Chao, Ming-tai
From:Harrison, Susan <sharri21@wm.com>
Sent:Monday, March 16, 2020 5:51 PM
To:Chao, Ming-tai
Cc:Kirchner, Chuck; Ritter, Christine; Stanley, Sherri; Paxton Arthurs
(Paxton.Arthurs@randolphcountync.gov); Rob Witcher; Jonathan Usher
Subject:[External] RE: comments on the pre-construction meeting minutes & other submittals, GOLF Phase1
- Cells 3B, 4 & 5
Attachments:schedule 03-16-20.pdf; 2020-03-16_Rev1-Drawings.pdf; Great Oak Landfill Burn Permit.jpg
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
report.spam@nc.gov
Ming,
Please see the responses below and attachments.
Let me know if you have any other concerns,
Susan
From: Chao, Ming‐tai <ming.chao@ncdenr.gov>
Sent: Saturday, March 14, 2020 4:18 PM
To: Harrison, Susan <sharri21@wm.com>
Cc: Kirchner, Chuck <chuck.kirchner@ncdenr.gov>; Ritter, Christine <christine.ritter@ncdenr.gov>; Stanley, Sherri
<Sherri.Stanley@ncdenr.gov>; Paxton Arthurs (Paxton.Arthurs@randolphcountync.gov)
<Paxton.Arthurs@randolphcountync.gov>
Subject: [EXTERNAL] comments on the pre‐construction meeting minutes & other submittals, GOLF Phase1 ‐ Cells 3B, 4
& 5
Hi Susan:
It is apparent that me, Christine, and Chuck missed a lot of funs with new members in both design and
construction teams in this project. As one of the representatives of the NC Solid Waste Section (SWS) for
this Project, I would like to say to our new team players that we are welcome you to join the party. By the
way please provide the SWS the contact info (name, phone #, & e-mail address) of the new Engineer &
CQA consultant for future communications.
After getting a chance to go over the meeting minutes, schedule, and construction drawings which are
attached to you e-mail dated 03/13/2020, the SWS has several requests below:
(1) According to the drawing Sheet No. 3, there is no bedrock outcrop in Cells 4 & 5, but in Cell 3B alone.
WM shall provide a drawing to show the locations of soil borings or piezometers in Cells 4 & 5 and
cross-sections over the project area to demonstrate that the bottom elevations/contours of the landfill
liner system meet the minimum vertical separation requirement per Rule 15A NCAC 13B
.1624(b)(4). The potential bedrock excavation area depicted on Sheet 3 is based on information
provided in the previously-approved Engineering Plan Drawings prepared by S&ME and dated
October 2015. Bedrock encountered during construction will be removed in accordance with the
Contractor’s rock removal plan, which includes rock being removed to a depth of 4 feet below
2
basegrade elevations. The elevation of the rock after removal will be documented in as-built drawings,
prepared by the surveyor.
(2) The SWS request a hard copy of the CQA plan and Technical Specifications for this Cell 3B, 4, & 5
construction. Several revisions had been made through the past cell constructions, the SWS wants to
make sure that we all have the same documents to follow. If any questions are found in the documents,
all sides can discuss and reach an agreement prior to installing landfill liner. Please send the requested
documents to the following address:
Ming Chao
Solid Waste Section, DWM
450 West Hanes Mill Road, Suite 300,
Winston-Salem, NC 27105
A hard copy will be mailed to the above address.
(3) (Meeting Minutes – Item 6a) Please forward the Solid Waste Section (to Chuck & me) an electronic
copy of the open burning permit for this project after Earnhardt has it (somewhere around April 15,
2020? According the info in item 6a). See attached copy of burn permit.
(4) (Meeting Minutes – Item 6c.vii.) A certified written subgrade report (prepared by BLE on behalf of
WM) shall be submitted to Christine for a review and approval. BLE shall notify Christine for final
subgrade inspection of each completely graded cell as stated in PERMIT CONDITION NO. 11, Part I,
Attachment 2 of the Permit (FID 1357256) dated August 30, 2019. A report will be submitted and
notification made as required.
(5) (Meeting Minutes – Item 7f.) The maximum grain size of the subgrade, at where the subgrade intimately
contacts the secondary 60-mil HDPE liner, must be screened and tested. The maximum grain size shall
be less than or equal to 1/2-inches or the value/size that recommended by the liner manufacturer,
whoever is smaller (this will have effect on the liner material warranty). The earthen material should be
tested for grain size analysis per Specification Section 31 2323.13. Structural fill will be tested as
required. Test data will be included in the CQA report.
Below are comments on the construction drawing set.
(6) (Sheet No. 2) The “200’ waste buffer” shows on this drawing sheet. Per Rule 15A NCAC 13B .1624(3),
the minimum buffer distance is 300 feet between landfill unit to all property lines. Please verify the
horizontal buffer distance and make necessary correction. The 200-foot dimension is a typographical
error and has been corrected in the revised drawings.
(7) (Sheet No. 5) The measurement of the as-built/ surveyed thickness of 2-feet protective layer must be
clearly defined. If a thickness at landfill floor area is measured based on the finished subgrade
elevation, the final thickness of the protective cover shall be at 2 feet plus all geosynthetic liner
thicknesses. At the 3 to 1 sloped area, the final thickness of the protective cover shall be at 2 feet which
is measured perpendicular to the slope plus all geosynthetic liner thicknesses. In a nutshell, if the as-built
surveyed thickness is 2 feet, then the thickness is not acceptable. Additional notes have been added to
Sheet 5 of the revised drawings to clarify the requirements for thickness measurement/verification.
(8) (Sheet No. 6)
i. According to Specification Section 31 2323.13, the types of soil/earthen fill for the landfill
project are specified at different locations and for various functions. Avoid any confusion and
3
consist with previous construction drawings, please add the soil/fill type (S-1 thru S-3) at
drawing details. Types of soils have been denoted on the details on the revised drawings.
ii. (Detail 2 of 6) Please confirm the 3 to 1 slope of landfill floor at Cell 3B. The grade at the Cell
3A / Cell 3B tie-in varies from 15% to 3:1 (33.3%). The detail has been revised to show the
range of grades.
iii. Should there be connection details of LCR piping and LDS piping between Cells 3A & 3B? A
detail has been added for the tie-in to existing LCR and LDS piping.
iv. (Details 2 of 8 and 6 of 8) At the tie-in area, please show the blow-up details of
connections/welding (extrusion or hot-wedge welding) between the existing liners and new
liners. These details have been revised to show the tie-in weld.
(9) (Sheet No. 7)
i. (Detail 1 of 7) What is the density (oz per yd2) of the geotextile wrapping around the gravel
column. The drawings have been revised to show that the geotextile is 8 oz/sy.
ii. (Detail 2 of 7) The extrusion weld HDPE boot to pipe shall be hold at that position by stainless
steel clamps with Neoprene caskets. The detail has been revised to show neoprene gaskets and
stainless steel clamps.
iii. (Detail 2 of 7) The secondary HDPE liner shall be welded to the HDPE boot near or inside the
anchor trench. Additionally, the cleanout riser shall be extended to a elevation above the
stormwater flow in the adjacent ditches. The detail has been revised to show the boot welded
near the anchor trench and the cleanout extended further out.
iv. (Detail 3 of 7) The exterior slope (2 to 1) of the diversion berm is like a 4 to 1 slope or it is 4 to 1
slope. Please confirm. Additionally, the berm base without a “key” structure, the stormwater
flow is highly possible to undercut the berm at area with soft or weak layer under strong flow
rate. The exterior slope of the diversion berm is proposed as 2:1. The detail has been revised to
show a key at the inside toe of berm.
(10). Schedule should include the date/duration for LCR piping flushing & camera inspection and liner leak
location test per NCGS 130A-295.6(h). See attached revised schedule.
Please contact me if you have any questions of the requested info and comments.
From: Harrison, Susan <sharri21@wm.com>
Sent: Friday, March 13, 2020 12:37 PM
To: Chao, Ming‐tai <ming.chao@ncdenr.gov>; Kirchner, Chuck <chuck.kirchner@ncdenr.gov>; Ritter, Christine
<christine.ritter@ncdenr.gov>
Subject: [External] Great Oak Landfill ‐ Cells 3B, 4 & 5
Ming-Tai, Chao
Environmental Engineer, Solid Waste Section
Division of Waste Management
North Carolina Department of Environmental Quality
919.707-8251 (Office)
Ming.Chao@ncdenr.gov
4
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
report.spam@nc.gov
Good Friday Afternoon All,
Now that the weather has cleared somewhat, we are beginning a new construction season at the Great Oak Landfill. We
will be building the next three small cells, 3B, 4 & 5. Attached are the construction drawings for your information. Also
attached is an aggressive construction schedule.
In an effort to accelerate the construction, I hurriedly scheduled the pre‐construction meeting and failed to extend an
invitation to any of the DEQ officials. My apologies. The minutes of the meeting, held yesterday, are attached. As you
can see, it was fairly routine in its content. While the cell area is simple, we do anticipate blasting to accelerate the
excavation. The contractor is preparing a blasting plan which will be submitted to both Ming and Christine. Bunnell‐
Lammons, CQA consultant, has a Professional Geologist on standby to perform the necessary review and certification
related to bedrock.
Please let me know if you have any questions and again my apologies for the invitation oversight,
Susan
SUSAN B. HARRISON, PE
Manager of Engineering
South Atlantic Area
sharri21@wm.com
C: 678.436.2719
1047 Highway Church Road
Elgin, SC 29045
Recycling is a good thing. Please recycle any printed emails.
ID Task Name Duration Start Finish Predecessors
1 Mobilization 2 days Mon 3/9/20 Tue 3/10/20
2 Clearing and Grubbing 7 days Mon 3/9/20 Tue 3/17/20
3 Stripping 6 days Mon 3/16/20 Mon 3/23/20 2SS+5 days
4 Rock Test Drilling 5 days Mon 3/16/20 Fri 3/20/20
5 Rock and Soil Excavation 40 days Wed 3/18/20 Tue 5/12/20 2
6 Leak Detection Corridor 5 days Wed 5/13/20 Tue 5/19/20 5
7 Clean and Video Leak Detection
Corridor
2 days Mon 5/18/20 Tue 5/19/20 6FF
8 Liner Installation 20 days Wed 5/20/20 Tue 6/16/20 7
9 Protective Cover 15 days Wed 6/17/20 Tue 7/7/20 8
10 Leachate Collection System 10 days Wed 7/8/20 Tue 7/21/20 9
11 Clean and Video Leachate Collection System 2 days Mon 7/20/20 Tue 7/21/20 10FF
12 Leak Detection Testing 5 days Wed 7/22/20 Tue 7/28/20 11
13 Access Road 5 days Wed 7/22/20 Tue 7/28/20 11
14 Final Dress Up and Seeding 4 days Wed 7/29/20 Mon 8/3/20 13
B M E B M E B M E B M E B M E B
March April May June July August
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
Page 1
Project: schedule 03-16-20Date: Mon 3/16/20
GREAT OAK LANDFILL
COVER PAGE1CELL 3B, 4, AND 5 CONSTRUCTIONGREAT OAK LANDFILLNCDEQ PERMIT #: 7607-MSWLF-20153597 OLD CEDAR FALLS ROADRANDLEMAN, NORTH CAROLINA 27317REVDESCRIPTIONDATEDRA. BYROBWITCHERDate:Last Saved By:3/5/2020 2:56 PMFile Path:M:\DROPBOX (PROMUS ENGINEERING)\PROJECTS-ACTIVE\190173-WMGO-CELL-3B-4-5-DESIGN\DRAWINGS\1-COVER-PAGE.DWGPROJECT NO.: 190173DES. BYAPPR. BYMLA
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
V
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
V
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
W W PREPARED FOR:PREPARED BY:1200 MOUNTAIN CREEK RD., SUITE 102CHATTANOOGA, TENNESSEE 37405Phone: (888) 811-9066NORTH CAROLINA ENGINEERING FIRM # P-1841WASTE MANAGEMENT OF CAROLINAS, INC.A11-27-2019CRWCRWDRAFT - OWNER REVIEWSHEET NUMBERMLB12-05-2019CRWCRWISSUED FOR BIDML003-05-2020CRWCRWISSUED FOR CONSTRUCTIONML103-16-2020CRWCRWREVISED PER NCDEQ COMMENTSVICINITY MAP
SITE LOCATION MAP
SITE
SITE
RANDOLPH
COUNTY
PREPARED FOR:
WASTE MANAGEMENT OF CAROLINAS, INC.
OWNER CONTACT:
MS. SUSAN HARRISON
1047 HIGHWAY CHURCH ROAD
ELGIN, SOUTH CAROLINA 29045
(678) 436-2719
PLANS PREPARED BY:
CONSTRUCTION DRAWINGS FOR CELLS 3B, 4, & 5 AND RELATED WORK
GREAT OAK LANDFILL
3597 OLD CEDAR FALLS ROAD
RANDLEMAN, NORTH CAROLINA 27317
SITE ENTRANCE AT:
N 35° 44" 38" (35.743809°)
W 79° 44' 32" (-79.742578°)
PROJECT NUMBER: 190173
1200 MOUNTAIN CREEK RD., SUITE 102 CHATTANOOGA, TENNESSEE 37405
Phone: (888) 811-9066
DRAWING SHEETS
Sheet Number Sheet Title
1 COVER PAGE
2 EXISTING SITE CONDITIONS
3 BASEGRADE PLAN
4 PROTECTIVE COVER PLAN
5 THICKNESS CERTIFICATION POINTS
6 CONSTRUCTION DETAILS I
7 CONSTRUCTION DETAILS II
ROWROWROWROWROWROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROWROWROWROWROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW ROW
ROW
ROW ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW
ROW ROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROW
ROW
ROW
ROW
ROW
ROW ROW
ROW
ROW ROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWOW-10
PZ-25
PZ-12
PZ-14
PZ-13
PZ-17S
PZ-17D
PZ-10SPZ-10D
PZ-21
PZ-8
PZ-9S
PZ-9D
PZ-6
PZ-3
PZ-2
PZ-5
PZ-4
PZ-16
PZ-15
PZ-53
PZ-57SPZ-57D
PZ-56
PZ-54
PZ-55
PZ-43
MW-1
MW-2
MW-3
MW-4
MW-5
MW-6
MMW-1
MMW-2
MMW-3MMW-4
PZ-63
OW-5
PZ-42
PZ-49
PZ-7
DUKE ENERGY
RIGHT-OF-WAY
EXISTING CELL 1B
7.3 ACRES
EXISTING CELL 1A
8.1 ACRES
EXISTING CELL 2
10.0 ACRES
EXISTING CELL 3A
8.2 ACRES
FUTURE CELLS 6 &7
9.8 ACRES
EXISITNG PERIMETER ACCESS ROAD
EXISITNG SEDIMENT POND #1
EXISITNG MAINTENANCE BUILDING
EXISITNG LEACHATE STORAGE TANK
EXISITNG SEDIMENT POND #2
PROPOSED CELLS 3B, 4, AND 5
LINED AREA = 12.7 ACRES APPROXIMATE LIMIT OF
DISTURBANCE
EXISTING SOIL
STOCKPILE, BORROW
AND SCREENING AREA
140' DUKE POWER RIGHT-OF-WAY
PERMITTED LIMIT OF WASTE
PROPERTY BOUNDARY
MATERIALS AND EQUIPMENT
STAGING AREA
EXISTING SCALE HOUSE
AND SCALES
300' WASTE BUFFER
EXISTING SITE CONDITIONS2
0 100 200 400200
CELL 3B, 4, AND 5 CONSTRUCTIONGREAT OAK LANDFILLNCDEQ PERMIT #: 7607-MSWLF-20153597 OLD CEDAR FALLS ROADRANDLEMAN, NORTH CAROLINA 27317REVDESCRIPTIONDATEDRA. BYROBWITCHERDate:Last Saved By:3/16/2020 2:20 PMFile Path:M:\DROPBOX (PROMUS ENGINEERING)\PROJECTS-ACTIVE\190173-WMGO-CELL-3B-4-5-DESIGN\DRAWINGS\2-EXISTING-SITE-CONDITIONS.DWGPROJECT NO.: 190173DES. BYAPPR. BYMLA
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
V
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
V
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
W W PREPARED FOR:PREPARED BY:1200 MOUNTAIN CREEK RD., SUITE 102CHATTANOOGA, TENNESSEE 37405Phone: (888) 811-9066NORTH CAROLINA ENGINEERING FIRM # P-1841WASTE MANAGEMENT OF CAROLINAS, INC.A11-27-2019CRWCRWDRAFT - OWNER REVIEWSHEET NUMBERMLB12-05-2019CRWCRWISSUED FOR BIDML003-05-2020CRWCRWISSUED FOR CONSTRUCTIONML103-16-2020CRWCRWREVISED PER NCDEQ COMMENTSLEGEND
PROPERTY LINE
PHASE 1 PERMITTED LIMIT OF WASTE
CELL LIMITS
300' WASTE BUFFER
EXISTING AERIAL TOPO SURVEY 10' CONTOUR
EXISTING AERIAL TOPO SURVEY 2' CONTOUR
EXISTING PIEZOMETER
EXISTING PIEZOMETER
EXISTING GROUNDWATER MONITORING WELL
EXISTING METHANE MONITORING WELL
APPROXIMATE LIMIT OF DISTURBANCE
DUKE ENERGY RIGHT-OF-WAY
NOTES/REFERENCES:
1.EXISTING TOPOGRAPHY SHOWN HERE IS REPRESENTATIVE OF SITE
CONDITIONS AT TIME OF AREAL TOPOGRAPHIC SURVEY PREPARED BY
SOUTHERN RESOURCES MAPPING, DATED JANUARY 5, 2020. IT IS THE
CONTRACTORS RESPONSIBILITY TO EVALUATE CURRENT CONDITIONS AS
THEY RELATE TO THIS WORK.
2.PROPERTY BOUNDARY, WASTE BUFFER, PHASE 1 PERMITTED LIMIT OF
WASTE OBTAINED FROM FACILITY PLAN DRAWINGS PREPARED BY S&ME,
DATED FEBRUARY 2015.
3.PIEZOMETER LOCATIONS AND SOIL TEST BORING LOCATIONS OBTAINED
FROM FACILITY PLAN DRAWINGS PREPARED BY S&ME, DATED FEBRUARY
2015.
4.GROUNDWATER MONITORING WELL AND METHANE MONITORING PROBE
LOCATIONS OBTAINED FROM OWNER DECEMBER 2019.
5.THE CONTRACTOR IS SOLELY RESPONSIBLE FOR SITE SAFETY ASSOCIATED
WITH THE WORK UNDER THIS CONTRACT AND FOR COMPLIANCE WITH ALL
FEDERAL, STATE AND LOCAL HEALTH AND SAFETY LAWS, CODES,
REGULATION, AND ORDINANCES INCLUDING BUT NOT LIMITED TO THOSE
CURRENTLY MANDATED BY THE OCCUPATIONAL SAFETY AND HEALTH
ADMINISTRATION (OSHA)
MMW-1
PZ-51
OW-1
MW-4
SURVEY LEGEND
AERIAL SURVEY NOTES:
1.THIS MAP WAS COMPILED BY SOUTHERN RESOURCES MAPPING USING
PHOTOGRAMMETRIC METHODS. CONTOURS PORTRAYED AS DASHED OR
BROKEN LINES REPRESENT AREAS OF DENSE VEGETATION AND SHOULD BE
CONSIDERED APPROXIMATE. THIS MAP HAS NOT BEEN FIELD VERIFIED. PRIOR
TO USE AS A BASIS FOR DESIGN OR CONSTRUCTION, IT SHOULD BE FIELD
VERIFIED.
2.BUILDINGS ARE SHOWN AS ROOFLINE ONLY.
3.THE PROPERTY LINES INDICATED ON THIS MAP WERE PROVIDED BY GREAT OAK.
SOUTHERN RESOURCES MAPPING ASSUMES NO RESPONSIBILITY FOR THE
ACCURACY OF THE PROPERTY LINES REPRESENTED HEREON.
4.THIS IS NOT A BOUNDARY SURVEY. APPARENT PROPERTY CORNERS ARE
SHOWN FOR ORIENTATION ONLY. BOUNDARY DATA SHOWN IS FROM PREVIOUS
SURVEY REFERENCED HEREON.
5.THE HORIZONTAL COORDINATES ARE BASED ON STATE PLANE COORDINATE
SYSTEM NORTH CAROLINA ZONE, NAD83, FEET. THE VERTICAL DATUM IS BASED
ON NAVD88, FEET.
6.GROUND CONTROL FOR AERIAL MAPPING SUPPLIED BY: CHARLIE MORGAN
SURVEYING
7.BENCHMARKS AND CONTROL WERE ESTABLISHED BY: CHARLIE MORGAN
SURVEYING
ROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROW>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
610
620
620
670
67
0
680680
690
690700700710710710710710720720730620630640650
650650660
6606606706806907006306406503:1 3:13:13:13:13:13:1
3:1
VARIE
S
VARIE
SVARIES
VARI
E
S
VARI
E
S
VARIES 3:13:1TIE-IN TO E
X
I
S
T
I
N
G
C
E
L
L
3
A
6
2NORTH PERIMETER BERMPERIMETER TIE-IN TO EXISTING CELLS68WEST PERIMETER BERM
6566ACCESS ROAD
CULVERT #1
185 LF, 24" Ø DUAL-WALL CPP WITH PRECAST HEADWALL
INV. IN: 695.9
INV. OUT: 675.6
CULVERT #2
120 LF, 36" Ø DUAL-WALL CPP WITH PRECAST HEADWALL
INV. IN: 612.9
INV. OUT: 601.3
PERMANENT VEGETATION
DOUBLE-SIDED EROSION
CONTROL MATTING
PERMANENT VEGETATION
6
10
6
10
RIPRAP OUTLET PROTECTION6
7
LDS CLEANOUT RISER
DUKE ENERGY
RIGHT-OF-WAY
LINER SYSTEM6
1
LEACHATE SYSTEM CORRIDOR7
1
RIPRAP OUTLET PROTECTION 6
7
STORMWATER DIVERSION BERM7
3
7
2
6
9
7
5
LDS CLEANOUT RISER7
2
ROCK CHECK DAM 6
9
CONTRACTOR SHALL CONSTRUCT SMOOTH
TRANSITION BETWEEN EXISTING AND
PROPOSED DITCHES
BASEGRADE PLAN3
0 25 50 10050
CELL 3B, 4, AND 5 CONSTRUCTIONGREAT OAK LANDFILLNCDEQ PERMIT #: 7607-MSWLF-20153597 OLD CEDAR FALLS ROADRANDLEMAN, NORTH CAROLINA 27317REVDESCRIPTIONDATEDRA. BYROBWITCHERDate:Last Saved By:3/5/2020 3:50 PMFile Path:M:\DROPBOX (PROMUS ENGINEERING)\PROJECTS-ACTIVE\190173-WMGO-CELL-3B-4-5-DESIGN\DRAWINGS\3-SUBGRADE-PLAN.DWGPROJECT NO.: 190173DES. BYAPPR. BYMLA
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
V
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
V
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
W W PREPARED FOR:PREPARED BY:1200 MOUNTAIN CREEK RD., SUITE 102CHATTANOOGA, TENNESSEE 37405Phone: (888) 811-9066NORTH CAROLINA ENGINEERING FIRM # P-1841WASTE MANAGEMENT OF CAROLINAS, INC.A11-27-2019CRWCRWDRAFT - OWNER REVIEWSHEET NUMBERMLB12-05-2019CRWCRWISSUED FOR BIDML003-05-2020CRWCRWISSUED FOR CONSTRUCTIONML103-16-2020CRWCRWREVISED PER NCDEQ COMMENTSLEGEND
LIMIT OF LINER
DIVERSION BERM
PROPOSED 10-FT SUBGRADE CONTOUR
PROPOSED 2-FT SUBGRADE CONTOUR
LEACHATE DETECTION SYSTEM PIPING
CULVERT
SLOPE INDICATOR
PERMANENT VEGETATION
DOUBLE-SIDED EROSION MATTING
GRAVEL PAVING
RIPRAP
POTENTIAL BEDROCK EXCAVATION AREA
550
3:1
>>
NOTES/REFERENCES:
1.EXISTING TOPOGRAPHY SHOWN HERE IS REPRESENTATIVE OF SITE
CONDITIONS AT TIME OF AREAL TOPOGRAPHIC SURVERY PREPARED
BY SOUTHERN RESOURCES MAPPING, DATED JANUARY 6, 2019.
EXISTING TOPOGRAPHY IN AND AROUND EXISITNG CELL 3A WAS
OBTAINED FROM THE CONSTRUCTION PLANS FOR CELL 3A
PREPARED BY SCS ENGINEERS, DATED NOVEMBER 2018. IT IS THE
CONTRACTORS RESPONSIBILITY TO EVALUATE CURRENT
CONDITIONS AS THEY RELATE TO THIS WORK.
2.PROPERTY BOUNDARY, WASTE BUFFER, PHASE 1 PERMITTED LIMIT
OF WASTE OBTAINED FROM FACILITY PLAN DRAWINGS PREPARED BY
S&ME, DATED FEBRUARY 2015.
3.THE CONTRACTOR IS SOLELY RESPONSIBLE FOR SITE SAFETY
ASSOCIATED WITH THE WORK UNDER THIS CONTRACT AND FOR
COMPLIANCE WITH ALL FEDERAL, STATE AND LOCAL HEALTH AND
SAFETY LAWS, CODES, REGULATION, AND ORDINANCES INCLUDING
BUT NOT LIMITED TO THOSE CURRENTLY MANDATED BY THE
OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA)
4.PERMITTED BASEGRADE CONTOURS WERE OBTAINED FROM
ENGINEERING PLANS PREPARED BY S&ME, DATED FEBRUARY 2015.
5.BASEGRADE CONTOURS REPRESENT TOP OF STRUCTURAL SOIL FILL
OR EXCAVATION. IF BEDROCK IS ENCOUNTERED DURING
EXCAVATION OF OVERBURDEN, CONTRACTOR SHALL REMOVE
MATERIAL TO A DEPTH OF FOUR (4) FEET BELOW DESIGN
BASEGRADE ELEVATION SHOWN HEREIN AND REPLACE WITH
STRUCTURAL SOIL FILL.
6.EROSION AND SEDIMENT CONTROL MEASURES SHALL BE INSTALLED
IN ACCORDANCE WITH EROSION AND SEDIMENT CONTROL PLAN
(ESPC) PRIOR TO ANY LAND DISTURBANCE. REFER TO DRAWING #3
FOR E&S CONTROLS.
7.CONTRACTOR IS RESPONSIBLE FOR MANAGING ALL LIQUIDS
(LEACHATE AND STORMWATER) ALONG EXISTING LINER TIE-INS.
TIE-IN SHALL NOT BE EXCAVATED EARLIER IN PROJECT THAN
NECESSARY.
610
620
620
670
67
0
680680
690
690700700710710710710710720720730620630640650
650650660
6606606706806907006306406503:1 3:13:13:13:13:13:1
3:1
VARIE
S
VARIE
SVARIES
VARI
E
S
VARI
E
S
VARIES 3:13:13:1
VARIE
S
VARIE
SVARIES
VARI
E
S
VARI
E
S
VARIES
LCP LCP LCP LCP LCP LCP LCP
LCP
LCP
LCP
LCP
LCP
LCP
LCP
LCP
LCP
LCP
LCP
LCP
LCP
LCP
LCP LCP
LCP
LCP
LCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCP630640640650650
65065066066
0
660660670680690700TIE-IN TO E
X
I
S
T
I
N
G
C
E
L
L
3
A
6
2NORTH PERIMETER BERMPERIMETER TIE-IN TO EXISTING CELLS68WEST PERIMETER BERM
6566E.O.L.
E.O.L.
E.O.L.
E.O.L.
E.O.L.
E.O.L.
SOLID CLEANOUT RISERS
SOLID CLEANOUT RISERS
SOLID CLEANOUT RISERS
LEACHATE SYSTEM CORRIDOR7
1
7
2
7
2
7
2
EDGE OF LINER MARKER AT 100' C/C
AROUND 2 CELL EDGES
DUKE ENERGY
RIGHT-OF-WAY
ROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWE.O.L.
E.O.L.
E.O.L.
E.O.L.
E.O.L.E.O.L.E.O.L.
E.O.L.
E.O.L.
E.O.L.
E.O.L.
LEACHATE SYSTEM CORRIDOR TIE-IN7
9
PROTECTIVE COVER PLAN4CELL 3B, 4, AND 5 CONSTRUCTIONGREAT OAK LANDFILLNCDEQ PERMIT #: 7607-MSWLF-20153597 OLD CEDAR FALLS ROADRANDLEMAN, NORTH CAROLINA 27317REVDESCRIPTIONDATEDRA. BYROBWITCHERDate:Last Saved By:3/16/2020 2:20 PMFile Path:M:\DROPBOX (PROMUS ENGINEERING)\PROJECTS-ACTIVE\190173-WMGO-CELL-3B-4-5-DESIGN\DRAWINGS\4 PROTECTIVE COVER PLAN.DWGPROJECT NO.: 190173DES. BYAPPR. BYMLA
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
V
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
V
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
W W PREPARED FOR:PREPARED BY:1200 MOUNTAIN CREEK RD., SUITE 102CHATTANOOGA, TENNESSEE 37405Phone: (888) 811-9066NORTH CAROLINA ENGINEERING FIRM # P-1841WASTE MANAGEMENT OF CAROLINAS, INC.A11-27-2019CRWCRWDRAFT - OWNER REVIEWSHEET NUMBERMLB12-05-2019CRWCRWISSUED FOR BIDML003-05-2020CRWCRWISSUED FOR CONSTRUCTIONML103-16-2020CRWCRWREVISED PER NCDEQ COMMENTSLEGEND
LIMIT OF LINER
PROPOSED 10-FT SUBGRADE CONTOUR
PROPOSED 2-FT SUBGRADE CONTOUR
SLOPE INDICATOR
LEACHATE COLLECTION PIPE (PERFORATED)
LCP CLEANOUT (SOLID)
LINER EDGE MARKER
550
3:1
LCP LCP
E.O.L.
0 25 50 10050
NOTES/REFERENCES:
1.EXISTING TOPOGRAPHY SHOWN HERE IS REPRESENTATIVE OF SITE
CONDITIONS AT TIME OF AREAL TOPOGRAPHIC SURVERY PREPARED
BY SOUTHERN RESOURCES MAPPING, DATED JANUARY 5, 2020. IT IS
THE CONTRACTORS RESPONSIBILITY TO EVALUATE CURRENT
CONDITIONS AS THEY RELATE TO THIS WORK.
2.PROPERTY BOUNDARY, WASTE BUFFER, PHASE 1 PERMITTED LIMIT
OF WASTE OBTAINED FROM FACILITY PLAN DRAWINGS PREPARED BY
S&ME, DATED FEBRUARY 2015.
3.THE CONTRACTOR IS SOLELY RESPONSIBLE FOR SITE SAFETY
ASSOCIATED WITH THE WORK UNDER THIS CONTRACT AND FOR
COMPLIANCE WITH ALL FEDERAL, STATE AND LOCAL HEALTH AND
SAFETY LAWS, CODES, REGULATION, AND ORDINANCES INCLUDING
BUT NOT LIMITED TO THOSE CURRENTLY MANDATED BY THE
OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA)
4.PERMITTED BASEGRADE CONTOURS WERE OBTAINED FROM
ENGINEERING PLANS PREPARED BY S&ME, DATED FEBRUARY 2015.
5.BASEGRADE CONTOURS REPRESENT TOP OF STRUCTURAL SOIL FILL
OR EXCAVATION. IF BEDROCK IS ENCOUNTERED DURING
EXCAVATION OF OVERBURDEN, CONTRACTOR SHALL REMOVE
MATERIAL TO A DEPTH OF FOUR (4) FEET BELOW DESIGN
BASEGRADE ELEVATION SHOWN HEREIN AND REPLACE WITH
STRUCTURAL SOIL FILL.
6.EROSION AND SEDIMENT CONTROL MEASURES SHALL BE INSTALLED
IN ACCORDANCE WITH EROSION AND SEDIMENT CONTROL PLAN
(ESPC) PRIOR TO ANY LAND DISTURBANCE. REFER TO DRAWING #3
FOR E&S CONTROLS.
7.CONTRACTOR IS RESPONSIBLE FOR MANAGING ALL LIQUIDS
(LEACHATE AND STORMWATER) ALONG EXISTING LINER TIE-INS.
TIE-IN SHALL NOT BE EXCAVATED EARLIER IN PROJECT THAN
NECESSARY.
1
710710720720730620630640650
650650660
6606606706806907006306406503:1
VARIE
S
VARIE
SVARIES
VARI
E
S
VARI
E
S
VARIES 3:13:11000
1001
1002
1003
1004
1005
1006
1007
1008
1009
1010
1011
1012
1013
1014
1015
1016
1017
1018
1019
1020
1021
1022
1023
1024
1025
1026
1027
1028
1029
1030
1031
1032
1033
1034 1035
1036
1037
1038
1039
1040
1041
1042
1043
1044
1045
1046
1047
1048
1049
1050
1051
1052
1053
1054
1055
1056
1057
1058
1059
1060
1061
1062
1063
1064
1065
1066
1067
1068
1069
1070
1071
1072
1073
1074
1075
1076
1077
1078
1079
1080
1081
1082
1083
1084
1085
1086
1087
1088
10891090
1091
1092
1093
1094
1095
1096
1097
1098
1099
1100
1101
1102
1103
1104
1105
1106
1107
1108
1109
1110
1111
1112
1113
1114
1115
1116
1117
1118
1119
1120
1121
1122
1123
1124
1125
1126
1127
1128
1129
1130
1131
1132
1133
1134
1135
1136
1137
1138
1139
1140
1141
1142
1143 1144
1145
1146 1147
1148
1149
1150 1151
1152
1153
1154 1155
1156
1157
1158
1159
1160
1161
1162
1163
1164
1165
1166
1167
1168
1169
1170
1171
1172
1173
1174
1175
1176
1177
1178
1179
1180
1181
1182
1183
11841185
1186
1187
1188
1189
1190
1191
1192
1193
1194
1195
1196
1197
1198
1199
1200
1201
1202
1203
1204
1205
1206
1207
1208
1209
12101211
1212
1213
1214
1215
THICKNESS CERTIFICATIONPOINTS5CELL 3B, 4, AND 5 CONSTRUCTIONGREAT OAK LANDFILLNCDEQ PERMIT #: 7607-MSWLF-20153597 OLD CEDAR FALLS ROADRANDLEMAN, NORTH CAROLINA 27317REVDESCRIPTIONDATEDRA. BYROBWITCHERDate:Last Saved By:3/16/2020 2:20 PMFile Path:M:\DROPBOX (PROMUS ENGINEERING)\PROJECTS-ACTIVE\190173-WMGO-CELL-3B-4-5-DESIGN\DRAWINGS\5-THICKNESS-CERTIFICATION-POINTS.DWGPROJECT NO.: 190173DES. BYAPPR. BYMLA
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
V
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
V
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
W W PREPARED FOR:PREPARED BY:1200 MOUNTAIN CREEK RD., SUITE 102CHATTANOOGA, TENNESSEE 37405Phone: (888) 811-9066NORTH CAROLINA ENGINEERING FIRM # P-1841WASTE MANAGEMENT OF CAROLINAS, INC.A11-27-2019CRWCRWDRAFT - OWNER REVIEWSHEET NUMBERMLB12-05-2019CRWCRWISSUED FOR BIDML003-05-2020CRWCRWISSUED FOR CONSTRUCTIONML103-16-2020CRWCRWREVISED PER NCDEQ COMMENTSLEGEND
PHASE 1 PERMITTED LIMIT OF WASTE
LIMIT OF LINER
PROPOSED 10-FT BASEGRADE CONTOUR
PROPOSED 2-FT BASEGRADE CONTOUR
SLOPE INDICATOR
THICKNESS CERTIFICATION POINT
550
3:1
1000
CERTIFICATION NOTES:
1.SURVEYOR SHALL "STACK" POINTS (i.e. USE SAME NORTHING AND
EASTING) FOR THICKNESS VERIFICATION OF LINER SYSTEM
COMPONENTS.
2.HORIZONTAL TOLERANCE FOR ALL POINTS SHALL BE 0.2 FEET.
3.MINIMUM PROTECTIVE COVER THICKNESS OF 24 INCHES SHALL BE
BASED ON A MEASUREMENT PERPENDICULAR TO THE SLOPE.
AS-BUILT THICKNESS MEASUREMENT SHALL BE ADJUSTED TO
ACCOUTN FOR SLOPE (I.E. 2.11 FEET MINIMUM THICKNESS REQUIRED
ON 3:1 SLOPE).
4.THE BASIS OF MEASUREMENT FOR PROTECTIVE COVER THICKNESS
SHALL BE THE TOP OF GEOSYNTHETICS, NOT THE AS-BUILT
BASEGRADE ELEVATIONS.
5.VERTICAL TOLERANCES SHALL BE AS FOLLOWS:
·BASEGRADE:WITHIN ± 0.08 FT OF DESIGN
·PROTECTIVE COVER: MIN. THICKNESS MEASURED
FROM AS-BUILT BASEGRADE TO +
0.2 FT
SCALE IN FEET
050 50 100
1
24" PROTECTIVE COVER
(FILL TYPE S2)
SUBGRADE OR STRUCTURAL FILL
(FILL TYPE S1)
LEACHATE COLLECTION SYSTEM (LCS)
GEOCOMPOSITE DRAINAGE LAYER
PRIMARY 60-MIL TEXTURED
HDPE GEOMEMBRANE
LEAK DETECTION SYSTEM (LDS)
GEOCOMPOSITE DRAINAGE LAYER
SECONDARY 60-MIL TEXTURED
HDPE GEOMEMBRANE
GEOSYNTHETIC CLAY LINER (GCL)
NOTES:
1.STRUCTURAL FILL SHALL CONSIST OF
BORROW SOILS CONSISTENT WITH
SPECIFICATION SECTION 31 2323.13.
2.GEOSYNTHETIC COMPONENTS ARE
EXAGGERATED FOR CLARITY.
~ WASTE ~
REMOVE EXISTING ANCHOR
TRENCH COMPONENTS
6
1LINER SYSTEM
EXISTING CELL 1B / 2 PROPOSED CELL 3B
EXTRUSION WELD EXISTING
LINER TO PROPOSED LINER
OVERLAP GEOCOMPOSITES
AND GCL 24" MINIMUM
FILL TYPE S2
GRADE VARIES
15% MIN
3:1 MAX~ WASTE ~6
1LINER SYSTEM
REMOVE EXISTING ANCHOR
TRENCH COMPONENTS
EXISTING CELL 3A PROPOSED CELL 3B
EXISTING GEOMEMBRANE RAIN FLAP
CONTRACTOR TO CUT AND REMOVE FLAP
AFTER COMPLETION OF CELL CONSTRUCTION
DISPOSE OF FLAP IN ACTIVE LANDFILL
EXISTING PROTECTIVE COVER
EXTRUSION WELD EXISTING
LINER TO PROPOSED LINER
FILL TYPE S2
OVERLAP GEOCOMPOSITES
AND GCL 24" MINIMUM
#57 STONE OR ENGINEER-APPROVED
EQUIVALENT
STRUCTURAL FILL (FILL TYPE S2)
COMPACTED TO MINIMUM 95%
MAXIMUM DRY DENSITY AS
DETERMINED BY ASTM D-698
DUAL-WALL CORRUGATED
PLASTIC PIPE
NATIVE MATERIAL OR
STRUCTURAL FILL
NOTES:
1.ALL PIPE SHALL BE INSTALLED IN ACCORDANCE WITH
ASTM D-2321, "STANDARD PRACTICE FOR
UNDERGROUND INSTALLATION OF THERMOPLASTIC
PIPE FOR SEWERS AND OTHER GRAVITY FLOW
APPLICATIONS", LATEST VERSION.
2.MEASURES SHALL BE TAKEN TO PREVENT MIGRATION
OF NATIVE FINES INTO BACKFILL MATERIAL.
3.WHERE THE TRENCH BOTTOM IS UNSUITABLE, THE
CONTRACTOR SHALL EXCAVATE AND REMOVE
MATERIAL TO A DEPTH AS DETERMINED BY CQA
ENGINEER AND REPLACE WITH SUITABLE MATERIAL.
4.IN NO CASE SHALL CONSTRUCTION EQUIPMENT BE
ALLOWED TO CROSS OVER THE PIPE WITH LESS THAN
3' OF COMPACTED SOIL COVER OVER THE CROWN OF
THE PIPE. IT MAY BE NECESSARY FOR THE
CONTRACTOR TO PLACE A TEMPORARY COMPACTED
SOIL RAMP OVER THE PIPE DURING CONSTRUCTION TO
ACHIEVE THE MINIMUM COVER DEPTH.
5.ANY DAMAGE TO THE PIPE AS A RESULT OF IMPROPER
INSTALLATION OR SOIL COVER SHALL BE REPAIRED BY
THE CONTRACTOR AT NO ADDITIONAL COST TO THE
OWNER.
6"
DEPTH VARIES
3' MIN IN ROADWAY
6"
12" (TYP)
3'
2'
2'
3:1
3:1
SUBGRADE
(TYPE S1 SOIL FILL)
4'E.O.L.3:1
4'
DAYLIGHT TO EXISTING
10'
6'
EDGE OF LINER MARKER EVERY 100'
ALONG BERM 4' BEHIND ANCHOR TRENCH
ANCHOR TRENCH 6
3
PROTECTIVE COVER
(FILL TYPE S2)
4'
10'
3'
2'
2'
3:1
SLOP
E
V
A
R
I
E
S
6'
SUBGRADE
(FILL TYPE S1)
3:1
DAYLIGHT TO EXISTING
ANCHOR TRENCH 6
3
4'E.O.L.EDGE OF LINER MARKER EVERY 100'
ALONG BERM 4' BEHIND ANCHOR TRENCH
PROTECTIVE COVER
(FILL TYPE S2)
VARIES
SEE PLAN
VARIES
SEE PLANCULVERT
18" THICK RIPRAP
D50 > 9"
3'
2'
TOE WALL
DISCHARGE CONDUIT
END OF CULVERT
8-OZ. NONWOVEN GEOTEXTILE
18" THICK RIPRAP
D50 > 9"
8-OZ. NONWOVEN GEOTEXTILE
18" THICK RIPRAP
D50 > 9"
VARIES
6
1
3'
CLEAN COMPACTED SOIL BACKFILL
(FILL TYPE S1)2'
3'
LINER SYSTEM
EXTEND SECONDARY GEOMEMBRANE AND
LCS GEOCOMPOSITE INTO ANCHOR TRENCH
EDGE OF LINER MARKER EVERY 100'
ALONG BERM 4' BEHIND ANCHOR TRENCH7
6
TERMINATE LDS
GEOCOMPOSITE AND GCL
EXTRUSION WELD PRIMARY
LINER TO SECONDARY LINER
SACRIFICIAL STRIP OF PROTECTIVE
GEOCOMPOSITE, + 4' WIDE
FILL TYPE S1
FILL TY
P
E
S
2
NOTES:
1.SINGLE-SIDED MATTING SHALL BE
NORTH AMERICAN GREEN S75, OR
ENGINEER-APPROVED EQUIVALENT.
2.SLOPE SURFACE SHALL BE FREE OF
ROCKS, CLODS, STICKS AND GRASS.
MATS/BLANKETS SHALL HAVE GOOD
SOIL CONTACT.
3.LAY BLANKETS LOOSELY AND STAKE
OR STAPLE TO MAINTAIN DIRECT
CONTACT WITH THE SOIL. DO NOT
STRETCH.
4.INSTALL PER MANUFACTURER'S
RECOMMENDATIONS.2h:1V SLOPE MAX(UNLESS MSE)6.5'
BERM
TAMP SOIL O
V
E
R
M
A
T
/
B
L
A
N
K
E
T
4.5'
MATS/BLANKETS SHALL BE
INSTALLED VERTICALLY
UP/DOWN SLOPE.
2 TO 3
INCH
OVERLAP
1 FT.
6"x6" ANCHOR TRENCH
48"
BERM
2 ft. OVERLAP
IN SPLICE
RIPRAP LINING
MATTING LINING
CONTRACTOR SHALL ANCHOR EROSION
CONTROL MATTING IN ACCORDANCE WITH
MANUFACTURER RECOMMENDATIONS
TENSAR SC-250 VEGETATED CHANEL
LINING, STAPLE PATTERN "D", OR
APPROVED EQUIVALENT
3:1
3:1
8-OZ. NONWOVEN GEOTEXTILE
RIPRAP
D50 > 9"
SEE DETAILS FOR
DIMENSIONS
1.5'
6
6
6
5
SEE DETAILS FOR
DIMENSIONS6
6
6
5
CONSTRUCTION DETAILS I6CELL 3B, 4, AND 5 CONSTRUCTIONGREAT OAK LANDFILLNCDEQ PERMIT #: 7607-MSWLF-20153597 OLD CEDAR FALLS ROADRANDLEMAN, NORTH CAROLINA 27317REVDESCRIPTIONDATEDRA. BYROBWITCHERDate:Last Saved By:3/16/2020 2:22 PMFile Path:M:\DROPBOX (PROMUS ENGINEERING)\PROJECTS-ACTIVE\190173-WMGO-CELL-3B-4-5-DESIGN\DRAWINGS\CONSTRUCTION-DETAILS-I.DWGPROJECT NO.: 190173DES. BYAPPR. BYMLA
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
V
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
V
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
W W PREPARED FOR:PREPARED BY:1200 MOUNTAIN CREEK RD., SUITE 102CHATTANOOGA, TENNESSEE 37405Phone: (888) 811-9066NORTH CAROLINA ENGINEERING FIRM # P-1841WASTE MANAGEMENT OF CAROLINAS, INC.A11-27-2019CRWCRWDRAFT - OWNER REVIEWSHEET NUMBERMLB12-05-2019CRWCRWISSUED FOR BIDML003-05-2020CRWCRWISSUED FOR CONSTRUCTIONML103-16-2020CRWCRWREVISED PER NCDEQ COMMENTSLINER SYSTEM1
NTS6
PERIMETER TIE-IN TO EXISTING CELLS8
NTS6
TIE-IN TO EXISTING CELL 3A2
NTS6
CULVERT INSTALLATION10
NTS6
WEST PERIMETER BERM5
NTS6
NORTH PERIMETER BERM6
NTS6
RIPRAP OUTLET PROTECTION7
NTS6
ANCHOR TRENCH3
NTS6
EROSION CONTROL MATTING9
NTS6
DET-CHANNEL-LINING4
NTS6
NOTES/REFERENCES:
1.THE CONTRACTOR IS SOLELY RESPONSIBLE FOR SITE SAFETY
ASSOCIATED WITH THE WORK UNDER THIS CONTRACT AND FOR
COMPLIANCE WITH ALL FEDERAL, STATE AND LOCAL HEALTH AND
SAFETY LAWS, CODES, REGULATION, AND ORDINANCES INCLUDING
BUT NOT LIMITED TO THOSE CURRENTLY MANDATED BY THE
OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA)
2.CONTRACTOR IS RESPONSIBLE FOR MANAGING ALL LIQUIDS
(LEACHATE AND STORMWATER) ALONG EXISTING LINER TIE-INS.
TIE-IN SHALL NOT BE EXCAVATED EARLIER IN PROJECT THAN
NECESSARY.
8"-DIA. SDR 11 LDS HEADER PIPE
(4" MIN. BEDDING AROUND PIPE)
8"-DIA. SDR 11 LCS HEADER PIPE
(4" MIN. BEDDING AROUND PIPE)
#57 DRAINAGE AGGREGATE
FLOW FLOW
1:11:
1
1:11:16
1
7
8
7
8
1.5' GEOTEXTILE OVERLAP6"
1'
1'
2
LINER SYSTEM
8 OZ/SY NONWOVEN GEOTEXTILE
FILL TYPE S2
FILL TYPE S1
LCP SOLID CLEANOUT RISER
LINER SYSTEM 3'±6
1
LDS SOLID CLEANOUT RISER
FILL TYPE S1
FILL TYPE S2
RIPRAP
D50 > 6"
8-OZ. NONWOVEN GEOTEXTILE
1.
5
:
1
1'
1.5' AT DITCH ℄
0.5'
1.5:1
CROSS SECTION THROUGH
ROCK CHECK DAM
RIPRAP, D50 > 6"
8-OZ. NONWOVEN GEOTEXTILE
1.5' AT DITCH ℄
CHANNEL SIDESLOPE
EXISTING
W
A
S
T
E
3:1
DAILY / IN
T
E
R
M
E
D
I
A
T
E
C
O
V
E
R
2'
2' MIN (1)
2:1
CLEAN COMPACTED STRUCTURAL FILL
PERMANENT VEGETATION
PERMANENT VEGETATION
NOTES:
1.DIVERSION BERM SHALL BE MINIMUM 4' DEEP AT
DOWNDRAIN PIPE INLET. MINIMUM TOP OF BERM ELEVATION
AT INLET SHALL BE MAINTAINED UNTIL HEIGHT REACHES 2'.
RE-COMPACTED SOIL EDGE OF LINER - 4' OFFSET3'
3'
ANCHOR TRENCH
PRESSURE-TREATED 4" x 4" WOODEN POST
POST SHALL BE PRIMED AND COATED WITH
SAFETY YELLOW EXTERIOR PAINT
BLACK LETTERING: "EDGE OF LINER"
4'
7
4
ANCHOR TRENCH
8" HDPE BLIND FLANGE WITH DI
BACKUP RING AND SS HARDWARE
WELDED HDPE BOOT
* +3' HORIZONTAL SEPARATION
BETWEEN CLEANOUT PIPES
SOLID CLEANOUT RISERS
NOTES:
1.PREFABRICATED AND SPARK TESTED
BOOT TO BE EXTRUSION WELDED TO
HDPE PIPE AND PRIMARY LINER.
8" SDR 11 SOLID HDPE LCS CLEANOUT PIPE
8" SDR 11 SOLID HDPE LDS CLEANOUT PIPE
STAINLESS STEEL BAND CLAMP AND NEOPRENE GASKET
5'
3'
24'
3'3:1 3:13:13:1
2%2%
WOVEN GEOTEXTILE MEETING AASHTO M288-00 SEPARATION
AND STABILIZATION, CLASS 1 - SOFT SUBGRADES
ROAD TOPPING - 4" CRUSHER RUN, OR ENGINEER-APPROVED EQUIVALENT
ROAD BASE - 6" AASHTO #2 STONE, OR ENGINEER-APPROVED EQUIVALENTDAYLIGHT TO EXISTING GROUND
(CUT SCENARIO)
FILL SLOPE TO EXISTING GROUND
(FILL SCENARIO)
NATIVE MATERIAL /
STRUCTURAL FILL
8" Ø SDR 11 HDPE PIPE
58" Ø PERFORATIONS
INVERT OF PIPE
90°'4"2"
* +3' HORIZONTAL SEPARATION
BETWEEN CLEANOUT PIPES
LEACHATE SYSTEM CORRIDOR7
1
8" SDR 11 SOLID HDPE LCS CLEANOUT PIPE
8" SDR 11 SOLID HDPE LDS CLEANOUT PIPE
REMOVE EXISTING ANCHOR
TRENCH COMPONENTS
EXISTING CELL 3A PROPOSED CELL 3B
EXISTING GEOMEMBRANE RAIN FLAP
CONTRACTOR TO CUT AND REMOVE FLAP
AFTER COMPLETION OF CELL CONSTRUCTION
DISPOSE OF FLAP IN ACTIVE LANDFILL
EXISTING PROTECTIVE COVER
GEOSYNTHETIC COMPONENTS TIE-IN6
2 CONSTRUCTION DETAILS II7CELL 3B, 4, AND 5 CONSTRUCTIONGREAT OAK LANDFILLNCDEQ PERMIT #: 7607-MSWLF-20153597 OLD CEDAR FALLS ROADRANDLEMAN, NORTH CAROLINA 27317REVDESCRIPTIONDATEDRA. BYROBWITCHERDate:Last Saved By:3/16/2020 5:00 PMFile Path:M:\DROPBOX (PROMUS ENGINEERING)\PROJECTS-ACTIVE\190173-WMGO-CELL-3B-4-5-DESIGN\DRAWINGS\CONSTRUCTION DETAILS II.DWGPROJECT NO.: 190173DES. BYAPPR. BYMLA
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
V
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
V
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
W W PREPARED FOR:PREPARED BY:1200 MOUNTAIN CREEK RD., SUITE 102CHATTANOOGA, TENNESSEE 37405Phone: (888) 811-9066NORTH CAROLINA ENGINEERING FIRM # P-1841WASTE MANAGEMENT OF CAROLINAS, INC.A11-27-2019CRWCRWDRAFT - OWNER REVIEWSHEET NUMBERMLB12-05-2019CRWCRWISSUED FOR BIDML003-05-2020CRWCRWISSUED FOR CONSTRUCTIONML103-16-2020CRWCRWREVISED PER NCDEQ COMMENTSLEACHATE SYSTEM CORRIDOR1
NTS7
SOLID CLEANOUT RISERS4
NTS7
RIPRAP CHECK DAM7
NTS7
DIVERSION BERM3
NTS7
EDGE OF LINER MARKER6
NTS7
SOLID CLEANOUT RISERS2
NTS7
ACCESS ROAD5
NTS7
NOTES/REFERENCES:
1.THE CONTRACTOR IS SOLELY RESPONSIBLE FOR SITE SAFETY
ASSOCIATED WITH THE WORK UNDER THIS CONTRACT AND FOR
COMPLIANCE WITH ALL FEDERAL, STATE AND LOCAL HEALTH AND
SAFETY LAWS, CODES, REGULATION, AND ORDINANCES INCLUDING
BUT NOT LIMITED TO THOSE CURRENTLY MANDATED BY THE
OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA)
2.CONTRACTOR IS RESPONSIBLE FOR MANAGING ALL LIQUIDS
(LEACHATE AND STORMWATER) ALONG EXISTING LINER TIE-INS.
TIE-IN SHALL NOT BE EXCAVATED EARLIER IN PROJECT THAN
NECESSARY.
COLLECTION PIPE PERFORATIONS8
NTS7
NOTE:
1.CONTRACTOR SHALL DE-BEAD THE INTERIOR OF ALL LEAK
DETECTION SYSTEM AND LEACHATE COLLECTION SYSTEM PIPING.
LEACHATE SYSTEM CORRIDOR TIE-IN9
NTS7