdictional
determinations.signed by
/�
LASTINGERJA LDASTINGERJAMES.C.1363642400
MES.C.136364
2400
DN: c=US, o=U.S. Government,
ou=DoD, ou=PKI, ou=USA,
cn=LASTI NG ERJAM ES.C.136364240
0
Date: 2017.06.26 10:21:46-04'00'
Signature and date of Regulatory
staff member completing PJD
Signature and date of person
requesting PJD (REQUIRED,
unless obtaining the signature
is impracticable)'
1 Districts may establish timeframes for requester to return signed PJD forms. If the requester does not respond within the
established time frame, the district may presume concurrence and no additional follow up is necessary prior to finalizing an
action.
NOTIFICATION OF ADMINISTRATIVE APPEAL OPTIONS AND PROCESS AND
REQUEST FOR APPEAL
Applicant: Pulte Home Company, LLC
Chris Rau hle
File Number: SAW-2017-01306
Date: June 25, 2017
Attached is:
See Section below
❑
INITIAL PROFFERED PERMIT Standard Permit or Letter ofpermission)
A
❑
PROFFERED PERMIT (Standard Permit or Letter of permission)
B
❑
PERMIT DENIAL
C
❑
APPROVED JURISDICTIONAL DETERMINATION
D
®
PRELIMINARY JURISDICTIONAL DETERMINATION
E
SECTION I - The following identifies your rights and options regarding an administrative appeal of the above decision.
Additional information may be found at http://www.usace.army.mil/Missions/CivilWorks/RegulatoryProgramandPenuits.asi)
or Corps regulations at 33 CFR Part 331.
A: INITIAL PROFFERED PERMIT: You may accept or object to the permit.
• ACCEPT: If you received a Standard Permit, you may sign the permit document and return it to the district engineer for final
authorization. If you received a Letter of Permission (LOP), you may accept the LOP and your work is authorized. Your
signature on the Standard Permit or acceptance of the LOP means that you accept the permit in its entirety, and waive all
rights to appeal the permit, including its terms and conditions, and approved jurisdictional determinations associated with the
permit.
• OBJECT: If you object to the permit (Standard or LOP) because of certain terms and conditions therein, you may request
that the permit be modified accordingly. You must complete Section II of this form and return the form to the district
engineer. Your objections must be received by the district engineer within 60 days of the date of this notice, or you will
forfeit your right to appeal the permit in the future. Upon receipt of your letter, the district engineer will evaluate your
objections and may: (a) modify the permit to address all of your concerns, (b) modify the permit to address some of your
objections, or (c) not modify the permit having determined that the permit should be issued as previously written. After
evaluating your objections, the district engineer will send you a proffered permit for your reconsideration, as indicated in
Section B below.
B: PROFFERED PERMIT: You may accept or appeal the permit
• ACCEPT: If you received a Standard Permit, you may sign the permit document and return it to the district engineer for final
authorization. If you received a Letter of Permission (LOP), you may accept the LOP and your work is authorized. Your
signature on the Standard Permit or acceptance of the LOP means that you accept the permit in its entirety, and waive all
rights to appeal the permit, including its terms and conditions, and approved jurisdictional determinations associated with the
permit.
• APPEAL: If you choose to decline the proffered permit (Standard or LOP) because of certain terms and conditions therein,
you may appeal the declined permit under the Corps of Engineers Administrative Appeal Process by completing Section II of
this form and sending the form to the division engineer. This form must be received by the division engineer within 60 days
of the date of this notice.
C: PERMIT DENIAL: You may appeal the denial of a permit under the Corps of Engineers Administrative Appeal Process by
completing Section II of this form and sending the form to the division engineer. This form must be received by the division
engineer within 60 days of the date of this notice.
D: APPROVED JURISDICTIONAL DETERMINATION: You may accept or appeal the approved JD or provide new
information.
• ACCEPT: You do not need to notify the Corps to accept an approved JD. Failure to notify the Corps within 60 days of the
date of this notice, means that you accept the approved JD in its entirety, and waive all rights to appeal the approved JD.
• APPEAL: If you disagree with the approved JD, you may appeal the approved JD under the Corps of Engineers
Administrative Appeal Process by completing Section II of this form and sending the form to the district engineer. This form
must be received by the division engineer within 60 days of the date of this notice.
E: PRELIMINARY JURISDICTIONAL DETERMINATION: You do not need to respond to the Corps regarding the
preliminary JD. The Preliminary JD is not appealable. If you wish, you may request an approved JD (which may be appealed),
by contacting the Corps district for further instruction. Also you may provide new information for further consideration by the
Corps to reevaluate the JD.
SECTION II - REQUEST FOR APPEAL or OBJECTIONS TO AN INITIAL PROFFERED PERMIT
REASONS FOR APPEAL OR OBJECTIONS: (Describe your reasons for appealing the decision or your objections to an initial
proffered permit in clear concise statements. You may attach additional information to this form to clarify where your reasons or
objections are addressed in the administrative record.)
ADDITIONAL INFORMATION: The appeal is limited to a review of the administrative record, the Corps memorandum for the
record of the appeal conference or meeting, and any supplemental information that the review officer has determined is needed to
clarify the administrative record. Neither the appellant nor the Corps may add new information or analyses to the record.
However, you may provide additional information to clarify the location of information that is already in the administrative
record.
POINT OF CONTACT FOR QUESTIONS OR INFORMATION:
If you have questions regarding this decision and/or the
If you only have questions regarding the appeal process you may
appeal process you may contact:
also contact:
District Engineer, Wilmington Regulatory Division,
Mr. Jason Steele, Administrative Appeal Review Officer
Raleigh Regulatory Field Office
CESAD-PDO
Attn: James Lastinger, Regulatory Project Manager
U.S. Army Corps of Engineers, South Atlantic Division
3331 Heritage Trade Dr., suite 105
60 Forsyth Street, Room 1OM15
Wake Forest, NC 27587
Atlanta, Georgia 30303-8801
919-554-4884 ext 32
Phone: 404 562-5137
RIGHT OF ENTRY: Your signature below grants the right of entry to Corps of Engineers personnel, and any government
consultants, to conduct investigations of the project site during the course of the appeal process. You will be provided a 15 day
notice of any site investigation, and will have the opportunit to participate in all site investi ations.
Date:
Telephone number:
Signature of appellant or agent.
For appeals on Initial Proffered Permits send this form to:
District Engineer, Wilmington Regulatory Division, Attn: James Lastinger, 69 Darlington Avenue, Wilmington, North
Carolina 28403
For Permit denials, Proffered Permits and Approved Jurisdictional Determinations send this form to:
Division Engineer, Commander, U.S. Army Engineer Division, South Atlantic, Attn: Mr. Jason Steele, Administrative Appeal
Officer, CESAD-PDO, 60 Forsyth Street, Room 1OM15, Atlanta, Georgia 30303-8801