Frost, Larry
From:Wayne Sullivan <wsullivan@mesco.com>
Sent:Friday, January 20, 2017 11:09 AM
To:Frost, Larry
Subject:Re: one more issue
Larry,
The rock and dirt were removed from the lines by the contractor which we observed and not re-videoed.
We had them video all lines in the project including the ones without clean outs. The ones with clean outs will
be used for future videoing. The connection points where these lines tie into the trunk lines was that they
would not run their camera across the connections fearing that it might get lodged in the main line and they
would have trouble retrieving it. Regardless, the main line was videoed its entire length and each lateral was
down to the connection at the main lines.
If you need more than this, juts let me know.
Thanks and have a nice day.
On Fri, Jan 20, 2017 at 10:45 AM, Frost, Larry <larry.frost@ncdenr.gov> wrote:
Attached is page 890 of 933.
The Jetclean report calls out 3 issues highlighted with the leachate system.
Were the issues addressed, if not why not, if so how?
Your response will be added to the CQA.
Larry Frost
Engineering Project Manager
Division of Waste Management, Solid Waste Section
North Carolina Department of Environmental Quality
(828) 296-4704 office
(919) 608-3523 mobile
larry.frost@ncdenr.gov
2
Asheville Regional Office
2090 US Highway 70
Swannanoa, North Carolina 28778
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
--
D. Wayne Sullivan
Project Manager
Municipal Engineering Services Co. PA
Email: wsullivan@mesco.com
Phone: (919) 772-5393
Fax: (919) 772-1176