HomeMy WebLinkAbout20091028 Ver 1_Approval Letter_20091008ern
NCDENR
North Carolina Department of Environment and Natural Resources
Division of Water Quality
Beverly Eaves Perdue Coleen H. Sullins
Governor Director
October 8, 2009
Durham County
NCDWQ Project No. 20091028
SR 1321
TIP No. U-3804
APPROVAL of 401 WATER QUALITY CERTIFICATION and NEUSE BUFFER AUTHORIZATION,
with ADDITIONAL CONDITIONS
Dr. Gregory J. Thorpe, Ph.D., Environmental Management Director
NCDOT PDEA
1598 Mail Service Center
Raleigh, NC 27699
Dear Dr. Thorpe:
Dee Freeman
Secretary
You have our approval, in accordance with the conditions listed below, for the following impacts for the purpose of
widening SR 1321 in Durham County:
Stream Impacts in the Neuse River Basin
Site Permanent Impact to Intermittent Stream linear ft Total Stream Impact linear ft
1 1796 1796
Total 1796 1796
Total Stream Impact for Project: 1,796 linear feet.
Neuse Riparian Buffer Impacts
Site Zone 1 minus = Zone 1 Zone 1 Buffer Zone 2 minus = Zone 2 Zone 2 Buffer
Impact Wetlands Buffers (not Mitigation Impact Wetlands Buffers Mitigation
(sq ft) in Zone 1 wetlands) Required (sq ft) in Zone 2 (not Required (using
(sq ft) (sq ft) (using 3:1 ratio) (sq ft) wetlands) 1.5:1 ratio)
s ft
1 37584 0 37584 112752 1 1271 0 1271 1907
Totals 37584 0 37584 112752 1271 0 1271 1907
Total Buffer Impact for Project: 38855 square feet.
The project shall be constructed in accordance with your application dated received September 24, 2009. After
reviewing your application, we have decided that these impacts are covered by General Water Quality Certification
Number 3704. This certification corresponds to the Nationwide Permit 14 issued by the Corps of Engineers. This
approval is also valid for the Neuse Riparian Buffer Rules (15A NCAC 2B.0233). In addition, you should acquire
any other federal, state or local permits before you proceed with your project including (but not limited to) Sediment
and Erosion Control, Non-Discharge and Water Supply Watershed regulations. This approval will expire with the
accompanying 404 permit.
Transportation Permitting Unit
1650 Mail service Center, Raleigh, North Carolina 27699-1650
Location: 2321 Crabtree Blvd., Raleigh, North Carolina 27604
Phone: 919-733-17661 FAX: 919-733-6693
Internet: hap:llh2o.enr.state.nc.uslncwetandsl
One
NhCarolina
Naturallt?
An Equal opportunity 1 Affirmative Action Employer
This approval is valid solely for the purpose and design described in your application (unless modified below).
Should your project change, you must notify the NCDWQ and submit a new application. If the property is sold, the
new owner must be given a copy of this Certification and approval letter, and is thereby responsible for complying
with all the conditions. If total wetland fills for this project (now or in the future) exceed one acre, or of total
impacts to streams (now or in the future) exceed 150 linear feet, compensatory mitigation may be required as
described in 15A NCAC 2H.0506 (h) (6) and (7). Additional buffer impacts may require compensatory mitigation
as described in For this approval to remain valid, you must adhere to the conditions listed in the attached
certification as well as those listed below.
Conditions of Certification
1. Compensatory mitigation for impacts to Noose Riparian Buffers is required. The mitigation requirement includes
112,752 square feet of Zone I Buffers and 1,907 square feet of Zone 2 Buffers. We understand that you have chosen
to debit mitigation from the Marks Creek Mitigation Bank. This certification gives approval to the debiting of 114,659
square feet of Neuse Buffer from the Marks Creek Mitigation Site in order to satisfy the wetland mitigation
requirements of U-3804.
2. All channel relocations and modifications will be constructed in a dry work area and stabilized before stream flows
are diverted. Channel relocations and modifications will be completed and stabilized prior to diverting water into the
new channel. Vegetation used for bank stabilization shall be limited to native riparian species, and should include
establishment of a vegetated buffer on the relocated channel to the maximum extent practical. All stream banks shall
be matted with coir fiber matting. Also, rip-rap may be allowed if it is necessary to maintain the physical integrity of
the stream, but the applicant must provide written justification and any calculations used to determine the extent of rip-
rap coverage requested.
3. If concrete is used during construction, a dry work area shall be maintained to prevent direct contact between
curing concrete and stream water. Water that inadvertently contacts uncured concrete shall not be discharged to
surface waters due to the potential for elevated pH and possible aquatic life and fish kills.
4. For all streams being impacted due to site dewatering activties, the site shall be graded to its preconstruction
contours and revegetated with appropriate native species.
5. Riprap shall not be placed in the active thalweg channel or placed in the streambed in a manner that precludes
aquatic life passage. Bioengineering boulders or structures should be properly designed, sized and installed.
6. All riparian buffers impacted by the placement of temporary fill or clearing activities shall be restored to the
preconstruction contours and revegetated. Maintained buffers shall be permanently revegetated with non-woody
species by the end of the growing season following completion of construction. For the purpose of this condition,
maintained buffer areas are defined as areas within the transportation corridor that will be subject to regular NCDOT
maintenance activities including mowing. The area with non-maintained buffers shall be permanently revegetated with
native woody species before the next growing season following completion of construction.
7. Pursuant to NCAC15A 2B.0233(6), sediment and erosion control devices shall not be placed in Zone 1 of any
Neuse Buffer without prior approval by NCDWQ. At this time, NCDWQ has approved no sediment and erosion
control devices in Zone 1, outside of the approved project impacts, anywhere on this project. Moreover, sediment and
erosion control devices shall be allowed in Zone 2 of the buffers provided that Zone 1 is not compromised and that
discharge is released as diffuse flow.
8. All work in or adjacent to stream waters shall be conducted in a dry work area. Approved BMP measures from
the most current version of NCDOT Construction and Maintenance Activities manual such as sandbags, rock berms,
cofferdams and other diversion structures shall be used to prevent excavation in flowing water.
9. All stormwater runoff shall be directed as sheetflow through stream buffers at nonerosive velocities, unless
otherwise approved by this certification.
10. Sediment and erosion control measures shall not be placed in wetlands or waters unless otherwise approved by
this Certification.
1 1. Unless otherwise approved in this certification, placement of culverts and other structures in waters, streams, and
wetlands shall be placed below the elevation of the streambed by one foot for all culverts with a diameter greater than
48 inches, and 20 percent of the culvert diameter for culverts having a diameter less than 48 inches, to allow low flow
passage of water and aquatic life. Design and placement of culverts and other structures including temporary erosion
control measures shall not be conducted in a manner that may result in dis-equilibrium of wetlands or streambeds or
banks, adjacent to or upstream and down stream of the above structures. The applicant is required to provide evidence
that the equilibrium is being maintained if requested in writing by NCDWQ. If this condition is unable to be met due
to bedrock or other limiting features encountered during construction, please contact NCDWQ for guidance on how to
proceed and to determine whether or not a permit modification will be required.
12. During the construction of the project, no staging of equipment of any kind is permitted in waters of the U.S., or
protected riparian buffers.
13. The dimension, pattern and profile of the stream above and below the crossing shall not be modified.
Disturbed floodplains and streams shall be restored to natural geomorphic conditions.
14. The use of rip-rap above the Normal High Water Mark shall be minimized. Any rip-rap placed for stream
stabilization shall be placed in stream channels in such a manner that it does not impede aquatic life passage.
15. The Permittee shall ensure that the final design drawings adhere to the permit and to the permit drawings
submitted for approval.
16. If concrete is used during construction, a dry work area shall be maintained to prevent direct contact between
curing concrete and stream water. Water that inadvertently contacts uncured concrete shall not be discharged to
surface waters due to the potential for elevated pH and possible aquatic life and fish kills.
17. Heavy equipment shall be operated from the banks rather than in the stream channel in order to minimize
sedimentation and reduce the introduction of other pollutants into the stream.
18. All mechanized equipment operated near surface waters must be regularly inspected and maintained to prevent
contamination of stream waters from fuels, lubricants, hydraulic fluids, or other toxic materials.
19. No rock, sand or other materials shall be dredged from the stream channel except where authorized by this
certification.
20. Discharging hydroseed mixtures and washing out hydroseeders and other equipment in or adjacent to surface
waters is prohibited.
21. The permittee and its authorized agents shall conduct its activities in a manner consistent with State water quality
standards (including any requirements resulting from compliance with §303(d) of the Clean Water Act) and any other
appropriate requirements of State and Federal law. If NCDWQ determines that such standards or laws are not being
met (including the failure to sustain a designated or achieved use) or that State or federal law is being violated, or that
further conditions are necessary to assure compliance, NCDWQ may reevaluate and modify this certification.
22. A copy of this Water Quality Certification shall be maintained on the construction site at all times. In addition,
the Water Quality Certification and all subsequent modifications, if any, shall be maintained with the Division
Engineer and the on-site project manager.
23. The outside buffer, wetland or water boundary located within the construction corridor approved by this
authorization shall be clearly marked by highly visible fencing prior to any land disturbing activities. Impacts to areas
within the fencing are prohibited unless otherwise authorized by this certification.
24. The issuance of this certification does not exempt the Permittee from complying with any and all statutes, rules,
regulations, or ordinances that may be imposed by other government agencies (i.e. local, state, and federal) having
jurisdiction, including but not limited to applicable buffer rules, stormwater management rules, soil erosion and
sedimentation control requirements, etc.
25. The Permittee shall report any violations of this certification to the Division of Water Quality within 24 hours of
discovery.
26. Upon completion of the project (including any impacts at associated borrow or waste sites), the NCDOT Division
Engineer shall complete and return the enclosed "Certification of Completion Form" to notify NCDWQ when all work
included in the 401 Certification has been completed.
27. Native riparian vegetation (i.e., trees and shrubs native to your geographic region) must be reestablished within
the construction limits of the project by the end of the growing season following completion of construction.
28. There shall be no excavation from, or waste disposal into, jurisdictional wetlands or waters associated with this
permit without appropriate modification. Should waste or borrow sites, or access roads to waste or borrow sites, be
located in wetlands or streams, compensatory mitigation will be required since that is a direct impact from road
construction activities.
29. Erosion and sediment control practices must be in full compliance with all specifications governing the proper
design, installation and operation and maintenance of such Best Management Practices in order to protect surface
waters standards:
a. The erosion and sediment control measures for the project must be designed, installed, operated, and
maintained in accordance with the most recent version of the North Carolina Sediment and Erosion
Control Planning and Design Manual.
b. The design, installation, operation, and maintenance of the sediment and erosion control measures
must be such that they equal, or exceed, the requirements specified in the most recent version of the
North Carolina Sediment and Erosion Control Manual. The devices shall be maintained on all
construction sites, borrow sites, and waste pile (spoil) projects, including contractor-owned or leased
borrow pits associated with the project.
c. For borrow pit sites, the erosion and sediment control measures must be designed, installed, operated,
and maintained in accordance with the most recent version of the North Carolina Surface Mining
Manual.
d. The reclamation measures and implementation must comply with the reclamation in accordance with
the requirements of the Sedimentation Pollution Control Act.
If you do not accept any of the conditions of this certification, you may ask for an adjudicatory hearing. You must act
within 60 days of the date that you receive this letter. To ask for a hearing, send a written petition that conforms to
Chapter 150B of the North Carolina General Statutes to the Office of Administrative Hearings, 6714 Mail Service
Center, Raleigh, N.C. 27699. This certification and its conditions are final and binding unless you ask for a hearing.
This letter completes the review of the Division of Water Quality under Section 401 of the Clean Water Act. If you
have any questions, please contact Rob Ridings at 919-733-9817.
Sincerely,
Coleen H. Sullins
Director
Cc: Chris Murray, Division 5 Environmental Officer
Eric'Alsmeyer, US Army Corps of Engineers, Raleigh Field Office
Travis Wilson, NC Wildlife Resources Commission
Sara Easterly, NCDOT NEU
LeiLani Paugh, NCDOT NEU
File Copy