HomeMy WebLinkAbout7904_CORR_20170901
September 1, 2017, Update Joyce Engineering Rockingham County – 7904 Page 1 September 2017
Reporting Period: August 19 – August 31, 2017 The work accomplished between August 19 and 31 is summarized below:
• Seeded northern slope, landfill entrance, and SB-2 (approximately 6 acres).
• Completed cleaning out SB-2, and installed E&S rock to armor the inlet areas.
• Began cleaning out SB-1.
• Repaired damage caused by August 11-15 rain events.
Northern Slopes Building diversion berm (extension of 720 bench) on August 21.
September 1, 2017, Update Joyce Engineering Rockingham County – 7904 Page 2 September 2017
Extending 760 bench.
Preparing northern slopes for seeding.
September 1, 2017, Update Joyce Engineering Rockingham County – 7904 Page 3 September 2017
Preparing northern slopes for seeding.
Slope drain installed on the extended 760 bench.
September 1, 2017, Update Joyce Engineering Rockingham County – 7904 Page 4 September 2017
Dry seeding on August 30. One trip with lime, one trip with fertilizer, one trip with broadcast
seeder pulling cultipacker.
Broadcasting lime on the slopes on August 30.
September 1, 2017, Update Joyce Engineering Rockingham County – 7904 Page 5 September 2017
Blowing straw mulch on the slopes on August 30.
Straw mulch.
September 1, 2017, Update Joyce Engineering Rockingham County – 7904 Page 6 September 2017
Tacking mulch on August 31 to help keep it on the slopes.
Sediment Basin No. 2 (North) Nearing completion of cleaning sediment from the North Sediment pond (SB-2). Sediment
placed back on the top of the landfill for use on working face.
September 1, 2017, Update Joyce Engineering Rockingham County – 7904 Page 7 September 2017
Sediment Basin No. 1 (South)
Cleaning sediment from the South Sediment pond (SB-1). Sediment placed back on the top of the landfill for use on working face.
SB-1 cleanout; filter rock replaced at the outfall.