HomeMy WebLinkAboutCCB0057_CorrectiveActionUpdate_DIN28129_20170627Swift Creek Corrective Action Plan Implementation
Monthly Project Update – Prepared by ERM NC, Inc.
Report #2 – June 26, 2017
ReUse Technology, Inc.
Former Swift Creek Coal Combustion By Product
(CCB) Structural Fill, CCB0057
Battleboro, North Carolina
Introduction
ERM NC, Inc. (ERM) has been contracted by ReUse Technology, Inc. (ReUse) to implement the
Groundwater Corrective Action Plan for the Former Swift Creek Coal Combustion By Product
(CCB) Structural Fill, CCB0057 approved by NCDEQ – Division of Waste Management on
March 12, 2015. As requested by NCDEQ, ERM will provide monthly updates to summarize
site activities including any changes in conditions as the project progresses.
ERM has subcontracted Earnhardt Grading, Inc. (Earnhardt) of Lowesville, North Carolina to
provide site preparation, excavation, grading, geosynthetic installation and final site
stabilization. ERM and Earnhardt have been on the Swift Creek site full time beginning April
24, 2017 for construction activities. ERM has compiled weekly update status reports that are
attached for reference.
Summary of Activities
Since the previously issued Monthly Project Update dated June 24, 2017, ERM and Earnhardt
Grading have remained onsite full time conducting corrective action plan activities. These
activities included:
Removal of CCB materials from the south end (Phase 1 area) of the project site.
Stockpiling of CCB materials on the north end (Phase 2) area of the project site.
Maintaining erosion and sedimentation control measures per NCDEMLR – Division of
Land Quality approved plans (approved March 31, 2017).
Excavation and removal of previously abandoned 24-inch reinforced concrete storm
pipe (partially complete).
Maintaining previously stockpiled cover soils area at the south end of the project site.
At the end of this second month of construction activities, Earnhardt has completed CCB
material removal of approximately 60 percent of the Phase 1 footprint area. Due to heavy rains
in the vicinity of the project, there have been several days lost to production due to weather
and/or wet conditions.
ERM NC, Inc.
15720 Brixham Hill Avenue
Suite 120
Charlotte, NC 28277
(704) 541-8345
(704) 541-8416 (fax)
Swift Creek Monthly Update Report #2 Page 2
June 26, 2017
Site Observations
To date there have been no visual indications of dust migration off site.
Since arriving on site, approximately 21-inches of rain has been recorded based on the
onsite rain gage and monitoring.
Erosion and sedimentation control measures are functioning appropriately and there
have been no observations of offsite sediment releases.
Monitoring wells have been marked with construction fence and maintained throughout
construction activities.
The abandoned 24-inch diameter reinforced concrete storm pipe located in the Phase 1
area of the project site was encountered on 6/8/17 while performing CCB material
removal along the southeastern portion of the site. At this location the pipe was open
and contained water; not full of grout as previously reported by the site owner. The
pipe continued open to the east approximately 60 feet from point of discovery and the
outlet end was observed as submerged in the “swamp area”. This section of pipe was
removed from the outlet to the point of discovery within the Phase 1 area. Following
removal, this area was backfilled with onsite soils to re-establish runoff containment
within Phase 1 of the project. As removal of ash continues from south to north, the pipe
will be evaluated for containing grout or open. If the pipe is open, pipe will be removed
and transported to the ash stockpile area. If the pipe is found to be filled with grout and
appears structurally sound, it may remain in place. The locations of pipe, pipe
abandonment and results of observations will be recorded. Reference the attached
Weekly Report dated June 14, 2017 for additional information.
ERM discussed the discovery of the pipe and conditions with Jackie Drummond of
NCDEQ on June 12, 2017.
Please let us know if you should have any questions or require additional information
concerning this report or attachments.
ERM NC, Inc.
David W. Wasiela, P.E.
Project Engineer
Attch: Weekly Update Reports
ReUse Technology, Inc.
Swift Creek Project
Weekly Update – May 31, 2017
Key Items Completed Last Week:
Permit Related
1. NCDEQ; DEMLR – Land Quality – Thad Valentine was notified that erosion and
sedimentation control measures are in place for an onsite meeting. Thad replied that he
would stop by next time he was in the area. No visit has occurred yet.
2. NCDEQ – Waste Management – Reached out to Jackie Drummond to ask if the Division
had decided on a date to visit the site. Jackie responded that it would likely be
sometime in July. Meeting has not been scheduled yet.
Project Related
3. Earnhardt Grading and ERM remain on site full time since 4/24/17.
4. Earnhardt has finished removal of topsoil and cover materials minus one path for access
on the west side of the site.
5. Excavation of ash materials has begun on the south end of the site with transportation to
the north end; excavation of Phase 1 area. The bottom of the beneficial fill has been
identified in the south end of the project (see photos).
6. Thus far for the week the site is dry and Earnhardt was able to excavate and transport
202 loads of ash materials on Tuesday May 30th.
7. Photo Log of activities is attached for reference.
Two (2) Week Look Ahead (6/1/17 – 6/14/17):
8. Earnhardt and ERM will remain on site full time.
9. Continue excavating ash working routinely from south to north for preparation of Phase
1 area.
10. ERM will continue to update Full Circle concerning site activities.
11. ERM is preparing the first monthly update for NCDEQ – Division of Waste
Management.
ReUse Technology, Inc.
Swift Creek Project
Weekly Update – June 7, 2017
Key Items Completed Last Week:
Permit Related
1. NCDEQ; DEMLR – Land Quality – Thad Valentine was notified that erosion and
sedimentation control measures are in place for an onsite meeting. Thad replied that he
would stop by next time he was in the area. No visit has occurred yet.
2. NCDEQ – Waste Management – Reached out to Jackie Drummond to ask if the Division
had decided on a date to visit the site. Jackie responded that it would likely be
sometime in July. Meeting has not been scheduled yet.
Project Related
3. Earnhardt Grading and ERM remain on site full time since 4/24/17.
4. Excavation of ash materials continues on the south end of the site with transportation to
the north end; excavation of Phase 1 area. The bottom of the beneficial fill has been
identified in the south end of the project (see photos).
5. This week the site is wet causing slow work Monday through Tuesday. Earnhardt was
able to work Sunday. To date Earnhardt has reported moving approximately 15,000
cubic yards. Progress Plan attached.
6. Tom Sears with Full Circle visited the site the morning of 6/7/17 and toured the
progress with Chris Means of ERM. Chris reports that Tom seemed pleased with the
progress and site conditions.
7. Photo Log of activities is attached for reference.
8. Progress Plan attached for reference.
Two (2) Week Look Ahead (6/7/17 – 6/21/17):
9. Earnhardt and ERM will remain on site full time.
10. Continue excavating ash working routinely from south to north for preparation of Phase
1 area.
11. ERM will continue to update Full Circle concerning site activities as needed.
ReUse Technology, Inc.
Swift Creek Project
Weekly Update – June 14, 2017
Key Items Completed Last Week:
Permit Related
1. NCDEQ; DEMLR – Land Quality – Thad Valentine was notified on May 12, 2017 that
erosion and sedimentation control measures are in place for an onsite meeting. Thad
replied that he would stop by next time he was in the area. No visit has occurred yet.
2. NCDEQ – Waste Management
a. On site meeting with NCDEQ is scheduled for August 8, 2017 at 9:00 am.
b. ERM updated Jackie Drummond via phone call on June 8, 2017 concerning open
pipe discovered in lieu of abandoned pipe. Jackie requested no additional
information and was appreciative of the update. ERM reported to Jackie that the
open pipe was removed and berm area was backfilled for containment. ERM
also added that the pipe will be discussed in our next monthly update report.
Project Related
3. Earnhardt Grading and ERM remain on site full time since 4/24/17.
4. Excavation of ash materials continues on the south end of the site with transportation to
the north end; excavation of Phase 1 area. The bottom of the beneficial fill continues to
be identified in the south end of the project (see photos).
5. This week the site has been dry allowing for good production. Phase 1 ash removal is
approximately 36% complete. Progress Plan attached.
6. Open reinforced concrete pipe discovered along east side of fill area approximately 30-ft
north of monitoring wells MW-1S and MW-1D. This pipe was reportedly abandoned
with grout according to Full Circle. Tom Sears with Full Circle was notified of the open
pipe discovery on Friday June 9th. Tom indicated that the pipe was abandoned from the
west end near Highway 301 by filling with grout. It appears that grout never reached
the east end of the pipe run. ERM developed a Technical Memorandum on June 9th and
distributed to Client Team. To date, Earnhardt has removed approximately 64 feet of
the reinforced concrete pipe working from the east end outlet west into the fill area. All
pipe removed has been observed as open. East berm was backfilled with soil following
pipe removal to maintain containment.
7. Water gathered in the area of the open pipe discovery was pumped to two (2) sprinklers
located on the top of the fill area to limit the amount of “ash contact water” reaching the
east basin and to also assist with dust control. Following pumping the water level did
not recover to original elevation upon discovery.
8. On June 12th, Earnhardt along with ERM pumped water into the storm water catch basin
along US 301 using the onsite water wagon and monitored the east end of the open pipe
to observe indications of increased flow. There was no increased flow at the east end
observed. Therefore, the reinforced concrete pipe may still be adequately abandoned at
some location within the fill area.
9. On the morning of June 12th, a vehicle accident occurred in front of the project site
entrance and office trailer location involving a State Trooper patrol car losing control
during a high speed pursuit and landing in the north bound roadside ditch within the
US highway 301 right of way. There was no property damage to the project site as the
incident was confined to the right of way limits. ERM observed orange conduit piping
exposed following removal of the car from the ditch area that may be associated with
the fiber optic communication line along 301.
10. Photo Log of activities is attached for reference.
11. Progress Plan attached for reference.
Two (2) Week Look Ahead (6/14/17 – 6/28/17):
12. Earnhardt and ERM will remain on site full time.
13. Continue excavating ash working routinely from south to north for preparation of Phase
1 area. Anticipate completing Phase 1 removal within the next two weeks.
14. An ERM onsite health and safety audit is scheduled for June 21st led by ERM’s Health
and Safety Director for the South Atlantic region.
15. ERM will continue to update Full Circle concerning site activities as needed.
Schedule
Original schedule submitted by Earnhardt completes removal of CCR materials from
Phase 1 area 10 weeks from beginning mobilization. Currently at 7-1/2 weeks Phase 1
removal is 36% complete with good production each day. With good workable weather
the project should remain on schedule.
ReUse Technology, Inc.
Swift Creek Project
Weekly Update – June 21, 2017
Key Items Completed Last Week:
Permit Related
1. NCDEQ; DEMLR – Land Quality – Thad Valentine was notified on May 12, 2017 that
erosion and sedimentation control measures are in place for an onsite meeting. Thad
replied that he would stop by next time he was in the area. No visit has occurred yet.
2. NCDEQ – Waste Management
a. On site meeting with NCDEQ is scheduled for August 8, 2017 at 9:00 am.
Project Related
3. Earnhardt Grading and ERM remain on site full time since 4/24/17.
4. Excavation of ash materials continues on the south end of the site with transportation to
the north end; excavation of Phase 1 area. The bottom of the beneficial fill continues to
be identified in the south end of the project (see photos).
5. ERM is conducting a health and safety audit at the site on 6/21/17 with ERM’s South
Atlantic Health & Safety Director Millard Griffin along with Earnhardt Grading’s Health
& Safety Director Anthony Dohmann.
6. Former temporary ash stockpile area located near the center of the site was removed and
transported to the north ash stockpile area.
7. This week the site has had over an inch of rain slowing production. Phase 1 ash removal
is approximately 60% complete. Progress Plan attached.
8. Due to rain, no work on site Tuesday June 20th. Photo Log of activities is attached for
reference.
9. Progress Plan attached for reference.
Two (2) Week Look Ahead (6/21/17 – 7/5/17):
10. Earnhardt and ERM will remain on site full time.
11. Continue excavating ash working routinely from south to north for preparation of Phase
1 area. Anticipate completing Phase 1 removal within the next two weeks.
12. Currently discussing an alternate approach including raising the first half of the Phase 1
floor to receive ash materials as the north stockpile is becoming difficult to manage due
to wet conditions. The floor would be raised using on site soils, compacted and
surveyed prior to receiving ash materials.
13. ERM will continue to update Full Circle concerning site activities as needed.
14. Earnhardt is discussing work schedule around July 4th holiday and will update.
15. ERM will prepare the second monthly update for NCDEQ for submittal on June 26th.
Schedule
Schedule submitted by Earnhardt completes removal of CCR materials from Phase 1
area 10 weeks from beginning mobilization. Currently at 8-1/2 weeks Phase 1 removal
is 60% complete with production delayed by rain. A 40 – 60 percent chance of rain
remains in the forecast for the next several days.