HomeMy WebLinkAbout1101_Buncombe_MSWLF_GWCA_PhytoSchedule_FID1890646_20240729� CANNONS
ENGINEERING
July 29, 2024
Solid Waste Section
Division of Waste Management
NCDEQ-ARO
2090 U.S. 70 Highway
Swannanoa, North Carolina 28778
Attention: Ms. Jaclynne Drummond, Hydrogeologist
Subject: Implementation Schedule for Phytoremediation (Supplemental Remedy)
Old Buncombe County Landfill
Woodfin, North Carolina
Permit Number 1101-MSWLF-1979
BLE Project Number J24-14175-13
Dear Ms. Drummond:
The Solid Waste Section (SWS) issued a letter dated June 25, 2024 (FID 1882834) to Buncombe
County approving the phytoremediation remedy described in Corrective Action Plan Addendum -
Phytoremediation dated May 29, 2024 (FID 1878215) prepared by Bunnell-Lammons Engineering,
Inc. (BLE). The approval letter requires submittal of a project schedule for implementation of the
approved phytoremediation remedy. Additionally, the letter specifies that planting in the pilot areas
must be completed by February 2025.
The Buncombe County Solid Waste Department received notice from the Buncombe County
Municipal Sewer District (MSD) that the MSD plans to replace the force main sewer line in the
vicinity of planting areas from October 2024 to March 2025. The annotated plan provided by MSD
is attached for reference (Appendix A). The MSD construction schedule conflicts with the SWS
planting schedule.
Therefore, we propose that the phytoremediation project schedule include planting immediately after
scheduled conclusion of the MSD construction project (March 2025). This change is mutually
beneficial because the MSD construction project should improve access to the phytoremediation pilot
areas and coincide with the ideal planting season (early spring). We have prepared a 5-year
implementation schedule (herein) as requested by the SWS from the start date described above.
Please note that if the MSD construction schedule is delayed and the planting areas are not accessible
during the spring of 2025, the project will be delayed until spring of 2026.
6004 Ponders Court. Greenville. SC 29615 (,864.288.1265 N864.288.4430 �infn@6leeorp.rom
BLECORMOM
1s 1m 11
Implementation Schedule for Phytoremediation July 29, 2024
Old Buncombe County Landfill — Woodfin, North Carolina BLE Project No. J24-14175-13
Year One
Task Approximate Completion Date
Soil Sampling & Analysis February 2025
Planting (with fertilization if necessary) April 2025
Planting Summary Report June 2025
Quarterly Inspection Report September 2025
Quarterly Inspection Report December 2025
Year Two
Task Approximate Completion Date
Quarterly Inspection Report March 2026
Annual Mass Flux Report May 2026
Quarterly Inspection Report June 2026
Quarterly Inspection Report September 2026
Quarterly Inspection Report December 2026
Year Three
Task Approximate Completion Date
Quarterly Inspection Report March 2027
Annual Mass Flux Report May 2027
Quarterly Inspection Report June 2027
Quarterly Inspection Report September 2027
Quarterly Inspection Report December 2027
Year Four
Task
Approximate Completion Date
Quarterly Inspection Report
March 2028
Tissue Sampling & Analysis
April 2028
Annual Mass Flux Report
May 2028
Quarterly Inspection Report
June 2028
Quarterly Inspection Report
September 2028
Tissue Sampling & Analysis
October 2028
Quarterly Inspection Report
December 2028
Year Five
Task
Approximate Completion Date
Quarterly Inspection Report
March 2029
Tissue Sampling & Analysis
April 2029
Annual Mass Flux Report
May 2029
Quarterly Inspection Report
June 2029
Quarterly Inspection Report
September 2029
Tissue Sampling & Analysis
October 2029
Quarterly Inspection Report
December 2029
2
1s 1m 11
Implementation Schedule for Phytoremediation July 29, 2024
Old Buncombe County Landfill — Woodfin, North Carolina BLE Project No. J24-14175-13
Please contact BLE if you have any questions or comments on this implementation schedule.
Sincerely,
BUNNELL-LAMMONS ENGINEERING, INC.
ery J. Downes, P.G.
Project Geologist
Registered, NC No. 2618
Attachments: Appendix A - Annotated MSD Plan
Copy: Mr. Dane Pedersen — Buncombe County
Ms. Kristy Smith — Buncombe County
Mr. Riley Blais, P.G. — BLE
a4l A"�
Andrew W. Alexender, P.G., RSM
Consultant Hydrogeologist
Registered, NC No. 1475
APPENDIX A
Annotated MSD Plan
,gip'•,• DWG �•' o: '•.
..• : — ,
.• pQ •-• ' New 6" FM installation expect to occur Dec 25-Mar 26
Work will begin at station and proceed SW toward
�� .•AoF m tie-in at high point ••��': }
<LLJ
�}
''. f►7 r
�� ' 2 •C��wJ: • ,o� .., •f Q .n •>• ''� GCS 0 0 ., = Q
�• .Y o m o : UU
;a o •� :o Z, oo •ono
:• w .cn m : y '•.
• ♦• w 'r Z
f BANNISTEROR
e
8 •.
N'•� CANOE LN •'
•' o ••: •�° FEU T ........
ERUyG
N
r•�x)•' O,. '•� IN •• •.
3A2 O
01
��.• o s
p� �• : N
4.
Replacement expected to occur Oct 2024-Mar 2025.
....
Work will begin at MSD dam and proceed •:
s northward toward BC Training Facility. o~ •• • •••., ••' ; �':,
..'.•• � �. � '•..... .•�.'••.� —� � .• ,� �,,� ':�•• ma's o ••�..�:•. �: .•''• •..,��
- •.
, J'] .•... ac w ...•• : BOO .••• • e . ..•. ••• • . �♦. ..: i
1 '
••♦ •. • B -
a
-A623119 „ • '. a ... ,
+ `' •cam •GS �• •..o� C �
B B :
RIVER RUN
• • : \ _ ° ° ; • : : .
.. +'. CP• '•• • ;'li
Op�</A , :.�Q� �, u ; B i B .• \ �k� `•' ••KAGY RD •••�'
1 inch - 600 feet = '