Loading...
HomeMy WebLinkAbout4303_INSP_20160817FACILITY COMPLIANCE INSPECTION REPORT Division of Waste Management Solid Waste Section Page 1 of 4 UNIT TYPE: Lined MSWLF LCID YW X Transfer Compost SLAS COUNTY: HARNETT Closed MSWLF X HHW White goods Incin T&P FIRM PERMIT NO.: 4303-CDLF-1997 CDLF X Tire T&P / Collection Tire Monofill Industrial Landfill DEMO SDTF FILE TYPE: COMPLIANCE Date of Site Inspection: August 17, 2016 Date of Last Inspection: October 29, 2015 FACILITY NAME AND ADDRESS: Harnett County Anderson Creek C&D Landfill 1086 Poplar Drive Spring Lake, NC 28390 GPS COORDINATES: N: 35.291432 E: -78.99537 FACILITY CONTACT NAME AND PHONE NUMBER: Andrew Holland (910)893-5626 FACILITY CONTACT ADDRESS: Amanda L. Bader, PE, LEED AP County Engineer Harnett County Engineering and Facilities Management P.O. Box 2773, Lillington, NC 27546 Phone: 910-814-6156 Fax: 910-814-4041 abader@harnett.org PARTICIPANTS: Liz Patterson, Environmental Senior Specialist – NCDEQ, Solid Waste Section Amanda Bader, PE, County Engineer – Harnett County Andrew Holland, Solid Waste Operations Crew Lead – Harnett County STATUS OF PERMIT: Permit to Operate issued September 30, 2015 Permit expires March 14, 2019 PURPOSE OF SITE VISIT: Comprehensive Inspection STATUS OF PAST NOTED VIOLATIONS: None OBSERVED VIOLATIONS: None The item(s) listed above were observed by Section staff and require action on behalf of the facility in order to come into or maintain compliance with the Statutes, Rules, and/or other regulatory requirements applicable to this facility. Be advised that pursuant to N.C.G.S. 130A-22, an administrative penalty of up to $15,000 per day may be assessed for each violation of the Solid Waste Laws, Regulations, Conditions of a Permit, or Order under Article 9 of Chapter 130A of the N.C. General Statutes. Further, the facility and/or all responsible parties may also be subject to enforcement actions including penalties, injunction from operation of a solid waste management facility or a solid waste collection service and any such further relief as may be necessary to achieve compliance with the North Carolina Solid Waste Management Act and Rules. FACILITY COMPLIANCE INSPECTION REPORT Division of Waste Management Solid Waste Section Page 2 of 4 ADDITIONAL COMMENTS 1. The facility is fenced and is secured by a locking gate when it is not open for operation. 2. The correct signage is at the entrance of the facility listing the facility name, permit number and emergency contact information as well as materials accepted at the facility. 3. The facility accepts waste Monday through Saturday from 7:30 am until 4:30 pm with the exception of Wednesday 7:30 am until 12:00 pm. 4. The permit and operations plans were readily accessible and were reviewed with the operator. 5. The permit to operate expires March 14, 2019. 6. The facility is permitted to receive C&D waste generated within Harnett County. 7. The facility is approved to accept the waste disposal rate up to 35,000 tons per year, average of 125 tons per day based on 280 operating days per year, consistent with the resolution passed by the Harnett County Commissioners on December 5, 2009 8. The Certified Landfill Operators as follows: Amanda Bader, Certified Manager of Landfill Operations, Cert #897302, expires 6/7/19 Andrew Holland, Certified Manager of Landfill Operations, Cert # 84458, expires 6/10/19 Nina C. Smithwick, Certified Landfill Operations Specialist, LF-2015059, expires 11/4/18 James S. Haney, Certified Landfill Operations Specialist, LF-2004127, expires 2/3/16 David Henry Baker, Certified Landfill Operations Specialist, LF-2004126, expires 11/17/18 9. The facility maintains semiannual groundwater and surface water monitoring records. Records for sampling events conducted on April 9, 2015, October 26, 2015, and April 27, 2016 were verified. 10. The facility conducts methane monitoring quarterly. Methane monitoring records were verified for samplings taken on April 27, 2016 and July 11, 2016. No exceedances noted. 11. The facility conducts waste screenings of 1 percent of truck loads received. Waste screening records were verified for January 4, 2016 through August 4, 2016. 12. Cover logs noting the date and time of placement were being kept on a calendar in the breakroom that was accidentally thrown out when someone was cleaning up. Calendar page will be printed for cover log monthly and maintained in a binder in the scale house to prevent this from occurring in the future. 13. The working face was being well managed and was not exceeding the ½ acre size limit. Six inches of earthen material should be properly applied once weekly or when the working face reaches ½ acre. 14. The waste type was reviewed and was construction and demolition waste. No unacceptable waste streams were noted. 15. Leachate breakout occurred on south side of landfill the week of August 8, 2016. Breakout was repaired immediately, then occurred again so facility dug down and found large piece of carpet causing the problem. Breakout was repaired again, properly covered, and graded. 16. Windblown waste is being well-managed, collected and returned to the working face prior to close of business daily. Good job! 17. The erosion and sedimentation control measures were reviewed. No off-site sediment was noted. 18. The edge of waste markers are installed and being maintained around the entire landfill. 19. Yard waste area being properly managed. Non-compostable bags should be removed from yard waste area. 20. I would strongly recommend that the yard waste, after grinding, be used as a soil amendment on the sandy soils at this facility. This mulch acts to amend the soil promoting plant growth and assists in controlling on-site erosion. Yard Waste distributed to the public must go through the composting process that includes recordation of temperatures. 21. A perimeter road has been established around the entire footprint of the landfill. Facility operations include a daily check of the entire landfill perimeter for any maintenance issues including locks on monitoring wells. The perimeter road is being well maintained. FACILITY COMPLIANCE INSPECTION REPORT Division of Waste Management Solid Waste Section Page 3 of 4 CLOSED MSW 22. Permanent edge of waste markers were in place and being maintained. 23. Good vegetation established, no bare spots noted. 24. Continue to keep vegetation properly mowed to allow for routine inspections and any issues noted should be addressed as soon as practical after detection to reduce or eliminate potential compliance issues. 25. Digital pictures were taken during the inspection. Please contact me if you have any questions or concerns regarding this inspection report. Phone: 919-707-8286(O) 919-805-6499(C) elizabeth.patterson@ncdenr.gov Liz Patterson Environmental Senior Specialist Regional Representative Sent on: 9-19-2016 X Email Hand delivery US Mail Certified No. [ _] Copies: Drew Hammonds, Eastern District Supervisor - Solid Waste Section Jessica Montie, Compliance Officer - Solid Waste Section Peter Scheer, P.E. – S+G Engineers FACILITY COMPLIANCE INSPECTION REPORT Division of Waste Management Solid Waste Section Page 4 of 4 Digital Pictures taken by Liz Patterson on August 17, 2016 Leachate breakout repaired on south side of landfill Working face of landfill Plastic bags in yard waste area