Werner, Elizabeth
From:Werner, Elizabeth
Sent:Thursday, May 18, 2017 9:25 AM
To:'Witt, Kimberlee'
Subject:RE: Mayo Steam Electric Plant Landfill (Permit No. 7305)
Dear Kim,
The Division of Waste Management, Solid Waste Section concurs with the alterations made to the assessment
schedule. Please don’t hesitate to contact me with any future questions or concerns.
Sincerely,
Elizabeth
Elizabeth S Werner
Permitting Hydrogeologist
North Carolina Department of Environmental Quality (DEQ)
Division of Waste Management
Solid Waste Section
Phone & Fax: 919.707.8253
Physical Address: 217 West Jones Street
Mailing Address: 1646 Mail Service Center Raleigh, NC 27699-1646
elizabeth.werner@ncdenr.gov
http://deq.nc.gov/
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
From: Witt, Kimberlee [mailto:Kimberlee.Witt@duke‐energy.com]
Sent: Wednesday, May 17, 2017 4:29 PM
To: Werner, Elizabeth <elizabeth.werner@ncdenr.gov>
Subject: Mayo Steam Electric Plant Landfill (Permit No. 7305)
Elizabeth‐
With this email Duke would like to inform the Division of a schedule alteration to the assessment activities at the Mayo
Steam Electric Plant Landfill (Permit No. 7305). The groundwater assessment workplan was submitted to your office on
1/31/17 and subsequently approved on 3/22/17.
As the project has progressed and detailed access field verified, Duke learned that there will need to be significant road
installation work to an existing embankment for three of the well clusters. The access road activities were determined
by Duke geotechnical engineers to require stability analysis and detailed construction plan development. The addition
of a geotechnical investigation and detailed construction plan development has required additional time including a
revision to the previously submitted E&SC plans.
2
The current proposed schedule for the assessment activities is outlined below. Please let me know if the Division
concurs with the alterations from the initial workplan schedule. Feel free to call with any questions or comments.
Thanks‐
Kim
Mayo Steam Electric Plant Landfill (Permit No. 7305) groundwater assessment schedule
Task Estimated Timeline
E&SC Plan preparation and submittal submitted 4/5/17
E&SC approval received 4/24/17
E&SC revision request for geotechnical
investigation
submitted 5/11/17
verbal approval 5/17/17
Geotechnical investigation and construction
package development
completed approximately 4 ‐ 6 weeks after
geotechnical field work
Monitoring well access and E&SC permit
implementation
completed approximately 4 ‐ 6 weeks after
completion of construction package completion
Monitoring well installation 5 weeks
Sample collection and analysis 2 weeks after completion of monitoring well
installation
Data validation 2 weeks after receipt of laboratory analytical
reports
Submittal of assessment report 8 weeks after completion of data validation
Kimberlee Witt, PE
DUKE ENERGY
Sr. Engineer - Environmental Services
3191 Pine Hall Rd.
Walnut Cove, NC 27009
336-215-4576