HomeMy WebLinkAbout4506_CrestRoad_Transfer_PermitDenial_DIN27181_20161221
PAT MCCRORY
Governor
DONALD R. VAN DER VAART
Secretary
MICHAEL SCOTT
Director
State of North Carolina | Environmental Quality | Waste Management
1646 Mail Service Center | 217 West Jones Street | Raleigh, NC 27699-1646
919 707 8200 T
December 21, 2016
Mr. Mark Pace, Owner
Pace Construction and Excavation, Inc.
625 Old Spartanburg Highway
Hendersonville, North Carolina 28792
Subject: Permit to Operate Application – Denial
Crest Road Recycling LLC – Transfer, Recycle Resource Recovery and
Processing Facility
Henderson County, DIN 27181
Dear Mr. Pace,
On January 14, 2014 the Division of Waste Management, Solid Waste Section (Section) sent you
a letter regarding your permit application entitled;
Permit to Operate Application – On Hold, Crest Road Recycling LLC – Transfer, Recycle
Resource Recovery and Processing Facility, Henderson County, DIN 20410. Prepared by the
Division of Waste Management. January 2014.
The letter informed you that your application for a transfer facility permit in Henderson County
had been placed on hold. The application was deemed incomplete because the required financial
assurance required for the permit was never established. The letter also established a final action
date of December 15, 2016, for you to submit the required information. Given the application
remains deficient, and there have been no communications regarding a desire or plan to remedy
the deficiencies, the Section cannot make a decision on the application. As a result, your
application for a permit to construct and operate a transfer facility is hereby cancelled.
If you should have any questions regarding this matter please contact me at (828) 296-4704, or
by email at larry.frost@ncdenr.gov .
Sincerely,
Larry Frost, Engineering Project Manager
Permitting Branch, Solid Waste Section
Division of Waste Management, NCDEQ
ec: Kris Riddle – SWS/ARO
Ed Mussler – SWS/RCO