HomeMy WebLinkAbout6036_MeckCompost_ApprovedApplic_27606_20170406Mecklenburg County Compost and Recycling Facility Solid Waste Compost Facility Permit Application 140 Valleydale Road Charlotte, NC September 2016 Mecklenburg County, North Carolina Mecklenburg County Compost and Recycling Facility 140 Valleydale Road Charlotte, North Carolina Signature page of applicant - Name of facility ____________________ _ I certify under penalty of law that this document and all attachments were prepared under my direction or supervision and that the information provided in this application is true, accurate, and complete to the best of my knowledge. I understand that North Carolina General Statute 130A-22 provides for administrative penalties of up to fifteen thousand dollars ($15,000.00) per day per each violation of the Solid Waste Management Rules. I further understand that the Solid Waste Management Rules may be revised or amended in the future and that the facility siting and operations of this solid waste management facility will be required to comply with all such revisions or amendments. Signature Print Name Date Title Business or organization name Mecklenburg County Compost and Recycling Facility 140 Valleydale Road Composting Permit Application 1 August 26, 2016 SOLID WASTE COMPOST FACILITY PERMIT APPLICATION SUBMITTAL Company Name:Mecklenburg County Site Name:Mecklenburg County Compost and Recycling Facility Site Address:140 Valleydale Road, Charlotte, NC Summary: This is an application submittal for the permitting of a new Type I facility. REQUIRED SUBMITTAL INFORMATION .1405 APPLICATION REQUIREMENTS FOR SOLID WASTE COMPOST FACILITIES (a) The following information is required for an application for a permit to construct and operate a proposed Type 1, or a Small Type 2 or 3 solid waste compost facility; unless the permitting requirements are exempted by Paragraph (g) of Rule .1402 of this Section: (a)(1) An aerial photograph or scaled drawing, where one inch is less than or equal to 400 feet, accurately showing the area within one-fourth mile of the proposed site' s boundaries with the following specifically identified: (A) Entire property owned or leased by the person proposing the facility; (B) Location of all homes, wells, industrial buildings, public or private utilities, roads, watercourses, dry runs, and other applicable information regarding the general topography within 500 feet of the proposed facility; and (C) Land use zoning of the proposed site. §An aerial exhibit of the facility can be found in Appendix VII as Figure 1. This figure shows the property boundaries of the facility as well as the area within one-fourth mile of the propertyboundary. §Figure 2 in Appendix VII includes an aerial exhibit that shows the location of all homes, wells, industrial buildings, utilities, roads, and other applicable information regarding the generaltopography within 500 feet of the proposed facility. §Figure 3 in Appendix VII includes the land use zoning (I-2 Heavy Industrial) and surrounding land use zoning. (a)(2) A letter from the unit of government having zoning jurisdiction over the site which states that the proposed use is allowed within the existing zoning, if any, and that any necessary zoning approval or permit has been obtained. §A zoning verification letter provided by the City of Charlotte Zoning Office is included in Appendix III (a)(3) An explanation of how the site complies with siting and design standards in Rule .1404 of this Section. §A detailed explanation documenting compliance with Rule .1404 is included in Appendix I. (a)(4) A detailed report indicating the following: 2 August 26, 2016 (A) Waste type(s), source and estimated quantity of the solid waste to be composted, including the source and expected quantity of any bulking agent or amendment (if applicable), any expected recycle of bulking agent or compost, and any seasonal variations in the solid waste type or quantity; and §The site is designed to accept up to 122,000 tons per year of commingled yard waste (brush, grass clippings and leaves) and vegetative land clearing debris. The source of these materials includes properties (residential and commercial) in Mecklenburg County and surrounding Counties. §Mecklenburg County may use this facility to process storm debris and vegetative material during inclement weather situations.The amount of material to be processed on site could exceed the design amount by as much as 100%. §The seasonal variation of waste quantity is insignificant; however, the variation in waste type isestimated to be 70% grass in the spring and 85% leaves in the fall. §Mecklenburg County may use bulking agents or amendments based on market conditions and material availability. (a)(4)(B) For facilities that utilize natural soils as a pad, a soil evaluation of the site conducted by a soil scientist down to a depth of four feet, or to bedrock or evidence of a seasonal high water table, to evaluate all chemical and physical soil properties and depth of the seasonal high water table. §Facility operations will be conducted on concrete pavement. Natural soil pads will not be used for the composting operations at this facility. (a)(5) Site plan at a scale where one inch is less than or equal to 100 feet to the inch that delineates the following: (A) Existing and proposed contours, at intervals appropriate to the topography; (B) Location and elevations of dikes, trenches, and other water control devices and structures for the diversion and controlled removal of surface water; (C) Designated setbacks and property lines; (D) Proposed utilities and structures; and (E) Areas for unloading, processing, active composting, curing, and storing of material. §The following plans are included in Appendix VII: o Figure 4 includes a Site plan showing setbacks, property lines, unloading, composting processand tree save areas. o Figure 5 includes a Grading plan showing existing and proposed contours at 1 foot intervals,permanent diversion ditches, and location of a wet detention pond. o Figure 6 includes a Utility plan showing proposed water, sanitary sewer, and storm sewer lines. 3 August 26, 2016 (a)(6) A description of the operation of the facility, which must include at a minimum: (A) Name, address and phone number for the person responsible for the operation of the facility; Solid Waste Director 2145 Suttle Avenue Charlotte, North Carolina 28208(980) 314-3863 (a)(6)(B) List of personnel required and the responsibilities of each position;Mecklenburg County will staff the facility with positions that are commensurate with duties that are required at the facility and are in conformance with the personnel regulations of Mecklenburg County.Typical positions may include the following: §Environmental Supervisor: Supervision of site personnel, marketing of materials, safety program,environmental compliance §Maintenance and Operations Supervisor: Responsible for day to day operations and maintenance. §Maintenance and Operations Specialist: Responsible for operating equipment (wheel loaders, tubgrinders, windrow turner, screening equipment, and trucks). §Senior Maintenance and Operations Technician: Responsible for servicing and repairing theequipment. §Maintenance and Operations Technician: Operation of light vehicles, environmental monitoring, site cleanliness §Cashier: Responsible for collecting fees and recording incoming and outgaining tonnages. (a)(6)(C) Operation plan for the facility; §The Operations and Maintenance Manual for the facility is included in Appendix VI (a)(6)(D) Special precautions or procedures for operating during wind, heavy rain, snow, freezing or other adverse conditions; §During inclement weather, facility operations will be modified to assure that the facility operates within the requirements of the Operating Permit. (a)(6)(E) A description of actions to be taken to minimize noise, vectors, air borne particulates, and odors; and §Noise – The facility will be located in an industrial zoned area. Staff will under normal operatingconditions position equipment to best minimize offsite noise. §Vectors – Vectors are rarely a problem for Type I compost facilities and historically have not been an issue for the existing Compost Central site on West Blvd. To ensure that vectors are minimized, putrescible garbage generated by customers and staff will be stored in closed containers andremoved from the site on a regular basis. In addition, yard waste will be ground and placed into windrows in a timely manner, as described in the Operations and Maintenance Manual included as Appendix VI. §Airborne Particles – To minimize airborne particles, moisture may be incorporated into materials when needed. 4 August 26, 2016 §Odors – To minimize odors, incoming yard waste will ground in a timely manner under normal operating conditions in accordance with the operations manual. Ground yard waste will either beplaced in a windrow or removed from the site in a timely manner under normal operatingconditions. Material will be turned as needed, ensuring aerobic conditions prevail. (a)(6)(F) A description of the ultimate use for the finished compost, method for removal from the site, and a contingency plan for disposal or alternative usage of residues or finished compost that cannot be used in the expected manner due to poor quality or change in market conditions. §The finished compost will be sold primarily to residents, landscapers, and landscape supply companies for use as a soil amendment. Mecklenburg County will continue to explore variousmarkets as they become available. §Residues and off-spec materials generated from the composting process will be sold as a supplemental fuel or disposed of in an approved disposal facility. (a)(7) A report on the design of the facility, including; (A) Design capacity of the facility; §The facility is designed to accept 122,000 tons per year of material. The composting design capacityfor this facility is approximately 91,600 tons of material annually for Year 2019 conditions. The remainder of materials will be ground and removed from the site. (a)(7)(B) A process flow diagram of the entire facility, including the type, size and location of all major equipment, and feedstock streams. The flow streams shall indicate the quantity of materials on the wet weight and volumetric basis; §The process flow diagram is included in Appendix V. (a)(7)(C) The means for measuring, shredding, mixing, and proportioning input materials; §As this facility will be a Type I composting facility, input materials for composting consist of yard waste, garden waste, wood waste, and water. The amount of water that needs to be added (if any)to the composting material to attain a percent moisture content of 40-60% based on weather conditions. This will be determined by sight, feel, and experience. §The composting process that will occur at the proposed facility is described in the Operations andMaintenance Manual, included as Appendix VI. §Major equipment used at the facility will include equipment that is sized and sufficient to handleand process all materials received. Mecklenburg County currently owns the following types ofequipment and is evaluating other types of equipment to improve the efficiency and environmental footprint of our organization. Equipment on hand currently includes the following: o Backhaus 6.65 Windrow Turner o Diamond Z 1460B Tub Grinder o Powerscreen Phoenix 1600 Trommel screener o McCloskey 621 Trommel screener o Airlift Separator (for removal of remaining plastics during the screening process.) 5 August 26, 2016 §Mecklenburg County from time to time will acquire and replace equipment commensurate with the needs of the facility. Specifications for the major equipment used at the facility is available uponrequest. (a)(7)(D) Anticipated process duration, including receiving, preparation, composting, curing, and distribution; §The composting facility process from reception to distribution will take approximately 6-7 months but may be reduced based on use of bulking agents, amendments and additional changes inprocessing equipment. (a)(7)(E) A description of the location of all temperature, air and any other type of monitoring points, and the frequency of monitoring; §As stated in the Operation and Maintenance Manual, as attached in Appendix VI, temperatures of the material will typically be measured at least once a week. The temperature will be measured with a four-foot long thermometer fully inserted toward the cross-sectional center of the material. (a)(7)(F) A description of how the temperature control and monitoring equipment will demonstrate that the facility meets the requirements in Rule .1406 Item (10), (11) or (12) of this Section, as appropriate for the feedstock; §Temperature measurements collected at least once a week will ensure that compost is maintained at or above 55o C (131o F) for at least three (3) days. The material will be aerated as needed using mechanized equipment to ensure temperatures are being maintained. (a)(7)(G) The method of aeration provided the capacity of aeration equipment; and §Material will be turned using mechanized equipment suitable for the operation. All material at thefacility will be turned as needed in accordance with the operations manual. Material will be turned to maintain aerobic conditions and maximize composting operations. (a)(7)(H) A description of the method to control surface water run-on and run-off; and the method to control, treat, and dispose of leachate generated; and §The facility will discharge stormwater in accordance with the NGC240000 General Permit for Storm Water and Process Wastewater Discharges associated with SIC Code 2875 CompostFacilities and like activities, dated October 1, 2011. See Appendix III. §Swales will be down gradient of the composting pad to collect surface water run-off and direct itto a large wet detention pond. §The site sits at the top of the Long Creek watershed so no run-on is anticipated (a)(8) A description of the label or other information source that meets the requirements of Rule .1407(g) of this Section. §Documentation of compliance is included in Appendix III. 6 August 26, 2016 (a)(9) Plans and specifications for the facility, including manufacturer’s performance data for all equipment selected. §Detailed plans and specifications will be maintained at the facility and available upon request. (a)(10) A detailed operations and maintenance manual outlining: (A) A quality assurance plan for the process and final product which lists the procedures used in inspecting incoming materials, monitoring, sampling, and analyzing the compost process and final product, testing schedule, and recordkeeping requirements; (B) Contingency plans detailing corrective or remedial action to be taken in the event of equipment breakdown; non-conforming waste delivered to the facility; spills, and undesirable conditions such as fires, vectors and odors; and (C) An explanation of how the facility will comply with operational requirements as outlined in Rule .146 of this Section, detailed operational information and instruction, an outline of reports to be submitted in compliance with this Section, and safety instructions. §An explanation of how the facility will comply with the operational requirements as outlined inRule .1406 is included in Appendix II. An Operation and Maintenance Manual is included in Appendix VI. Appendix I Section .1404 Compliance 1 August 26, 2016 SOLID WASTE COMPOST FACILITY SITING/DESIGN REQUIREMENTS SUBMITTAL Company Name:Mecklenburg County Site Name:Mecklenburg County Compost and Recycling Facility Site Address:140 Valleydale Road, Charlotte, NC .1404 SITING/DESIGN REQUIREMETNS FOR SOLID WASTE COMPOST FACITLITIES (a) A site shall meet the following requirements at the time of initial permitting and shall continue to meet these requirements throughout the life of the permit only on the property owned or controlled by the landowner(s) at the time permitting; (a)(1) A site located in a floodplain shall not restrict the flow of the 100-year flood; reduce the temporary storage capacity of the floodplain; or result in washout of solid waste so as to pose a hazard to human life, wildlife, land or water resources; §As shown on Figure 7 in Appendix VII, the site is not located in a floodplain. (a)(2) A 100-foot minimum buffer is required between all property lines and compost areas for Type 3 and 4 facilities; 50-foot for Type 1 or 2 facilities; §As the facility will be a Type I facility, a 50-foot buffer will be maintained between composting areas and the property lines. (a)(3) a 500-foot minimum buffer is required between compost areas and residences or dwellings not owned and occupied by the permittee; except that Type 1 and Small Type 2 and 3 shall have a 200-foot minimum buffer; §As the facility will be a Type I facility, a 200-foot minimum buffer is required between compost areas and residences or dwellings. As shown on Figure 2 in Appendix VII, no residences ordwellings existing within 200 feet of the facility. (a)(4) A 100-foot buffer is required between all wells and compost areas, except monitoring wells; §Charlotte Water provides water service to the area. As a result, no potable water wells are locatedwithin 100 feet of the compost area, as shown on Figure 2 in Appendix VII. (a)(5) A 50-foot buffer is required between perennial streams/rivers and compost areas; §The nearest stream is an unnamed tributary of Gum Branch that runs along the eastern property line of the site. All composting operations will occur over 50-feet away from this tributary. (a)(6) A compost facility shall be located in accordance with 15A NCAC 2B .0200, Classification and Water Quality Standards Applicable to Surface Waters in North Carolina; §Gum Branch, Long Creek and the Catawba River at Lake Wylie are all classified as WS-IV waters. The storm water runoff discharge from the facility will not cause any violations of water qualitystandards for WS-IV waters 2 August 26, 2016 (a)(7) All portions of any compost facility located over a closed-out disposal area shall be designed with a pad adequate to protect the disposal area cap from being disturbed, as defined in Part (a)(10)(E) of this Rule, and there shall be no runoff from the pad onto the cap or side slopes of the closed out area; §This composting facility will not be located over a closed-out disposal area. (a)(8) A 25-foot minimum distance is required between compost areas and swales or berms to allow for adequate access of firefighting equipment; §This facility will allow for twenty-five (25) foot minimum distance between berms and compost areas for adequate access of firefighting equipment. (a)(9) A site shall meet the following surface water requirements: (a)(9)(A) A site shall not cause a discharge of materials or fill materials into waters or wetlands of the state that is in violation of Section 404 of the Clean Water Act; §This facility will not discharge dredged or fill materials into waters or wetlands of the state. (a)(9)(B) A site shall not cause a discharge of pollutants into waters of the state that is in violation of the requirements of the National Pollutant Discharge Elimination System (NPDES), under Section 402 of the Clean Water Act; And §The site will discharge storm water runoff in accordance with the NGC240000 General Permit for Storm Water and Process Wastewater Discharges associated with SIC Code 2875 Compost Facilities and like activities, dated October 1, 2011. See Appendix III. (a)(9)(C) A site shall not cause non-point source pollution of waters of the state that violates assigned water quality standards; §Operations at the facility have been designed to minimize the impact on the surface waters of thestate. All stormwater will be discharged from the facility via a wet detention pond to one stormwater outfall. Swales will be located down gradient of the composting pad to collect surface water run-off and direct it to a wet detention pond. The material will generally be turned when itis raining in order to incorporate the moisture throughout the material. A natural buffer will remain around the perimeter of the site to filter any stormwater runoff or leachate prior to leaving the site. (a)(10) (A) A site shall not contravene groundwater standards as established under 15A NCAC 2L; §Operations at the facility have been designed to minimize the impact on the ground-waters of thestate. Composting activities will be performed on concrete pavement. Borings were performed on the site and extended from 8.1 to 15 below the surface. No groundwater was observed. A summary of the boring results is located in Appendix IV. 3 August 26, 2016 (a)(10)(B) Portions of a site used for waste receipt and storage, active composting, and curing shall have a soil texture finer than loamy sand and the depth to the seasonal high water table shall be maintained at least 12 inches for a Type 1 or 2 facility and 24 inches for a Type 3 facility, unless a pad is provided; §Operations at the facility have been designed to minimize the impact on the ground-waters of the state. Composting activities will be performed on concrete pavement. Borings were performed onthe site and extended from 8.1 to 15 below the surface. No groundwater was observed. A summary of boring results is located in Appendix IV. (a)(10)(C) A pad shall be provided for portions of Type 4 facility used for waste receiving and storage, active composting, and curing; §This facility will not process Type 4 waste. (D) A pad not required for storage of finished product that is dried as to pass the Paint Filter Liquid Test (EPA Method 9095), and for which the storage area is prepared in such a manner that water does not collect around the base of the stored material, and where the depth to the seasonal high watertable is maintained at least 12 inches; and §Finished product at this facility will be stored on a concrete pad. (E) The linear coefficient of permeability of pads required in accordance with this Rule shall not be greater than 1 x 10ି଻ centimeters per second. If natural soils are used, the liner must be at least 18 inches thick. §Composting activities at this facility will be performed on concrete pads with a linear coefficient of permeability greater than 1 x 10-7 centimeters per second. (b) For subparagraphs (a)(2) through (a)(4) and Part (a)(10)(B) of this Rule, (dependent upon waste type, facility design, and regional topography) alternative minimum buffers or requirements may be increased if deemed necessary by the Division in order to protect public health and the environment or to prevent the creation of a nuisance. §The Division has not added additional buffers or requirements for this facility. (c) A site shall meet the following design requirements: (c)(1) A site shall not allow uncontrolled public access; §The site access will be controlled through the use of fences and gates as well as natural barriers. (c)(2) A site shall meet the requirements of the Sedimentation Pollution Control Law (15 A NCAC 4); §The site has been designed to meet the requirements of the Sedimentation Pollution Control Law. A copy of the letter of Approval from the North Carolina Department of Environment, Health andNatural Resources is included in Appendix III. (c)(3) A site shall meet the requirements of the Air Pollution Control Requirements (15A NCAC 2D) to minimize fugitive admissions and odors; and 4 August 26, 2016 §To minimize odors, incoming yard waste will ground in a timely manner under normal operatingconditions in accordance with the operations manual. Ground yard waste will either be placed in awindrow or removed from the site in a timely manner under normal operating conditions. Material will be turned as needed, ensuring aerobic conditions prevail. To minimize airborne particles, moisture may be incorporated into materials when needed. (c)(4) The site shall be designed to minimize odors at the property boundary. §To minimize odors, incoming yard waste will ground in a timely manner under normal operating conditions in accordance with the operations manual. Ground yard waste will either be placed in awindrow or removed from the site in a timely manner under normal operating conditions. Materialwill be turned as needed, ensuring aerobic conditions prevail. Appendix II Section .1406 Compliance 1 August 26, 2016 SOLID WASTE COMPOST FACILITY OPERATIONAL REQUIREMENTS SUBMITTAL Company Name:Mecklenburg County Site Name:Mecklenburg County Compost and Recycling Facility Site Address:140 Valleydale Road, Charlotte, NC .1406 OPERATIONAL REQUIREMENTS FOR SOLID WASTE COMPOST FACILITIES Any person who maintains or operates a solid waste compost facility shall maintain and operate the site to conform with the following practices: (1)Plans and Permit Requirements (1)(A) Construction plans and conditions of permit shall be followed; and (1)(B) A copy of the permit, plans, and operational reports shall be maintained on site at all times. §Conditions of the operating permit will be followed at all times and a copy of the permit, plans, and operational reports will be maintained on site at all times. (2) Adequate erosion control measures shall be practiced to prevent on-site erosion and to control the movement of soil or contaminants from the site. §All processing areas are located on concrete. The perimeter of the site will be vegetated to prevent erosion. In addition, grass swales are located at the end of the processing area to capture site run-off and direct it to a wet detention pond. (3) Surface water shall be diverted from the operational, compost curing, and storage areas. §The site will be located near the top of the Long Creek watershed and no surface water run-on is anticipated. Site runoff will be routed through bioswales to an extended detention wet pond. (4) Leachate shall be contained on site and treated to meet the standards of the off-site disposal method. §Rain that falls directly on the material will be absorbed into the material and will not run-off. The material will be managed to incorporate moisture throughout the material. The perimeter of thesite will be completely vegetated to prevent erosion. In addition, grass swales will be located atthe end of the processing area to capture site run-off and direct it to a large wet detention pond. (5) Access and Security Requirements: (5)(A) Large sites shall be secured by means of gates, chains, berms, fences, or other security measures demonstrated to provide equivalent protection approved by the Division, to prevent unauthorized entry. §A perimeter fence will be used to secure the site. The entry will be through a security gate, whichwill be locked after hours. (5)(B) An operator shall be on duty at the site at all times while the facility is open for public use to ensure compliance with the operational requirements and access to such facilities shall be controlled. 2 August 26, 2016 §An operator will be on duty at all times during which the facility is open for public use. (5)(C) The access road to the site shall be of all-weather construction and maintained in good condition. §The access road will be constructed with concrete to provide all weather access. (6) A site shall only accept those solid wastes that it is permitted to receive. §The site will accept only those materials that it is permitted to receive. (7) Safety Requirements (7)(A) Open burning of solid waste is prohibited. §Open burning of anything will be prohibited on site. (7)(B) Equipment shall be provided to control accidental fires and arrangements made with the local fire protection agency to immediately provide fire-fighting services when needed. §All pieces of equipment will include a fire extinguisher. Fire hydrants will be available to provide firefighting capabilities. The City of Charlotte fire department will also be available to provideimmediate firefighting services. (7)(C) Personnel training shall be provided to insure that all employees are trained in site specific safety, remedial and corrective action procedures. §Staff will receive the training required. (8) Sign Requirements: (8)(A) Signs providing information on waste that can be received, dumping procedures, the hours during which the site is open for public use, the permit number and other pertinent information shall be posted at the site entrance. (8)(B) Traffic signs/markers shall be provided as necessary to promote an orderly traffic pattern to and from the discharge area and to maintain efficient operating conditions. (8)(C) Signs shall be posted stating that no hazardous waste, asbestos containing waste, or medical waste can be received on this site. §Signage will include hours of operation, material accepted, fees, permit number, emergency contact information, traffic routing, “No Hazardous Waste” signage, “No Asbestos Containing Waste”signage, and “No Medical Waste” signage. (9) Monitoring Requirements: (9)(A) Specific monitoring and reporting requirements shall be met. 3 August 26, 2016 (9)(B) The temperature of all compost produced shall be monitored sufficiently to ensure that the pathogen reduction criteria is met. §Temperatures of the material will typically be measured at least once a week. The temperature will be measured with a four-foot long thermometer fully inserted toward the cross-sectional center of the material. Annual reporting will be submitted. (10) Compost processed at Type 1 facilities shall be maintained at or above 55 degrees Celsius for 3 days and aerated to maintain elevated temperatures. §Temperature measurements collected at least once a week will ensure that compost is maintainedat or above 55o C (131o F) for at least three (3) days. The material will be aerated as needed usingmechanized equipment to ensure temperatures are being maintained. (11) Types 2, 3, and 4 facilities shall maintain the compost process at a temperature above 40 degrees Celsius (104 degrees F) for 14 days or longer and the average temperature for that time shall be higher than 45 degrees Celsius (113 degrees F) or, Types 2, 3, and 4 facilities shall met the vector attraction reduction requirements in 40 CFR 503.33(b)(4) or (7). Requirements of 40 CFR 503.33(b)(4) or (7) are hereby incorporated by references, including and subsequent amendments or additions. §As this facility will be a Type I facility, this section does not apply. (12) The composting process shall qualify as a process to further reduce pathogens for all Type 3 and Type 4 facilities. The following are acceptable methods: (12)(A) The windrow composting method, in which the following requirements apply: aerobic conditions shall be maintained during the compost process. A temperature of 131 degrees F (55 degrees Celsius) or greater shall be maintained in the windrow for at least 15 days. During the high temperature period, the windrow shall be turned at least 5 times. (12)(B) The static aerated pile composting method, in which the following requirements apply: Aerobic conditions shall be maintained during the compost process. The temperature of the compost pile shall be maintained at 131 degrees F (55 degrees Celsius) or greater for at least three days. (12)(C) The within-vessel composting method, in which the temperature in the compost pile shall be maintained at a minimal temperature of 131 degrees F (55 degrees Celsius) for at least three days. §As this facility will be a Type I facility, this section does not apply. (13) Nitrogen bearing waste shall be incorporated as necessary to minimize odor and the migration of nutrients. §The incorporation of nitrogen-bearing waste is described in the Operation and Maintenance Manual included in Appendix VI. (14) Miscellaneous Requirements: (14)(A) The finished compost shall meet the classifications and distributions requirements outlined in Rule .1407 of this Section. §The finished compost will meet the classification of “Produced at Type I Facility.” 4 August 26, 2016 (14)(B) The quality of the final product shall determine the allowable uses as outlined in Rule .1407 of this Section. §The finished compost will have an “Unrestricted Application and Distribution” grade. (14)(C) The final product shall be approved by the Solid Waste Section as outlined in Rule .1407 Subparagraph (6)(b) if this Section. §The final product will be approved by the Solid Waste Section. (14)(C))(i) Non-compostable solid waste and unacceptable compost shall be disposed in solid waste management facility permitted to receive the particular type of waste under 15A NCAC 13B. §Should any non-compostable materials be detected by frontline staff during operations, thematerials will be removed from the site to be disposed in a proper solid waste management facility. Once the compost has reached maturity, the material will be screened at 3/8 inch to remove any non-conforming waste that may have been missed during the original screening. The material notpassing the 3/8-inch screen will be sent back to the grinder for reprocessing. (14)(C)(ii) The amount of compost stored at the facility shall not exceed the designed storage capacity. §The amount of compost stored at the facility will not exceed the design storage capacity. Appendix III Solid Waste Compost Facility Permit Supporting Regulatory Documentation Zoning Verification Letter Erosion and Sedimentation Control Plan Letter of Approval Compost Customer Handouts NPDES Stormwater Discharge Permit USING COMPOST IN THE LANDSCAPE Compost has been used by gardeners in backyard landscaping and gardening for many years. The benefits are substantial, especially when compost is used on the compacted, nutrient-deficient soils common in many urban areas and on red clay soil such as we have in Mecklenburg County. Your product. The compost you have purchased is classified as “unrestricted application and distribution” and can be used on any soil. The compost is made from yard waste, including leaves, limbs, grass clippings and brush. It has been treated by pathogen-free requirement procedures (PFRP), which means it is maintained at 131 °F for a minimum of 72 hours. This treatment ensures that the compost is free of disease-causing organisms. Benefits. Compost enhances the physical, chemical and biological properties of soils. In clay soils, organic materials such as compost increase drainage and air space. Compost tends to raise pH and increase the soil’s biological activity. In sandy soils, compost increases the ability to hold moisture and nutrients. Landscapers find that all these characteristics help ornamental plants become established and develop a good root system. How to use: 1. For landscape use and vegetable gardening: (a) apply compost in a 3 to 4 inch layer spread over the soil surface; (b) incorporate it into the root zone 2. For over seeding established lawns: (a) core aerate; (b) apply a ½-inch layer of compost over the lawn; (c) incorporate the seed and fertilizer into this layer 3. For new lawns: (a) apply a 1-inch layer of compost over the soil surface; (b) incorporate it into the top 1 inch of soil; (c) apply the seed and fertilizer per manufacturers’ recommendations Visit our website at WipeOutWaste.com or call 704-583-7371 for more information about Mecklenburg County’s compost and mulch operations. Mecklenburg County Solid Waste Management 2145 Suttle Avenue Charlotte, NC 28208 GENERAL PERMIT NO. NCG240000 Compost Facilities IMPORTANT CHANGES & GUIDANCE Authorization to Construct GENERAL PERMIT NO. NCG240000 Compost Facilities discharge of stormwater and process wastewater tothe surfacewaters of NorthCarolina Coverage underthis GeneralPermit is applicableto: Except upon DWQ determination of similarity as provided immediately above, the following activities and associated discharges are excluded from coverage under this General Permit: Original signed by Matt Matthews for TABLE OF CONTENTS PARTI–INTRODUCTION SECTION A: GENERALPERMIT COVERAGE For discharges to watersheds affected by a TMDL, coverage under this permit maydepend onthe facility demonstrating it does not have reasonable potential to violate applicable water quality standards for those pollutants as a result of discharges. SECTION B: PERMITTED ACTIVITIES The types of authorized discharges are dependent upon DWQ approval and are detailed in the permittee’s individual Certificate of Coverage (COC); where applicable, the COC also details DWQ’s Authorizationto Construct (ATC) and authorization to operate process wastewatertreatment facilities. The discharges allowed by this General Permit shall not cause or contribute to violations of Water Quality Standards. SECTION C: COMPLIANCE SCHEDULEFOR NEWAND EXISTINGDISCHARGERS New dischargers. Existing dischargers. PART II –MONITORING,CONTROLS, AND LIMITATIONS FOR PERMITTED DISCHARGES SECTION A: STORMWATER DISCHARGES: STORMWATERPOLLUTION PREVENTION PLAN develop and implement SitePlan impaired watershed for which a TMDL has been established, The permittee shall re certify annuallythat the stormwater outfalls have beenevaluated for the presence of non stormwater discharges. Stormwater Management Plan. Feasibility Study Secondary Containment Requirementsand Records BMP Summary. Rain gauge. Spill Prevention and Response Plan. PreventativeMaintenanceand GoodHousekeeping Program Employee Training ResponsibleParty. SPPP Amendment. Facility Inspections. SPPPImplementation.The permittee shall implement the SPPP and all appropriateBMPs to ensure that contaminants do not enter surface waters via stormwater.Implementation of the SPPP shall include documentation of all monitoring, measurements, inspections, maintenance activities, and training provided to employees, including the log of the sampling data and of actions taken to implement BMPs associated with the industrial activities, including vehicle and equipment maintenanceactivities. Such documentation shall be kept on-site for a period of five years and made available to the Director or the Director’s authorized representative immediately upon request. SECTION B: STORMWATER DISCHARGES: ANALYTICAL MONITORING REQUIREMENTS Tables1 through3 Table1 AnalyticalMonitoringRequirements forStormwaterDischarges Discharge Characteristics Units Measurement Frequency1 Sample Type2 Sample Location3 1.. The permittee may petition DWQ to reduce the monitoring frequency for any parameter after four consecutive quarters of analytical resultsbelow the benchmark values in Table 3. 4. . The permittee is not required to sample stormwater discharges resulting from a rainfall greater than the 25 yr, 24 hr event for the site location. A measurable storm event results in anactual at least 48 hours Table2 Table2 StormwaterAnnual MonitoringSchedule QuarterlyMonitoring Events1,2 StartDate3 End Date 3 If no discharge occurs during the sampling period, the permittee must record “No Flow”or “No Discharge” within 30 days of theend of the quarterly sampling period in the SPPP.“No Flow”or “No Discharge”shallbe reported onthe individual quarterly DMRs Table3 Table3 Benchmark Values for Stormwater Discharges Discharge Characteristics Benchmark Values Tier One If: Then: within two weeks of receiving sampling results. within two months of theinspection. Tier Two If:two (2) consecutive Then: Tier Three four (4) occasions within 30 days of receipt of the fourth analytical result SECTION C: STORMWATERDISCHARGES: ON SITE VEHICLE AND EQUIPMENT MAINTENANCE MONITORINGREQUIREMENTS Table4 Table2 Table4 AnalyticalMonitoringRequirements from On Site Vehicle and Equipment Maintenance Activities Discharge Characteristics Units Measurement Frequency Sample Type Sample Location EPA Method 1664 (SGT HEM) The permittee may petition DWQ to reduce the monitoring frequency for any parameter after fourconsecutive quarters of analytical results below the benchmark values in Table5. The permittee is not required to sample stormwater discharges resulting from a rainfall greater than the 25 yr, 24 hr event for thesite location. Table5 Table5 Benchmark Values for On Site Vehicle and Equipment Maintenance Activities SECTION D: STORMWATER DISCHARGES:QUALITATIVE MONITORING REQUIREMENTS Table6 . Table2 Table6 Qualitative Monitoring Requirements Discharge Characteristics Frequency1 Monitoring Location 2,3 The quarterly monitoring frequency for qualitative monitoring is not eligible for a reduced monitoring frequency. The permittee is not required tomonitor stormwater discharges resulting froma rainfall greater than the 25 yr, 24 hr event for the site location. Discharge Characteristics Benchmark Values A written recordof the permittee’s investigation,evaluation, and response actions shallbe keptin theSPPP ; SECTION E: PROCESS WASTEWATER DISCHARGES: EFFLUENT LIMITATIONS AND MONITORING REQUIREMENTS Finished Compost Table7 Table8 Table 7 Monitoring Requirements for Process Wastewater Discharges Discharge Characteristics Units Measurement Frequency Sample Type Sample Location Table9 The quarterly monitoring frequency for process wastewater discharges is not eligible for a reduced monitoring frequency. Table8 Effluent LimitationsforProcess WastewaterDischarges Discharge Characteristics Effluent Limitations 1 Quarterly Average Daily Maximum Table9 Table9 Process Wastewater Discharge Monitoring Schedule Quarterly Monitoring Events 1,2 StartDate3 EndDate3 If no discharge occurs during the sampling period, the permittee must record “No Flow”or “No Discharge” within 30 days of theend of the quarterly sampling period in the SPPP.“No Flow”or “No Discharge”shallbe reported onthe individual quarterly DMR PART III –AUTHORIZATION TO CONSTRUCT AND OPERATEA PROCESS WASTEWATER TREATMENT FACILITY SECTION A: REQUIREMENTS TO CONSTRUCT A PROCESS WASTEWATER TREATMENT FACILITY ATA NEWCOMPOSTINGFACILITY SECTION B: REQUIREMENTS FOR OPERATION OF A PROCESS WASTEWATER TREATMENT FACILITY PART IV –STANDARD CONDITIONS SECTION A: COMPLIANCE AND LIABILITY SECTION B: GENERAL CONDITIONS Permitteeis requiredto notify DWQ within 90 days in the event the permitted facility is sold or closed SECTION C: OPERATION AND MAINTENANCE OF POLLUTION CONTROLS SECTION D: MONITORING AND RECORDS SECTION E: REPORTING REQUIREMENTS no later than 30 days from the date the facility receives the sampling results from the laboratory not PARTV–LIMITATIONS REOPENER PART VI –ADMINISTERING AND COMPLIANCE MONITORING FEE REQUIREMENTS PART VII –DEFINITIONS Process wastewater Appendix IV Solid Waste Compost Facility Permit Groundwater Level Readings Report of Preliminary Geotechnical Exploration Rozzelles Ferry Road Site Charlotte, North CarolinaS&ME Project No. 1351-13-133 Prepared For: Mecklenburg County Land Use & Environmental Services Agency 700 North Tryon Street Charlotte, North Carolina 28202 Prepared By: S&ME, Inc. 9751 Southern Pine Boulevard Charlotte, North Carolina 28273 NC PE Firm License No. F-0176 October 1, 2013 TABLE OF CONTENTS 1. INTRODUCTION.....................................................................................................................1 1.1 PROJECT BACKGROUND....................................................................................................1 1.2 PURPOSE AND SCOPE.......................................................................................................1 2. EXPLORATION PROCEDURES............................................................................................2 2.1 FIELD ACTIVITIES ..............................................................................................................2 2.2 LABORATORY ACTIVITIES...................................................................................................2 3. AREA GEOLOGY AND SUBSURFACE CONDITIONS ........................................................3 3.1 PHYSIOGRAPHY AND AREA GEOLOGY ................................................................................3 3.2 SUBSURFACE CONDITIONS ................................................................................................5 3.3 WATER LEVEL MEASUREMENTS.........................................................................................5 4. PRELIMINARY CONCLUSIONS AND RECOMMENDATIONS ............................................5 4.1 SITE CONSIDERATIONS......................................................................................................5 4.1.1 Expansive Soils and Fill Soils.....................................................................................5 4.1.2 Fill Soils......................................................................................................................6 4.1.3 Excavations................................................................................................................6 4.1.4 Re-Use of On-site Soils as Structural Fill...................................................................7 4.1.5 Fill Placement.............................................................................................................7 4.2 SEISMIC DESIGN PARAMETERS..........................................................................................7 4.3 FOUNDATIONS ..................................................................................................................7 4.4 FLOOR SLABS...................................................................................................................8 4.5 PAVEMENTS......................................................................................................................8 4.6 FINAL GEOTECHNICAL EXPLORATION .................................................................................9 5.0 LIMITATIONS.....................................................................................................................9 APPENDIX Site Vicinity Map, Figure 1 Boring Location Plan, Figure 2 Legend to Soil Classification Boring Logs Lab Results Report of Preliminary Geotechnical Exploration S&ME Project No. 1351-13-133 Rozzelles Ferry Road Site – Charlotte, North Carolina October 1, 2013 1 1. INTRODUCTION 1.1 Project Background Project information is based on a telephone conversation between Mr. Steinhilber with Mecklenburg County and Mr. Brian McKean of S&ME on August 21, 2013. It is our understanding that the county is looking to purchase the parcel located along Rozelles Ferry Road in Charlotte, North Carolina and identified as parcel No. 03505423. Based on aerial photographs, the parcel appears to be relatively open in the center and surrounded by trees. Additionally, historical aerial images obtained from Google Earth ®, indicate that the site was previously wooded and the current open area is a result of the site being previously used as a borrow source, most likely for the construction of Fred Alexander Boulevard as seen in the photo below. While the site appears to have been lowered generally uniformly, the potential of waste borrow pits on the site does exist. The site is currently covered in low-grasses and some waist-high brush. Mr. Steinhilber indicated that future development plans for the site are still preliminary but that construction will include asphalt and concrete pavements, stockpile storage areas and small structures consistent with a compost facility. No site plans are available at this time. It is our understanding that the county wants to evaluate the subsurface conditions at the site to evaluate the site’s suitability for future development. 1.2 Purpose and Scope The purpose of this preliminary geotechnical study was to explore the subsurface conditions at the site and develop preliminary geotechnical recommendations for the design and construction of the project. S&ME has completed the following scope of geotechnical services for this project: Report of Preliminary Geotechnical Exploration S&ME Project No. 1351-13-133 Rozzelles Ferry Road Site – Charlotte, North Carolina October 1, 2013 2 Visited the site to observe site conditions and mark proposed boring locations. Contacted the North Carolina One-Call Center to mark the locations of existing underground utilities in the exploration area; Mobilized a power drilling rig and crew to the site; Drilled nine soil test borings at the site; Measured groundwater levels, backfilled the boreholes with soil cuttings to the ground surface; Prepared this preliminary geotechnical engineering report. Please note that this report does not address potential environmental contamination of the soil, rock, or groundwater at this site. 2. EXPLORATION PROCEDURES 2.1 Field Activities In order to explore the general subsurface conditions at the project site, nine soil test borings (B-1 through B-9) were drilled to depths of 8.1 to 15 feet below existing grades. The soil test borings were advanced at the approximate locations shown on the attached Boring Location Plan (Figure No. 2) in the Appendix. The locations of the borings were selected and located in the field by an S&ME staff professional by using a handheld GPS device. A track-mounted, D-50 drill rig was used to advance the borings with hollow-stem, continuous flight augers. Standard Penetration Test (SPT) split spoon sampling was performed at designated intervals in the soil test borings in general accordance with ASTM D 1586 to provide an index for estimating soil strength and relative density or consistency and to retrieve samples for soil classification purposes. Representative portions of each soil sample were taken to our laboratory. The drill rig used to drill the borings is equipped with a hydraulic automatic hammer for Standard Penetrations tests rather than the traditional rope, cathead and safety hammer. The N-values reported on the attached Boring Logs are the actual field measured blow counts and are not corrected for the hammer energy. Water level measurements were attempted at the termination of drilling activities. All boreholes were backfilled with soil cuttings prior to de-mobilizing from the site. 2.2 Laboratory Activities A geotechnical staff professional visually examined each sample in general accordance with the Unified Soil Classification System (USCS) to estimate the distribution of grain sizes, plasticity, organic content, color, and apparent geological origin. The results of the classifications, as well as the field test results, are presented on the individual boring logs included in the Appendix. Similar materials were grouped into strata on the logs. The Report of Preliminary Geotechnical Exploration S&ME Project No. 1351-13-133 Rozzelles Ferry Road Site – Charlotte, North Carolina October 1, 2013 3 strata contact lines represent approximate boundaries between the soil and rock types; the actual transition between the soil and rock types in the field may be gradual in both the horizontal and vertical directions. Laboratory testing was performed on a selected soil sample obtained during the field exploration. The laboratory testing included the following tests and the results are presented in the Appendix: Soil Plasticity Tests (Atterberg Limits Test):Representative samples were selected for Atterberg Limits testing to determine the soil's plasticity characteristics. The Plasticity Index (PI) is representative of this characteristic and is bracketed by the Liquid Limit (LL) and the Plastic Limit (PL). The Liquid Limit is the moisture content at which the soil will flow as a heavy viscous fluid and the Plastic Limit is the moisture content at which the soil begins to lose its plasticity. These tests were conducted in accordance with ASTM D 4318. 3. AREA GEOLOGY AND SUBSURFACE CONDITIONS 3.1 Physiography and Area Geology The site is located within the Charlotte Belt of the Piedmont Physiographic Province of North Carolina as shown in the following figure. The Piedmont Province generally consists of well-rounded hills and ridges, which are dissected by a well-developed system of draws and streams. The Piedmont Province is predominantly underlain by metamorphic rock (formed by heat, pressure and/or chemical action) and igneous rock (formed directly from molten material), which were initially formed during the Precambrian and Paleozoic eras. The volcanic and sedimentary rocks deposited in the Piedmont Province during the Precambrian eras were the host for the metamorphism and were changed to gneiss and schist. The more recent Paleozoic era had periods of igneous emplacement, with at least several episodes of regional metamorphism resulting in the majority of the rock types seen today. Physiographic Provinces of North Carolina The topography and relief of the Piedmont Province have developed from differential weathering of the igneous and metamorphic rock. Because of the continued chemical and physical weathering, the rocks in the Piedmont Province are now generally covered with APPROXIMATESITE LOCATION Report of Preliminary Geotechnical Exploration S&ME Project No. 1351-13-133 Rozzelles Ferry Road Site – Charlotte, North Carolina October 1, 2013 4 a mantle of soil that has weathered in place from the parent bedrock. These soils have variable thicknesses and are referred to as residuum or residual soils. The residuum is typically finer grained and has higher clay content near the surface because of the advanced weathering. Similarly, the soils typically become coarser grained with increasing depth because of decreased weathering. As the degree of weathering decreases, the residual soils generally retain the overall appearance, texture, gradation and foliations of the parent rock. The 1985 Geologic Map of North Carolina indicates that the site is underlain by metamorphosed quartz diorite. The boundary between soil and rock in the Piedmont is not sharply defined. A transitional zone termed “Partially Weathered Rock” is normally found overlying the parent bedrock. Partially Weathered Rock (PWR) is defined for engineering purposes as residual material with Standard Penetration Resistances (N-values) exceeding 100 blows per foot. The transition between hard/dense residual soils and PWR occurs at irregular depths due to variations in degree of weathering. A depiction of typical weathering profiles in the Piedmont Province is presented in the following figure. Typical Piedmont Weathering Profiles (After Sowers/Richardson, 1983) Water is typically present in the residual soils and within fractures in the PWR or underlying bedrock in the Piedmont. On upland ridges in the Piedmont, water may or may not be present in the residual soils above the PWR and bedrock. Alluvial soils, which have been transported and deposited by water, are typically found in floodplains and are generally saturated to within a few feet of the ground surface. Fluctuations in water levels are typical in residual soils and PWR in the Piedmont, depending on variations in precipitation, evaporation and surface water runoff. Seasonal high water levels are expected to occur during or just after the typically wetter months of the year (November through April). Report of Preliminary Geotechnical Exploration S&ME Project No. 1351-13-133 Rozzelles Ferry Road Site – Charlotte, North Carolina October 1, 2013 5 3.2 Subsurface Conditions The generalized subsurface conditions as based on the soil test borings are further described below. For more detailed soil descriptions, stratifications, water levels, cave-in depths, etc. at a particular boring location, the respective boring log should be reviewed. Fill:Fill soils were encountered in Borings B-1 and B-5 to depths of approximately 1 to 3 feet below the surface materials. The fill generally consisted of silty clays (CH) and sandy clay (CL). N-values ranging from 7 to 9 bpf were observed in the fill material. Residuum:Residual soils were encountered below the fill soils or at the surface in all of the borings. The residuum generally consisted of clayey silts (MH), sandy silts (ML), and silty sands (SM). N-values in the residual soils ranged from 3 to 55 bpf. Partially Weathered Rock and Auger Refusal:Partially Weathered Rock was encountered in Boring B-8 at a depth of 6 feet below the existing ground surface. When sampled, the PWR encountered generally breaks down into silty fine to coarse sands. Boring B-8 was terminated at an approximate depth of 8.1 feet below the ground surface due to auger refusal. Auger refusal is defined as material that could not be penetrated with the drill rig equipment used on the project. Auger refusal material may consist of large boulders, rock ledges, lenses, seams or the top of parent bedrock. Core drilling techniques would be required to evaluate the character and continuity of the refusal material. However, rock coring was beyond the scope of the previous study. 3.3 Water Level Measurements Water level measurements were attempted in all of the borings at the termination of drilling operations. Water was not observed in the soil borings. The observed hole cave- in depths for the soil test borings are also included on the individual logs and may be an indication of the groundwater level at or near the hole cave-in depth. The boreholes were backfilled prior to de-mobilizing from the site. Water levels tend to fluctuate with seasonal and climatic variations, as well as with some types of construction operations. Therefore, water maybe encountered during construction at depths not indicated during this study. 4. PRELIMINARY CONCLUSIONS AND RECOMMENDATIONS 4.1 Site Considerations 4.1.1 Expansive Soils and Fill Soils Based on the results of the soil test borings and laboratory tests performed, highly plastic, residual silty clays (CH) and clayey silts (MH) were encountered at the site in Borings B- 1, B-2 and B-7 to depths of 1 to 3 feet. These soils have a moderate to high shrink-swell potential, are very moisture sensitive, and can be difficult to work. Due to their shrink/swell potential, support of foundations, slabs and pavements directly above these materials poses a risk of excessive settlement and structural distress and should be Report of Preliminary Geotechnical Exploration S&ME Project No. 1351-13-133 Rozzelles Ferry Road Site – Charlotte, North Carolina October 1, 2013 6 accounted for during planning of general site development. To reduce this risk, we recommend adequate separation be provided between these plastic soils and structural subgrades. We recommend a minimum of 2 feet of separation material consisting of clean, low- plasticity soils be provided between stable, in-place moderate to high plasticity clay and silt soils (CH, MH) and structural subgrades (e.g., pavement, slab and foundation bearing elevations). Site grading should be performed with this recommendation in mind, which may increase “stripping” depths locally. 4.1.2 Fill Soils As previously mentioned, this site was once used as a source of borrow material and historical aerials indicate that stockpiles of fill may be present on the site. Borings B-1 and B-5 encountered some fill soils to depths of 1 to 3 feet, but the potential for other areas of undocumented fill does exist. The extent of fill soils on the site is unknown at this time. An additional evaluation including test pits and more borings would be required to further evaluate the presence and extent of fill soils at this site and their potential impact on site grading. If fill materials are encountered during grading operations, they should be further evaluated by the project geotechnical engineer. 4.1.3 Excavations The residual and fill soils can typically be excavated using backhoes, trackhoes, front-end loaders, bull dozers and other types of typical earthmoving equipment. Areas that encountered PWR or auger refusal (B-8) will require non-conventional methods for excavation. Our experience in this geological area indicates that the upper 2 to 3 feet of PWR can generally be excavated using pans and scrapers by first loosening with a single tooth ripper attached to a suitable sized dozer, such as a Caterpillar D-8 or D-9, or suitable sized trackhoe such as a Caterpillar C320 equipped with a rock bucket. Jackhammering or blasting should be anticipated for excavation of the majority of the PWR, rock, and, if present, boulders during open site excavation (i.e., excavations more than 10 feet wide and 30 feet long). In confined excavations (footings, utility trenches, etc.), these materials will probably require the use of blasting, pneumatic hammers, or hydraulic hammers to excavate. This should be anticipated for footing and utility excavations in these materials. Rock in a weathered, boulder, and massive form varies erratically in depth and location in the Piedmont Geologic Province. Therefore, there is always a potential that these materials could be encountered at shallower depths between the boring locations and may be encountered during general site grading and in trench excavations for the installation of footings and utilities. Report of Preliminary Geotechnical Exploration S&ME Project No. 1351-13-133 Rozzelles Ferry Road Site – Charlotte, North Carolina October 1, 2013 7 4.1.4 Re-Use of On-site Soils as Structural Fill The near-surface highly plastic clays and silts are not suitable for re-use as structural fill for the project unless used in deeper fill areas and are separated from structural subgrades and foundation bearing elevations by a minimum of two feet. The low plasticity residuals soils and PWR materials are suitable for re-use as structural fill. Some moisture conditioning may be required, for materials excavated from beneath the water table. 4.1.5 Fill Placement All fill used for site grading operations should consist of a clean (free of organics and debris), low plasticity soil (Liquid Limit less than 50, Plasticity Index less than 25). The proposed fill should have a maximum dry density of at least 90 pounds per cubic foot as determined by a Standard Proctor compaction test, ASTM D 698. All fill should be placed in loose lifts not exceeding eight inches in thickness and compacted to a minimum of 95 percent of its standard Proctor maximum dry density, with the final 18 inches below subgrade compacted to at least 98 percent. We recommend that field density tests, including one-point Proctor verification tests, be performed on the fill as it is being placed at a frequency of 1 test per 5,000 square feet per lift in the building, 10,000 square feet in parking areas and one test per lift per 100 linear feet in utility trenches. Final project slopes should be designed at 3 horizontal to 1 vertical or flatter. The tops and bases of all slopes should be located a minimum of 10 feet from structural limits and a minimum of 5 feet from pavement limits. The fill slopes should be adequately compacted, as outlined in this report, and all slopes should be seeded and maintained after construction. 4.2 Seismic Design Parameters For preliminary design , the proposed building should be designed to resist possible earthquake effects as determined in accordance with the North Carolina Building Code. We estimate weighted average N-values in the soils underlying the building area to be greater than 15 and less than 50 in the top 100 feet below the existing ground surface. Based on Section 1615.1.1 and Equation 16-45 of the International Building Code, the calculated weighted average N-values indicate a Seismic Site Class D. 4.3 Foundations Provided the earthwork procedures and recommendations outlined in this report are implemented, we anticipate that buildings with typical column loads of less than 75 kips could be supported on a shallow foundation system with allowable bearing pressures of 2,000 to 3,000 pounds per square foot (psf) for design of the foundations bearing on the low-plasticity residual soils or on newly placed structural fill compacted to at least 95 percent of its Standard Proctor maximum dry density. Report of Preliminary Geotechnical Exploration S&ME Project No. 1351-13-133 Rozzelles Ferry Road Site – Charlotte, North Carolina October 1, 2013 8 All footing excavations should be observed by the geotechnical engineer's representative to verify that suitable soils are present at and below the proposed bearing elevation and to confirm their consistency with the conditions upon which our recommendations are based. If evaluation with DCP testing encounters very soft to soft or other unsuitable materials in the footing excavations, they should be corrected per the recommendations of the project geotechnical engineer. 4.4 Floor Slabs Immediately prior to constructing the floor slabs, we recommend that the areas be evaluated via probing, hand auger borings with DCP testing or proofrolling to detect any softened, loosened or disturbed areas that may have been exposed to wet weather or construction traffic. Areas that are found to be disturbed or indicate pumping action during the proofrolling should be undercut and replaced with adequately compacted structural fill. Proofrolling should be observed by the staff professional or a senior soil technician under his/her direction. Proofrolling procedures are discussed in previous sections of this report. 4.5 Pavements Provided the site grading and separation recommendations are implemented during construction we anticipate that the resulting subgrades will provide suitable support for asphalt pavement thicknesses as follows: PavementType Material Thickness Light-Duty Heavy Duty Flexible Asphalt Concrete 2 to 3 3 to 4 Crushed Stone (ABC) 5 to 6 6 to 10 Rigid Reinforced Concrete --6 to 7 ABC Stone --5 to 6 These recommendations are based on CBR values of 4 to 5 percent and ESAL loadings of 20,000 to 100,000. Traffic loading was not provided to us at this time. Light-duty pavements should be designated for car parking areas and lightly traveled service roads. Heavy-duty pavements should be designated for entrances and exits, access roads and driveways. Heavy-duty concrete pavement should be used in areas in front of loading docks and dumpsters. The early placement of the graded aggregate base course will minimize the deterioration of the prepared soil subgrades. However, some loss of graded aggregate due to rutting and surface contamination may occur prior to final asphalt paving. Some infilling and re- grading of the graded aggregate in conjunction with sweeping with a wire broom may be required. Report of Preliminary Geotechnical Exploration S&ME Project No. 1351-13-133 Rozzelles Ferry Road Site – Charlotte, North Carolina October 1, 2013 9 Prevention of infiltration of water into the subgrade is essential for the successful performance of any pavement. Both the subgrade and the pavement surface should be sloped to promote surface drainage away from the pavement structure. 4.6 Final Geotechnical Exploration The preliminary conclusions and recommendations submitted in this report are based in part upon the data obtained from a limited subsurface exploration program and are intended to provide a general assessment of geotechnical conditions at select locations on the site. Once final grades, building locations, and pavement locations have been determined, we recommend that additional soil test borings and supplemental test pits be performed to develop the geotechnical design and construction recommendations for design and construction purposes. 5.0 LIMITATIONS The test locations given in this report should be considered accurate only to the degree implied by the methods used to determine them. The test pit and boring logs represent our interpretation of the subsurface conditions based on the field logs, and visual examinations of excavated soils and samples by a staff professional or technician, in addition to tests of the field samples. The lines designating the interfaces between various strata may be gradual. The generalized subsurface strata and profiles described in this report are intended to convey trends in subsurface conditions. The boundaries between strata are approximate and idealized. They have been developed by interpretations of widely-spaced tests. Therefore, actual subsurface conditions may vary from those given between test locations. Water levels have been measured or inferred in the test pits and borings at the times and under the conditions stated on the exploration logs in this report. Changes in the water conditions may occur due to variations in rainfall, evaporation, construction activity, surface water runoff, and other site specific factors. Our geotechnical services include storing the samples collected and making them available for inspection for 90 days. The samples are then discarded unless our client requests otherwise. The assessment of site environmental conditions and the determination of contaminants in the soil, rock, surface water or groundwater of the site were beyond the scope of this geotechnical study. The recommendations provided in this report are based on our understanding of the project information given in this report and on our interpretation of the surface and subsurface data collected. We have made our recommendations based on our experience with similar subsurface conditions and similar projects. The recommendations apply to the specific project discussed in this report; therefore, any changes in the project Report of Preliminary Geotechnical Exploration S&ME Project No. 1351-13-133 Rozzelles Ferry Road Site – Charlotte, North Carolina October 1, 2013 10 information should be provided to us so we may review our conclusions and recommendations and make any appropriate modifications. S&ME should be retained for a general review of the design drawings and specifications to verify that geotechnical recommendations are properly interpreted and implemented. Regardless of the thoroughness of a geotechnical study, there is always a possibility that subsurface conditions will be different from those at test locations, that conditions will not be as anticipated by the designers or contractors, or that the construction process will alter soil conditions. Therefore, qualified geotechnical personnel should observe construction to confirm that the conditions indicated by the geotechnical borings actually exist. We recommend the owner retain S&ME for this service since we are already familiar with the project, the subsurface conditions at the site, and the intent of the recommendations and design. This report has been prepared for the exclusive use of the client for specific application to the subject project and project site. It has been prepared in accordance with generally accepted geotechnical engineering practice for specific application to this project. The conclusions and recommendations contained in this report are based upon applicable standards of our practice in this geographic area at the time this report was prepared. No other warranty, expressed or implied, is made. SCALE: CHECKED BY: DRAWN BY: DATE: FIGURE NO. 1 PROJECT NO.: 1351-13-133 NTS BCM KHH 10/1/13 SITE VICINITY MAP Rozzelles Ferry Road SIte CHARLOTTE, NORTH CAROLINA Approximate Site Location SCALE: CHECKED BY: DRAWN BY: DATE: FIGURE NO. 2 PROPOSAL NO.: 1351-13-133 NTS BCM LAC 10/2/2013 BORING LOCATION PLAN ROZELLES FERRY ROAD PROPERTY CHARLOTTE, NORTH CAROLINA 30’ Approximate Boring Location B-2 B-7 B-3 B-8 B-1 LEGEND B-4 B-6 B-5 B-9 3 2 3 2 2 4 2 3 2 2 4 2 2 3 2 7 4 6 4 4 SS-1 SS-2 SS-3 SS-4 SS-5 FILL: SILTY CLAY (CH) - red orange brown RESIDUUM: SANDY SILT (ML) - soft to firm, tan orange, fine Boring terminated at 15 feet HC THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT. BORING, SAMPLING AND PENETRATION TEST DATA IN GENERAL ACCORDANCEWITH ASTM D-1586. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT. WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY. 1. 2. 3. 4. PROJECT:B-1 EASTING: 2n d 6 i n / R E C BORING DEPTH:15.0 ft LOGGED BY:B. McKean 3r d 6 i n / R Q D GR A P H I C LO G N V A L U E DE P T H (f e e t ) Page 1 of 1 NOTES: DATE DRILLED: 9/10/13 DRILL RIG: D-50 DRILLER: J. Cain HAMMER TYPE: Automatic SAMPLING METHOD: Split DRILLING METHOD: 2¼" H.S.A. 5 10 15 1s t 6 i n / R U N # BLOW COUNT/ CORE DATA MATERIAL DESCRIPTION BORING LOG NOTES: S&ME Project No. 1351-13-133 Rozzelles FerryCharlotte, NC NORTHING: ELEVATION: WATER LEVEL: EL E V A T I O N (f e e t ) WA T E R L E V E L REMARKS SA M P L E N O . SP T R E C . ( i n . ) SA M P L E T Y P E S& M E B O R I N G L O G 1 3 - 1 3 3 R O Z Z E L L E S F E R R Y . G P J S & M E . G D T 1 0 / 2 / 1 3 8060302010 STANDARD PENETRATION TEST DATA(blows/ft) 7 4 6 4 4 4 1 2 2 1 3 3 2 2 2 3 2 2 2 2 7 4 4 4 3 SS-1 SS-2 SS-3 SS-4 SS-5 RESIDUUM: CLAYEY SILT (MH) - firm, tanorange SANDY SILT (ML) - soft, tan orange, fine Boring terminated at 15 feet HC THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT. BORING, SAMPLING AND PENETRATION TEST DATA IN GENERAL ACCORDANCEWITH ASTM D-1586. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT. WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY. 1. 2. 3. 4. PROJECT:B-2 EASTING: 2n d 6 i n / R E C BORING DEPTH:15.0 ft LOGGED BY:B. McKean 3r d 6 i n / R Q D GR A P H I C LO G N V A L U E DE P T H (f e e t ) Page 1 of 1 NOTES: DATE DRILLED: 9/10/13 DRILL RIG: D-50 DRILLER: J. Cain HAMMER TYPE: Automatic SAMPLING METHOD: Split DRILLING METHOD: 2¼" H.S.A. 5 10 15 1s t 6 i n / R U N # BLOW COUNT/ CORE DATA MATERIAL DESCRIPTION BORING LOG NOTES: S&ME Project No. 1351-13-133 Rozzelles FerryCharlotte, NC NORTHING: ELEVATION: WATER LEVEL: EL E V A T I O N (f e e t ) WA T E R L E V E L REMARKS SA M P L E N O . SP T R E C . ( i n . ) SA M P L E T Y P E S& M E B O R I N G L O G 1 3 - 1 3 3 R O Z Z E L L E S F E R R Y . G P J S & M E . G D T 1 0 / 2 / 1 3 8060302010 STANDARD PENETRATION TEST DATA(blows/ft) 7 4 4 4 3 3 5 2 3 3 5 7 6 3 4 3 3 2 2 3 8 12 8 6 7 SS-1 SS-2 SS-3 SS-4 SS-5 RESIDUUM: SANDY SILT (ML) - firm to stiff,tan orange brown, fine Boring terminated at 15 feet HC THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT. BORING, SAMPLING AND PENETRATION TEST DATA IN GENERAL ACCORDANCEWITH ASTM D-1586. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT. WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY. 1. 2. 3. 4. PROJECT:B-3 EASTING: 2n d 6 i n / R E C BORING DEPTH:15.0 ft LOGGED BY:B. McKean 3r d 6 i n / R Q D GR A P H I C LO G N V A L U E DE P T H (f e e t ) Page 1 of 1 NOTES: DATE DRILLED: 9/10/13 DRILL RIG: D-50 DRILLER: J. Cain HAMMER TYPE: Automatic SAMPLING METHOD: Split DRILLING METHOD: 2¼" H.S.A. 5 10 15 1s t 6 i n / R U N # BLOW COUNT/ CORE DATA MATERIAL DESCRIPTION BORING LOG NOTES: S&ME Project No. 1351-13-133 Rozzelles FerryCharlotte, NC NORTHING: ELEVATION: WATER LEVEL: EL E V A T I O N (f e e t ) WA T E R L E V E L REMARKS SA M P L E N O . SP T R E C . ( i n . ) SA M P L E T Y P E S& M E B O R I N G L O G 1 3 - 1 3 3 R O Z Z E L L E S F E R R Y . G P J S & M E . G D T 1 0 / 2 / 1 3 8060302010 STANDARD PENETRATION TEST DATA(blows/ft) 8 12 8 6 7 6 8 9 11 10 12 14 14 5 6 7 6 16 20 23 25 SS-1 SS-2 SS-3 SS-4 RESIDUUM: SANDY SILT (ML) - very stiff, tanbrown, fine Boring terminated at 10 feet HC THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT. BORING, SAMPLING AND PENETRATION TEST DATA IN GENERAL ACCORDANCEWITH ASTM D-1586. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT. WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY. 1. 2. 3. 4. PROJECT:B-4 EASTING: 2n d 6 i n / R E C BORING DEPTH:10.0 ft LOGGED BY:B. McKean 3r d 6 i n / R Q D GR A P H I C LO G N V A L U E DE P T H (f e e t ) Page 1 of 1 NOTES: DATE DRILLED: 9/10/13 DRILL RIG: D-50 DRILLER: J. Cain HAMMER TYPE: Automatic SAMPLING METHOD: Split DRILLING METHOD: 2¼" H.S.A. 5 10 1s t 6 i n / R U N # BLOW COUNT/ CORE DATA MATERIAL DESCRIPTION BORING LOG NOTES: S&ME Project No. 1351-13-133 Rozzelles FerryCharlotte, NC NORTHING: ELEVATION: WATER LEVEL: EL E V A T I O N (f e e t ) WA T E R L E V E L REMARKS SA M P L E N O . SP T R E C . ( i n . ) SA M P L E T Y P E S& M E B O R I N G L O G 1 3 - 1 3 3 R O Z Z E L L E S F E R R Y . G P J S & M E . G D T 1 0 / 2 / 1 3 8060302010 STANDARD PENETRATION TEST DATA(blows/ft) 16 20 23 25 4 14 17 13 6 5 20 15 14 8 5 10 13 9 6 9 34 32 27 14 SS-1 SS-2 SS-3 SS-4 SS-5 FILL: SANDY CLAY (CL) - stiff, brown redorange RESIDUUM: SILTY SAND (SM) - dense, graywhite, fine to medium SANDY SILT (ML) - stiff, gray brown, fine Boring terminated at 15 feet HC THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT. BORING, SAMPLING AND PENETRATION TEST DATA IN GENERAL ACCORDANCEWITH ASTM D-1586. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT. WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY. 1. 2. 3. 4. PROJECT:B-5 EASTING: 2n d 6 i n / R E C BORING DEPTH:15.0 ft LOGGED BY:B. McKean 3r d 6 i n / R Q D GR A P H I C LO G N V A L U E DE P T H (f e e t ) Page 1 of 1 NOTES: DATE DRILLED: 9/10/13 DRILL RIG: D-50 DRILLER: J. Cain HAMMER TYPE: Automatic SAMPLING METHOD: Split DRILLING METHOD: 2¼" H.S.A. 5 10 15 1s t 6 i n / R U N # BLOW COUNT/ CORE DATA MATERIAL DESCRIPTION BORING LOG NOTES: S&ME Project No. 1351-13-133 Rozzelles FerryCharlotte, NC NORTHING: ELEVATION: WATER LEVEL: EL E V A T I O N (f e e t ) WA T E R L E V E L REMARKS SA M P L E N O . SP T R E C . ( i n . ) SA M P L E T Y P E S& M E B O R I N G L O G 1 3 - 1 3 3 R O Z Z E L L E S F E R R Y . G P J S & M E . G D T 1 0 / 2 / 1 3 8060302010 STANDARD PENETRATION TEST DATA(blows/ft) 9 34 32 27 14 6 10 6 7 28 7 12 8 9 22 5 8 4 7 21 13 22 14 16 50 SS-1 SS-2 SS-3 SS-4 SS-5 RESIDUUM: SILTY SAND (SM) - mediumdense to dense, gray white, fine to medium Boring terminated at 15 feet HC THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT. BORING, SAMPLING AND PENETRATION TEST DATA IN GENERAL ACCORDANCEWITH ASTM D-1586. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT. WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY. 1. 2. 3. 4. PROJECT:B-6 EASTING: 2n d 6 i n / R E C BORING DEPTH:15.0 ft LOGGED BY:B. McKean 3r d 6 i n / R Q D GR A P H I C LO G N V A L U E DE P T H (f e e t ) Page 1 of 1 NOTES: DATE DRILLED: 9/10/13 DRILL RIG: D-50 DRILLER: J. Cain HAMMER TYPE: Automatic SAMPLING METHOD: Split DRILLING METHOD: 2¼" H.S.A. 5 10 15 1s t 6 i n / R U N # BLOW COUNT/ CORE DATA MATERIAL DESCRIPTION BORING LOG NOTES: S&ME Project No. 1351-13-133 Rozzelles FerryCharlotte, NC NORTHING: ELEVATION: WATER LEVEL: EL E V A T I O N (f e e t ) WA T E R L E V E L REMARKS SA M P L E N O . SP T R E C . ( i n . ) SA M P L E T Y P E S& M E B O R I N G L O G 1 3 - 1 3 3 R O Z Z E L L E S F E R R Y . G P J S & M E . G D T 1 0 / 2 / 1 3 8060302010 STANDARD PENETRATION TEST DATA(blows/ft) 13 22 14 16 50 3 2 2 5 3 3 4 6 3 2 1 3 6 5 6 11 SS-1 SS-2 SS-3 SS-4 RESIDUUM: CLAYEY SILT (MH) - firm, browntan red SANDY SILT (ML) - firm to stiff, brown tan red,fine to medium Boring terminated at 10 feet HC THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT. BORING, SAMPLING AND PENETRATION TEST DATA IN GENERAL ACCORDANCEWITH ASTM D-1586. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT. WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY. 1. 2. 3. 4. PROJECT:B-7 EASTING: 2n d 6 i n / R E C BORING DEPTH:10.0 ft LOGGED BY:B. McKean 3r d 6 i n / R Q D GR A P H I C LO G N V A L U E DE P T H (f e e t ) Page 1 of 1 NOTES: DATE DRILLED: 9/10/13 DRILL RIG: D-50 DRILLER: J. Cain HAMMER TYPE: Automatic SAMPLING METHOD: Split DRILLING METHOD: 2¼" H.S.A. 5 10 1s t 6 i n / R U N # BLOW COUNT/ CORE DATA MATERIAL DESCRIPTION BORING LOG NOTES: S&ME Project No. 1351-13-133 Rozzelles FerryCharlotte, NC NORTHING: ELEVATION: WATER LEVEL: EL E V A T I O N (f e e t ) WA T E R L E V E L REMARKS SA M P L E N O . SP T R E C . ( i n . ) SA M P L E T Y P E S& M E B O R I N G L O G 1 3 - 1 3 3 R O Z Z E L L E S F E R R Y . G P J S & M E . G D T 1 0 / 2 / 1 3 8060302010 STANDARD PENETRATION TEST DATA(blows/ft) 6 5 6 11 22 7 50/5" 28 8 7 10 22 50/1.5" 50 15 50/5" 50/1.5" SS-1 SS-2 SS-3 SS-4 RESIDUUM: SILTY SAND (SM) - mediumdense to dense, gray, fine to medium PARTIALLY WEATHERED ROCK - sampled as gray brown silty fine to medium sand Refusal at 8.1 feet Boring terminated at 8.1 feet HC THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT. BORING, SAMPLING AND PENETRATION TEST DATA IN GENERAL ACCORDANCEWITH ASTM D-1586. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT. WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY. 1. 2. 3. 4. PROJECT:B-8 EASTING: 2n d 6 i n / R E C BORING DEPTH:8.1 ft LOGGED BY:B. McKean 3r d 6 i n / R Q D GR A P H I C LO G N V A L U E DE P T H (f e e t ) Page 1 of 1 NOTES: DATE DRILLED: 9/10/13 DRILL RIG: D-50 DRILLER: J. Cain HAMMER TYPE: Automatic SAMPLING METHOD: Split DRILLING METHOD: 2¼" H.S.A. 5 1s t 6 i n / R U N # BLOW COUNT/ CORE DATA MATERIAL DESCRIPTION BORING LOG NOTES: S&ME Project No. 1351-13-133 Rozzelles FerryCharlotte, NC NORTHING: ELEVATION: WATER LEVEL: EL E V A T I O N (f e e t ) WA T E R L E V E L REMARKS SA M P L E N O . SP T R E C . ( i n . ) SA M P L E T Y P E S& M E B O R I N G L O G 1 3 - 1 3 3 R O Z Z E L L E S F E R R Y . G P J S & M E . G D T 1 0 / 2 / 1 3 8060302010 STANDARD PENETRATION TEST DATA(blows/ft) 50 15 100 100 37 7 4 1 18 8 6 3 27 9 3 3 55 15 10 4 SS-1 SS-2 SS-3 SS-4 RESIDUUM: SILTY SAND (SM) - dense, tanwhite, fine to coarse, with weathered rock fragments SILTY SAND (SM) - medium dense, tan white,fine to medium SANDY SILT (ML) - soft to stiff, tan brown, fine Boring terminated at 10 feet HC THIS LOG IS ONLY A PORTION OF A REPORT PREPARED FOR THE NAMEDPROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT. BORING, SAMPLING AND PENETRATION TEST DATA IN GENERAL ACCORDANCEWITH ASTM D-1586. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT. WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY. 1. 2. 3. 4. PROJECT:B-9 EASTING: 2n d 6 i n / R E C BORING DEPTH:10.0 ft LOGGED BY:B. McKean 3r d 6 i n / R Q D GR A P H I C LO G N V A L U E DE P T H (f e e t ) Page 1 of 1 NOTES: DATE DRILLED: 9/10/13 DRILL RIG: D-50 DRILLER: J. Cain HAMMER TYPE: Automatic SAMPLING METHOD: Split DRILLING METHOD: 2¼" H.S.A. 5 10 1s t 6 i n / R U N # BLOW COUNT/ CORE DATA MATERIAL DESCRIPTION BORING LOG NOTES: S&ME Project No. 1351-13-133 Rozzelles FerryCharlotte, NC NORTHING: ELEVATION: WATER LEVEL: EL E V A T I O N (f e e t ) WA T E R L E V E L REMARKS SA M P L E N O . SP T R E C . ( i n . ) SA M P L E T Y P E S& M E B O R I N G L O G 1 3 - 1 3 3 R O Z Z E L L E S F E R R Y . G P J S & M E . G D T 1 0 / 2 / 1 3 8060302010 STANDARD PENETRATION TEST DATA(blows/ft) 55 15 10 4 A B C D E F N LL 25 45.1% This report shall not be reproduced, except in full, without the written approval of S&ME, Inc. 1.000 0% Group Symbol Laboratory Manager 24.71 One-point Method 30 Tare Weight LL =F * FACTOR Revision No. 0 Oven 1454 2/27/2013 1024 LL Apparatus 21217 6/13/2013 Balance (0.01 g) Type and Specification Project #: Project Name: Form No. TR-D4318-T89-90 AASHTO T 90xo Revision Date: 11/20/07 Cal Date: Type and Specification 11/3/2012 Red Brown Sandy SILT S&ME ID # Cal Date: ASTM D 4318 AASHTO T 89 SS-1 o B-2 Sample #: Test Methods: Client Address: Client Name: Quality Assurance S&ME, Inc. Raleigh, 3201 Spring Forest Road, Raleigh, North Carolina 27616 Sample Description: N/A Report Date: 9/25 - 9/26/2013 9/26/2013 Location: Boring #: Wet Soil Weight + A Dry Soil Weight + A Sample Date: Rozelles Ferry Property Test Date(s) 25.03 20.17 Liquid Limit Grooving tool 4.54 # OF DROPS % Moisture (D/E)*100 62.8% 35 Water Weight (B-C) Dry Soil Weight (C-A)7.23 12.89 8.40 44.5% 21.22 21.43 13.03 15 65.1% 70.3% Moisture Contents determined by ASTM D 2216 3.81 8.33 18.9820.47 3.74 25.17 6.06 23.24 12.92 4.26 12.94 7 21 13.08 25.28 7.39 4.81 25 Offset:Site Borehole Plastic Index 45.7% Plastic Limit Notes / Deviations / References: Ave. Average Signature 66 45 21 Multipoint Method ASTM D 4318: Liquid Limit, Plastic Limit, & Plastic Index of Soils MH o 0.995 0.974 28 30 26 1.018 NP, Non-Plastic 0.99 24 2923 1 - 2.5 ft. 0.979 0.985 Air Dried Estimate the % Retained on the #40 Sieve: Liquid Limit Position Mal Krajan, ET Wet Preparation Dry Preparation Date 1051-13-133 1.022 20 21 N Factor Tare #: 1.005 1.014 1.00927 Technical Responsibility Pan # Factor One Point Liquid Limit Depth (ft): 9 S-1 5/20/2013 9/13/2013 Plastic Limit 26 S&ME ID # Liquid Limit, Plastic Limit, and Plastic Index 22 N 15 20 25 30 35 40 61.0 62.0 63.0 64.0 65.0 66.0 67.0 68.0 69.0 70.0 71.0 10 100 % M o i s t u r e C o n t e n t A B C D E F N LL 25 Liquid Limit, Plastic Limit, and Plastic Index 22 N Depth (ft): 3 S-1 Pan # 1.014 29 1.018 1.00927 One Point Liquid Limit 26 Test Methods: Tare #: Plastic Limit 5/20/2013 9/13/2013 Estimate the % Retained on the #40 Sieve: Liquid Limit NP, Non-Plastic 23 FactorFactor 1051-13-133 1.022 20 21 N 0.99 24 1.005 Wet Preparation Signature Position Air Dried 1%Dry Preparation Date 1 - 2.5 ft. 0.979 0.985 25.60 Moisture Contents determined by ASTM D 2216 1.000 Group Symbol Notes / Deviations / References: Ave. Average 18.3% Mal Krajan, ET 44 18 26 Multipoint Method Plastic Index Technical Responsibility ASTM D 4318: Liquid Limit, Plastic Limit, & Plastic Index of Soils 0.995 0.974 CL Plastic Limit 1.90 10.66 17.8% o 28 B-5 Sample #: Offset:Site Borehole 26.90 22.41 Liquid Limit 12.97 12 16 13.06 4.24 3.63 20.7722.66 24.40 13.03 9.60 7.74 25 15 44.2% 46.9% 13.0412.52 25.12 10.65 1.95 11 23.17 23.70 4.00 # OF DROPS % Moisture (D/E)*100 42.4% 35 Water Weight (B-C) Dry Soil Weight (C-A)9.44 Wet Soil Weight + A Dry Soil Weight + A Report Date: Sample Date: Rozelles Ferry Property Test Date(s)9/25 - 9/26/2013 9/26/2013 ASTM D 4318 AASHTO T 89 o S&ME ID # Cal Date: Quality Assurance S&ME, Inc. Raleigh, 3201 Spring Forest Road, Raleigh, North Carolina 27616 Sample Description: N/A Type and Specification Project #: Project Name: Form No. TR-D4318-T89-90 AASHTO T 90xo Revision Date: 11/20/07 Revision No. 0 Client Address: Client Name: Grooving tool Cal Date: Type and Specification SS-1 S&ME ID # Brown Sandy CLAY Location: Boring #: Oven 1454 2/27/2013 1024 LL Apparatus 21217 6/13/2013 11/3/2012Balance (0.01 g) 26.41 One-point Method 28 Tare Weight LL =F * FACTOR Laboratory Manager 18.1% This report shall not be reproduced, except in full, without the written approval of S&ME, Inc. 30 15 20 25 30 35 40 40.0 41.0 42.0 43.0 44.0 45.0 46.0 47.0 48.0 49.0 50.0 10 100 % M o i s t u r e C o n t e n t A B C D E F N LL 25 Liquid Limit, Plastic Limit, and Plastic Index 22 N Depth (ft): 15 S-1 Pan # 1.014 29 1.018 1.00927 One Point Liquid Limit 26 Test Methods: Tare #: Plastic Limit 5/20/2013 9/13/2013 Estimate the % Retained on the #40 Sieve: Liquid Limit NP, Non-Plastic 23 FactorFactor 1051-13-133 1.022 20 21 N 0.99 24 1.005 Wet Preparation Signature Position Air Dried 0%Dry Preparation Date 1 - 2.5 ft. 0.979 0.985 29.18 Moisture Contents determined by ASTM D 2216 1.000 Group Symbol Notes / Deviations / References: Ave. Average 43.9% Mal Krajan, ET 67 43 24 Multipoint Method Plastic Index Technical Responsibility ASTM D 4318: Liquid Limit, Plastic Limit, & Plastic Index of Soils 0.995 0.974 MH Plastic Limit 3.73 8.76 42.6% o 28 B-7 Sample #: Offset:Site Borehole 22.44 20.26 Liquid Limit 13.05 22 8 12.46 3.98 5.25 20.2618.46 25.51 13.01 6.00 7.25 25 15 66.3% 72.4% 16.6912.94 25.40 8.66 3.80 25 21.60 25.45 4.54 # OF DROPS % Moisture (D/E)*100 63.0% 35 Water Weight (B-C) Dry Soil Weight (C-A)7.21 Wet Soil Weight + A Dry Soil Weight + A Report Date: Sample Date: Rozelles Ferry Property Test Date(s)9/25 - 9/26/2013 9/26/2013 ASTM D 4318 AASHTO T 89 o S&ME ID # Cal Date: Quality Assurance S&ME, Inc. Raleigh, 3201 Spring Forest Road, Raleigh, North Carolina 27616 Sample Description: N/A Type and Specification Project #: Project Name: Form No. TR-D4318-T89-90 AASHTO T 90xo Revision Date: 11/20/07 Revision No. 0 Client Address: Client Name: Grooving tool Cal Date: Type and Specification SS-1 S&ME ID # Red Brown Sandy Clayey SILT (Vis.) Location: Boring #: Oven 1454 2/27/2013 1024 LL Apparatus 21217 6/13/2013 11/3/2012Balance (0.01 g) 24.80 One-point Method 809 Tare Weight LL =F * FACTOR Laboratory Manager 43.3% This report shall not be reproduced, except in full, without the written approval of S&ME, Inc. 30 15 20 25 30 35 40 62.0 63.0 64.0 65.0 66.0 67.0 68.0 69.0 70.0 71.0 72.0 73.0 10 100 % M o i s t u r e C o n t e n t Appendix V Mecklenburg County Compost and Recycling Facility Process Flow Diagram Wa s t e R e c e i p t (1 4 , 8 0 0 S F ) Fe e d s t o c k G r i n d i n g & St o r a g e (5 0 , 5 0 0 S F ) Ac t i v e C o m p o s t i n g (4 5 d a y s ) (5 2 2 , 0 0 0 S F ) Product Storage (60,000 SF)Compost to Market Me c k l e n b u r g C o u n t y N C C o m p o s t C e n t r a l 91 , 6 0 0 T P Y Y a r d W a s t e C o m p o s t i n g F a c i l i t y Vo l u m e t r i c P r o c e s s F l o w D i a g r a m An n u a l C o m p o s t P r o d u c t i o n – Y r 2 0 1 9 Overs to Boiler Fuel or Mulch Screening (6,500 SF) In c o m i n g Y a r d W a s t e (1 2 2 , 0 0 0 T P Y ) Cu r i n g ( 6 0 d a y s ) (4 1 2 , 8 0 0 S F ) Gr o u n d B r u s h t o Bo i l e r F u e l o r M u l c h (3 0 , 4 0 0 T P Y ; 1 1 6 , 5 0 0 C Y / y r ) (9 1 , 6 0 0 T P Y ; 40 0 , 0 0 0 C Y / y r ) (8 5 , 8 0 0 T P Y ; 25 4 , 0 0 0 C Y / y r ) (8 3 , 2 0 0 T P Y ; 23 7 , 6 0 0 C Y / y r ) (12,400 TPY; 47,500 CY/yr)(70,800 TPY; 190,000 CY/yr)(70,800 TPY; 190,000 CY/yr) Appendix VI Solid Waste Compost Facility Permit Operation Manual Composting Operation and Maintenance Manual for Mecklenburg County Compost and Recycling Facility 2 Operation & Maintenance Manual Mecklenburg County Compost and Recycling Center Composting Operations Table of Contents General Information ..................................................................................... 1 Quality Assurance Plan ................................................................................ 2 Inspection of Incoming Material .................................................................. 2 Material Preparation .................................................................................... 2 Composting Process ..................................................................................... 3 Final Product ............................................................................................... 3 Contingency Plan ......................................................................................... 4 Equipment Breakdown ................................................................................. 4 Non-conforming Waste ................................................................................ 4 Fire Contingency ......................................................................................... 4 Vectors and Odors ....................................................................................... 5 Reporting and Record Keeping .................................................................... 6 1 General Information The Mecklenburg County Compost and Recycling Facility is located on 55 acres at 140Valleydale Road. The land is located within the limits of the City of Charlotte. An additional portion of the land is used for a full service, staffed recycling center. The facility is designed to receive up to approximately 122,000 tons of yard waste. There will be two scales at the compost and recycling facility. All paying customersdisposing of material and customers purchasing products must cross the scale at the scalehouse for transactions. All incoming material is weighed with the exception of pick-up and automobile traffic.These customers are charged by the size of vehicle and their weight is based upon volume.Material sent out as boiler fuel in tractor trailers is weighed using the scales. Material being sold (compost, mulch, nuggets, and etc.) is sold on a per cubic yard basis. Compost will be tested on a regular basis. Testing may include the U.S. Composting Council’s Seal of Testing Assurance (STA) Program. 2 Quality Assurance Plan Inspection of Incoming Material 1.The cashier initially performs visual screening of incoming material at the time it is being weighed. The inspection is to insure that no municipal solid waste, recyclables, household hazardous waste, treated wood, dirt or other contaminants are in the load. 2.If any of these items are detected at this time, the customer is directed to dispose of the materials either at the on-site full-service recycling center or at another appropriate approved disposal facility. 3.On-site compost facility staff perform secondary screening on the tipping pad. These operators inspect the material both at the time of tipping as well as immediately before the material is placed into the tub grinders to ensure that material type as well as size are appropriate to be processed by the grinders. 4.Should any non-conforming waste be detected by the operators during grinding operations, the waste will be removed from the site to be disposed properly. Material Preparation 1.After inspection, the material is processed through a grinder. 2.The ground material is then removed from the processing area and either placedinto windrows for composting or shipped off site for use in other markets. 3.Upon placement of the material into windrows, moisture requirements are determined by performing a squeeze test of the material: a.A handful of material is gathered and squeezed in one hand. b.If the material does not stay in a ball, but falls apart after squeezing it, the moisture is probably below 50%. c.If the material stays in a ball and little or no moisture drips from the ball, then this is interpreted as 40%-60% moisture – the optimum moisturecontent. d.If water is dripping from the ball of material, then moisture content is most likely above 65%. 4.Natural rainfall usually provides enough water to keep the moisture content of thematerial at optimum conditions. The windrows will generally be turned when it is raining in order to incorporate moisture throughout the windrow. In the event of a 3 low rainfall period, water hydrants are located on site to provide additional water to maintain optimal moisture content in the windrows. Additional equipment may be used as needed to incorporate moisture in the process. 5.In normal operations, high nitrogen yard wastes are incorporated into windrows assoon as possible to minimize odors. All yard waste, including green waste (grass clippings), under normal operating conditions is processed through the grinder in a timely manner. The grinding process gives the material its initial charge of oxygen for its aerobic decomposition. Under normal operating conditions, the material isthen incorporated into windrows within a timely manner if space is available or is sent out to be used in other markets. Mecklenburg County may use bulking agents or amendments based on market conditions and material availability. Composting Process 1.Generally, the windrowed material will be turned as needed using mechanized equipment suitable for the operation. Material will be turned to maintain aerobicconditions and maximize composting operations. 2.Throughout the composting process the material is monitored qualitatively for moisture content and aesthetics. 3.Temperature measurements will be collected at least once a week to ensure thatcompost is maintained at or above 55oC (131oF) for at least three (3) days. The material will be aerated as needed using mechanized equipment to ensure temperatures are being maintained. The temperature will be measured with a four- foot thermometer fully inserted toward the cross-sectional center of the windrow. Final Product 1.The compost material is turned regularly until the internal temperature falls below55 °C. 2.Upon reaching the desirable temperature the material is screened to remove any off-spec material. 3.The material not passing the screen is returned for reprocessing. Residues and off-spec materials generated from the composting process may also be sold as a supplemental fuel or disposed of in an approved disposal facility. 4.The material passing the screen is placed in a curing pile separate from the rest ofthe facility for ultimate distribution. 4 5.The finished compost will be sold primarily to residents, landscapers, and landscape supply companies for use as a soil amendment. Mecklenburg Countywill continue to explore various markets as they become available. 6.Mecklenburg County may use bulking agents or amendments based on market conditions and material availability. Contingency Plan Equipment Breakdown 1.All equipment has at least one backup. The concern that all pieces of a specific kindof equipment are out of service for any period of time is minimal. Non-conforming Waste 1.All waste is screened as described in the Quality Assurance Plan. Waste notconforming to the facility’s compost permit is not excepted at the facility. 2.Should waste not conforming to the facility’s permit be received at the tipping area, any contaminants are immediately loaded back onto the vehicle from which it came and are redirected to a proper solid waste management facility. 3.Should any non-conforming waste be detected by the operators during grinding operations, the waste is removed from the site to be disposed of in a proper solid waste management facility. 4.Mecklenburg County may use this facility to process storm debris and vegetative material during inclement weather situations. The amount of material to be processed on site could exceed the design amount by as much as 100%. Fire Contingency 1.The local Fire Department station will be made aware of the compost facility and the nature of its operation. 2.Threat of fire is minimized by not allowing stock piles to age over four weeks and by keeping its volume to a minimum. 3.Water hydrants area located throughout the site in case of a fire. 4.All pieces of equipment will include a fire extinguisher. 5 Vectors and Odors 1.Vectors are rarely a problem for yard waste (Type I) composting facilities. 2.The timely manner in which yard waste is ground and placed into windrows will assist in the prevention of vectors. 3.To minimize odors, incoming yard waste will be ground in a timely manner undernormal operating conditions. Ground yard waste will either be placed in a windrow or removed from the site. Material will be turned as needed to ensure that aerobic conditions prevail. To minimize airborne particles, moisture may be incorporated into materials when needed. 6 Reporting and Record keeping 1.An annual report, covering the period from July 1 to June 30, will be submitted tothe North Carolina Department of Environment and Natural Resources (NCDENR)by August 1 for the prior year. The annual report shall contain the information ascontained in Section 1408 of the North Carolina Solid Waste Management Rules. Note:Monitoring records are maintained for five years and are available for inspection by division personnel. Records include daily quantity of processed material, temperature data, quantity and source of material received, and the quantity and type of material removed for the use or disposal by product classification and the market or permitted disposal facility. Appendix VII Solid Waste Compost Facility Permit Maps & Drawings V ALLEY D ALE R O A D F R E D D .A L E X A N D E R B O U L E V A R D ROZZELLES FERRY ROAD B R O O K S HIR E B O U L E V A R D O A K S T R E E T LAND USE: SINGLE FAMILY RESIDENTIAL LAND USE: SINGLE FAMILY RESIDENTIAL LAND USE: SINGLE FAMILY RESIDENTIAL LAND USE: SINGLE FAMILY RESIDENTIAL LAND USE: SINGLE FAMILY RESIDENTIAL LAND USE: INDUSTRIAL LAND USE: INDUSTRIAL LAND USE: INDUSTRIAL LAND USE: INDUSTRIAL PROJECT SITE AP P R O V E D B Y CA D F I L E P A T H PR E P A R E D B Y CH E C K E D B Y DA T E JO B N O . SC A L E NO . D A T E B Y DE S C R I P T I O N K:\ C H L _ P R J \ 0 1 5 2 3 6 M e c k l e n b u r g C o u n t y \ 0 2 0 R e l o c a t e d C o m p o s t C e n t r a l \ 0 2 - D W G \ E x h i b i t \ 2 0 1 5 - 0 1 2 6 P E R M I T E X H I B I T S \ F I G 1 2 3 . d w g ME C K L E N B U R G C O U N T Y CO M P O S T A N D RE C Y C L I N G F A C I L I T Y MECKLENBURG COUNTY3205 FREEDOM DRIVE, SUITE 101CHARLOTTE, NC 28208 Pl a n s P r e p a r e d B y : C 2 0 1 5 NC L i c e n s e # F - 0 1 0 2 20 0 0 S o u t h B o u l e v a r d , S u i t e 4 4 0 Ch a r l o t t e , N C 2 8 2 0 3 FIGUREKnow what's R 1 NORTH LEGEND QUARTER MILE PROPERTY LINE OFFSET PROPERTY LINE QU A R T E R M I L E SI T E R A D I U S VALLE Y D ALE R O A D F R E D D .A L E X A N D E R B O U L E V A R D ROZZELLES FERRY ROAD B R O O K S H I R E B O U L E V A R D O A K S T R E E T LAND USE: SINGLE FAMILY RESIDENTIAL LAND USE: SINGLE FAMILY RESIDENTIAL LAND USE: SINGLE FAMILY RESIDENTIAL LAND USE: INDUSTRIAL LAND USE: INDUSTRIAL PROJECT SITE AP P R O V E D B Y CA D F I L E P A T H PR E P A R E D B Y CH E C K E D B Y DA T E JO B N O . SC A L E NO . D A T E B Y DE S C R I P T I O N K:\ C H L _ P R J \ 0 1 5 2 3 6 M e c k l e n b u r g C o u n t y \ 0 2 0 R e l o c a t e d C o m p o s t C e n t r a l \ 0 2 - D W G \ E x h i b i t \ 2 0 1 5 - 0 1 2 6 P E R M I T E X H I B I T S \ F I G 1 2 3 . d w g ME C K L E N B U R G C O U N T Y CO M P O S T A N D RE C Y C L I N G F A C I L I T Y MECKLENBURG COUNTY3205 FREEDOM DRIVE, SUITE 101CHARLOTTE, NC 28208 Pl a n s P r e p a r e d B y : C 2 0 1 5 NC L i c e n s e # F - 0 1 0 2 20 0 0 S o u t h B o u l e v a r d , S u i t e 4 4 0 Ch a r l o t t e , N C 2 8 2 0 3 FIGUREKnow what's R NORTH LEGEND 500 FT PROPERTY LINE OFFSET PROPERTY LINE 2 50 0 F O O T SI T E R A D I U S EXISTING SANITARY SEWER EXISTING DITCH EXISTING WATER LINE ROZZELLES FERRY ROAD B R O O K S H I R E B O U L E V A R D O A K S T R E E T AP P R O V E D B Y CA D F I L E P A T H PR E P A R E D B Y CH E C K E D B Y DA T E JO B N O . SC A L E NO . D A T E B Y DE S C R I P T I O N K:\ C H L _ P R J \ 0 1 5 2 3 6 M e c k l e n b u r g C o u n t y \ 0 2 0 R e l o c a t e d C o m p o s t C e n t r a l \ 0 2 - D W G \ E x h i b i t \ 2 0 1 5 - 0 1 2 6 P E R M I T E X H I B I T S \ F I G 1 2 3 . d w g ME C K L E N B U R G C O U N T Y CO M P O S T A N D RE C Y C L I N G F A C I L I T Y MECKLENBURG COUNTY3205 FREEDOM DRIVE, SUITE 101CHARLOTTE, NC 28208 Pl a n s P r e p a r e d B y : C 2 0 1 5 NC L i c e n s e # F - 0 1 0 2 20 0 0 S o u t h B o u l e v a r d , S u i t e 4 4 0 Ch a r l o t t e , N C 2 8 2 0 3 FIGUREKnow what's R NORTH LEGEND PROPERTY LINE 3 SU R R O U N D I N G ZO N I N G & L A N D U S E F R E D D .A L E X A N D E R B O U L E V A R D PROJECT SITE (ZONING: I-2) EXIT ONLY EXIT ONLY SC A L E S ON L Y SC A L E S ON L Y SCALES ONLY SCALES ONLY SC A L E S ON L Y VA N V A N RECYCLE CENTER GRINDING AND MIXING AREA MU L C H CO M P O S T ROZZELLES FERRY ROAD (VARIABLE PUBLIC RIGHT-OF-WAY) MB 55, PG 744 7 DO U B L E HA M M E R E D MU L C H TIPPING INFO BOOTH MAINTENANCE BUILDING WINDROWSPRODUCT STORAGE AND SCREENING AREA V A L L E Y D A L E R O A D ( V A R I A B L E P U B L I C R I G H T - O F - W A Y ) M B 5 5 , P G 7 4 4 ; D B 2 3 3 0 8 , P G 9 2 7 TYP. J BB A Z B A A D D E E BEGIN F G G G G G G G G G G G G G G G G G G G TYP. I TYP. I TE TP TE TE UUUUUUUU UU UU UU UU UU UU UU T2 T2 UU T2T2 T2 TD B L M TE TE THTH T2 UUUU T2 O UI UU T2 TEE N TE QQ R R SS UI UI T K END F BEGIN C END C A D D D P P X P U THW Z WW WW WW WW WW TYP. I AA W W W W WW W BEGIN C END C 1 SITE LEGEND PROPOSED 30" CURB AND GUTTER, TYP. PROPOSED 18" CURB AND GUTTER, TYP. HANDRAIL (SEE DETAIL SHEET) PROPOSED CONCRETE SIDEWALK PROPOSED PARKING SPACE 9' X 18', TYP. (WHITE 4" PAINT STRIPING) PROPOSED RETAINING WALL (SEE STRUCTURAL PLANS) PROPOSED WINDROW (SEE SITE PLAN FOR SPACING) PROPOSED CURING PAD ROW (SEE SITE PLAN FOR SPACING) PROPOSED RECYCLING COMPACTORS WITH CONCRETE PAD (SEE DETAIL SHEETS) (COMPACTORS TO BE PROVIDED BY MECKLENBURG COUNTY) PROPOSED BULK CONTAINERS (PROVIDED BY MECKLENBURG COUNTY) 6' TALL MANUAL DOUBLE CANTILEVERED SLIDING GATE. (SEE DETAIL SHEET) PRODUCT WALL (PROVIDED BY MECKLENBURG COUNTY) SCREEN WALL (SEE ARCH. PLANS) WHEEL STOPS STRIPING LEGEND PAINT (4" WHITE, 120 MILS) 4" X 10" MINISKIP PAINT (4" WHITE, 120 MILS) SOLID LANE LINE PAINT (4" YELLOW, 120 MILS) SINGLE SOLID LINE PAINT (8" WHITE, 90 MILS) GORE LINE NOT USED PAINT (24" WHITE, 120 MILS) STOP BAR PAINT ( WHITE ALPHANUMERIC CHARACTERS, 90 MILS) PAINT (WHITE TRAFFIC ARROW, 90 MILS) SITE LEGEND (CONTINUED) INFO BOOTH (PROVIDED BY MECKLENBURG COUNTY) 6' CHAIN LINK FENCE CONCRETE SCALES (PROVIDED BY CONTRACTOR) "STOP" SIGN. SEE DETAIL SHEET. ACCESSIBLE PARKING SPACE TYPICAL. SEE DETAIL SHEET FOR ACCESSIBLE PARKING SPACE SIZE, SIGN AND SYMBOL ("VAN"-INDICATES VAN ACCESSIBLE SPACE). SHORT TERM BICYCLE PARKING (2 REQUIRED) LONG TERM COVERED BICYCLE PARKING. SEE ARCH. PLANS. (1 REQUIRED) 20' WIDE FENCE GATE BOLLARDS PROPOSED MONUMENT SIGN (BY MECKLENBURG COUNTY) 4' WIDE FENCE GATE TRANSITION CURB POST CONSTRUCTION CONTROLS EASEMENT SITE LEGEND (CONTINUED) 6' TALL ELECTRIC CANTILEVERED SLIDING GATE (SEE DETAIL SHEET). ELECTRIC GATE TO HAVE DETECTOR LOOPS ON THE SECURE SIDE AND REMOTE ACCESS FROM THE PUBLIC SIDE. AP P R O V E D B Y CA D F I L E P A T H PR E P A R E D B Y CH E C K E D B Y DA T E JO B N O . SC A L E NO . D A T E B Y DE S C R I P T I O N K:\ C H L _ P R J \ 0 1 5 2 3 6 M e c k l e n b u r g C o u n t y \ 0 2 0 R e l o c a t e d C o m p o s t C e n t r a l \ 0 2 - D W G \ E x h i b i t \ 2 0 1 6 - 0 8 0 8 - S o l i d W a s t P e r m i t \ 6 2 2 0 - S I T E P L A N - 0 0 2 0 . d w g ME C K L E N B U R G C O U N T Y CO M P O S T A N D RE C Y C L I N G F A C I L I T Y MECKLENBURG COUNTY3205 FREEDOM DRIVE, SUITE 101CHARLOTTE, NC 28208 Pl a n s P r e p a r e d B y : C 2 0 1 5 NC L i c e n s e # F - 0 1 0 2 20 0 0 S o u t h B o u l e v a r d , S u i t e 4 4 0 Ch a r l o t t e , N C 2 8 2 0 3 FIGUREKnow what's R SI T E P L A N NORTH MATCHLINE - SEE SHEET 6221 - SITE PLAN 4.1 FIGURE STORMWATER POND WINDROWS PRODUCT STORAGE AND SCREENING AREA V A LL E Y D A L E R O A D (V A RIA B L E P U BLIC RIG H T-O F- W A Y) M B 55,P G 744; D B 23308,P G 927 F R E D D .A L E X A N D E R B O U L E V A R D (1 0 0 'P U B L I C R I G H T -O F -W A Y ) M B 5 5,P G 7 4 4 ;D B 2 3 3 0 8 ,P G 9 2 7 CURING PAD MAINTENANCE EQUIPMENT STORAGE FOREBAY G G GGGGGGGGGGGG GGGGGGG HHHHH HHHHHHHHHHHHHHHH H H H H H H H TE E E PP Y P V V P AA AA WW W 1 SITE LEGEND PROPOSED 30" CURB AND GUTTER, TYP. PROPOSED 18" CURB AND GUTTER, TYP. HANDRAIL (SEE DETAIL SHEET) PROPOSED CONCRETE SIDEWALK PROPOSED PARKING SPACE 9' X 18', TYP. (WHITE 4" PAINT STRIPING) PROPOSED RETAINING WALL (SEE STRUCTURAL PLANS) PROPOSED WINDROW (SEE SITE PLAN FOR SPACING) PROPOSED CURING PAD ROW (SEE SITE PLAN FOR SPACING) PROPOSED RECYCLING COMPACTORS WITH CONCRETE PAD (SEE DETAIL SHEETS) (COMPACTORS TO BE PROVIDED BY MECKLENBURG COUNTY) PROPOSED BULK CONTAINERS (PROVIDED BY MECKLENBURG COUNTY) 6' TALL MANUAL DOUBLE CANTILEVERED SLIDING GATE. (SEE DETAIL SHEET) PRODUCT WALL (PROVIDED BY MECKLENBURG COUNTY) SCREEN WALL (SEE ARCH. PLANS) WHEEL STOPS STRIPING LEGEND PAINT (4" WHITE, 120 MILS) 4" X 10" MINISKIP PAINT (4" WHITE, 120 MILS) SOLID LANE LINE PAINT (4" YELLOW, 120 MILS) SINGLE SOLID LINE PAINT (8" WHITE, 90 MILS) GORE LINE NOT USED PAINT (24" WHITE, 120 MILS) STOP BAR PAINT ( WHITE ALPHANUMERIC CHARACTERS, 90 MILS) PAINT (WHITE TRAFFIC ARROW, 90 MILS) SITE LEGEND (CONTINUED) INFO BOOTH (PROVIDED BY MECKLENBURG COUNTY) 6' CHAIN LINK FENCE CONCRETE SCALES (PROVIDED BY CONTRACTOR) "STOP" SIGN. SEE DETAIL SHEET. ACCESSIBLE PARKING SPACE TYPICAL. SEE DETAIL SHEET FOR ACCESSIBLE PARKING SPACE SIZE, SIGN AND SYMBOL ("VAN"-INDICATES VAN ACCESSIBLE SPACE). SHORT TERM BICYCLE PARKING (2 REQUIRED) LONG TERM COVERED BICYCLE PARKING. SEE ARCH. PLANS. (1 REQUIRED) 20' WIDE FENCE GATE BOLLARDS PROPOSED MONUMENT SIGN (BY MECKLENBURG COUNTY) 4' WIDE FENCE GATE TRANSITION CURB POST CONSTRUCTION CONTROLS EASEMENT SITE LEGEND (CONTINUED) 6' TALL ELECTRIC CANTILEVERED SLIDING GATE (SEE DETAIL SHEET). ELECTRIC GATE TO HAVE DETECTOR LOOPS ON THE SECURE SIDE AND REMOTE ACCESS FROM THE PUBLIC SIDE. AP P R O V E D B Y CA D F I L E P A T H PR E P A R E D B Y CH E C K E D B Y DA T E JO B N O . SC A L E NO . D A T E B Y DE S C R I P T I O N K:\ C H L _ P R J \ 0 1 5 2 3 6 M e c k l e n b u r g C o u n t y \ 0 2 0 R e l o c a t e d C o m p o s t C e n t r a l \ 0 2 - D W G \ E x h i b i t \ 2 0 1 6 - 0 8 0 8 - S o l i d W a s t P e r m i t \ 6 2 2 0 - S I T E P L A N - 0 0 2 0 . d w g ME C K L E N B U R G C O U N T Y CO M P O S T A N D RE C Y C L I N G F A C I L I T Y MECKLENBURG COUNTY3205 FREEDOM DRIVE, SUITE 101CHARLOTTE, NC 28208 Pl a n s P r e p a r e d B y : C 2 0 1 5 NC L i c e n s e # F - 0 1 0 2 20 0 0 S o u t h B o u l e v a r d , S u i t e 4 4 0 Ch a r l o t t e , N C 2 8 2 0 3 FIGUREKnow what's R SI T E P L A N NORTH MATCHLINE - SEE SHEET 6220 - SITE PLAN 4.2 FIGURE AP P R O V E D B Y CA D F I L E P A T H PR E P A R E D B Y CH E C K E D B Y DA T E JO B N O . SC A L E NO . D A T E B Y DE S C R I P T I O N K:\ C H L _ P R J \ 0 1 5 2 3 6 M e c k l e n b u r g C o u n t y \ 0 2 0 R e l o c a t e d C o m p o s t C e n t r a l \ 0 2 - D W G \ E x h i b i t \ 2 0 1 6 - 0 8 0 8 - S o l i d W a s t P e r m i t \ 6 2 5 0 - G R A D I N G A N D D R A I N A G E P L A N - 0 0 2 0 . d w g ME C K L E N B U R G C O U N T Y CO M P O S T A N D RE C Y C L I N G F A C I L I T Y MECKLENBURG COUNTY3205 FREEDOM DRIVE, SUITE 101CHARLOTTE, NC 28208 Pl a n s P r e p a r e d B y : C 2 0 1 5 NC L i c e n s e # F - 0 1 0 2 20 0 0 S o u t h B o u l e v a r d , S u i t e 4 4 0 Ch a r l o t t e , N C 2 8 2 0 3 FIGUREKnow what's R GR A D I N G A N D DR A I N A G E P L A N NORTH MATCHLINE - SEE SHEET 6251 - GRADING AND DRAINAGE PLAN 5.1 FIGURE AP P R O V E D B Y CA D F I L E P A T H PR E P A R E D B Y CH E C K E D B Y DA T E JO B N O . SC A L E NO . D A T E B Y DE S C R I P T I O N K:\ C H L _ P R J \ 0 1 5 2 3 6 M e c k l e n b u r g C o u n t y \ 0 2 0 R e l o c a t e d C o m p o s t C e n t r a l \ 0 2 - D W G \ E x h i b i t \ 2 0 1 6 - 0 8 0 8 - S o l i d W a s t P e r m i t \ 6 2 5 0 - G R A D I N G A N D D R A I N A G E P L A N - 0 0 2 0 . d w g ME C K L E N B U R G C O U N T Y CO M P O S T A N D RE C Y C L I N G F A C I L I T Y MECKLENBURG COUNTY3205 FREEDOM DRIVE, SUITE 101CHARLOTTE, NC 28208 Pl a n s P r e p a r e d B y : C 2 0 1 5 NC L i c e n s e # F - 0 1 0 2 20 0 0 S o u t h B o u l e v a r d , S u i t e 4 4 0 Ch a r l o t t e , N C 2 8 2 0 3 FIGUREKnow what's R GR A D I N G A N D DR A I N A G E P L A N NORTH MATCHLINE - SEE SHEET 6250 - GRADING AND DRAINAGE PLAN 5.2 FIGURE A A B C FE H H I F G G 6 11 13 13 11 12 1312 10 15 6 14 16 16 9 16 12 15 6 14 ROZZELLES FERRY ROAD (SR 1784) (VARIABLE PUBLIC RIGHT-OF-WAY) MB 55, PG 744 J 11 K K K K K I I 16 16 18 20 19 19 19 I I H I 16 D H 16 15 CLTWATER TRACKING NUMBER 600-15-550 WATER LINES TO BE PERMITTED SIZE (INCHES)MATERIAL LENGTH (LF) 3"PVC 2068 8"PVC 1469 TOTAL LF 3537 PVT. FH'S 5 ISSUING PROJECT PERMIT NUMBER ____________________ DATE__________ SIGNING OFFICIAL___________________ TITLE____________ 9 9 16 16 I 9 16 L L L L LL LL L L 6 21 M12 K K K K SANITARY SEWER NOTES 1. CONTRACTOR TO COORDINATE WITH CHARLOTTE WATER AND PAY FOR TIE IN TO CHARLOTTE WATER SANITARY SEWER PROPOSED FOR THIS PROJECT. 2. CONTRACTOR TO LOCATE LATERAL CONNECTIONS TO BUILDING PER PLUMBING PLANS. 3. PLACE CLEAN-OUTS ON SANITARY SEWER LATERALS AS REQUIRED BY PLUMBING CODE. 4. TRENCHES FOR SEWER LATERALS MUST REMAIN OPEN FOR PLUMBING INSPECTION. FIRE DEPARTMENT CONNECTION (F.D.C.) NOTES 5. ALL FIRE DEPARTMENT CONNECTIONS SHALL BE PROVIDED A CLEAR SPACE OF TEN FEET HORIZONTALLY AND VERTICALLY IN ALL DIRECTIONS. (GAS METERS, ELECTRICAL TRANSFORMERS, AND PARKED VEHICLES CANNOT BE LOCATED WITHIN THIS SPACE.) 6. ALL FIRE DEPARTMENT CONNECTIONS SHALL BE READILY VISIBLE AND NOT MORE THAN FIFTY FEET FROM A STREET, FIRE LANE, OR SIMILAR AREA PROVIDING ACCESS TO FIRE DEPARTMENT APPARATUS. THE AREA BETWEEN THE CONNECTION AND VEHICULAR ACCESS SHALL BE FREE OF OBSTRUCTION. 7. THERE SHALL BE AN APPROVED PUMPER FIRE HYDRANT WITHIN TWO HUNDRED FEET OF THE FIRE DEPARTMENT CONNECTION MEASURED ALONG AN APPROVED PATH OF TRAVEL FOR THE FIRE APPARATUS. 8. FOR ADDITIONAL INFORMATION OF FIRE PROTECTION SYSTEM, REFER TO FIRE PROTECTION PLANS BY OTHERS. UTILITY NOTES 9. SEE GENERAL NOTES SHEET FOR UTILITY PLAN NOTES. 10. ALL CHANGES IN DIRECTION OF THE CONDUIT SHALL UTILIZE STANDARD SWEEPS WITH A MINIMUM BENDING RADIUS LISTED IN THE NEC. NO MORE THAN (2) 90-DEGREE BENDS WILL BE ALLOWED BETWEEN PULLING POINTS, OR A TOTAL OF 180 DEGREES COMBINED IN SEVERAL BENDS. PULL BOXES SHALL BE LOCATED EVERY 400 FEET UNLESS THE COMBINED TOTAL OF BENDS REQUIRE ADDITIONAL MANHOLES. 11. ALL EMPTY CONDUITS SHALL HAVE PULL BOXES AT A MINIMUM EVERY 150', AND 200' OF RUN. EACH PULL BOX SHALL HAVE A ROAD GRADE LIDS MARKED "COMMUNICATIONS". 12. ALL CONDUITS FOR FUTURE USE (i.e. GATES), SHALL TERMINATE IN A PULL BOX WITH A ROAD GRADE LID MARKED "COMMUNICATIONS. BACKFLOW NOTES 13. THERE SHALL BE NO TAPS, PIPING BRANCHES, UNAPPROVED BYPASS PIPING, HYDRANTS, FIRE DEPT. CONNECTION POINTS, OR OTHER WATER USING APPURTENANCES CONNECTED TO THE SUPPLY LINE BETWEEN ANY WATER METER AND ITS CHARLOTTE WATER-REQUIRED BACKFLOW PREVENTER. 14. EACH CHARLOTTE WATER-REQUIRED BACKFLOW PREVENTION ASSEMBLY IS REQUIRED TO BE TESTED BY A CHARLOTTE WATER-APPROVED CERTIFIED TESTER PRIOR TO PLACING THE WATER SYSTEM IN SERVICE. 15. 2”, 3" AND 6" REDUCED PRESSURE PRINCIPLE BACKFLOW PREVENTION ASSEMBLY AS APPROVED BY CHARLOTTE WATER AND INSTALLED BY CONTRACTOR DURING CONSTRUCTION. ASSEMBLY TO BE INSTALLED ABOVE-GROUND WITHIN INSULATED ENCLOSURE PER CHARLOTTE WATER REQUIREMENTS. ENCLOSURE TO INCLUDE DRAIN PORT(S) FOR DISCHARGE WATER PER CHARLOTTE WATER REQUIREMENTS. ENCLOSURE TO BE LOCATED OUT OF SETBACK. SEE DETAILS. 16. PERMANENT INSULATION SHALL NOT BE INSTALLED ON BACKFLOW ASSEMBLY. BACKFLOW ASSEMBLY INSPECTOR REGARDING HEATING OPTIONS. 17. BACKFLOW ASSEMBLY SERVING A FIRE LINE SHALL BE HEATED TO MAINTAIN A MINIMUM OF 40° F. UTILITY NOTES WATER DISTRIBUTION NOTES 16. FIRE LINE METER INSTALLED BY CHARLOTTE WATER; CONTRACTOR IS RESPONSIBLE FOR COORDINATING AND PAYING FOR INSTALLATION. 17.3" DOMESTIC WATER METER INSTALLED BY CHARLOTTE WATER; CONTRACTOR IS RESPONSIBLE FOR COORDINATING AND PAYING FOR INSTALLATION. 18.2”, 3" AND 8" REDUCED PRESSURE PRINCIPLE BACKFLOW PREVENTION ASSEMBLY AS APPROVED BY CHARLOTTE WATER AND INSTALLED BY CONTRACTOR DURING CONSTRUCTION. ASSEMBLY TO BE INSTALLED ABOVE-GROUND WITHIN BUILDING PER CHARLOTTE WATER REQUIREMENTS. SEE DETAIL SHEETS FOR FURTHER INFORMATION. 19. CONTRACTOR TO LOCATE TIE-INS TO ALL BUILDINGS BASED ON PLUMBING PLANS. 20. ALL WATER MAINS 6" AND LARGER SHALL BE PVC IN ACCORDANCE WITH AWWA C-900. THE PIPE SHALL BE PRESSURE CLASS 200 WITH SDR OF 14. DUCTILE IRON PIPE (NO PVC) TO BE USED WITHIN 5 FT. OF BACKFLOW PREVENTION DEVICES. 21. THERE SHALL BE NO TAPS, PIPING BRANCHES, UNAPPROVED BYPASS PIPING, HYDRANTS, FIRE DEPT. CONNECTION POINTS, OR OTHER WATER USING APPURTENANCES CONNECTED TO THE SUPPLY LINE BETWEEN ANY WATER METER AND ITS CHARLOTTE WATER-REQUIRED BACKFLOW PREVENTER. 22. TAMPER SWITCHES TO BE INSTALLED ON THE FIRE LINE BACKFLOW PREVENTER. INSTALL 1" CONDUIT FROM FIRE LINE BACKFLOW VAULT TO BUILDING ALARM SYSTEM INSIDE BUILDING. COORDINATE WITH ALARM SYSTEM MANUFACTURER. 23. EACH CHARLOTTE WATER-REQUIRED BACKFLOW PREVENTION ASSEMBLY IS REQUIRED TO BE TESTED BY A CHARLOTTE WATER-APPROVED CERTIFIED TESTER PRIOR TO PLACING THE WATER SYSTEM IN SERVICE. 24. CONTRACTOR IS RESPONSIBLE FOR OBTAINING AN ENCROACHMENT AGREEMENT PERMIT TO CONSTRUCT UTILITY CONNECTIONS. 25. LOCATE FIRE DEPARTMENT CONNECTION (FDC) AS SHOWN ON THESE PLANS AND FIRE DEPARTMENT REQUIREMENTS. 26. ALL FIRE HYDRANTS SHALL HAVE A 5-INCH STORZ PUMPER CONNECTION. 27. ALL METERS SHALL HAVE A VALVE BEFORE AND AFTER METER PER CHARLOTTE WATER REQUIREMENTS (SEE CHARLOTTE WATER STANDARD DETAILS). 28. APPLY FOR CLTWATER TO MAKE SERVICE CONNECTIONS TO EXISTING PUBLIC WATER AND SEWER MAINS THROUGH THE NEW SERVICES SECTION. THE DEVELOPER'S CONTRACTOR IN NOT AUTHORIZED TO MAKE THE WATER AND SEWER SERVICE CONNECTIONS. UTILITY LEGEND 2" REDUCED PRESSURE PRINCIPAL BACKFLOW PREVENTION ASSEMBLY INSTALLED ABOVE GROUND WITHIN INSULATED ENCLOSURE PER CHARLOTTE WATER REQUIREMENTS. ENCLOSURE TO INCLUDE DRAIN PORT(S) FOR DISCHARGE WATER PER CHARLOTTE WATER REQUIREMENTS. 3" REDUCED PRESSURE PRINCIPAL BACKFLOW PREVENTION ASSEMBLY INSTALLED ABOVE GROUND WITHIN INSULATED ENCLOSURE PER CHARLOTTE WATER REQUIREMENTS. ENCLOSURE TO INCLUDE DRAIN PORT(S) FOR DISCHARGE WATER PER CHARLOTTE WATER REQUIREMENTS. 8" REDUCED PRESSURE PRINCIPAL BACKFLOW PREVENTION ASSEMBLY INSTALLED ABOVE GROUND WITHIN INSULATED ENCLOSURE PER CHARLOTTE WATER REQUIREMENTS. ENCLOSURE TO INCLUDE DRAIN PORT(S) FOR DISCHARGE WATER PER CHARLOTTE WATER REQUIREMENTS. 2" IRRIGATION METER 3" COMPOUND METER 8" DETECTOR CHECK,1" DETECTOR METER 12"X8" TAPPING SLEEVE & VALVE 8"X8"X8" TEE 4"X3" REDUCER 12"X4" TAPPING SLEEVE & VALVE 2"X2"X2" TEE 3"X3"X3" TEE 8" 90° BEND W/ BLOCKING 3" 90° BEND W/ BLOCKING 2" 90° BEND 8" GATE VALVE 3" GATE VALVE 2" GATE VALVE 12" X2" SERVICE SADDLE & CORPORATION STOP 2" 45° BEND 2" 22.5° BEND 2" 11.25° BEND 8"X8"X8" TEE UTILITY KEY NOTES 6" SANITARY SEWER LATERAL AT MINIMUM 0.6% SLOPE. COORDINATE WITH ARCHITECTURAL PLANS. GAS ENTRY WITH GAS METER. CONTRACTOR RESPONSIBLE FOR INSTALLING PIPE BOLLARD PROTECTION AT METER. CONTRACTOR SHALL COORDINATE WITH GAS COMPANY FOR TYING OF INDIVIDUAL METER. CONTRACTOR IS RESPONSIBLE FOR COORDINATION WITH GAS COMPANY REGARDING THE SIZE AND INSTALLATION OF GAS SERVICE LINE. PROPOSED LOCATION OF TRANSFORMER PAD. CONTRACTOR TO VERIFY EXACT LOCATION AND SIZE WITH POWER COMPANY PRIOR TO INSTALLATION. CONTRACTOR SHALL BE RESPONSIBLE FOR INSTALLATION OF CONCRETE PAD. CONDUIT AND PIPE BOLLARDS AS REQUIRED BY THE ELECTRIC COMPANY. CONTRACTOR SHALL COORDINATE SAID WORK WITH THE ELECTRIC COMPANY. FINAL LOCATION OF TRANSFORMER AND BOLLARD CANNOT CONFLICT WITH TRUCK ACCESS TO DOCK DOOR. UNDERGROUND TELEPHONE FROM POLE TO BUILDING TO BE EXTENDED BY TELEPHONE COMPANY. CONTRACTOR IS RESPONSIBLE TO COORDINATE WITH THE TELEPHONE COMPANY FOR THE INSTALLATION OF OVERHEAD TELEPHONE LINES. CONTRACTOR SHALL COORDINATE THE TYING OF INDIVIDUAL METERS WITH THE ELECTRIC COMPANY. CONTRACTOR TO COORDINATE WITH TELEPHONE COMPANY TO INSURE PROPER SEPARATION BETWEEN OVERHEAD LINES AND LIGHT POLES. 3" DOMESTIC WATER LINE ENTRY. CONTRACTOR SHALL BE RESPONSIBLE FOR INSTALLING ANY APPURTENANCES ON THE DOMESTIC LINE SUCH AS BACKFLOW PREVENTION DEVICES, GATE VALVES, ETC., WHICH MAY BE REQUIRED. CONTRACTOR TO COORDINATE WITH CHARLOTTE WATER. PROPOSED PVT. FIRE HYDRANT AND ASSEMBLY, TYPICAL AS INDICATED. SEE DETAIL SHEET. YARD HYDRANT. SEE DETAIL SHEET PROPOSED LOCATION OF GAS LINE FOR FUTURE COMPRESSED NATURAL GAS FUELING STATION. 2" SCHEDULE 40 PVC CONDUIT PULL BOXES EVERY 300' OR (2) 90° BENDS. ALL PULL BOXES LOCATED IN PAVED AREAS SHALL BE "H-20" LOAD RATED. THE TYPICAL PULL BOX SIZE WILL BE 17"X30"X28" "QUAZITE" PG1730BA28 BOX WITH PG1730HH00 LID OR APPROVED EQUAL. DEEPER BOXES MAY BE REQUIRED WHEN THE CONDUIT ALIGNMENT IS AFFECTED BY OTHER UTILITIES. THE PULL BOX SHALL BE INSTALLED PER THE MANUFACTURER'S SPECIFICATION WITH A CONCRETE COLLAR AND A MINIMUM OF 8" OF GRAVEL COMPACTED PER PROJECT SPECIFICATIONS. 6" FIRE ENTRY. CONTRACTOR SHALL BE RESPONSIBLE FOR INSTALLING ANY APPURTENANCES ON THE DOMESTIC LINE SUCH AS BACKFLOW PREVENTION DEVICES, GATE VALVES, ETC., WHICH MAY BE REQUIRED. CONTRACTOR TO COORDINATE WITH CHARLOTTE WATER. AP P R O V E D B Y CA D F I L E P A T H PR E P A R E D B Y CH E C K E D B Y DA T E JO B N O . SC A L E NO . D A T E B Y DE S C R I P T I O N K:\ C H L _ P R J \ 0 1 5 2 3 6 M e c k l e n b u r g C o u n t y \ 0 2 0 R e l o c a t e d C o m p o s t C e n t r a l \ 0 2 - D W G \ E x h i b i t \ 2 0 1 6 - 0 8 0 8 - S o l i d W a s t P e r m i t \ 6 2 8 0 - U T I L I T Y P L A N - 0 0 2 0 . d w g ME C K L E N B U R G C O U N T Y CO M P O S T A N D RE C Y C L I N G F A C I L I T Y MECKLENBURG COUNTY3205 FREEDOM DRIVE, SUITE 101CHARLOTTE, NC 28208 Pl a n s P r e p a r e d B y : C 2 0 1 5 NC L i c e n s e # F - 0 1 0 2 20 0 0 S o u t h B o u l e v a r d , S u i t e 4 4 0 Ch a r l o t t e , N C 2 8 2 0 3 FIGURE AP P R O V E D B Y CA D F I L E P A T H PR E P A R E D B Y CH E C K E D B Y DA T E JO B N O . SC A L E NO . D A T E B Y DE S C R I P T I O N K:\ C H L _ P R J \ 0 1 5 2 3 6 M e c k l e n b u r g C o u n t y \ 0 2 0 R e l o c a t e d C o m p o s t C e n t r a l \ 0 2 - D W G \ E x h i b i t \ 2 0 1 6 - 0 8 0 8 - S o l i d W a s t P e r m i t \ 6 2 8 0 - U T I L I T Y P L A N - 0 0 2 0 . d w g ME C K L E N B U R G C O U N T Y CO M P O S T A N D RE C Y C L I N G F A C I L I T Y MECKLENBURG COUNTY3205 FREEDOM DRIVE, SUITE 101CHARLOTTE, NC 28208 Pl a n s P r e p a r e d B y : C 2 0 1 5 NC L i c e n s e # F - 0 1 0 2 20 0 0 S o u t h B o u l e v a r d , S u i t e 4 4 0 Ch a r l o t t e , N C 2 8 2 0 3 FIGURE Know what's R UT I L I T Y P L A N NORTH MATCHLINE - SEE SHEET 6281 - UTILITY PLAN DETAIL "B" DETAIL "A" 6.1 A I 16 H I 16 16 I 16 11 K K I169 L L UTILITY LEGEND 2" REDUCED PRESSURE PRINCIPAL BACKFLOW PREVENTION ASSEMBLY INSTALLED ABOVE GROUND WITHIN INSULATED ENCLOSURE PER CHARLOTTE WATER REQUIREMENTS. ENCLOSURE TO INCLUDE DRAIN PORT(S) FOR DISCHARGE WATER PER CHARLOTTE WATER REQUIREMENTS. 3" REDUCED PRESSURE PRINCIPAL BACKFLOW PREVENTION ASSEMBLY INSTALLED ABOVE GROUND WITHIN INSULATED ENCLOSURE PER CHARLOTTE WATER REQUIREMENTS. ENCLOSURE TO INCLUDE DRAIN PORT(S) FOR DISCHARGE WATER PER CHARLOTTE WATER REQUIREMENTS. 8" REDUCED PRESSURE PRINCIPAL BACKFLOW PREVENTION ASSEMBLY INSTALLED ABOVE GROUND WITHIN INSULATED ENCLOSURE PER CHARLOTTE WATER REQUIREMENTS. ENCLOSURE TO INCLUDE DRAIN PORT(S) FOR DISCHARGE WATER PER CHARLOTTE WATER REQUIREMENTS. 2" IRRIGATION METER 3" COMPOUND METER 8" DETECTOR CHECK,1" DETECTOR METER 12"X8" TAPPING SLEEVE & VALVE 8"X8"X8" TEE 4"X3" REDUCER 12"X4" TAPPING SLEEVE & VALVE 2"X2"X2" TEE 3"X3"X3" TEE 8" 90° BEND W/ BLOCKING 3" 90° BEND W/ BLOCKING 2" 90° BEND 8" GATE VALVE 3" GATE VALVE 2" GATE VALVE 12" X2" SERVICE SADDLE & CORPORATION STOP 2" 45° BEND 2" 22.5° BEND 2" 11.25° BEND 8"X8"X8" TEE UTILITY KEY NOTES 6" SANITARY SEWER LATERAL AT MINIMUM 0.6% SLOPE. COORDINATE WITH ARCHITECTURAL PLANS. GAS ENTRY WITH GAS METER. CONTRACTOR RESPONSIBLE FOR INSTALLING PIPE BOLLARD PROTECTION AT METER. CONTRACTOR SHALL COORDINATE WITH GAS COMPANY FOR TYING OF INDIVIDUAL METER. CONTRACTOR IS RESPONSIBLE FOR COORDINATION WITH GAS COMPANY REGARDING THE SIZE AND INSTALLATION OF GAS SERVICE LINE. PROPOSED LOCATION OF TRANSFORMER PAD. CONTRACTOR TO VERIFY EXACT LOCATION AND SIZE WITH POWER COMPANY PRIOR TO INSTALLATION. CONTRACTOR SHALL BE RESPONSIBLE FOR INSTALLATION OF CONCRETE PAD. CONDUIT AND PIPE BOLLARDS AS REQUIRED BY THE ELECTRIC COMPANY. CONTRACTOR SHALL COORDINATE SAID WORK WITH THE ELECTRIC COMPANY. FINAL LOCATION OF TRANSFORMER AND BOLLARD CANNOT CONFLICT WITH TRUCK ACCESS TO DOCK DOOR. UNDERGROUND TELEPHONE FROM POLE TO BUILDING TO BE EXTENDED BY TELEPHONE COMPANY. CONTRACTOR IS RESPONSIBLE TO COORDINATE WITH THE TELEPHONE COMPANY FOR THE INSTALLATION OF OVERHEAD TELEPHONE LINES. CONTRACTOR SHALL COORDINATE THE TYING OF INDIVIDUAL METERS WITH THE ELECTRIC COMPANY. CONTRACTOR TO COORDINATE WITH TELEPHONE COMPANY TO INSURE PROPER SEPARATION BETWEEN OVERHEAD LINES AND LIGHT POLES. 3" DOMESTIC WATER LINE ENTRY. CONTRACTOR SHALL BE RESPONSIBLE FOR INSTALLING ANY APPURTENANCES ON THE DOMESTIC LINE SUCH AS BACKFLOW PREVENTION DEVICES, GATE VALVES, ETC., WHICH MAY BE REQUIRED. CONTRACTOR TO COORDINATE WITH CHARLOTTE WATER. PROPOSED PVT. FIRE HYDRANT AND ASSEMBLY, TYPICAL AS INDICATED. SEE DETAIL SHEET. YARD HYDRANT. SEE DETAIL SHEET PROPOSED LOCATION OF GAS LINE FOR FUTURE COMPRESSED NATURAL GAS FUELING STATION. 2" SCHEDULE 40 PVC CONDUIT PULL BOXES EVERY 300' OR (2) 90° BENDS. ALL PULL BOXES LOCATED IN PAVED AREAS SHALL BE "H-20" LOAD RATED. THE TYPICAL PULL BOX SIZE WILL BE 17"X30"X28" "QUAZITE" PG1730BA28 BOX WITH PG1730HH00 LID OR APPROVED EQUAL. DEEPER BOXES MAY BE REQUIRED WHEN THE CONDUIT ALIGNMENT IS AFFECTED BY OTHER UTILITIES. THE PULL BOX SHALL BE INSTALLED PER THE MANUFACTURER'S SPECIFICATION WITH A CONCRETE COLLAR AND A MINIMUM OF 8" OF GRAVEL COMPACTED PER PROJECT SPECIFICATIONS. 6" FIRE ENTRY. CONTRACTOR SHALL BE RESPONSIBLE FOR INSTALLING ANY AP P R O V E D B Y CA D F I L E P A T H PR E P A R E D B Y CH E C K E D B Y DA T E JO B N O . SC A L E NO . D A T E B Y DE S C R I P T I O N K:\ C H L _ P R J \ 0 1 5 2 3 6 M e c k l e n b u r g C o u n t y \ 0 2 0 R e l o c a t e d C o m p o s t C e n t r a l \ 0 2 - D W G \ E x h i b i t \ 2 0 1 6 - 0 8 0 8 - S o l i d W a s t P e r m i t \ 6 2 8 0 - U T I L I T Y P L A N - 0 0 2 0 . d w g ME C K L E N B U R G C O U N T Y CO M P O S T A N D RE C Y C L I N G F A C I L I T Y MECKLENBURG COUNTY3205 FREEDOM DRIVE, SUITE 101CHARLOTTE, NC 28208 Pl a n s P r e p a r e d B y : C 2 0 1 5 NC L i c e n s e # F - 0 1 0 2 20 0 0 S o u t h B o u l e v a r d , S u i t e 4 4 0 Ch a r l o t t e , N C 2 8 2 0 3 FIGURE MATCHLINE - SEE SHEET 6280 - UTILITY PLAN Know what's R NORTH 1. SEE SHEET 6280 - UTILITY PLAN FOR NOTES. UTILITY NOTES UT I L I T Y P L A N 6.2