Good Morning Jim:
We are uploading the revised documents this morning and will mail the hard copies out today as well. In response to
your comments, we offer the following:
- Permit Application
o Section IV, 8 —The percent impervious area should be calculated as the total post -construction
impervious area on -site (47,307 sf per Supplement-EZ) divided by the total project area (4.77
ac). Revised per comment
o Section IV, 10—All of the areas should be shown in square feet, not acres. Revised per comment
o Section IV, 10—The Proposed Impervious Area value should be the Total value from the Impervious
Surface Area table. Revised per comment
o Section IV, 10—The Percent Impervious Area value should be the Proposed Impervious Area divided by
the Total Drainage Area. Revised per comment
- Supplement-EZ
o Section V — The hard copy of the Supplement-EZ form needs an original signature (No
photocopies). Revised per comment
o Supplement-EZ Drainage Area Page
■ Line 16 — Please include the Percent BUA ( % BUA = Line 5 / drainage area) Revised per
comment
o Supplement-EZ Sand Filter Page
■ Line 8 — Should be "Yes" based on plans (A riser structure and emergency spillway are
provided). Revised per comment
■ Line 22 — Should be "Yes" based on plans (The sand filter store storms up to the 25-year
storm). Revised per comment
■ Line 31—The bottom of the sand chamber is the elevation of the lowest point of the sand
chamber. This is used for verifying Sand Filter MDC 1. Revised per comment
■ Line 33 —This depth should also include the sand, gravel, and underdrain portion of the
chamber. Revised per comment
Please submit 2 corrected permit applications and a corrected, original Supplement-EZ form.
Your expeditious approval would be greatly appreciated as this is the only remaining permit required for our client to get
started.
Thankyou
1
'/GG" zaffmm, P. S.
TH MJW L T�R55 � 0 WM_-RM6, MC
16507-A Northcross Drive
Huntersville, NC 28078
(704)895-8484
(704) 237-4362 (Fox)
mitch@lwengineer.com
www.lwengineer.com
From: Farkas, Jim J <Jim.Farkas@ncdenr.gov>
Sent: Thursday, September 26, 2019 9:32 AM
To: Mitch Latham <mitch@lwengineer.com>
Cc: Jeff Larson <jeff.larson@perigoneng.com>
Subject: RE: [External] Project Number SW3190701 - Harwood Automotive, Midland, NC
Mitch,
I was looking over the additional information you provided. Everything looks good except for a few small issues:
- Permit Application
o Section IV, 8 —The percent impervious area should be calculated as the total post -construction
impervious area on -site (47,307 sf per Supplement-EZ) divided by the total project area (4.77 ac).
o Section IV, 10 — All of the areas should be shown in square feet, not acres.
o Section IV, 10—The Proposed Impervious Area value should be the Total value from the Impervious
Surface Area table.
o Section IV, 10—The Percent Impervious Area value should be the Proposed Impervious Area divided by
the Total Drainage Area.
- Supplement-EZ
o Section V — The hard copy of the Supplement-EZ form needs an original signature (No photocopies).
o Supplement-EZ Drainage Area Page
■ Line 16 — Please include the Percent BUA ( % BUA = Line 5 / drainage area)
o Supplement-EZ Sand Filter Page
■ Line 8 — Should be "Yes" based on plans (A riser structure and emergency spillway are provided).
■ Line 22 — Should be "Yes" based on plans (The sand filter store storms up to the 25-year storm).
■ Line 31—The bottom of the sand chamber is the elevation of the lowest point of the sand
chamber. This is used for verifying Sand Filter MDC 1.
■ Line 33 —This depth should also include the sand, gravel, and underdrain portion of the
chamber.
Please submit 2 corrected permit applications and a corrected, original Supplement-EZ form.
Since these are really minor things, once I get the hard copies and the documents are uploaded to Laserfiche (Provided
everything is still in order), we can issue the permit without doing another 30+ day review period.
Jim Farkas
Environmental Engineer
North Carolina Department of Environmental Quality
Division of Energy, Mineral, & Land Resources — Stormwater Program
512 N. Sailsbury Street
1612 Mail Service Center
Raleigh, NC 27699-1612
(919) 707-3646
Jim.Farkas(c�r�,ncdenr.gov
E
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
From: Mitch Latham <mitch@lwengineer.com>
Sent: Wednesday, September 25, 2019 4:16 PM
To: Farkas, Jim J <Jim.Farkas@ncdenr.gov>
Cc: Jeff Larson <ieff.larson@perigoneng.com>
Subject: RE: [External] Project Number SW3190701 - Harwood Automotive, Midland, NC
External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
report.spam@nc.gov
Good Afternoon Mr. Farkas: Can you give us an update on the Harwood Automotive permit? (Project SW3190701). It
was resubmitted about a month ago and the owner is anxious to get started.
Thanks
i? v: .Clad a , P. S.
16507-A Northcross Drive
Huntersville, NC 28078
(704)895-8484
(704) 237-4362 (Fox)
mitch@lwengineer.com
www.lwengineer.com
From: Farkas, Jim J <Jim.Farkas@ncdenr.gov>
Sent: Thursday, August 15, 2019 8:06 AM
To: Mitch Latham <mitch@Iwengineer.com>
Subject: RE: [External] Project Number SW3190701 - Harwood Automotive, Midland, NC
Mr. Latham,
Yes, you are supposed to complete both drainage area columns. The entire site column takes into account the entire
project site, there is no need to remove the area draining to the proposed SCM.
Please feel free to contact me if you have any further questions.
Jim Farkas
Environmental Engineer
North Carolina Department of Environmental Quality
Division of Energy, Mineral, & Land Resources — Stormwater Program
512 N. Sailsbury Street
1612 Mail Service Center
Raleigh, NC 27699-1612
(919) 707-3646
Jim.Farkas@ncdenr.gov
D, E�
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
From: Mitch Latham <mitch@Iwengineer.com>
Sent: Wednesday, August 14, 2019 5:30 PM
To: Farkas, Jim J <Jim.Farkas@ncdenr.gov>
Subject: [External] Project Number SW3190701 - Harwood Automotive, Midland, NC
• External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
repoMWm@nc.gov
Good Afternoon Mr. Farkas: Based upon your RFI dated July 31st, I am working on the additional information for the
referenced project.
Item 6 request the submission of Supplement EZ form. For the drainage area portion on the second page of the
spreadsheet, there are two
columns labeled "Entire Site" and "l
Can you please clarify if I am supposed to complete both columns? If I am doing both columns, do I complete the
"Entire Site" based upon
the entire site, or the remaining portion of the site that is not draining to SCM 1.
Thanks for your help with this.
i *: zaffwm, A 45.