HomeMy WebLinkAbout7607_GreatOakMSWLF_Cell3B_4&5_Pre-ConstructionMeetingMinutes_FID1394267_20200312 Pre-Construction Meeting - Minutes Great Oak Landfill Cells 3B, 4 & 5 March 12, 2020 10:00 AM 1. Introductions – sign-in sheet attached a. Owner – Waste Management i. Mike McFeeley –District Manager ii. Susan Harrison – Project Manager iii. Don Misenheimer – Environmental Protection Manager iv. Bobby Owens – Operations Manager b. Design Engineer – Promus Engineering i. Rob Witcher c. Construction Quality Assurance - BLE i. Jonathan Usher - Construction Quality Assurance Manager d. Contractor – Earnhardt Grading i. Mark LeGrand – Construction Project Manager ii. Marc Gilbert –Site Project Manager e. Surveyor – Carolina Survey f. Liner Install - ESI g. Property Owner – Randolph County i. Paxton Arthurs – County Engineer 2. Safety a. All personnel on-site must complete WM required on-line safety training and obtain certificate of completion. b. Special guidelines related to coronavirus were distributed via email after the meeting. c. Required personal protective equipment includes hard hat, steel-toed boots, and safety vest. Equipment to be worn at all times for work performed in any area beyond the scale house. Those found to be without the required equipment will be told to leave the site. d. Contractors are responsible for the safety of their employees and must report any accidents or injuries immediately to WM onsite personnel. e. In case of site emergency, WM employees muster at shop. Contractor’s to designate a gathering place for their employees. 3. Environmental a. Mobile fuel truck to be used b. Earnhardt to maintain SPCC plan c. Use recovery system for equipment repairs to prevent spillage and onsite used fluid storage d. Notify WM immediately of any spill 4. Schedule a. Work Hours – Allowable onsite work hours are: M-Sat 6am-8pm; no Sunday activities allowed i. Earnhardt indicated they plan to work M-F 12 hours each day; Saturdays will only be used to makeup for rain delays b. Updated schedule to be provided by Earnhardt March 13, 2020 i. Based on schedule WM will order materials; pipe will be for immediate delivery to allow storm water installation 5. Site Access a. All deliveries of equipment and supplies will be made through the front gate; Earnhardt has been provided the gate code i. Carolina Cat to install parts box within next two weeks at site entrance b. All visitors, non-daily site personnel, to the site must sign-in at the scale house c. WM shop is off-limits to all contractor or CQA personnel. i. All Earnhardt employees to use their office trailer ii. BLE personnel will store all equipment in vehicle 6. Current Activities a. Earnhardt will complete clearing by next Wednesday, March 18 i. Additional small clearing area discussed near power line; clearing area will be expanded to give ESI open access to construction area ii. Currently burning debris; Earnhardt has burning permit and will complete within 30 days b. Blasting i. Drilling to begin Monday, March 16 to determine potential blast area based on resistance 1. BLE and Earnhardt to document based on field drill logs ii. Blast plan will be prepared and submitted to NCDEQ for information two weeks prior to blasting iii. All blast events to be coordinated with WM personnel to ensure notification to neighbors and County fire marshal iv. Earnhardt to install monitors in shop, at leachate tank, and powerline c. CQA i. Observe drilling beginning Monday, March 16 ii. Perform inventory of existing onsite liner materials and verify certs– GCL enclosed in liner for protection iii. Obtain extensive samples for proctors iv. Provide list of submittals to Earnhardt 1. Submittals to be provided to both BLE and Promus for review v. Provide daily reports to Rob Witcher, Mark LeGrand, Josh Earnhardt and Susan Harrison. vi. Obtain approval from Promus to use density gauge that doesn’t require isolation storage vii. Subgrade must be inspected by BLE geologist prior to placement of structural fill; minimum 72-hour notice 7. Design Clarification a. Primary and secondary leachate lines are slightly off as located by control points. i. Per Rob Witcher, place both lines in low point along the cell; ensure as-built correctly shows location b. Wells & Piezometers – all piezometers have been abandoned within the work area; wells should be clearly marked c. Piping – all piping should be debeaded to allow for camera to move smoothly d. Liner tie-in – uncovering of existing liner edge along Cells 1B, 2 and 3A should not be performed until immediately before liner installation to ensure waste is not left uncovered. Maintenance of the tie-in area is the responsibility of Earnhardt. e. Rock - as clean rock is removed following blasting, it can be placed adjacent to the onsite crusher rather than in soil stockpile. f. Subgrade surface – specification for subgrade surface are 3” < rock protrusion whether cut or structural fill g. Survey – Earnhardt will use a drone to verify elevations in comparison to most recent aerial ID Task Name Duration Start Finish 1 Mobilization 2 days Mon 3/9/20 Tue 3/10/20 2 Clearing and Grubbing 7 days Mon 3/9/20 Tue 3/17/20 3 Stripping 6 days Mon 3/16/20 Mon 3/23/20 4 Rock Test Drilling 5 days Mon 3/16/20 Fri 3/20/20 5 Rock and Soil Excavation 40 days Wed 3/18/20 Tue 5/12/20 6 Leak Detection Corridor 5 days Wed 5/13/20 Tue 5/19/20 7 Liner Installation 20 days Wed 5/20/20 Tue 6/16/20 8 Protective Cover 15 days Wed 6/17/20 Tue 7/7/20 9 Leachate Collection System 10 days Wed 7/8/20 Tue 7/21/20 10 Access Road 5 days Wed 7/22/20 Tue 7/28/20 11 Final Dress Up and Seeding 4 days Wed 7/29/20 Mon 8/3/20 B M E B M E B M E B M E B M E B March April May June July August Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Progress Deadline Page 1 Project: schedule 03-13-20Date: Fri 3/13/20 GREAT OAK LANDFILL COVER PAGE1CELL 3B, 4, AND 5 CONSTRUCTIONGREAT OAK LANDFILLNCDEQ PERMIT #: 7607-MSWLF-20153597 OLD CEDAR FALLS ROADRANDLEMAN, NORTH CAROLINA 27317REVDESCRIPTIONDATEDRA. BYROBWITCHERDate:Last Saved By:3/5/2020 2:46 PMFile Path:M:\DROPBOX (PROMUS ENGINEERING)\PROJECTS-ACTIVE\190173-WMGO-CELL-3B-4-5-DESIGN\DRAWINGS\1-COVER-PAGE.DWGPROJECT NO.: 190173DES. BYAPPR. BYMLA B C D E F G H I J K L M N O P Q R S T U V 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 A B C D E F G H I J K L M N O P Q R S T U V 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 W W PREPARED FOR:PREPARED BY:1200 MOUNTAIN CREEK RD., SUITE 102CHATTANOOGA, TENNESSEE 37405Phone: (888) 811-9066NORTH CAROLINA ENGINEERING FIRM # P-1841WASTE MANAGEMENT OF CAROLINAS, INC.A11-27-2019CRWCRWDRAFT - OWNER REVIEWSHEET NUMBERMLB12-05-2019CRWCRWISSUED FOR BIDML003-05-2020CRWCRWISSUED FOR CONSTRUCTIONVICINITY MAP SITE LOCATION MAP SITE SITE RANDOLPH COUNTY PREPARED FOR: WASTE MANAGEMENT OF CAROLINAS, INC. OWNER CONTACT: MS. SUSAN HARRISON 1047 HIGHWAY CHURCH ROAD ELGIN, SOUTH CAROLINA 29045 (678) 436-2719 PLANS PREPARED BY: CONSTRUCTION DRAWINGS FOR CELLS 3B, 4, & 5 AND RELATED WORK GREAT OAK LANDFILL 3597 OLD CEDAR FALLS ROAD RANDLEMAN, NORTH CAROLINA 27317 SITE ENTRANCE AT: N 35° 44" 38" (35.743809°) W 79° 44' 32" (-79.742578°) PROJECT NUMBER: 190173 1200 MOUNTAIN CREEK RD., SUITE 102 CHATTANOOGA, TENNESSEE 37405 Phone: (888) 811-9066 DRAWING SHEETS Sheet Number Sheet Title 1 COVER PAGE 2 EXISTING SITE CONDITIONS 3 BASEGRADE PLAN 4 PROTECTIVE COVER PLAN 5 THICKNESS CERTIFICATION POINTS 6 CONSTRUCTION DETAILS I 7 CONSTRUCTION DETAILS II ROWROWROWROWROWROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROWROWROWROWROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROW ROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROW ROWROW ROW ROW ROW ROW ROW ROW ROW ROW ROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWOW-10 PZ-25 PZ-12 PZ-14 PZ-13 PZ-17S PZ-17D PZ-10SPZ-10D PZ-21 PZ-8 PZ-9S PZ-9D PZ-6 PZ-3 PZ-2 PZ-5 PZ-4 PZ-16 PZ-15 PZ-53 PZ-57SPZ-57D PZ-56 PZ-54 PZ-55 PZ-43 MW-1 MW-2 MW-3 MW-4 MW-5 MW-6 MMW-1 MMW-2 MMW-3MMW-4 PZ-63 OW-5 PZ-42 PZ-49 PZ-7 DUKE ENERGY RIGHT-OF-WAY EXISTING CELL 1B 7.3 ACRES EXISTING CELL 1A 8.1 ACRES EXISTING CELL 2 10.0 ACRES EXISTING CELL 3A 8.2 ACRES FUTURE CELLS 6 &7 9.8 ACRES EXISITNG PERIMETER ACCESS ROAD EXISITNG SEDIMENT POND #1 EXISITNG MAINTENANCE BUILDING EXISITNG LEACHATE STORAGE TANK EXISITNG SEDIMENT POND #2 PROPOSED CELLS 3B, 4, AND 5 LINED AREA = 12.7 ACRES APPROXIMATE LIMIT OF DISTURBANCE EXISTING SOIL STOCKPILE, BORROW AND SCREENING AREA 140' DUKE POWER RIGHT-OF-WAY PERMITTED LIMIT OF WASTE PROPERTY BOUNDARY MATERIALS AND EQUIPMENT STAGING AREA EXISTING SCALE HOUSE AND SCALES 200' WASTE BUFFER EXISTING SITE CONDITIONS2 0 100 200 400200 CELL 3B, 4, AND 5 CONSTRUCTIONGREAT OAK LANDFILLNCDEQ PERMIT #: 7607-MSWLF-20153597 OLD CEDAR FALLS ROADRANDLEMAN, NORTH CAROLINA 27317REVDESCRIPTIONDATEDRA. BYROBWITCHERDate:Last Saved By:3/5/2020 2:56 PMFile Path:M:\DROPBOX (PROMUS ENGINEERING)\PROJECTS-ACTIVE\190173-WMGO-CELL-3B-4-5-DESIGN\DRAWINGS\2-EXISTING-SITE-CONDITIONS.DWGPROJECT NO.: 190173DES. BYAPPR. BYMLA B C D E F G H I J K L M N O P Q R S T U V 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 A B C D E F G H I J K L M N O P Q R S T U V 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 W W PREPARED FOR:PREPARED BY:1200 MOUNTAIN CREEK RD., SUITE 102CHATTANOOGA, TENNESSEE 37405Phone: (888) 811-9066NORTH CAROLINA ENGINEERING FIRM # P-1841WASTE MANAGEMENT OF CAROLINAS, INC.A11-27-2019CRWCRWDRAFT - OWNER REVIEWSHEET NUMBERMLB12-05-2019CRWCRWISSUED FOR BIDML003-05-2020CRWCRWISSUED FOR CONSTRUCTIONLEGEND PROPERTY LINE PHASE 1 PERMITTED LIMIT OF WASTE CELL LIMITS 200' WASTE BUFFER EXISTING AERIAL TOPO SURVEY 10' CONTOUR EXISTING AERIAL TOPO SURVEY 2' CONTOUR EXISTING PIEZOMETER EXISTING PIEZOMETER EXISTING GROUNDWATER MONITORING WELL EXISTING METHANE MONITORING WELL APPROXIMATE LIMIT OF DISTURBANCE DUKE ENERGY RIGHT-OF-WAY NOTES/REFERENCES: 1.EXISTING TOPOGRAPHY SHOWN HERE IS REPRESENTATIVE OF SITE CONDITIONS AT TIME OF AREAL TOPOGRAPHIC SURVEY PREPARED BY SOUTHERN RESOURCES MAPPING, DATED JANUARY 5, 2020. IT IS THE CONTRACTORS RESPONSIBILITY TO EVALUATE CURRENT CONDITIONS AS THEY RELATE TO THIS WORK. 2.PROPERTY BOUNDARY, WASTE BUFFER, PHASE 1 PERMITTED LIMIT OF WASTE OBTAINED FROM FACILITY PLAN DRAWINGS PREPARED BY S&ME, DATED FEBRUARY 2015. 3.PIEZOMETER LOCATIONS AND SOIL TEST BORING LOCATIONS OBTAINED FROM FACILITY PLAN DRAWINGS PREPARED BY S&ME, DATED FEBRUARY 2015. 4.GROUNDWATER MONITORING WELL AND METHANE MONITORING PROBE LOCATIONS OBTAINED FROM OWNER DECEMBER 2019. 5.THE CONTRACTOR IS SOLELY RESPONSIBLE FOR SITE SAFETY ASSOCIATED WITH THE WORK UNDER THIS CONTRACT AND FOR COMPLIANCE WITH ALL FEDERAL, STATE AND LOCAL HEALTH AND SAFETY LAWS, CODES, REGULATION, AND ORDINANCES INCLUDING BUT NOT LIMITED TO THOSE CURRENTLY MANDATED BY THE OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA) MMW-1 PZ-51 OW-1 MW-4 SURVEY LEGEND AERIAL SURVEY NOTES: 1.THIS MAP WAS COMPILED BY SOUTHERN RESOURCES MAPPING USING PHOTOGRAMMETRIC METHODS. CONTOURS PORTRAYED AS DASHED OR BROKEN LINES REPRESENT AREAS OF DENSE VEGETATION AND SHOULD BE CONSIDERED APPROXIMATE. THIS MAP HAS NOT BEEN FIELD VERIFIED. PRIOR TO USE AS A BASIS FOR DESIGN OR CONSTRUCTION, IT SHOULD BE FIELD VERIFIED. 2.BUILDINGS ARE SHOWN AS ROOFLINE ONLY. 3.THE PROPERTY LINES INDICATED ON THIS MAP WERE PROVIDED BY GREAT OAK. SOUTHERN RESOURCES MAPPING ASSUMES NO RESPONSIBILITY FOR THE ACCURACY OF THE PROPERTY LINES REPRESENTED HEREON. 4.THIS IS NOT A BOUNDARY SURVEY. APPARENT PROPERTY CORNERS ARE SHOWN FOR ORIENTATION ONLY. BOUNDARY DATA SHOWN IS FROM PREVIOUS SURVEY REFERENCED HEREON. 5.THE HORIZONTAL COORDINATES ARE BASED ON STATE PLANE COORDINATE SYSTEM NORTH CAROLINA ZONE, NAD83, FEET. THE VERTICAL DATUM IS BASED ON NAVD88, FEET. 6.GROUND CONTROL FOR AERIAL MAPPING SUPPLIED BY: CHARLIE MORGAN SURVEYING 7.BENCHMARKS AND CONTROL WERE ESTABLISHED BY: CHARLIE MORGAN SURVEYING ROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROW>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>> 610 620 620 670 67 0 680680 690 690700700710710710710710720720730620630640650 650650660 6606606706806907006306406503:1 3:13:13:13:13:13:1 3:1 VARIE S VARIE SVARIES VARI E S VARI E S VARIES 3:13:1TIE-IN TO E X I S T I N G C E L L 3 A 6 2NORTH PERIMETER BERMPERIMETER TIE-IN TO EXISTING CELLS68WEST PERIMETER BERM 6566ACCESS ROAD CULVERT #1 185 LF, 24" Ø DUAL-WALL CPP WITH PRECAST HEADWALL INV. IN: 695.9 INV. OUT: 675.6 CULVERT #2 120 LF, 36" Ø DUAL-WALL CPP WITH PRECAST HEADWALL INV. IN: 612.9 INV. OUT: 601.3 PERMANENT VEGETATION DOUBLE-SIDED EROSION CONTROL MATTING PERMANENT VEGETATION 6 10 6 10 RIPRAP OUTLET PROTECTION6 7 LDS CLEANOUT RISER DUKE ENERGY RIGHT-OF-WAY LINER SYSTEM6 1 LEACHATE SYSTEM CORRIDOR7 1 RIPRAP OUTLET PROTECTION 6 7 STORMWATER DIVERSION BERM7 3 7 2 6 9 7 5 LDS CLEANOUT RISER7 2 ROCK CHECK DAM 6 9 CONTRACTOR SHALL CONSTRUCT SMOOTH TRANSITION BETWEEN EXISTING AND PROPOSED DITCHES BASEGRADE PLAN3 0 25 50 10050 CELL 3B, 4, AND 5 CONSTRUCTIONGREAT OAK LANDFILLNCDEQ PERMIT #: 7607-MSWLF-20153597 OLD CEDAR FALLS ROADRANDLEMAN, NORTH CAROLINA 27317REVDESCRIPTIONDATEDRA. BYROBWITCHERDate:Last Saved By:3/5/2020 3:48 PMFile Path:M:\DROPBOX (PROMUS ENGINEERING)\PROJECTS-ACTIVE\190173-WMGO-CELL-3B-4-5-DESIGN\DRAWINGS\3-SUBGRADE-PLAN.DWGPROJECT NO.: 190173DES. BYAPPR. BYMLA B C D E F G H I J K L M N O P Q R S T U V 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 A B C D E F G H I J K L M N O P Q R S T U V 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 W W PREPARED FOR:PREPARED BY:1200 MOUNTAIN CREEK RD., SUITE 102CHATTANOOGA, TENNESSEE 37405Phone: (888) 811-9066NORTH CAROLINA ENGINEERING FIRM # P-1841WASTE MANAGEMENT OF CAROLINAS, INC.A11-27-2019CRWCRWDRAFT - OWNER REVIEWSHEET NUMBERMLB12-05-2019CRWCRWISSUED FOR BIDML003-05-2020CRWCRWISSUED FOR CONSTRUCTIONLEGEND LIMIT OF LINER DIVERSION BERM PROPOSED 10-FT SUBGRADE CONTOUR PROPOSED 2-FT SUBGRADE CONTOUR LEACHATE DETECTION SYSTEM PIPING CULVERT SLOPE INDICATOR PERMANENT VEGETATION DOUBLE-SIDED EROSION MATTING GRAVEL PAVING RIPRAP POTENTIAL BEDROCK EXCAVATION AREA 550 3:1 >> NOTES/REFERENCES: 1.EXISTING TOPOGRAPHY SHOWN HERE IS REPRESENTATIVE OF SITE CONDITIONS AT TIME OF AREAL TOPOGRAPHIC SURVERY PREPARED BY SOUTHERN RESOURCES MAPPING, DATED JANUARY 6, 2019. EXISTING TOPOGRAPHY IN AND AROUND EXISITNG CELL 3A WAS OBTAINED FROM THE CONSTRUCTION PLANS FOR CELL 3A PREPARED BY SCS ENGINEERS, DATED NOVEMBER 2018. IT IS THE CONTRACTORS RESPONSIBILITY TO EVALUATE CURRENT CONDITIONS AS THEY RELATE TO THIS WORK. 2.PROPERTY BOUNDARY, WASTE BUFFER, PHASE 1 PERMITTED LIMIT OF WASTE OBTAINED FROM FACILITY PLAN DRAWINGS PREPARED BY S&ME, DATED FEBRUARY 2015. 3.THE CONTRACTOR IS SOLELY RESPONSIBLE FOR SITE SAFETY ASSOCIATED WITH THE WORK UNDER THIS CONTRACT AND FOR COMPLIANCE WITH ALL FEDERAL, STATE AND LOCAL HEALTH AND SAFETY LAWS, CODES, REGULATION, AND ORDINANCES INCLUDING BUT NOT LIMITED TO THOSE CURRENTLY MANDATED BY THE OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA) 4.PERMITTED BASEGRADE CONTOURS WERE OBTAINED FROM ENGINEERING PLANS PREPARED BY S&ME, DATED FEBRUARY 2015. 5.BASEGRADE CONTOURS REPRESENT TOP OF STRUCTURAL SOIL FILL OR EXCAVATION. IF BEDROCK IS ENCOUNTERED DURING EXCAVATION OF OVERBURDEN, CONTRACTOR SHALL REMOVE MATERIAL TO A DEPTH OF FOUR (4) FEET BELOW DESIGN BASEGRADE ELEVATION SHOWN HEREIN AND REPLACE WITH STRUCTURAL SOIL FILL. 6.EROSION AND SEDIMENT CONTROL MEASURES SHALL BE INSTALLED IN ACCORDANCE WITH EROSION AND SEDIMENT CONTROL PLAN (ESPC) PRIOR TO ANY LAND DISTURBANCE. REFER TO DRAWING #3 FOR E&S CONTROLS. 7.CONTRACTOR IS RESPONSIBLE FOR MANAGING ALL LIQUIDS (LEACHATE AND STORMWATER) ALONG EXISTING LINER TIE-INS. TIE-IN SHALL NOT BE EXCAVATED EARLIER IN PROJECT THAN NECESSARY. 610 620 620 670 67 0 680680 690 690700700710710710710710720720730620630640650 650650660 6606606706806907006306406503:1 3:13:13:13:13:13:1 3:1 VARIE S VARIE SVARIES VARI E S VARI E S VARIES 3:13:13:1 VARIE S VARIE SVARIES VARI E S VARI E S VARIES LCP LCP LCP LCP LCP LCP LCP LCP LCP LCP LCP LCP LCP LCP LCP LCP LCP LCP LCP LCP LCP LCP LCP LCP LCP LCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCPLCP63064064065065 0 65065066066 0 660660670680690700TIE-IN TO EXI S T I N G C E L L 3 A 6 2NORTH PERIMETER BERMPERIMETER TIE-IN TO EXISTING CELLS68WEST PERIMETER BERM 6566E.O.L. E.O.L. E.O.L. E.O.L. E.O.L. E.O.L. SOLID CLEANOUT RISERS SOLID CLEANOUT RISERS SOLID CLEANOUT RISERS LEACHATE SYSTEM CORRIDOR7 1 7 2 7 2 7 2 EDGE OF LINER MARKER AT 100' C/C AROUND 2 CELL EDGES DUKE ENERGY RIGHT-OF-WAY ROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWROWE.O.L. E.O.L. E.O.L. E.O.L. E.O.L.E.O.L.E.O.L. E.O.L. E.O.L. E.O.L. E.O.L.PROTECTIVE COVER PLAN4CELL 3B, 4, AND 5 CONSTRUCTIONGREAT OAK LANDFILLNCDEQ PERMIT #: 7607-MSWLF-20153597 OLD CEDAR FALLS ROADRANDLEMAN, NORTH CAROLINA 27317REVDESCRIPTIONDATEDRA. BYROBWITCHERDate:Last Saved By:3/5/2020 2:56 PMFile Path:M:\DROPBOX (PROMUS ENGINEERING)\PROJECTS-ACTIVE\190173-WMGO-CELL-3B-4-5-DESIGN\DRAWINGS\4 PROTECTIVE COVER PLAN.DWGPROJECT NO.: 190173DES. BYAPPR. BYMLA B C D E F G H I J K L M N O P Q R S T U V 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 A B C D E F G H I J K L M N O P Q R S T U V 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 W W PREPARED FOR:PREPARED BY:1200 MOUNTAIN CREEK RD., SUITE 102CHATTANOOGA, TENNESSEE 37405Phone: (888) 811-9066NORTH CAROLINA ENGINEERING FIRM # P-1841WASTE MANAGEMENT OF CAROLINAS, INC.A11-27-2019CRWCRWDRAFT - OWNER REVIEWSHEET NUMBERMLB12-05-2019CRWCRWISSUED FOR BIDML003-05-2020CRWCRWISSUED FOR CONSTRUCTIONLEGEND LIMIT OF LINER PROPOSED 10-FT SUBGRADE CONTOUR PROPOSED 2-FT SUBGRADE CONTOUR SLOPE INDICATOR LEACHATE COLLECTION PIPE (PERFORATED) LCP CLEANOUT (SOLID) LINER EDGE MARKER 550 3:1 LCP LCP E.O.L. 0 25 50 10050 NOTES/REFERENCES: 1.EXISTING TOPOGRAPHY SHOWN HERE IS REPRESENTATIVE OF SITE CONDITIONS AT TIME OF AREAL TOPOGRAPHIC SURVERY PREPARED BY SOUTHERN RESOURCES MAPPING, DATED JANUARY 5, 2020. IT IS THE CONTRACTORS RESPONSIBILITY TO EVALUATE CURRENT CONDITIONS AS THEY RELATE TO THIS WORK. 2.PROPERTY BOUNDARY, WASTE BUFFER, PHASE 1 PERMITTED LIMIT OF WASTE OBTAINED FROM FACILITY PLAN DRAWINGS PREPARED BY S&ME, DATED FEBRUARY 2015. 3.THE CONTRACTOR IS SOLELY RESPONSIBLE FOR SITE SAFETY ASSOCIATED WITH THE WORK UNDER THIS CONTRACT AND FOR COMPLIANCE WITH ALL FEDERAL, STATE AND LOCAL HEALTH AND SAFETY LAWS, CODES, REGULATION, AND ORDINANCES INCLUDING BUT NOT LIMITED TO THOSE CURRENTLY MANDATED BY THE OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA) 4.PERMITTED BASEGRADE CONTOURS WERE OBTAINED FROM ENGINEERING PLANS PREPARED BY S&ME, DATED FEBRUARY 2015. 5.BASEGRADE CONTOURS REPRESENT TOP OF STRUCTURAL SOIL FILL OR EXCAVATION. IF BEDROCK IS ENCOUNTERED DURING EXCAVATION OF OVERBURDEN, CONTRACTOR SHALL REMOVE MATERIAL TO A DEPTH OF FOUR (4) FEET BELOW DESIGN BASEGRADE ELEVATION SHOWN HEREIN AND REPLACE WITH STRUCTURAL SOIL FILL. 6.EROSION AND SEDIMENT CONTROL MEASURES SHALL BE INSTALLED IN ACCORDANCE WITH EROSION AND SEDIMENT CONTROL PLAN (ESPC) PRIOR TO ANY LAND DISTURBANCE. REFER TO DRAWING #3 FOR E&S CONTROLS. 7.CONTRACTOR IS RESPONSIBLE FOR MANAGING ALL LIQUIDS (LEACHATE AND STORMWATER) ALONG EXISTING LINER TIE-INS. TIE-IN SHALL NOT BE EXCAVATED EARLIER IN PROJECT THAN NECESSARY. 710710720720730620630640650 650650660 6606606706806907006306406503:1 VARIE S VARIE SVARIES VARI E S VARI E S VARIES 3:13:11000 1001 1002 1003 1004 1005 1006 1007 1008 1009 1010 1011 1012 1013 1014 1015 1016 1017 1018 1019 1020 1021 1022 1023 1024 1025 1026 1027 1028 1029 1030 1031 1032 1033 1034 1035 1036 1037 1038 1039 1040 1041 1042 1043 1044 1045 1046 1047 1048 1049 1050 1051 1052 1053 1054 1055 1056 1057 1058 1059 1060 1061 1062 1063 1064 1065 1066 1067 1068 1069 1070 1071 1072 1073 1074 1075 1076 1077 1078 1079 1080 1081 1082 1083 1084 1085 1086 1087 1088 10891090 1091 1092 1093 1094 1095 1096 1097 1098 1099 1100 1101 1102 1103 1104 1105 1106 1107 1108 1109 1110 1111 1112 1113 1114 1115 1116 1117 1118 1119 1120 1121 1122 1123 1124 1125 1126 1127 1128 1129 1130 1131 1132 1133 1134 1135 1136 1137 1138 1139 1140 1141 1142 1143 1144 1145 1146 1147 1148 1149 1150 1151 1152 1153 1154 1155 1156 1157 1158 1159 1160 1161 1162 1163 1164 1165 1166 1167 1168 1169 1170 1171 1172 1173 1174 1175 1176 1177 1178 1179 1180 1181 1182 1183 11841185 1186 1187 1188 1189 1190 1191 1192 1193 1194 1195 1196 1197 1198 1199 1200 1201 1202 1203 1204 1205 1206 1207 1208 1209 12101211 1212 1213 1214 1215 THICKNESS CERTIFICATIONPOINTS5CELL 3B, 4, AND 5 CONSTRUCTIONGREAT OAK LANDFILLNCDEQ PERMIT #: 7607-MSWLF-20153597 OLD CEDAR FALLS ROADRANDLEMAN, NORTH CAROLINA 27317REVDESCRIPTIONDATEDRA. BYROBWITCHERDate:Last Saved By:3/5/2020 2:55 PMFile Path:M:\DROPBOX (PROMUS ENGINEERING)\PROJECTS-ACTIVE\190173-WMGO-CELL-3B-4-5-DESIGN\DRAWINGS\5-THICKNESS-CERTIFICATION-POINTS.DWGPROJECT NO.: 190173DES. BYAPPR. BYMLA B C D E F G H I J K L M N O P Q R S T U V 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 A B C D E F G H I J K L M N O P Q R S T U V 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 W W PREPARED FOR:PREPARED BY:1200 MOUNTAIN CREEK RD., SUITE 102CHATTANOOGA, TENNESSEE 37405Phone: (888) 811-9066NORTH CAROLINA ENGINEERING FIRM # P-1841WASTE MANAGEMENT OF CAROLINAS, INC.A11-27-2019CRWCRWDRAFT - OWNER REVIEWSHEET NUMBERMLB12-05-2019CRWCRWISSUED FOR BIDML003-05-2020CRWCRWISSUED FOR CONSTRUCTIONLEGEND PHASE 1 PERMITTED LIMIT OF WASTE LIMIT OF LINER PROPOSED 10-FT BASEGRADE CONTOUR PROPOSED 2-FT BASEGRADE CONTOUR SLOPE INDICATOR THICKNESS CERTIFICATION POINT 550 3:1 1000 CERTIFICATION NOTES: 1.SURVEYOR SHALL "STACK" POINTS (i.e. USE SAME NORTHING AND EASTING) FOR THICKNESS VERIFICATION OF LINER SYSTEM COMPONENTS. 2.HORIZONTAL TOLERANCE FOR ALL POINTS SHALL BE 0.2 FEET. 3.VERTICAL TOLERANCES SHALL BE AS FOLLOWS: ·BASEGRADE:WITHIN ± 0.08 FT OF DESIGN ·PROTECTIVE COVER: MIN. THICKNESS MEASURED FROM AS-BUILT BASEGRADE TO + 0.2 FT SCALE IN FEET 050 50 100 24" PROTECTIVE COVER (SOIL) SUBGRADE OR STRUCTURAL FILL (NOTE 1) LEACHATE COLLECTION SYSTEM (LCS) GEOCOMPOSITE DRAINAGE LAYER PRIMARY 60-MIL TEXTURED HDPE GEOMEMBRANE LEAK DETECTION SYSTEM (LDS) GEOCOMPOSITE DRAINAGE LAYER SECONDARY 60-MIL TEXTURED HDPE GEOMEMBRANE GEOSYNTHETIC CLAY LINER (GCL) NOTES: 1.STRUCTURAL FILL SHALL CONSIST OF BORROW SOILS CONSISTENT WITH SPECIFICATION SECTION 31 2323.13. 2.GEOSYNTHETIC COMPONENTS ARE EXAGGERATED FOR CLARITY. ~ WASTE ~ REMOVE EXISTING ANCHOR TRENCH COMPONENTS EXTRUSION WELD EXISTING LINERS TO PROPOSED LINERS OVERLAP GEOCOMPOSITES AND GCL 12" MIN. 6 1LINER SYSTEM EXISTING CELL 1B / 2 PROPOSED CELL 3B REMOVE EXISTING ANCHOR TRENCH COMPONENTS EXISTING CELL 3A PROPOSED CELL 3B VARIES 3:1 MAX EXISTING GEOMEMBRANE RAIN FLAP CONTRACTOR TO CUT AND REMOVE FLAP AFTER COMPLETION OF CELL CONSTRUCTION DISPOSE OF FLAP IN ACTIVE LANDFILL ~ WASTE ~ EXISTING PROTECTIVE COVER 6 1 EXTRUSION WELD EXISTING LINERS TO PROPOSED LINERS OVERLAP GEOCOMPOSITES AND GCL 12" MIN. LINER SYSTEM #57 STONE OR ENGINEER-APPROVED EQUIVALENT STRUCTURAL FILL COMPACTED TO MINIMUM 95% MAXIMUM DRY DENSITY AS DETERMINED BY ASTM D-698 DUAL-WALL CORRUGATED PLASTIC PIPE NATIVE MATERIAL OR STRUCTURAL FILL NOTES: 1.ALL PIPE SHALL BE INSTALLED IN ACCORDANCE WITH ASTM D-2321, "STANDARD PRACTICE FOR UNDERGROUND INSTALLATION OF THERMOPLASTIC PIPE FOR SEWERS AND OTHER GRAVITY FLOW APPLICATIONS", LATEST VERSION. 2.MEASURES SHALL BE TAKEN TO PREVENT MIGRATION OF NATIVE FINES INTO BACKFILL MATERIAL. 3.WHERE THE TRENCH BOTTOM IS UNSUITABLE, THE CONTRACTOR SHALL BE TO A DEPTH AS DETERMINED BY CQA ENGINEER AND REPLACE WITH SUITABLE MATERIAL. 4.IN NO CASE SHALL CONSTRUCTION EQUIPMENT BE ALLOWED TO CROSS OVER THE PIPE WITH LESS THAN 3' OF COMPACTED SOIL COVER OVER THE CROWN OF THE PIPE. IT MAY BE NECESSARY FOR THE CONTRACTOR TO PLACE A TEMPORARY COMPACTED SOIL RAMP OVER THE PIPE DURING CONSTRUCTION TO ACHIEVE THE MINIMUM COVER DEPTH. 5.ANY DAMAGE TO THE PIPE AS A RESULT OF IMPROPER INSTALLATION OR SOIL COVER SHALL BE REPAIRED BY THE CONTRACTOR AT NO ADDITIONAL COST TO THE OWNER. 6" DEPTH VARIES 3' MIN IN ROADWAY 6" 12" (TYP) 3' 2' 2' 3:1 3:1 SUBGRADE PROTECTIVE COVER MATERIAL 4'E.O.L.3:1 4' DAYLIGHT TO EXISTING 10' 6' EDGE OF LINER MARKER EVERY 100' ALONG BERM 4' BEHIND ANCHOR TRENCH ANCHOR TRENCH 6 3 4' 10' 3' 2' 2' 3:1 SLO P E V A R I E S 6' SUBGRADE PROTECTIVE COVER MATERIAL 3:1 DAYLIGHT TO EXISTING ANCHOR TRENCH 6 3 4'E.O.L.EDGE OF LINER MARKER EVERY 100' ALONG BERM 4' BEHIND ANCHOR TRENCH VARIES SEE PLAN VARIES SEE PLANCULVERT 18" THICK RIPRAP D50 > 9" 3' 2' TOE WALL DISCHARGE CONDUIT END OF CULVERT 8-OZ. NONWOVEN GEOTEXTILE 18" THICK RIPRAP D50 > 9" 8-OZ. NONWOVEN GEOTEXTILE 18" THICK RIPRAP D50 > 9" VARIES 6 1 3' CLEAN COMPACTED SOIL BACKFILL2' 3' LINER SYSTEM EXTEND SECONDARY GEOMEMBRANE AND LCS GEOCOMPOSITE INTO ANCHOR TRENCH EDGE OF LINER MARKER EVERY 100' ALONG BERM 4' BEHIND ANCHOR TRENCH7 6 TERMINATE LDS GEOCOMPOSITE AND GCL EXTRUSION WELD PRIMARY LINER TO SECONDARY LINER SACRIFICIAL STRIP OF PROTECTIVE GEOCOMPOSITE, + 4' WIDE NOTES: 1.SINGLE-SIDED MATTING SHALL BE NORTH AMERICAN GREEN S75, OR ENGINEER-APPROVED EQUIVALENT. 2.SLOPE SURFACE SHALL BE FREE OF ROCKS, CLODS, STICKS AND GRASS. MATS/BLANKETS SHALL HAVE GOOD SOIL CONTACT. 3.LAY BLANKETS LOOSELY AND STAKE OR STAPLE TO MAINTAIN DIRECT CONTACT WITH THE SOIL. DO NOT STRETCH. 4.INSTALL PER MANUFACTURER'S RECOMMENDATIONS.2h:1V SLOPE MAX(UNLESS MSE)6.5' BERM TAMP SOIL O V E R M A T / B L A N K E T 4.5' MATS/BLANKETS SHALL BE INSTALLED VERTICALLY UP/DOWN SLOPE. 2 TO 3 INCH OVERLAP 1 FT. 6"x6" ANCHOR TRENCH 48" BERM 2 ft. OVERLAP IN SPLICE RIPRAP LINING MATTING LINING CONTRACTOR SHALL ANCHOR EROSION CONTROL MATTING IN ACCORDANCE WITH MANUFACTURER RECOMMENDATIONS TENSAR SC-250 VEGETATED CHANEL LINING, STAPLE PATTERN "D", OR APPROVED EQUIVALENT 3:1 3:1 8-OZ. NONWOVEN GEOTEXTILE RIPRAP D50 > 9" SEE DETAILS FOR DIMENSIONS 1.5' 6 6 6 5 SEE DETAILS FOR DIMENSIONS6 6 6 5 CONSTRUCTION DETAILS I6CELL 3B, 4, AND 5 CONSTRUCTIONGREAT OAK LANDFILLNCDEQ PERMIT #: 7607-MSWLF-20153597 OLD CEDAR FALLS ROADRANDLEMAN, NORTH CAROLINA 27317REVDESCRIPTIONDATEDRA. BYROBWITCHERDate:Last Saved By:2/13/2020 8:44 AMFile Path:M:\DROPBOX (PROMUS ENGINEERING)\PROJECTS-ACTIVE\190173-WMGO-CELL-3B-4-5-DESIGN\DRAWINGS\CONSTRUCTION-DETAILS-I.DWGPROJECT NO.: 190173DES. BYAPPR. BYMLA B C D E F G H I J K L M N O P Q R S T U V 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 A B C D E F G H I J K L M N O P Q R S T U V 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 W W PREPARED FOR:PREPARED BY:1200 MOUNTAIN CREEK RD., SUITE 102CHATTANOOGA, TENNESSEE 37405Phone: (888) 811-9066NORTH CAROLINA ENGINEERING FIRM # P-1841WASTE MANAGEMENT OF CAROLINAS, INC.A11-27-2019CRWCRWDRAFT - OWNER REVIEWSHEET NUMBERMLB12-05-2019CRWCRWISSUED FOR BIDML003-05-2020CRWCRWISSUED FOR CONSTRUCTIONLINER SYSTEM1 NTS6 PERIMETER TIE-IN TO EXISTING CELLS8 NTS6 TIE-IN TO EXISTING CELL 3A2 NTS6 CULVERT INSTALLATION10 NTS6 WEST PERIMETER BERM5 NTS6 NORTH PERIMETER BERM6 NTS6 RIPRAP OUTLET PROTECTION7 NTS6 ANCHOR TRENCH3 NTS6 EROSION CONTROL MATTING9 NTS6 DET-CHANNEL-LINING4 NTS6 NOTES/REFERENCES: 1.THE CONTRACTOR IS SOLELY RESPONSIBLE FOR SITE SAFETY ASSOCIATED WITH THE WORK UNDER THIS CONTRACT AND FOR COMPLIANCE WITH ALL FEDERAL, STATE AND LOCAL HEALTH AND SAFETY LAWS, CODES, REGULATION, AND ORDINANCES INCLUDING BUT NOT LIMITED TO THOSE CURRENTLY MANDATED BY THE OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA) 2.CONTRACTOR IS RESPONSIBLE FOR MANAGING ALL LIQUIDS (LEACHATE AND STORMWATER) ALONG EXISTING LINER TIE-INS. TIE-IN SHALL NOT BE EXCAVATED EARLIER IN PROJECT THAN NECESSARY. 8"-DIA. SDR 11 LDS HEADER PIPE (4" MIN. BEDDING AROUND PIPE) 8"-DIA. SDR 11 LCS HEADER PIPE (4" MIN. BEDDING AROUND PIPE) #57 DRAINAGE AGGREGATE FLOW FLOW 1:11:11: 1 1:16 1 7 8 7 8 1.5' GEOTEXTILE OVERLAP6" 1' 1' 2 LINER SYSTEM LCP SOLID CLEANOUT RISER LINER SYSTEM 3'±6 1 LDS SOLID CLEANOUT RISER RIPRAP D50 > 6" 8-OZ. NONWOVEN GEOTEXTILE 1. 5 : 1 1' 1.5' AT DITCH ℄ 0.5' 1.5:1 CROSS SECTION THROUGH ROCK CHECK DAM RIPRAP, D50 > 6" 8-OZ. NONWOVEN GEOTEXTILE 1.5' AT DITCH ℄ CHANNEL SIDESLOPE EXISTING W A S T E 3:1 DAILY / IN T E R M E D I A T E C O V E R 2' 2' MIN (1) 2:1 CLEAN COMPACTED STRUCTURAL FILL PERMANENT VEGETATION PERMANENT VEGETATION NOTES: 1.DIVERSION BERM SHALL BE MINIMUM 4' DEEP AT DOWNDRAIN PIPE INLET. MINIMUM TOP OF BERM ELEVATION AT INLET SHALL BE MAINTAINED UNTIL HEIGHT REACHES 2'.EDGE OF LINER - 4' OFFSET3' 3' ANCHOR TRENCH PRESSURE-TREATED 4" x 4" WOODEN POST POST SHALL BE PRIMED AND COATED WITH SAFETY YELLOW EXTERIOR PAINT BLACK LETTERING: "EDGE OF LINER" 4' 7 4 ANCHOR TRENCH 8" HDPE BLIND FLANGE WITH DI BACKUP RING AND SS HARDWARE 8" SDR 11 SOLID HDPE LCS CLEANOUT PIPE WELDED HDPE BOOT 8" SDR 11 SOLID HDPE LDS CLEANOUT PIPE * +3' HORIZONTAL SEPARATION BETWEEN CLEANOUT PIPES SOLID CLEANOUT RISERS3' + NOTES: 1.PREFABRICATED AND SPARK TESTED BOOT TO BE EXTRUSION WELDED TO HDPE PIPE AND PRIMARY LINER. 3' 24' 3'3:1 3:13:13:1 2%2% WOVEN GEOTEXTILE MEETING AASHTO M288-00 SEPARATION AND STABILIZATION, CLASS 1 - SOFT SUBGRADES ROAD TOPPING - 4" CRUSHER RUN, OR ENGINEER-APPROVED EQUIVALENT ROAD BASE - 6" AASHTO #2 STONE, OR ENGINEER-APPROVED EQUIVALENTDAYLIGHT TO EXISTING GROUND (CUT SCENARIO) FILL SLOPE TO EXISTING GROUND (FILL SCENARIO) NATIVE MATERIAL / STRUCTURAL FILL 8" Ø SDR 11 HDPE PIPE 58" Ø PERFORATIONS INVERT OF PIPE 90°'4"2"CONSTRUCTION DETAILS II7CELL 3B, 4, AND 5 CONSTRUCTIONGREAT OAK LANDFILLNCDEQ PERMIT #: 7607-MSWLF-20153597 OLD CEDAR FALLS ROADRANDLEMAN, NORTH CAROLINA 27317REVDESCRIPTIONDATEDRA. BYROBWITCHERDate:Last Saved By:2/13/2020 8:59 AMFile Path:M:\DROPBOX (PROMUS ENGINEERING)\PROJECTS-ACTIVE\190173-WMGO-CELL-3B-4-5-DESIGN\DRAWINGS\CONSTRUCTION DETAILS II.DWGPROJECT NO.: 190173DES. BYAPPR. BYMLA B C D E F G H I J K L M N O P Q R S T U V 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 A B C D E F G H I J K L M N O P Q R S T U V 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 W W PREPARED FOR:PREPARED BY:1200 MOUNTAIN CREEK RD., SUITE 102CHATTANOOGA, TENNESSEE 37405Phone: (888) 811-9066NORTH CAROLINA ENGINEERING FIRM # P-1841WASTE MANAGEMENT OF CAROLINAS, INC.A11-27-2019CRWCRWDRAFT - OWNER REVIEWSHEET NUMBERMLB12-05-2019CRWCRWISSUED FOR BIDML003-05-2020CRWCRWISSUED FOR CONSTRUCTIONLEACHATE SYSTEM CORRIDOR1 NTS7 SOLID CLEANOUT RISERS4 NTS7 RIPRAP CHECK DAM7 NTS7 DIVERSION BERM3 NTS7 EDGE OF LINER MARKER6 NTS7 SOLID CLEANOUT RISERS2 NTS7 ACCESS ROAD5 NTS7 NOTES/REFERENCES: 1.THE CONTRACTOR IS SOLELY RESPONSIBLE FOR SITE SAFETY ASSOCIATED WITH THE WORK UNDER THIS CONTRACT AND FOR COMPLIANCE WITH ALL FEDERAL, STATE AND LOCAL HEALTH AND SAFETY LAWS, CODES, REGULATION, AND ORDINANCES INCLUDING BUT NOT LIMITED TO THOSE CURRENTLY MANDATED BY THE OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA) 2.CONTRACTOR IS RESPONSIBLE FOR MANAGING ALL LIQUIDS (LEACHATE AND STORMWATER) ALONG EXISTING LINER TIE-INS. TIE-IN SHALL NOT BE EXCAVATED EARLIER IN PROJECT THAN NECESSARY. COLLECTION PIPE PERFORATIONS8 NTS7 NOTE: 1.CONTRACTOR SHALL DE-BEAD THE INTERIOR OF ALL LEAK DETECTION SYSTEM AND LEACHATE COLLECTION SYSTEM PIPING. From:Harrison, Susan To:Chao, Ming-tai; Kirchner, Chuck; Ritter, Christine Subject:[External] Great Oak Landfill - Cells 3B, 4 & 5 Date:Friday, March 13, 2020 12:38:44 PM Attachments:image002.png 2020-03-05_IFC-Drawings Cells 3B, 4, & 5.pdf schedule 03-13-20.pdf Pre-Construction Meeting Minutes 3-12-20 - rev1.docx CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to report.spam@nc.gov Good Friday Afternoon All, Now that the weather has cleared somewhat, we are beginning a new construction season at the Great Oak Landfill. We will be building the next three small cells, 3B, 4 & 5. Attached are the construction drawings for your information. Also attached is an aggressive construction schedule. In an effort to accelerate the construction, I hurriedly scheduled the pre-construction meeting and failed to extend an invitation to any of the DEQ officials. My apologies. The minutes of the meeting, held yesterday, are attached. As you can see, it was fairly routine in its content. While the cell area is simple, we do anticipate blasting to accelerate the excavation. The contractor is preparing a blasting plan which will be submitted to both Ming and Christine. Bunnell-Lammons, CQA consultant, has a Professional Geologist on standby to perform the necessary review and certification related to bedrock. Please let me know if you have any questions and again my apologies for the invitation oversight, Susan SUSAN B. HARRISON, PE Manager of Engineering South Atlantic Areasharri21@wm.com C: 678.436.2719 1047 Highway Church RoadElgin, SC 29045 Recycling is a good thing. Please recycle any printed emails.