HomeMy WebLinkAbout2509_CRSWMAdrillplan_DIN26024_20160428.pdf 2211 West Meadowview Road Suite 101 Greensboro, NC 27407 tel: 336-323-0092 fax: 336-323-0093 www.JoyceEngineering.com April 28, 2016 Christine Ritter, P.G., Hydrogeologist Division of Waste Management- Solid Waste Section NC Department of Environmental Quality 1646 Mail Service Center Raleigh, NC 27699-1646 RE: Coastal Regional Solid Waste Management Authority’s Tuscarora Landfill Phase 4 Expansion Drilling Program JOYCE Project No. 618.1602.12, Task No. 01 Dear Christine: On behalf of the Coastal Regional Solid Waste Management Authority (CRSWMA) Joyce Engineering (JOYCE) is submitting this drilling and sampling plan for the proposed Phase 4 MSW landfill expansion. This plan is prepared to address the requirements of the Rule .1623 for geologic and hydrogeologic investigations for MSW landfills. The hydrogeologic field investigations will provide the data needed to complete the Design Hydrogeologic Report for the 17.7-acre Phase 4 expansion. This will include the installation of 11 piezometers within the proposed footprint of Phase 4 and six monitoring wells in the compliance area outside of the footprint for future monitoring of Phase 4. Most of the piezometers and wells will be constructed as nested pairs (one shallow and one deep in close proximity). The shallow wells/piezometers are expected to average 15 feet deep and will be screened in the upper-most aquifer, while the deeper wells/piezometers are expected to average 40 feet deep and will be screened in the deeper aquifer. Actual depths may vary based on conditions encountered during drilling. The attached drawing shows the approximate proposed locations of the wells and piezometers and the attached table summarizes the proposed drilling plan. There are currently five existing monitoring wells inside the Phase 4 footprint and two more that are less than 20 feet outside of the footprint. The proposed new wells and piezometers will bring the total number of borings in (or very near) the footprint to 18, or 24 if the compliance area is included. The proposed drilling plan is designed for a Geoprobe drill rig that can perform both direct-push and auger drilling. In lieu of continuous split-spoon sampling, we propose first collecting continuous Geoprobe soil cores to the desired total depth (typically 40 feet) at each drilling location, and then going back with hollow-stem augers to install the wells or piezometers. This will provide a more accurate determination of the stratigraphy, including identifying the clay Christine Ritter April 28, 2016 Page 2 of 2 aquitard which separates the upper and lower aquifers at this site. For locations with a nested pair, both the shallow and deep wells/piezometers will be drilled to a target depth and screened based on the stratigraphy observed in the soil core. During the auger drilling, we will collect one or two targeted split-spoon samples with Standard Penetration Test (STP) to confirm the characteristics of the soil. Shelby-tube samples will be collected for geotechnical testing from selected borings based on the soil core data. Lithological and geotechnical data will be collected from the borings during drilling, including collection of approximately eight Shelby-tube samples for geotechnical laboratory testing. The Shelby-tube samples will be tested for the following parameters: • Particle Size / Hydrometer Analysis (ASTM D 422); • Water Content (ASTM D 2216); • Unified Soil Classification (ASTM 2487); • Atterberg Limits (ASTM D 4318); • Flex Wall Permeameter (ASTM D 5084) (2-3 tests); and • Consolidated Triaxial Shear (ASTM D 4767) (1 test). One comprehensive set of groundwater level measurements will be obtained after the wells/piezometers are installed. These water level data, in conjunction with the historical water level data from the site, will be used to create a seasonal high water table and a long-term high water table map. Slug tests will be performed on selected wells/piezometers to determine the hydraulic conductivity of the shallow and deep aquifers. These data will be used to demonstrate compliance with vertical separation requirements, establish foundation characteristics, and provide more detailed understanding of the hydrogeologic regime beneath the Phase 4 footprint. This information is needed for landfill design requirements and to aide in the design of an effective water quality monitoring system. If you have any questions during your review of the proposed drilling plan, please contact either me or Van Burbach at (336) 323-0092. Sincerely, JOYCE ENGINEERING, INC. Hannu Kemppinen, P.G. Senior Project Consultant Attachments: Table - Proposed Phase 4 Drilling Program Drawing - Proposed Phase 4 Boring Locations cc: Bobby Darden, CRSWMA Alex Everhart, Joyce Engineering CRSWMA Tuscarora Landfill Permit # 25-09 Joyce Engineering Drilling MW/PZ Total Depth Screen Stick-up Geoprobe Split-spoons Shelby Surface Location ID (Feet)(Feet)(Feet)Cores w SPTs Tubes Completion PZ-40 S 15 10 3 1-2 No PZ-40 D 40 10 3 60' continuous 2 No PZ-41 S 15 10 3 1-2 No PZ-41 D 40 10 3 40' continuous 2 No PZ-42 S 15 10 3 1-2 No PZ-42 D 40 10 3 60' continuous 2 No PZ-43 S 15 10 3 1-2 No PZ-43 D 40 10 3 40' continuous 2 No PZ-44 S 15 10 3 1-2 No PZ-44 D 40 10 3 40' continuous No 6 PZ-45 15 10 3 20' continuous 1-2 No MW-20 S 15 10 3 20' continuous Yes MW-20 D 40 10 3 40' continuous Yes 8 MW-21 15 10 3 20' continuous Yes MW-22 S 15 10 3 20' continuous Yes MW-22 D 40 10 3 40' continuous Yes 10 MW-23 15 10 3 20' continuous Yes TOTALS:430 170 51 420 7-14 8 6 Continuous Geoprobe cores in all deep borings and in three single shallow borings, followed by hollow-stem auger installation of wells/piezometers at each drilling location. One or two optional split-spoon samples with SPTs in selected auger borings. Shelby-tube samples in selected borings. (Note that two of the PZ and four shallow MW geoprobe cores will extend deeper than the PZ/Well will be installed.) Total Geoprobe cores:420 feet Total HSA drilling with 1-2 split-spoons per boring:90 feet Total HSA drilling with geoprobe cores:355 feet Estimated total PVC pipe (screen & riser, including 3' stick-up):496 feet MW/PZ construction must be done inside of augers to avoid boring collapse. Surface completions for MWs include an above-ground steel cover and a 2'x2'x6" well pad. PZs will be left as PVC stick-up. 9 CRSWMA Phase 4 - Proposed Drilling Program 5 7 1 2 3 4 i 1 i 2 CLOSED CRAVE N COUNTY LANDFI L L LEGENDEDGE OF LINER PAVED ROAD EXISTING 2 FT CONTOUR EXISTING 10 FT CONTOURGRAVEL ROADGROUNDWATER MONITORING WELL LOCATION,IDENTIFICATION, AND GROUNDWATER ELEVATION POINT IN TIME GROUNDWATER CONTOUR(APPROXIMATE) 1 FT. CONTOUR INTERVALGROUNDWATER FLOW PATHWAY USED TOCALCULATE HYDRAULIC GRADIENTi1SEGMENT USED FOR GRADIENT CALCULATIONSURFACE WATER MONITORING LOCATIONSAND IDENTIFICATIONS1.PIEZOMETERS AND MONITORING WELLS SCREENED IN THE DEEP AQUIFER DO NOT HAVE WATER LEVEL ELEVATION LABELS.2.STATIC WATER LEVELS MEASURED ON OCTOBER 20 AND 21, 2015.3.GROUNDWATER CONTOURS BASED ON LINEAR INTERPOLATION BETWEEN AND EXTRAPOLATION FROM KNOWN DATA,TOPOGRAPHIC CONTOURS, AND KNOWN FIELD CONDITIONS. THEREFORE, GROUNDWATER CONTOURS MUST BE ASSUMED TOBE APPROXIMATE.4.GROUNDWATER ELEVATIONS ARE MEASURED IN FEET AND REFERENCED TO MEAN SEA LEVEL.NOTES 46LEACHATE MONITORING LOCATION ANDIDENTIFICATION i 3 4 1 . 1 3 4 1 . 9 2 NOT MONITOREDNM39.73 4 3 . 2 7 I R L ( C L O S E D ) P H A S E 1 ( C L O S E D ) 4 5 . 1 3 4 0 . 6 1 4 2 . 7 1 4 0 . 1 9 4 0 . 2 4 38.42 4 4 . 5 9 4 5 . 8 1 4 6 . 4 3 4 6 . 2 8 4 4 . 8 7 4 5 . 9 9 4 1 . 6 9 4 2 . 5 6 39.50 40.91 P H A S E 2 4 6 . 3 7 4 5 . 9 8 SWPT-1 S W P T - 2 U D - 2 4 0 . 6 7 4 5 . 3 5 4 0 . 7 5 4 1 . 8 0 4 5 4 4 43 44 42 4 2 4 1 4140 3 9 40 LEACHATE MANHOLE M W - 1 9 D M W - 1 9 S MW-A M W - 1 4 R M W - 1 3 S M W - 1 3 D IRL-3SIRL-3D I R L - 4 S I R L - 4 D I R L - 5 S I R L - 5 D L S T - 2 S L S T - 2 D L S T - 3 S L S T - 3 D L S T - 4 S L S T - 4 D L S T - 6 S L S T - 6 D M W - 1 2 S M W - 1 2 D M W - 8 M W - 7 M W - 1 5 D M W - 1 5 S M W - 1 6 D M W - 1 7 D M W - 1 7 S M W - 2 0 D M W - 2 1 D M W - 8 D M W - 7 D PZ-Z I R L - 2 D A I R L - 2 S A M W - 1 0 MW-B M W - 1 6 S R L S T - 1 S L S T - 1 D L S T - 5 S L S T - 5 D M W - 1 1 D M W - 1 1 S I R L - 2 S I R L - 2 D P H A S E 3 M W - 1 8 D M W - 1 8 S L E A C H A T E M A N H O L E SEGMENT LENGTHi1i2i3= 1,826 LF= 1,527 LF= 1,543 LF39 4 6 4 5 4 6 4 4 4 4 4 3 I R L - 1 S I R L - 1 D 5 0 50 4 0 4 0 P H A S E 4 1 7 . 7 A C ( F U T U R E ) M W - 2 0 S & D M W - 2 1 M W - 2 2 S & D C O M P L I A N C E B O U N D A R Y 2 5 0 ' - 0 " P Z - 4 4 S & D P Z - 4 5 P Z - 4 2 S & D P Z - 4 1 S & D P Z - 4 3 S & D P Z - 4 0 S & D MW-21PZ-45 PROPOSED MONITORING WELL LOCATION AND IDENTIFICATIONPROPOSED PIEZOMETER LOCATION AND IDENTIFICATION M W - 2 3 P R O J E C T N O . APPROVED CHECKED DRAWN DESIGNED DATE DATE REVISIONS AND RECORD OF ISSUE BYNO APPCK S C A L E All rights reserved. Ó Joyce Engineering, Inc. D R A W I N G N O . L:\CRSWMA\dwg\2016 PHASE 4 EXPANSION\HYDROGEO\DRILLING MAP FINAL.dwg Layout=Layout1 2211 W. MEADOWVIEW ROAD GREENSBORO, NC 27407 PHONE: (336) 323-0092 6 1 8 CRSWMA: TUSCARORA LANDFILL TUSCARORA, NORTH CAROLINA 2016 1 A S N O T E D PROPOSED MONITORING WELL AND PIEZOMETER LOCATION VB RWH DSG VB 04/25/16 0 ( F E E T ) G R A P H I C S C A L E 4 0 0 2 0 0 1 0 0 NC CORP LIC: C-0782