HomeMy WebLinkAbout4302_INSP_20170426FACILITY COMPLIANCE INSPECTION REPORT
Division of Waste Management
Solid Waste Section
Page 1 of 4
UNIT TYPE:
Lined
MSWLF LCID X YW Transfer Compost SLAS COUNTY: HARNETT
Closed
MSWLF X HHW White
goods Incin T&P FIRM PERMIT NO.: 4302-CDLF-1998
CDLF Tire T&P /
Collection Tire
Monofill Industrial
Landfill DEMO SDTF FILE TYPE: COMPLIANCE
Date of Site Inspection: April 26, 2017 Date of Last Inspection: August 5, 2016
FACILITY NAME AND ADDRESS:
Dunn-Erwin C&D Landfill
449 Daniels Road,
Dunn, NC 28334
GPS COORDINATES: N: 35.36564 W: 78.64981
FACILITY CONTACT NAME AND PHONE NUMBER:
Randy Smith
910-897-3222
FACILITY CONTACT ADDRESS:
Amanda L. Bader, PE, LEED AP County Engineer
Harnett County Engineering and Facilities Management
P.O. Box 2773, Lillington, NC 27546
Phone 910-814-6156 Fax 910-814-4041
abader@harnett.org
PARTICIPANTS:
Liz Patterson – NCDEQ, Solid Waste Section
Bryan Davis – Harnett County
STATUS OF PERMIT:
Approval of Transition Plan – January 22, 1996
Closure of Landfill units Phase I and II – March 19, 1996
Approval of Borrow Location #2 – May 8, 1998
MSWLF Facility Transition Plan Modification #3 – June 30, 1998
MSWLF Facility Transition Plan Modification #4 – March 3, 1999
To be reviewed by February 3, 2003, extension of permit requested August 14, 2003
PTO expired July 1, 2008, extension of permit requested June 26, 2008
PTO and PTC issued May 26, 2015
PTC expires November 28, 2016
PTO expires May 24, 2020
PURPOSE OF SITE VISIT:
Partial Inspection
STATUS OF PAST NOTED VIOLATIONS:
NONE
OBSERVED VIOLATIONS:
NONE
FACILITY COMPLIANCE INSPECTION REPORT
Division of Waste Management
Solid Waste Section
Page 2 of 4
ADDITIONAL COMMENTS
C&DLF
1. The service area for this facility is Harnett County.
2. The hours of operation are 7:30am – 4:30 pm Monday thru Saturday except close at 12:00pm Wednesday.
3. The facility has proper signage.
4. The facility is properly secured with a locked gate. Personnel are onsite during operating hours.
5. Records were not reviewed during this inspection.
6. The working face was being well managed and was not exceeding the ½ acre size limit. Six inches of earthen
material should be properly applied once weekly or when the working face reaches ½ acre.
7. Several areas of erosion and exposed waste observed along the eastern and southern side slopes. Recent
heavy rains had contributed to site condition. Adequate sediment control measures consisting of
vegetative cover, materials, structures or devices must be utilized to prevent excessive on-site erosion of
the C&DLF facility or unit. Additional areas of waste outside the working face were exposed and needed
additional cover. Areas that become uncovered from other activities or erosion need to be covered as they
are noticed.
8. The waste type was reviewed and was construction and demolition waste. No unacceptable waste streams were
noted.
9. Tires are being removed as they are noticed.
10. Other than minimal windblown waste observed in southern sediment pond windblown waste is being well-
managed. Windblown waste must be collected and returned to the working face prior to close of business daily.
LCID Landfill
1. Mulch has been moved and is only being stored in approved areas per updated facility plan. Some of the mulch
is being used for stabilization of the side slopes on the CDLF.
2. Yard waste area has been graded to ensure positive drainage of surface water off the yard waste area.
3. LCID has been graded accordingly and has a defined working face. All areas of waste that were not part of the
working face have been properly covered. Active area was not exceeding one acre maximum size.
4. Permanent waste boundary markers have been installed around the entire to include active and inactive areas.
Existing markers have been repaired and repainted to make them clearly visible. Good job!
Closed MSWLF
5. Closed MSW has been mowed and could be properly inspected.
6. Continue to monitor for areas of settling and ponding water, especially after heavy rains. Continue to ensure
positive drainage of surface water off the closed landfill.
7. Asbestos area has been graded and properly covered. Asbestos is rarely received at the facility.
8. Yard waste stockpiled in the asbestos area has been moved to the yard waste area.
9. Digital pictures were taken during inspection.
The item(s) listed above were observed by Section staff and require action on behalf of the facility in order to come into or maintain compliance
with the Statutes, Rules, and/or other regulatory requirements applicable to this facility. Be advised that pursuant to N.C.G.S. 130A-22, an
administrative penalty of up to $15,000 per day may be assessed for each violation of the Solid Waste Laws, Regulations, Conditions of a Permit,
or Order under Article 9 of Chapter 130A of the N.C. General Statutes. Further, the facility and/or all responsible parties may also be subject to
enforcement actions including penalties, injunction from operation of a solid waste management facility or a solid waste collection service and any
such further relief as may be necessary to achieve compliance with the North Carolina Solid Waste Management Act and Rules.
FACILITY COMPLIANCE INSPECTION REPORT
Division of Waste Management
Solid Waste Section
Page 3 of 4
Please contact me if you have any questions or concerns regarding this inspection report.
Phone: 919-707-8286(O) 919-805-6499(C)
elizabeth.patterson@ncdenr.gov
Liz Patterson
Environmental Senior Specialist
Regional Representative
Sent on: 6-2-2016 X Email Hand delivery US Mail Certified No. [ _]
Copies: Drew Hammonds, Eastern District Supervisor - Solid Waste Section
Jessica Montie, Compliance Officer - Solid Waste Section
Pieter Scheer, P.E. – Smith + Gardner
FACILITY COMPLIANCE INSPECTION REPORT
Division of Waste Management
Solid Waste Section
Page 4 of 4
Digital pictures taken by Liz Patterson on April 26, 2017
Working face of landfill Southern sediment pond
Areas of erosion on southeastern corner of CDLF
Areas of erosion on eastern side of CDLF